%DOCUMENT% index.html
by
Chris Hendrickson
and
Tung Au
Department of Civil Engineering
Carnegie Mellon University
Pittsburgh, PA l52l3
June 28, 1999
Copyright C. Hendrickson and T. Au, 1988
Prepared under contract for publication with
Prentice-Hall, Inc.
Englewood Cliffs, New Jersey
1988
Preface
This book develops a specific viewpoint in discussing the participants, the
processes and the techniques of project management for construction. This
viewpoint is that of owners who desire completion of projects in a timely, cost
effective fashion. Some profound implications for the objectives and methods
of project management result from this perspective:
While this book is devoted to a particular viewpoint with respect to project
management for construction, it is not solely intended for owners and their
direct representatives. By understanding the entire process, all participants
can respond more effectively to the owner's needs in their own work, in
marketing their services, and in communicating with other participants. In
addition, the specific techniques and tools discussed in this book (such as
economic evaluation, scheduling, management information systems, etc.) can be
readily applied to any portion of the process.
As a result of the focus on the effective management of entire projects, a
number of novel organizational approaches and techniques become of interest.
First and foremost is the incentive to replace confrontation and adversarial
relationships with a spirit of joint endeavor and accomplishment. For example,
we discuss the appropriate means to evaluate risks and the appropriate
participants to assume the unavoidable risks associated with constructed
facilities. Scheduling, communication of data, and quality assurance have
particular significance from the viewpoint of an owner, but not necessarily for
individual participants. The use of computer-based technology and automation
also provides opportunities for increased productivity in the process.
Presenting such modern management options in a unified fashion is a major
objective of this book.
The unified viewpoint of the entire process of project management in this
book differs from virtually all other literature on the subject. Most
textbooks in the area treat special problems, such as cost estimating, from the
viewpoint of particular participants such as construction managers or
contractors. This literature reflects the fragmentation of the construction
process among different organizations and professionals. Even within a single
profession such as civil engineering, there are quite distinct groups of
specialists in planning, design, management, construction and other
sub-specialties. Fragmentation of interest and attention also exists in nearly
all educational programs. While specialty knowledge may be essential to
accomplish particular tasks, participants in the process should also understand
the context and role of their special tasks.
This book is intended primarily as a text for advanced undergraduates or
beginning graduate students in engineering, construction, architecture or
facilities management. Examples and discussion are chosen to remind readers
that project management is a challenging, dynamic and exciting enterprise and
not just a record of past practices. It should also be useful to professionals
who wish an up-to-date reference on project management.
Chapters 1 to 3 present an overview of the construction management and
design process which should be of interest to anyone engaged in project
management for construction. One need not have detailed knowledge about
individual tasks or techniques for this part. Individuals can read these
chapters and understand the basic philosophy and principles without further
elaboration.
Chapters 4 through 14 describe specific functions and techniques useful in
the process of project management. This part presents techniques and
requirements during project planning, including risk assessment, cost
estimation, forecasting and economic evaluation. It is during this planning
and design phase in which major cost savings may be obtained during the
eventual construction and operation phases. It also addresses programming and
financing issues, such as contracting and bidding for services, financing,
organizing communication and insuring effective use of information. It further
discusses techniques for control of time, cost and quality during the
construction phase. Beginning courses in engineering economics (including cash
flow analysis and discounting), use of computers, probability and statistics
would be useful. Furthermore, access to a personal computer with spreadsheet
or equation solving software would be helpful for readers attempting some of
the problems in Chapters 4 to 14. Numerous software programs could be used for
this purpose, including both spreadsheet and equation solving programs.
Problems in some chapters could also be done on any number of existing software
packages for information management and project scheduling. However, the use
of personal computers in this fashion is not required in following the text
material. Each instructor may exercise discretion in omitting some of the
material in these chapters if they are redundant with other classes or too
advanced for students in his or her own class.
The last two chapters of this book discuss some future prospects for new
technology in the construction field. We expect that these new technologies
will have a substantial impact on productivity improvement in the next two
decades even though they are not part of standard practice today. By including
these chapters, we are challenging readers with the remarkable opportunities
for innovation and improvement that exist in the field. These latter chapters
may also be reserved for an advanced course.
It is our hope that students beginning their career in project management
for construction will be prepared to adopt the integrated approach emphasized
in this book. Furthermore, experienced professionals in various fields may
discover in this book some surprises that even they have not anticipated. High
level decision makers in owner organizations who are not directly involved in
the project management process may find the basic philosophy and principles of
interest, especially in Chapters 1 through 3, as owners must invariably pay for
constructed facilities, for better or worse. If the book can fulfill even a
small part of its promises to influence the future of project management for
construction, our efforts will have been amply rewarded.
We wish to acknowledge our appreciation to Dr. William J. Hall for his
encouragement and assistance in expediting the publication of this book. We
are indebted to several colleagues at Carnegie Mellon University, Drs. Paul
Christiano, Steven Fenves and Daniel Rehak who reviewed parts of the manuscript
and offered valuable suggestions. We also wish to thank Debbie Scappatura and
Shirley Knapp for their efforts in typing the manuscript. This book also
reflects the contributions of numerous students and colleagues in industry who
have challenged us with problems and shared their own ideas and experience over
many years. We are grateful to all of these individuals.
Some material in this book has been taken from several papers authored by us
and published by the American Society of Civil Engineers. Materials taken from
other sources are acknowledged in footnotes, tables or figures. We gratefully
acknowledge the permissions given to us by these individuals, publishers and
organizations.
Finally, a series of photographs depicting various stages of construction of
the PPG building in Pittsburgh, PA is inserted in sequence between chapters.
We wish to thank PPG Industries for its cooperation in providing these
photographs.
Like the five blind men encountering different parts of an elephant, each of
the numerous participants in the process of planning, designing, financing,
constructing and operating physical facilities has a different perspective on
project management for construction. Specialized knowledge can be very
beneficial, particularly in large and complicated projects, since experts in
various specialties can provide valuable services. However, it is advantageous
to understand how the different parts of the process fit together. Waste,
excessive cost and delays can result from poor coordination and communication
among specialists. It is particularly in the interest of owners to insure that
such problems do not occur. And it behooves all participants in the process to
heed the interests of owners because, in the end, it is the owners who provide
the resources and call the shots.
By adopting the viewpoint of the owners, we can focus our attention on the
complete process of project management for constructed facilities rather than
the historical roles of various specialists such as planners, architects,
engineering designers, constructors, fabricators, material suppliers, financial
analysts and others. To be sure, each specialty has made important advances in
developing new techniques and tools for efficient implementation of
construction projects. However, it is through the understanding of the entire
process of project management that these specialists can respond more
effectively to the owner's desires for their services, in marketing their
specialties, and in improving the productivity and quality of their work.
The introduction of innovative and more effective project management for
construction is not an academic exercise. As reported by the "Construction
Industry Cost Effectiveness Project" of the Business Roundtable:[The Business
Roundtable, More Construction for the Money, Summary Report of the
Construction Industry Cost Effectiveness Project, January 1983, p. 11.]
The acquisition of a constructed facility usually represents a major capital
investment, whether its owner happens to be an individual, a private
corporation or a public agency. Since the commitment of resources for such an
investment is motivated by market demands or perceived needs, the facility is
expected to satisfy certain objectives within the constraints specified by the
owner and relevant regulations. With the exception of the speculative housing
market, where the residential units may be sold as built by the real estate
developer, most constructed facilities are custom made in consultation with the
owners. A real estate developer may be regarded as the sponsor of building
projects, as much as a government agency may be the sponsor of a public project
and turns it over to another government unit upon its completion. From the
viewpoint of project management, the terms "owner" and "sponsor" are synonymous
because both have the ultimate authority to make all important decisions.
Since an owner is essentially acquiring a facility on a promise in some form of
agreement, it will be wise for any owner to have a clear understanding of the
acquisition process in order to maintain firm control of the quality,
timeliness and cost of the completed facility.
From the perspective of an owner, the project life cycle for a constructed
facility may be illustrated schematically in Figure 1-1. Essentially, a
project is conceived to meet market demands or needs in a timely fashion.
