| Painting is complete. Press preview. 2004-10-8 |
|
|
| Painting, planting and mulching continues. Skatestoppers are installed. 2004-10-7 |
|
|
| Primer coat of blue (lighter than final color) on the quote wall. 2004-10-6 |
|
|
| Pathway color is not true to the actual color in these images. 2004-10-5 |
|
|
| Beginning to coat the pathways. All of the tiles on the French curve are set. 2004-10-4 |
|
|
| Installing the numbered tiles. 2004-10-3 |
|
|
| Quote wall panels are installed. Installing expansion joints in the mud bed. 2004-10-2 |
|
|
| Sample of stainless steel "skatestopper." 2004-10-1 |
|
|
| Quote wall panels being installed. Stainless steel edge and mud bed installation. 2004-10-1 |
|
|
| Quote wall panels at the plant. Stainless steel edge installation. 2004-09-30 |
|
|
| Quote wall panels getting cleaned and grouted. Final cleaning will be done after the grout sets. 2004-09-28 |
|
|
| Brick is removed from the Tepper wall 2004-09-27 |
|
|
| Mulching, Light Pole Foundations and Brickwork 2004-09-24 |
|
|
| Planting Progress 2004-09-22 |
|
|
| Planting and finetuning the pathways 2004-09-16 |
|
|
| Planting Details 2004-09-14 |
|
|
| Placing the organic soil and stockpiling the first plant material 2004-09-10 |
|
|
| Pouring the last of the orange sidewalk and the stairs at South Court 2004-09-03 |
|
|
| Tile Sample with grout and caulk, 2004-08-31 |
|
|
| New Concrete Pathways 2004-08-30 |
|
|
| Pouring the sidewalk at the French curve 2004-08-23 |
|
|
| Sidewalk curing 2004-08-20 |
|
|
| Pouring the sidewalk 2004-08-19 |
|
|
| Sidewalk forming 2004-08-18 |
|
|
| Sidewalk forming 2004-08-17 |
|
|
| Surbeck Waterjet, Ardmore, PA 2004-08-16 |
|
|
| Mel Bochner Site Visit 2004-08-10 |
|
|
| Soil Placement 2004-08-09 |
|
|
| Soil Placement and French Curve Slab Poured 2004-08-05 |
|
|
| Soil Placement and French Curve Slab 2004-08-04 |
|
|
| French Curve Formwork 2004-08-03 |
|
|
| French Curve Formwork 2004-07-20 |
|
|
| French Curve Formwork 2004-06-25 |
|
|
| French Curve Formwork 2004-06-21 |
|
|
| French Curve Formwork 2004-06-10 |
|
|
| Pathway Retaining Wall 2004-01-21 |
|
|