Various possibilities may be considered in the conceptual planning stage, and
the technological and economic feasibility of each alternative will be assessed
and compared in order to select the best possible project. The financing
schemes for the proposed alternatives must also be examined, and the project
will be programmed with respect to the timing for its completion and for
available cash flows. After the scope of the project is clearly defined,
detailed engineering design will provide the blueprint for construction, and
the definitive cost estimate will serve as the baseline for cost control. In
the procurement and construction stage, the delivery of materials and the
erection of the project on site must be carefully planned and controlled.
After the construction is completed, there is usually a brief period of
start-up or shake-down of the constructed facility when it is first occupied.
Finally, the management of the facility is turned over to the owner for full
occupancy until the facility lives out its useful life and is designated for
demolition or conversion.
Of course, the stages of development in Figure 1-1 may not be strictly
sequential. Some of the stages require iteration, and others may be carried
out in parallel or with overlapping time frames, depending on the nature, size
and urgency of the project. Furthermore, an owner may have in-house capacities
to handle the work in every stage of the entire process, or it may seek
professional advice and services for the work in all stages. Understandably,
most owners choose to handle some of the work in-house and to contract outside
professional services for other components of the work as needed. By examining
the project life cycle from an owner's perspective we can focus on the proper
roles of various activities and participants in all stages regardless of the
contractual arrangements for different types of work.
In the United States, for example, the U.S. Army Corps of Engineers has
in-house capabilities to deal with planning, budgeting, design, construction
and operation of waterway and flood control structures. Other public agencies,
such as state transportation departments, are also deeply involved in all
phases of a construction project. In the private sector, many large firms such
as DuPont, Exxon, and IBM are adequately staffed to carry out most activities
for plant expansion. All these owners, both public and private, use outside
agents to a greater or lesser degree when it becomes more advantageous to do
so.
The project life cycle may be viewed as a process through which a project is
implemented from cradle to grave. This process is often very complex; however,
it can be decomposed into several stages as indicated by the general outline in
Figure 1-1. The solutions at various stages are then integrated to obtain the
final outcome. Although each stage requires different expertise, it usually
includes both technical and managerial activities in the knowledge domain of
the specialist. The owner may choose to decompose the entire process into more
or less stages based on the size and nature of the project, and thus obtain the
most efficient result in implementation. Very often, the owner retains direct
control of work in the planning and programming stages, but increasingly
outside planners and financial experts are used as consultants because of the
complexities of projects. Since operation and maintenance of a facility will
go on long after the completion and acceptance of a project, it is usually
treated as a separate problem except in the consideration of the life cycle
cost of a facility. All stages from conceptual planning and feasibility
studies to the acceptance of a facility for occupancy may be broadly lumped
together and referred to as the Design/Construct process, while the procurement
and construction alone are traditionally regarded as the province of the
construction industry.
Owners must recognize that there is no single best approach in organizing
project management throughout a project's life cycle. All organizational
approaches have advantages and disadvantages, depending on the knowledge of the
owner in construction management as well as the type, size and location of the
project. It is important for the owner to be aware of the approach which is
most appropriate and beneficial for a particular project. In making choices,
owners should be concerned with the life cycle costs of constructed facilities
rather than simply the initial construction costs. Saving small amounts of
money during construction may not be worthwhile if the result is much larger
operating costs or not meeting the functional requirements for the new facility
satisfactorily. Thus, owners must be very concerned with the quality of the
finished product as well as the cost of construction itself. Since facility
operation and maintenance is a part of the project life cycle, the owners'
expectation to satisfy investment objectives during the project life cycle will
require consideration of the cost of operation and maintenance. Therefore, the
facility's operating management should also be considered as early as possible,
just as the construction process should be kept in mind at the early stages of
planning and programming.
Since most owners are generally interested in acquiring only a specific type
of constructed facility, they should be aware of the common industrial
practices for the type of construction pertinent to them. Likewise, the
construction industry is a conglomeration of quite diverse segments and
products. Some owners may procure a constructed facility only once in a long
while and tend to look for short term advantages. However, many owners require
periodic acquisition of new facilities and/or rehabilitation of existing
facilities. It is to their advantage to keep the construction industry healthy
and productive. Collectively, the owners have more power to influence the
construction industry than they realize because, by their individual actions,
they can provide incentives or disincentives for innovation, efficiency and
quality in construction. It is to the interest of all parties that the owners
take an active interest in the construction and exercise beneficial influence
on the performance of the industry.
In planning for various types of construction, the methods of procuring
professional services, awarding construction contracts, and financing the
constructed facility can be quite different. For the purpose of discussion,
the broad spectrum of constructed facilities may be classified into four major
categories, each with its own characteristics.
Residential housing construction includes single-family houses, multi-family
dwellings, and highrise apartments. During the development and construction of
such projects, the developers or sponsors who are familiar with the
construction industry usually serve as surrogate owners and take charge, making
necessary contractual agreements for design and construction, and arranging the
financing and sale of the completed structures. Residential housing designs
are usually performed by architects and engineers, and the construction
executed by builders who hire subcontractors for the structural, mechanical,
electrical and other specialty work. An exception to this pattern is for
single-family houses which may be designed by the builders as well.
The residential housing market is heavily affected by general economic
conditions, tax laws, and the monetary and fiscal policies of the government.
Often, a slight increase in total demand will cause a substantial investment in
construction, since many housing projects can be started at different locations
by different individuals and developers at the same time. Because of the
relative ease of entry, at least at the lower end of the market, many new
builders are attracted to the residential housing construction. Hence, this
market is highly competitive, with potentially high risks as well as high
rewards.
Because of the higher costs and greater sophistication of institutional and
commercial buildings in comparison with residential housing, this market
segment is shared by fewer competitors. Since the construction of some of
these buildings is a long process which once started will take some time to
proceed until completion, the demand is less sensitive to general economic
conditions than that for speculative housing. Consequently, the owners may
confront an oligopoly of general contractors who compete in the same market.
In an oligopoly situation, only a limited number of competitors exist, and a
firm's price for services may be based in part on its competitive strategies in
the local market.
Specialized industrial construction usually involves very large scale
projects with a high degree of technological complexity, such as oil
refineries, steel mills, chemical processing plants and coal-fired or nuclear
power plants. The owners usually are deeply involved in the development of a
project, and prefer to work with designers-builders such that the total time
for the completion of the project can be shortened. They also want to pick a
team of designers and builders with whom the owner has developed good working
relations over the years.
Although the initiation of such projects is also affected by the state of
the economy, long range demand forecasting is the most important factor since
such projects are capital intensive and require considerable amount of planning
and construction time. Governmental regulation such as the rulings of the
Environmental Protection Agency and the Nuclear Regulatory Commission in the
United States can also profoundly influence decisions on these projects.
The engineers and builders engaged in infrastructure construction are
usually highly specialized since each segment of the market requires different
types of skills. However, demands for different segments of infrastructure and
heavy construction may shift with saturation in some segments. For example, as
the available highway construction projects are declining, some heavy
construction contractors quickly move their work force and equipment into the
field of mining where jobs are available.
When an owner decides to seek professional services for the design and
construction of a facility, he is confronted with a broad variety of choices.
The type of services selected depends to a large degree on the type of
construction and the experience of the owner in dealing with various
professionals in the previous projects undertaken by the firm. Generally,
several common types of professional services may be engaged either separately
or in some combination by the owners.
In the past two decades, this traditional approach has become less popular
for a number of reasons, particularly for large scale projects. The A/E firms,
which are engaged by the owner as the prime professionals for design and
inspection, have become more isolated from the construction process. This has
occurred because of pressures to reduce fees to A/E firms, the threat of
litigation regarding construction defects, and lack of knowledge of new
construction techniques on the part of architect and engineering professionals.
Instead of preparing a construction plan along with the design, many A/E firms
are no longer responsible for the details of construction nor do they provide
periodic field inspection in many cases. As a matter of fact, such firms will
place a prominent disclaimer of responsibilities on any shop drawings they may
check, and they will often regard their representatives in the field as
observers instead of inspectors. Thus, the A/E firm and the general contractor
on a project often become antagonists who are looking after their own competing
interests. As a result, even the constructibility of some engineering designs
may become an issue of contention. To carry this protective attitude to the
extreme, the specifications prepared by an A/E firm for the general contractor
often protects the interest of the A/E firm at the expense of the interests of
the owner and the contractor.
In order to reduce the cost of construction, some owners introduce value
engineering, which seeks to reduce the cost of construction by soliciting a
second design that might cost less than the original design produced by the A/E
firm. In practice, the second design is submitted by the contractor after
receiving a construction contract at a stipulated sum, and the saving in cost
resulting from the redesign is shared by the contractor and the owner. The
contractor is able to absorb the cost of redesign from the profit in
construction or to reduce the construction cost as a result of the re-design.
If the owner had been willing to pay a higher fee to the A/E firm or to better
direct the design process, the A/E firm might have produced an improved design
which would cost less in the first place. Regardless of the merit of value
engineering, this practice has undermined the role of the A/E firm as the prime
professional acting on behalf of the owner to supervise the contractor.
One of the most obvious advantages of the integrated design/construct
process is the use of phased construction for a large project. In this
process, the project is divided up into several phases, each of which can be
designed and constructed in a staggered manner. After the completion of the
design of the first phase, construction can begin without waiting for the
completion of the design of the second phase, etc. If proper coordination is
exercised. the total project duration can be greatly reduced. Another
advantage is to exploit the possibility of using the turnkey approach whereby
an owner can delegate all responsibility to the design/construct firm which
will deliver to the owner a completed facility that meets the performance
specifications at the specified price.
It should be obvious to all involved in the construction process that the
party which is required to take higher risk demands larger rewards. If an
owner wants to engage an A/E firm on the basis of low fees instead of
established qualifications, it often gets what it deserves; or if the owner
wants the general contractor to bear the cost of uncertainties in construction
such as foundation conditions, the contract price will be higher even if
competitive bidding is used in reaching a contractual agreement. Without
mutual respect and trust, an owner cannot expect that construction managers can
produce better results than other professionals. Hence, an owner must
understand its own responsibility and the risk it wishes to assign to itself
and to other participants in the process.
A common denominator of all firms entering into these new services is that
they all have strong computer capabilities and heavy computer investments. In
addition to the use of computers for aiding design and monitoring construction,
the service includes the compilation of a computer record of building plans
that can be turned over at the end of construction to the facilities management
group of the owner. A computer data base of facilities information makes it
possible for planners in the owner's organization to obtain overview
information for long range space forecasts, while the line managers can use
as-built information such as lease/tenant records, utility costs, etc. for
day-to-day operations.
Builders who supervise the execution of construction projects are
traditionally referred to as contractors, or more appropriately called
constructors. The general contractor coordinates various tasks for a project
while the specialty contractors such as mechanical or electrical contractors
perform the work in their specialties. Material and equipment suppliers often
act as installation contractors; they play a significant role in a
construction project since the conditions of delivery of materials and
equipment affect the quality, cost, and timely completion of the project. It
is essential to understand the operation of these contractors in order to deal
with them effectively.
A major construction project requires an enormous amount of capital that is
often supplied by lenders who want to be assured that the project will offer a
fair return on the investment. The direct costs associated with a major
construction project may be broadly classified into two categories: (1) the
construction expenses paid to the general contractor for erecting the facility
on site and (2) the expenses for land acquisition, legal fees,
architect/engineer fees, construction management fees, interest on construction
loans and the opportunity cost of carrying empty space in the facility until it
is fully occupied. The direct construction costs in the first category
represent approximately 60 to 80 percent of the total costs in most
construction projects. Since the costs of construction are ultimately borne by
the owner, careful financial planning for the facility must be made prior to
construction.
Construction loans provided for different types of construction vary. In
the case of residential housing, construction loans and long-term mortgages can
be obtained from savings and loans associations or commercial banks. For
institutional and commercial buildings, construction loans are usually obtained
from commercial banks. Since the value of specialized industrial buildings as
collateral for loans is limited, construction loans in this domain are rare,
and construction financing can be done from the pool of general corporate
funds. For infrastructure construction owned by government, the property
cannot be used as security for a private loan, but there are many possible ways
to finance the construction, such as general appropriation from taxation or
special bonds issued for the project.
Traditionally, banks serve as construction lenders in a three-party
agreement among the contractor, the owner and the bank. The stipulated loan
will be paid to the contractor on an agreed schedule upon the verification of
completion of various portions of the project. Generally, a payment request
together with a standard progress report will be submitted each month by the
contractor to the owner which in turn submits a draw request to the bank.
Provided that the work to date has been performed satisfactorily, the
disbursement is made on that basis during the construction period. Under such
circumstances, the bank has been primarily concerned with the completion of the
facility on time and within the budget. The economic life of the facility
after its completion is not a concern because of the transfer of risk to the
owner or an institutional lender.
Because of the sudden surge of interest rates in the late 1970's, many
financial institutions offer, in addition to the traditional fixed rate
long-term mortgage commitments, other arrangements such as a combination of
debt and a percentage of ownership in exchange for a long-term mortgage or the
use of adjustable rate mortgages. In some cases, the construction loan may be
granted on an open-ended basis without a long-term financing commitment. For
example, the plan might be issued for the construction period with an option to
extend it for a period of up to three years in order to give the owner more
time to seek alternative long-term financing on the completed facility. The
bank will be drawn into situations involving financial risk if it chooses to be
a lender without long-term guarantees.
The owners of facilities naturally want legal protection for all the
activities involved in the construction. It is equally obvious that they
should seek competent legal advice. However, there are certain principles that
should be recognized by owners in order to avoid unnecessary pitfalls.
Owners must be aware of the impacts of these regulations on the costs and
durations of various types of construction projects as well as possibilities of
litigation due to various contentions. For example, owners acquiring sites for
new construction may be strictly liable for any hazardous wastes already on the
site or removed from the site under the U.S. Comprehensive Environmental
Response Compensation and Liability (CERCL) Act of 1980. For large scale
projects involving new technologies, the construction costs often escalate with
the uncertainty associated with such restrictions.
The construction industry is a conglomeration of diverse fields and
participants that have been loosely lumped together as a sector of the economy.
The construction industry plays a central role in national welfare, including
the development of residential housing, office buildings and industrial plants,
and the restoration of the nation's infrastructure and other public facilities.
The importance of the construction industry lies in the function of its
products which provide the foundation for industrial production, and its
impacts on the national economy cannot be measured by the value of its output
or the number of persons employed in its activities alone.
To be more specific, construction refers to all types of activities usually
associated with the erection and repair of immobile facilities. Contract
construction consists of a large number of firms that perform construction work
for others, and is estimated to be approximately 85% of all construction
activities. The remaining 15% of construction is performed by owners of the
facilities, and is referred to as force-account construction. Although the
number of contractors in the United States exceeds a million, over 60% of all
contractor construction is performed by the top 400 contractors. The value of
new construction in the United States (expressed in constant dollars) and the
value of construction as a percentage of the gross national products from 1950
to 1985 are shown in Figure 1-0. It can be seen that construction is a
significant factor in the Gross National Product although its importance has
been declining in recent years.[The graph is derived from data in "Value of New
Construction Put in Place, 1960-1983", Statistical Abstract of the United
States, 105th Edition, U.S. Department of Commerce, Bureau of Census, 1985,
pp. 722-723, as well as the information in earlier editions.] Not to be
ignored is the fact that as the nation's constructed facilities become older,
the total expenditure on rehabilitation and maintenance may increase relative
to the value of new construction.
Owners who pay close attention to the peculiar characteristics of the
construction industry and its changing operating environment will be able to
take advantage of the favorable conditions and to avoid the pitfalls. Several
factors are particularly noteworthy because of their significant impacts on the
quality, cost and time of construction.
The effects of new technologies on construction costs have been mixed
because of the high development costs for new technologies. However, it is
unmistakable that design professionals and construction contractors who have
not adapted to changing technologies have been forced out of the mainstream of
design and construction activities. Ultimately, construction quality and cost
can be improved with the adoption of new technologies which are proved to be
efficient from both the viewpoints of performance and economy.
While aggregate construction industry productivity is important as a measure
of national economy, owners are more concerned about the labor productivity of
basic units of work produced by various crafts on site. Thus, an owner can
compare the labor performance at different geographic locations, under
different working conditions, and for different types and sizes of projects.
Construction costs usually run parallel to material prices and labor wages.
Actually, over the years, labor productivity has increased in some traditional
types of construction and thus provides a leveling or compensating effect when
hourly rates for labor increase faster than other costs in construction.
However, labor productivity has been stagnant or even declined in
unconventional or large scale projects.
Figure 1-0 can serve to indicate public attitudes towards the siting of new
facilities. It represents the cumulative percentage of individuals who would
be willing to accept a new industrial facility at various distances from their
homes. For example, over fifty percent of the people surveyed would accept a
ten-story office building within five miles of their home, but only twenty-five
percent would accept a large factory or coal fired power plant at a similar
distance. An even lower percentage would accept a hazardous waste disposal
site or a nuclear power plant. Even at a distance of one hundred miles, a
significant fraction of the public would be unwilling to accept hazardous waste
facilities or nuclear power plants.
This objection to new facilities is a widespread public attitude,
representing considerable skepticism about the external benefits and costs
which new facilities will impose. It is this public attitude which is likely
to make public scrutiny and regulation a continuing concern for the
construction industry.
A bidding competition for a major new offshore drilling platform illustrates
the competitive environment in construction. As described in the Wall Street
Journal:[See Petzinger, Thomas Jr., "Upstart's Winning Bid for Offshore
Platform Stuns its Older Rivals," Wall Street Journal, p. 1, c. 6, Nov. 20,
1985.]
Of course, U.S. firms including A/E firms, contractors and construction
managers are also competing in foreign countries. Their success or failure in
the international arena may also affect their capacities and vitality to
provide services in the domestic U.S. market.
This type of joint venture has become more important in the international
construction market where aggressive contractors often win contracts by
offering a more attractive financing package rather than superior technology.
With a deepening shadow of international debts in recent years, many developing
countries are not in a position to undertake any new project without
contractor-backed financing. Thus, the contractors or joint ventures in
overseas projects are forced into very risky positions if they intend to stay
in the competition.
In the project life cycle, the most influential factors affecting the
outcome of the project often reside at the early stages. At this point,
decisions should be based on competent economic evaluation with due
consideration for adequate financing, the prevalent social and regulatory
environment, and technological considerations. Architects and engineers might
specialize in planning, in construction field management, or in operation, but
as project managers, they must have some familiarity with all such aspects in
order to understand properly their role and be able to make competent
decisions.
Since the 1970's, many large-scale projects have run into serious problems
of management, such as cost overruns and long schedule delays. Actually, the
management of megaprojects or superprojects is not a practice peculiar to our
time. Witness the construction of transcontinental railroads in the Civil War
era and the construction of the Panama Canal at the turn of this century.
Although the megaprojects of this generation may appear in greater frequency
and present a new set of challenge, the problems are organizational rather than
technical. As noted by Hardy Cross:[See H. Cross, Engineers and Ivory Towers,
McGraw-Hill Book Co., Inc., New York, 1952.]
The greatest stumbling block to effective management in construction is the
inertia and historic divisions among planners, designers and constructors.
While technical competence in design and innovation remains the foundation of
engineering practice, the social, economic and organizational factors that are
pervasive in influencing the success and failure of construction projects must
also be dealt with effectively by design and construction organizations. Of
course, engineers are not expected to know every detail of management
techniques, but they must be knowledgeable enough to anticipate the problems of
management so that they can work harmoniously with professionals in related
fields to overcome the inertia and historic divisions.
Paradoxically, engineers who are creative in engineering design are often
innovative in planning and management since both types of activities involve
problem solving. In fact, they can reinforce each other if both are included
in the education process, provided that creativity and innovation instead of
routine practice are emphasized. A project manager who is well educated in the
fundamental principles of engineering design and management can usefully apply
such principles once he or she has acquired basic understanding of a new
application area. A project manager who has been trained by rote learning for
a specific type of project may merely gain one year of experience repeated
twenty times even if he or she has been in the field for twenty years. A
broadly educated project manager can reasonably hope to become a leader in the
profession; a narrowly trained project manager is often relegated to the role
of his or her first job level permanently.
The owners have much at stake in selecting a competent project manager and
in providing her or him with the authority to assume responsibility at various
stages of the project regardless of the types of contractual agreements for
implementing the project. Of course, the project manager must also possess the
leadership quality and the ability to handle effectively intricate
interpersonal relationships within an organization. The ultimate test of the
education and experience of a project manager for construction lies in her or
his ability to apply fundamental principles to solving problems in the new and
unfamiliar situations which have become the hallmarks of the changing
environment in the construction industry.
The management of construction projects requires knowledge of modern
management as well as an understanding of the design and construction process.
Construction projects have a specific set of objectives and constraints such as
a required time frame for completion. While the relevant technology,
institutional arrangements or processes will differ, the management of such
projects has much in common with the management of similar types of projects in
other specialty or technology domains such as aerospace, pharmaceutical and
energy developments.
Generally, project management is distinguished from the general management
of corporations by the mission-oriented nature of a project. A project
organization will generally be terminated when the mission is accomplished.
According to the Project Management Institute, the discipline of project
management can be defined as follows:[See R. M. Wideman, "The PMBOK Report --
PMI Body of Knowledge Standard," Project Management Journal, Vol. 17, No. 3,
August l986, pp. l5-24.]
The basic ingredients for a project management framework [See
L. C. Stuckenbruck, "Project Management Framework," Project Management
Journal, Vol. 17, No. 3, August 1986, pp. 25-30.] may be represented
schematically in Figure 2-0. A working knowledge of general management and
familiarity with the special knowledge domain related to the project are
indispensable. Supporting disciplines such as computer science and decision
science may also play an important role. In fact, modern management practices
and various special knowledge domains have absorbed various techniques or tools
which were once identified only with the supporting disciplines. For example,
computer-based information systems and decision support systems are now
common-place tools for general management. Similarly, many operations research
techniques such as linear programming and network analysis are now widely used
in many knowledge or application domains. Hence, the representation in Figure
2-0 reflects only the sources from which the project management framework
evolves.
Specifically, project management in construction encompasses a set of
objectives which may be accomplished by implementing a series of operations
subject to resource constraints. There are potential conflicts between the
stated objectives with regard to scope, cost, time and quality, and the
constraints imposed on human material and financial resources. These conflicts
should be resolved at the onset of a project by making the necessary tradeoffs
or creating new alternatives. Subsequently, the functions of project
management for construction generally include the following:
In recent years, major developments in management reflect the acceptance to
various degrees of the following elements: (1) the management process
approach, (2) the management science and decision support approach, and (3) the
behavioral science approach for human resource development. These three
approaches complement each other in current practice, and provide a useful
groundwork for project management.
The management process approach emphasizes the systematic study of
management by identifying management functions in an organization and then
examining each in detail. There is general agreement regarding the functions
of planning, organizing and controlling. A major tenet is that by analyzing
management along functional lines, a framework can be constructed into which
all new management activities can be placed. Thus, the manager's job is
regarded as coordinating a process of interrelated functions, which are neither
totally random nor rigidly predetermined, but are dynamic as the process
evolves. Another tenet is that management principles can be derived from an
intellectual analysis of management functions. By dividing the manager's job
into functional components, principles based upon each function can be
extracted. Hence, management functions can be organized into a hierarchical
structure designed to improve operational efficiency, such as the example of
the organization for a manufacturing company shown in Figure 2-0. The basic
management functions are performed by all managers, regardless of enterprise,
activity or hierarchical levels. Finally, the development of a management
philosophy results in helping the manager to establish relationships between
human and material resources. The outcome of following an established
philosophy of operation helps the manager win the support of the subordinates
in achieving organizational objectives.
The management science and decision support approach contributes to the
development of a body of quantitative methods designed to aid managers in
making complex decisions related to operations and production. In decision
support systems, emphasis is placed on providing managers with relevant
information. In management science, a great deal of attention is given to
defining objectives and constraints, and to constructing mathematical analysis
models in solving complex problems of inventory, materials and production
control, among others. A topic of major interest in management science is the
maximization of profit, or in the absence of a workable model for the operation
of the entire system, the suboptimization of the operations of its components.
The optimization or suboptimization is often achieved by the use of operations
research techniques, such as linear programming, quadratic programming, graph
theory, queueing theory and Monte Carlo simulation. In addition to the
increasing use of computers accompanied by the development of sophisticated
mathematical models and information systems, management science and decision
support systems have played an important role by looking more carefully at
problem inputs and relationships and by promoting goal formulation and
measurement of performance. Artificial intelligence has also begun to be
applied to provide decision support systems for solving ill-structured problems
in management.
The behavioral science approach for human resource development is important
because management entails getting things done through the actions of people.
An effective manager must understand the importance of human factors such as
needs, drives, motivation, leadership, personality, behavior, and work groups.
Within this context, some place more emphasis on interpersonal behavior which
focuses on the individual and his/her motivations as a socio-psychological
being; others emphasize more group behavior in recognition of the organized
enterprise as a social organism, subject to all the attitudes, habits,
pressures and conflicts of the cultural environment of people. The major
contributions made by the behavioral scientists to the field of management
include: (1) the formulation of concepts and explanations about individual and
group behavior in the organization, (2) the empirical testing of these concepts
methodically in many different experimental and field settings, and (3) the
establishment of actual managerial policies and decisions for operation based
on the conceptual and methodical frameworks.
The programming of capital projects is shaped by the strategic plan of an
organization, which is influenced by market demands and resources constraints.
The programming process associated with planning and feasibility studies sets
the priorities and timing for initiating various projects to meet the overall
objectives of the organizations. However, once this decision is made to
initiate a project, market pressure may dictate early and timely completion of
the facility.
Among various types of construction, the influence of market pressure on the
timing of initiating a facility is most obvious in industrial
construction.(See, for example, O'Connor, J.T., and Vickory, C.G., Control of
Construction Project Scope, A Report to the Construction Industry Institute,
The University of Texas at Austin, December 1985.) Demand for an industrial
product may be short-lived, and if a company does not hit the market first,
there may not be demand for its product later. With intensive competition for
national and international markets, the trend of industrial construction moves
toward shorter project life cycles, particularly in technology intensive
industries.
In order to gain time, some owners are willing to forego thorough planning
and feasibility study so as to proceed on a project with inadequate definition
of the project scope. Invariably, subsequent changes in project scope will
increase construction costs; however, profits derived from earlier facility
operation often justify the increase in construction costs. Generally, if the
owner can derive reasonable profits from the operation of a completed facility,
the project is considered a success even if construction costs far exceed the
estimate based on an inadequate scope definition. This attitude may be
attributed in large part to the uncertainties inherent in construction
projects. It is difficult to argue that profits might be even higher if
construction costs could be reduced without increasing the project duration.
However, some projects, notably some nuclear power plants, are clearly
unsuccessful and abandoned before completion, and their demise must be
attributed at least in part to inadequate planning and poor feasibility
studies.
The owner or facility sponsor holds the key to influence the construction
costs of a project because any decision made at the beginning stage of a
project life cycle has far greater influence than those made at later stages,
as shown schematically in Figure 2-0. Therefore, an owner should obtain the
expertise of professionals to provide adequate planning and feasibility
studies. Many owners do not maintain an in-house engineering and construction
management capability, and they should consider the establishment of an ongoing
relationship with outside consultants in order to respond quickly to requests.
Even among those owners who maintain engineering and construction divisions,
many treat these divisions as reimbursable, independent organizations. Such an
arrangement should not discourage their legitimate use as false economies in
reimbursable costs from such divisions can indeed be very costly to the overall
organization.
Finally, the initiation and execution of capital projects places demands on
the resources of the owner and the professionals and contractors to be engaged
by the owner. For very large projects, it may bid up the price of engineering
services as well as the costs of materials and equipment and the contract
prices of all types. Consequently, such factors should be taken into
consideration in determining the timing of a project.
Example 2-1: Setting priorities for projects
A department store planned to expand its operation by acquiring 20 acres of
land in the southeast of a metropolitan area which consists of well established
suburbs for middle income families. An architectural/engineering (A/E) firm
was engaged to design a shopping center on the 20-acre plot with the department
store as its flagship plus a large number of storefronts for tenants. One year
later, the department store owner purchased 2,000 acres of farm land in the
northwest outskirts of the same metropolitan area and designated 20 acres of
this land for a shopping center. The A/E firm was again engaged to design a
shopping center at this new location.
The A/E firm was kept completely in the dark while the assemblage of the
2,000 acres of land in the northwest quietly took place. When the plans and
specifications for the southeast shopping center were completed, the owner
informed the A/E firm that it would not proceed with the construction of the
southeast shopping center for the time being. Instead, the owner urged the A/E
firm to produce a new set of similar plans and specifications for the northwest
shopping center as soon as possible, even at the sacrifice of cost saving
measures. When the plans and specifications for the northwest shopping center
were ready, the owner immediately authorized its construction. However, it
took another three years before the southeast shopping center was finally
built.
The reason behind the change of plan was that the owner discovered the
availability of the farm land in the northwest which could be developed into
residential real estate properties for upper middle income families. The
immediate construction of the northwest shopping center would make the land
development parcels more attractive to home buyers. Thus, the owner was able
to recoup enough cash flow in three years to construct the southeast shopping
center in addition to financing the construction of the northeast shopping
center, as well as the land development in its vicinity.
While the owner did not want the construction cost of the northwest shopping
center to run wild, it apparently was satisfied with the cost estimate based on
the detailed plans of the southeast shopping center. Thus, the owner had a
general idea of what the construction cost of the northwest shopping center
would be, and did not wish to wait for a more refined cost estimate until the
detailed plans for that center were ready. To the owner, the timeliness of
completing the construction of the northwest shopping center was far more
important than reducing the construction cost in fulfilling its investment
objectives.
Example 2-2: Resource Constraints for Mega Projects
A major problem with mega projects is the severe strain placed on the
environment, particularly on the resources in the immediate area of a
construction project. "Mega" or "macro" projects involve construction of very
large facilities such as the Alaska pipeline constructed in the 1970's or the
Panama Canal constructed in the 1900's. The limitations in some or all of the
basic elements required for the successful completion of a mega project
include:
The uncertainty in undertaking a construction project comes from many
sources and often involves many participants in the project. Since each
participant tries to minimize its own risk, the conflicts among various
participants can be detrimental to the project. Only the owner has the power
to moderate such conflicts as it alone holds the key to risk assignment through
proper contractual relations with other participants. Failure to recognize
this responsibility by the owner often leads to undesirable results. In recent
years, the concept of "risk sharing/risk assignment" contracts has gained
acceptance by the federal government.(See, for example, Federal Form 23-A and
EPA's Appendix C-2 clauses.) Since this type of contract acknowledges the
responsibilities of the owners, the contract prices are expected to be lower
than those in which all risks are assigned to contractors.
In approaching the problem of uncertainty, it is important to recognize that
incentives must be provided if any of the participants is expected to take a
greater risk. The willingness of a participant to accept risks often reflects
the professional competence of that participant as well as its propensity to
risk. However, society's perception of the potential liabilities of the
participant can affect the attitude of risk-taking for all participants. When
a claim is made against one of the participants, it is difficult for the public
to know whether a fraud has been committed, or simply that an accident has
occurred.
Risks in construction projects may be classified in a number of ways. (See
E. D'Appolonia, "Coping with Uncertainty in Geotechnical Engineering and
Construction," Special Proceedings of the 9th International Conference on Soil
Mechanics and Foundation Engineering, Tokyo, Japan, Vol. 4, 1979, pp. 1-18.)
One form of classification is as follows:
The environmental protection movement has contributed to the uncertainty for
construction because of the inability to know what will be required and how
long it will take to obtain approval from the regulatory agencies. The
requirements of continued re-evaluation of problems and the lack of definitive
criteria which are practical have also resulted in added costs. Public safety
regulations have similar effects, which have been most noticeable in the energy
field involving nuclear power plants and coal mining. The situation has
created constantly shifting guidelines for engineers, constructors and owners
as projects move through the stages of planning to construction. These moving
targets add a significant new dimension of uncertainty which can make it
virtually impossible to schedule and complete work at budgeted cost. Economic
conditions of the past decade have further reinforced the climate of
uncertainty with high inflation and interest rates. The deregulation of
financial institutions has also generated unanticipated problems related to the
financing of construction.
Uncertainty stemming from regulatory agencies, environmental issues and
financial aspects of construction should be at least mitigated or ideally
eliminated. Owners are keenly interested in achieving some form of
breakthrough that will lower the costs of projects and mitigate or eliminate
lengthy delays. Such breakthroughs are seldom planned. Generally, they happen
when the right conditions exist, such as when innovation is permitted or when a
basis for incentive or reward exists. However, there is a long way to go
before a true partnership of all parties involved can be forged.
During periods of economic expansion, major capital expenditures are made by
industries and bid up the cost of construction. In order to control costs,
some owners attempt to use fixed price contracts so that the risks of
unforeseen contingencies related to an overheated economy are passed on to
contractors. However, contractors will raise their prices to compensate for
the additional risks.
The risks related to organizational relationships may appear to be
unnecessary but are quite real. Strained relationships may develop between
various organizations involved in the design/construct process. When problems
occur, discussions often center on responsibilities rather than project needs
at a time when the focus should be on solving the problems. Cooperation and
communication between the parties are discouraged for fear of the effects of
impending litigation. This barrier to communication results from the
ill-conceived notion that uncertainties resulting from technological problems
can be eliminated by appropriate contract terms. The net result has been an
increase in the costs of constructed facilities.
The risks related to technological problems are familiar to the
design/construct professions which have some degree of control over this
category. However, because of rapid advances in new technologies which present
new problems to designers and constructors, technological risk has become
greater in many instances. Certain design assumptions which have served the
professions well in the past may become obsolete in dealing with new types of
facilities which may have greater complexity or scale or both. Site
conditions, particularly subsurface conditions which always present some degree
of uncertainty, can create an even greater degree of uncertainty for facilities
with heretofore unknown characteristics during operation. Because construction
procedures may not have been fully anticipated, the design may have to be
modified after construction has begun. An example of facilities which have
encountered such uncertainty is the nuclear power plant, and many owners,
designers and contractors have suffered for undertaking such projects.
If each of the problems cited above can cause uncertainty, the combination
of such problems is often regarded by all parties as being out of control and
inherently risky. Thus, the issue of liability has taken on major proportions
and has influenced the practices of engineers and constructors, who in turn
have influenced the actions of the owners.
Many owners have begun to understand the problems of risks and are seeking
to address some of these problems. For example, some owners are turning to
those organizations that offer complete capabilities in planning, design, and
construction, and tend to avoid breaking the project into major components to
be undertaken individually by specialty participants. Proper coordination
throughout the project duration and good organizational communication can avoid
delays and costs resulting from fragmentation of services, even though the
components from various services are eventually integrated.
Attitudes of cooperation can be readily applied to the private sector, but
only in special circumstances can they be applied to the public sector. The
ability to deal with complex issues is often precluded in the competitive
bidding which is usually required in the public sector. The situation becomes
more difficult with the proliferation of regulatory requirements and resulting
delays in design and construction while awaiting approvals from government
officials who do not participate in the risks of the project.
The top management of the owner sets the overall policy and selects the
appropriate organization to take charge of a proposed project. Its policy will
dictate how the project life cycle is divided among organizations and which
professionals should be engaged. Decisions by the top management of the owner
will also influence the organization to be adopted for project management. In
general, there are many ways to decompose a project into stages. The most
typical ways are:
There are two basic approaches to organize for project implementation, even
though many variations may exist as a result of different contractual
relationships adopted by the owner and builder. These basic approaches are
divided along the following lines:
Since construction projects may be managed by a spectrum of participants in
a variety of combinations, the organization for the management of such projects
may vary from case to case. On one extreme, each project may be staffed by
existing personnel in the functional divisions of the organization on an ad-hoc
basis as shown in Figure 2-0 until the project is completed. This arrangement
is referred to as the matrix organization as each project manager must
negotiate all resources for the project from the existing organizational
framework. On the other hand, the organization may consist of a small central
functional staff for the exclusive purpose of supporting various projects, each
of which has its functional divisions as shown in Figure 2-0. This
decentralized set-up is referred to as the project oriented organization as
each project manager has autonomy in managing the project. There are many
variations of management style between these two extremes, depending on the
objectives of the organization and the nature of the construction project. For
example, a large chemical company with in-house staff for planning, design and
construction of facilities for new product lines will naturally adopt the
matrix organization. On the other hand, a construction company whose existence
depends entirely on the management of certain types of construction projects
may find the project-oriented organization particularly attractive. While
organizations may differ, the same basic principles of management structure are
applicable to most situations.
To illustrate various types of organizations for project management, we
shall consider two examples, the first one representing an owner organization
while the second one representing the organization of a construction management
consultant under the direct supervision of the owner.
Example 2-3: . Matrix Organization of an Engineering Division
The Engineering Division of an Electric Power and Light Company has
functional departments as shown in Figure 2-0. When small scale projects such
as the addition of a transmission tower or a sub-station are authorized, a
matrix organization is used to carry out such projects. For example, in the
design of a transmission tower, the professional skill of a structural engineer
is most important. Consequently, the leader of the project team will be
selected from the Structural Engineering Department while the remaining team
members are selected from all departments as dictated by the manpower
requirements. On the other hand, in the design of a new sub-station, the
professional skill of an electrical engineer is most important. Hence, the
leader of the project team will be selected from the Electrical Engineering
Department.
Example 2-4: . Example of Construction Management Consultant Organization
When the same Electric Power and Light Company in the previous example
decided to build a new nuclear power plant, it engaged a construction
management consultant to take charge of the design and construction completely.
However, the company also assigned a project team to coordinate with the
construction management consultant as shown in Figure 2-0.
Since the company eventually will operate the power plant upon its
completion, it is highly important for its staff to monitor the design and
construction of the plant. Such coordination allows the owner not only to
assure the quality of construction but also to be familiar with the design to
facilitate future operation and maintenance. Note the close direct
relationships of various departments of the owner and the consultant. Since
the project will last for many years before its completion, the staff members
assigned to the project team are not expected to rejoin the Engineering
Department but will probably be involved in the future operation of the new
plant. Thus, the project team can act independently toward its designated
mission.
For ordinary projects of moderate size and complexity, the owner often
employs a designer (an architectural/engineering firm) which prepares the
detailed plans and specifications for the constructor (a general contractor).
The designer also acts on behalf of the owner to oversee the project
implementation during construction. The general contractor is responsible for
the construction itself even though the work may actually be undertaken by a
number of specialty subcontractors.
The owner usually negotiates the fee for service with the
architectural/engineering (A/E) firm. In addition to the responsibilities of
designing the facility, the A/E firm also exercises to some degree supervision
of the construction as stipulated by the owner. Traditionally, the A/E firm
regards itself as design professionals representing the owner who should not
communicate with potential contractors to avoid collusion or conflict of
interest. Field inspectors working for an A/E firm usually follow through the
implementation of a project after the design is completed and seldom have
extensive input in the design itself. Because of the litigation climate in the
last two decades, most A/E firms only provide observers rather than inspectors
in the field. Even the shop drawings of fabrication or construction schemes
submitted by the contractors for approval are reviewed with a disclaimer of
responsibility by the A/E firms.
The owner may select a general constructor either through competitive
bidding or through negotiation. Public agencies are required to use the
competitive bidding mode, while private organizations may choose either mode of
operation. In using competitive bidding, the owner is forced to use the
designer-constructor sequence since detailed plans and specifications must be
ready before inviting bidders to submit their bids. If the owner chooses to
use a negotiated contract, it is free to use phased construction if it so
desires.
The general contractor may choose to perform all or part of the construction
work, or act only as a manager by subcontracting all the construction to
subcontractors. The general contractor may also select the subcontractors
through competitive bidding or negotiated contracts. The general contractor
may ask a number of subcontractors to quote prices for the subcontracts before
submitting its bid to the owner. However, the subcontractors often cannot
force the winning general contractor to use them on the project. This
situation may lead to practices known as bid shopping and bid peddling. Bid
shopping refers to the situation when the general contractor approaches
subcontractors other than those whose quoted prices were used in the winning
contract in order to seek lower priced subcontracts. Bid peddling refers to
the actions of subcontractors who offer lower priced subcontracts to the
winning general subcontractors in order to dislodge the subcontractors who
originally quoted prices to the general contractor prior to its bid submittal.
In both cases, the quality of construction may be sacrificed, and some state
statutes forbid these practices for public projects.
Although the designer-constructor sequence is still widely used because of
the public perception of fairness in competitive bidding, many private owners
recognize the disadvantages of using this approach when the project is large
and complex and when market pressures require a shorter project duration than
that which can be accomplished by using this traditional method.
Professional construction management refers to a project management team
consisting of a professional construction manager and other participants who
will carry out the tasks of project planning, design and construction in an
integrated manner. Contractual relationships among members of the team are
intended to minimize adversarial relationships and contribute to greater
response within the management group. A professional construction manager is a
firm specialized in the practice of professional construction management which
includes:
Professional construction management is usually used when a project is very
large or complex. The organizational features that are characteristics of
mega-projects can be summarized as follows:(These features and the following
example are described in F.P. Moolin, Jr. and F.A. McCoy, "Managing the Alaska
Pipeline Project," Civil Engineering, November 1981, pp. 51-54.)
Example 2-5: Managing of the Alaska Pipeline Project
The Alaska Pipeline Project was the largest, most expensive private
construction project in the 1970's, which encompassed 800 miles, thousands of
employees, and 10 billion dollars.
At the planning stage, the owner (a consortium) employed a Construction
Management Contractor (CMC) to direct the pipeline portion, but retained
centralized decision making to assure single direction and to integrate the
effort of the CMC with the pump stations and the terminals performed by another
contractor. The CMC also centralized its decision making in directing over 400
subcontractors and thousands of vendors. Because there were 19 different
construction camps and hundreds of different construction sites, this
centralization caused delays in decision making.
At about the 15% point of physical completion, the owner decided to
reorganize the decision making process and change the role of the CMC. The new
organization was a combination of owner and CMC personnel assigned within an
integrated organization. The objective was to develop a single project team
responsible for controlling all subcontractors. Instead of having nine tiers
of organization from the General Manager of the CMC to the subcontractors, the
new organization had only four tiers from the Senior Project Manager of the
owner to subcontractors. Besides unified direction and coordination, this
reduction in tiers of organization greatly improved communications and the
ability to make and implement decisions. The new organization also allowed
decentralization of decision making by treating five sections of the pipeline
at different geographic locations as separate projects, with a section manager
responsible for all functions of the section as a profit center.
At about 98% point of physical completion, all remaining activities were to
be consolidated to identify single bottom-line responsibility, to reduce
duplication in management staff, and to unify coordination of remaining work.
Thus, the project was first handled by separate organizations but later was run
by an integrated organization with decentralized profit centers. Finally, the
organization in effect became small and was ready to be phased out of
operation.
In this approach an owner must have a steady flow of on-going projects in
order to maintain a large work force for in-house operation. However, the
owner may choose to subcontract a substantial portion of the project to outside
consultants and contractors for both design and construction, even though it
retains centralized decision making to integrate all efforts in project
implementation.
Example 2-6: : U.S. Army Corps of Engineers Organization
The District Engineer's Office of the U.S. Army Corps of Engineers may be
viewed as a typical example of an owner-builder approach as shown in Figure
2-0.
In the District Engineer's Office of the U.S. Corps of Engineers, there
usually exist an Engineering Division and an Operations Division, and, in a
large district, a Construction Division. Under each division, there are
several branches. Since the authorization of a project is usually initiated by
the U.S. Congress, the planning and design functions are separated in order to
facilitate operations. Since the authorization of the feasibility study of a
project may precede the authorization of the design by many years, each stage
can best be handled by a different branch in the Engineering Division. If
construction is ultimately authorized, the work may be handled by the
Construction Division or by outside contractors. The Operations Division
handles the operation of locks and other facilities which require routine
attention and maintenance.
When a project is authorized, a project manager is selected from the most
appropriate branch to head the project, together with a group of staff drawn
from various branches to form the project team. When the project is completed,
all members of the team including the project manager will return to their
regular posts in various branches and divisions until the next project
assignment. Thus, a matrix organization is used in managing each project.
Some owners wish to delegate all responsibilities of design and construction
to outside consultants in a turnkey project arrangement. A contractor agrees
to provide the completed facility on the basis of performance specifications
set forth by the owner. The contractor may even assume the responsibility of
operating the project if the owner so desires. In order for a turnkey
operation to succeed, the owner must be able to provide a set of unambiguous
performance specifications to the contractor and must have complete confidence
in the capability of the contractor to carry out the mission.
This approach is the direct opposite of the owner-builder approach in which
the owner wishes to retain the maximum amount of control for the
design-construction process.
Example 2-7: : An Example of a Turnkey Organization
A 150-Mw power plant was proposed in 1985 by the Texas-New Mexico Power
Company of Fort Worth, Texas, which would make use of the turnkey
operation.("Private Money Finances Texas Utility's Power Plant" Engineering
News Record: July 25, 1985, p. 13.) Upon approval by the Texas Utility
Commission, a consortium consisting of H.B. Zachry Co., Westinghouse Electric
Co., and Combustion Engineering, Inc. would design, build and finance the power
plant for completion in 1990 for an estimated construction cost of $200 million
in 1990 dollars. The consortium would assume total liability during
construction, including debt service costs, and thereby eliminate the risks of
cost escalation to rate payers, stockholders and the utility company
management.
The project manager, in the broadest sense of the term, is the most
important person for the success or failure of a project. The project manager
is responsible for planning, organizing and controlling the project. In turn,
the project manager receives authority from the management of the organization
to mobilize the necessary resources to complete a project.
The project manager must be able to exert interpersonal influence in order
to lead the project team. The project manager often gains the support of
his/her team through a combination of the following:
In a matrix organization, the members of the functional departments may be
accustomed to a single reporting line in a hierarchical structure, but the
project manager coordinates the activities of the team members drawn from
functional departments. The functional structure within the matrix
organization is responsible for priorities, coordination, administration and
final decisions pertaining to project implementation. Thus, there are
potential conflicts between functional divisions and project teams. The
project manager must be given the responsibility and authority to resolve
various conflicts such that the established project policy and quality
standards will not be jeopardized. When contending issues of a more
fundamental nature are developed, they must be brought to the attention of a
high level in the management and be resolved expeditiously.
In general, the project manager's authority must be clearly documented as
well as defined, particularly in a matrix organization where the functional
division managers often retain certain authority over the personnel temporarily
assigned to a project. The following principles should be observed:
While a successful project manager must be a good leader, other members of
the project team must also learn to work together, whether they are assembled
from different divisions of the same organization or even from different
organizations. Some problems of interaction may arise initially when the team
members are unfamiliar with their own roles in the project team, particularly
for a large and complex project. These problems must be resolved quickly in
order to develop an effective, functioning team.
Many of the major issues in construction projects require effective
interventions by individuals, groups and organizations. The fundamental
challenge is to enhance communication among individuals, groups and
organizations so that obstacles in the way of improving interpersonal relations
may be removed. Some behavior science concepts are helpful in overcoming
communication difficulties that block cooperation and coordination. In very
large projects, professional behavior scientists may be necessary in diagnosing
the problems and advising the personnel working on the project. The power of
the organization should be used judiciously in resolving conflicts.
The major symptoms of interpersonal behavior problems can be detected by
experienced observers, and they are often the sources of serious communication
difficulties among participants in a project. For example, members of a
project team may avoid each other and withdraw from active interactions about
differences that need to be dealt with. They may attempt to criticize and
blame other individuals or groups when things go wrong. They may resent
suggestions for improvement, and become defensive to minimize culpability
rather than take the initiative to maximize achievements. All these actions
are detrimental to the project organization.
While these symptoms can occur to individuals at any organization, they are
compounded if the project team consists of individuals who are put together
from different organizations. Invariably, different organizations have
different cultures or modes of operation. Individuals from different groups
may not have a common loyalty and may prefer to expand their energy in the
directions most advantageous to themselves instead of the project team.
Therefore, no one should take it for granted that a project team will work
together harmoniously just because its members are placed physically together
in one location. On the contrary, it must be assumed that good communication
can be achieved only through the deliberate effort of the top management of
each organization contributing to the joint venture.
Although owners and contractors may have different perceptions on project
management for construction, they have a common interest in creating an
environment leading to successful projects in which performance quality,
completion time and final costs are within prescribed limits and tolerances.
It is interesting therefore to note the opinions of some leading contractors
and owners who were interviewed in 1984.(See J.E. Diekmann and K.B. Thrush,
Project Control in Design Engineering, A Report to the Construction Industry
Institute, The University of Texas at Austin, Texas, May 1986.)
From the responses of six contractors, the key factors cited for successful
projects are:
The responses of eight owners indicated that they did not always understand
the concerns of the contractors although they generally agreed with some of the
key factors for successful and unsuccessful projects cited by the contractors.
The significant findings of the interviews with owners are summarized as
follows:
From the results of these interviews, it is obvious that owners must be more
aware and involved in the process in order to generate favorable conditions for
successful projects. Design professionals and construction contractors must
provide better communication with each other and with the owner in project
implementation.
In the planning of facilities, it is important to recognize the close
relationship between design and construction. These processes can best be
viewed as an integrated system. Broadly speaking, design is a process of
creating the description of a new facility, usually represented by detailed
plans and specifications; construction planning is a process of identifying
activities and resources required to make the design a physical reality.
Hence, construction is the implementation of a design envisioned by architects
and engineers. In both design and construction, numerous operational tasks
must be performed with a variety of precedence and other relationships among
the different tasks.
Several characteristics are unique to the planning of constructed facilities
and should be kept in mind even at the very early stage of the project life
cycle. These include the following:
In an integrated system, the planning for both design and construction can
proceed almost simultaneously, examining various alternatives which are
desirable from both viewpoints and thus eliminating the necessity of extensive
revisions under the guise of value engineering. Furthermore, the review of
designs with regard to their constructibility can be carried out as the project
progresses from planning to design. For example, if the sequence of assembly
of a structure and the critical loadings on the partially assembled structure
during construction are carefully considered as a part of the overall
structural design, the impacts of the design on construction falsework and on
assembly details can be anticipated. However, if the design professionals are
expected to assume such responsibilities, they must be rewarded for sharing the
risks as well as for undertaking these additional tasks. Similarly, when
construction contractors are expected to take over the responsibilities of
engineers, such as devising a very elaborate scheme to erect an unconventional
structure, they too must be rewarded accordingly. As long as the owner does
not assume the responsibility for resolving this risk-reward dilemma, the
concept of a truly integrated system for design and construction cannot be
realized.
It is interesting to note that European owners are generally more open to
new technologies and to share risks with designers and contractors. In
particular, they are more willing to accept responsibilities for the unforeseen
subsurface conditions in geotechnical engineering. Consequently, the designers
and contractors are also more willing to introduce new techniques in order to
reduce the time and cost of construction. In European practice, owners
typically present contractors with a conceptual design, and contractors prepare
detailed designs, which are checked by the owner's engineers. Those detailed
designs may be alternate designs, and specialty contractors may also prepare
detailed alternate designs.
Example 3-1: Proposed Responsibility for Shop Drawings
The willingness to assume responsibilities does not come easily from any
party in the current litigious climate of the construction industry in the
United States. On the other hand, if owner, architect, engineer, contractor
and other groups that represent parts of the industry do not jointly fix the
responsibilities of various tasks to appropriate parties, the standards of
practice will eventually be set by court decisions. In an attempt to provide a
guide to the entire spectrum of participants in a construction project, the
American Society of Civil Engineers issued a preliminary edition of a Manual of
Professional Practice for Quality in the Constructed Project in early 1988.
After an 18-month period for trial use and comment, a final version is expected
to be published as recommended standards for industry-wide adoption.
Hopefully, this manual will help bring a turn around of the fragmentation of
activities in the design and construction process.
Shop drawings represent the assembly details for erecting a structure which
should reflect the intent and rationale of the original structural design.
They are prepared by the construction contractor and reviewed by the design
professional. However, since the responsibility for preparing shop drawings
was traditionally assigned to construction contractors, design professionals
took the view that the review process was advisory and assumed no
responsibility for their accuracy. This justification was ruled unacceptable
by a court in connection with the walkway failure at the Hyatt Hotel in Kansas
City in 1985. In preparing the ASCE Manual of Professional Practice for
Quality in the Constructed Project, the responsibilities for preparation of
shop drawings proved to be the most difficult to develop.(See "ASCE Unveils
Quality Manual", ENR, November 5, 1987, p. 14) The reason for this situation
is not difficult to fathom since the responsibilities for the task are
diffused, and all parties must agree to the new responsibilities assigned to
each in the recommended risk-reward relations shown in Table 3-1.
Traditionally, the owner is not involved in the preparation and review of
shop drawings, and perhaps is even unaware of any potential problems. In the
recommended practice, the owner is required to take responsibility for
providing adequate time and funding, including approval of scheduling, in order
to allow the design professionals and construction contractors to perform
satisfactorily.
~!^!~Responsible Party
~!^!~~!^!~Design~!^!~Construction
Task~!^!~Owner~!^!~Professional~!^!~Contractor
Provide adequate time and funding for shop~!^!~Prime
drawing preparation and review
Specify that drawings be prepared~!^!~Review~!^!~Prime
by professional engineer
Do structural design~!^!~~!^!~Prime
Provide loading requirements~!^!~~!^!~Prime
Specify shop drawing requirements~!^!~Review~!^!~Prime
Provide for structural design of~!^!~~!^!~~!^!~Prime
connections by engineer
Approve scheduling~!^!~Prime~!^!~Advise~!^!~Advise
Provide shop drawings~!^!~~!^!~~!^!~Prime
and submit on schedule
Make timely reviews~!^!~~!^!~Prime
Accept responsibility for~!^!~~!^!~~!^!~Prime
construction bracing, shoring, constructibility
tolerances, fit and detail dimensions.
Example 3-2: Model Metro Project in Milan, Italy(See V. Fairweather,
"Milan's Model Metro", Civil Engineering, December 1987, pp. 40-43.)
Under Italian law, unforeseen subsurface conditions are the owner's
responsibility, not the contractor's. This is a striking difference from U.S.
construction practice where changed conditions clauses and claims and the
adequacy of prebid site investigations are points of contention. In effect,
the Italian law means that the owner assumes those risks. But under the same
law, a contractor may elect to assume the risks in order to lower the bid price
and thereby beat the competition.
According to the Technical Director of Rodio, the Milan-based contractor
which is heavily involved in the grouting job for tunneling in the Model Metro
project in Milan, Italy, there are two typical contractual arrangements for
specialized subcontractor firms such as theirs. One is to work on a unit price
basis with no responsibility for the design. The other is what he calls the
"nominated subcontractor" or turnkey method: prequalified subcontractors offer
their own designs and guarantee the price, quality, quantities, and, if they
wish, the risks of unforeseen conditions.
At the beginning of the Milan metro project, the Rodio contract ratio was
50/50 unit price and turnkey. The firm convinced the metro owners that they
would save money with the turnkey approach, and the ratio became 80% turnkey.
What's more, in the work packages where Rodio worked with other grouting
specialists, those subcontractors paid Rodio a fee to assume all risks for
unforeseen conditions.
Under these circumstances, it was critical that the firm should know the
subsurface conditions as precisely as possible, which was a major reason why
the firm developed a computerized electronic sensing program to predict
stratigraphy and thus control grout mixes, pressures and, most important,
quantities.
The planning for a construction project begins with the generation of
concepts for a facility which will meet market demands and owner needs.
Innovative concepts in design are highly valued not for their own sake but for
their contributions to reducing costs and to the improvement of aesthetics,
comfort or convenience as embodied in a well-designed facility. However, the
constructor as well as the design professionals must have an appreciation and
full understanding of the technological complexities often associated with
innovative designs in order to provide a safe and sound facility. Since these
concepts are often preliminary or tentative, screening studies are carried out
to determine the overall technological viability and economic attractiveness
without pursuing these concepts in great detail. Because of the ambiguity of
the objectives and the uncertainty of external events, screening studies call
for uninhibited innovation in creating new concepts and judicious judgment in
selecting the appropriate ones for further consideration.
One of the most important aspects of design innovation is the necessity of
communication in the design/construction partnership. In the case of bridge
design, it can be illustrated by the following quotation from Lin and Gerwick
concerning bridge construction: (See T.Y. Lin and B.G. Gerwick, Jr. "Design of
Long Span Concrete Bridges with Special References to Prestressing, Precasting,
Structural Behavior and Economics," ACI Publication SP-23, First International
Symposium, 1969, pp. 693-704)
Innovative design concepts must be tested for technological feasibility.
Three levels of technology are of special concern: technological requirements
for operation or production, design resources and construction technology. The
first refers to the new technologies that may be introduced in a facility which
is used for a certain type of production such as chemical processing or nuclear
power generation. The second refers to the design capabilities that are
available to the designers, such as new computational methods or new materials.
The third refers to new technologies which can be adopted to construct the
facility, such as new equipment or new construction methods.
A new facility may involve complex new technology for operation in hostile
environments such as severe climate or restricted accessibility. Large
projects with unprecedented demands for resources such as labor supply,
material and infrastructure may also call for careful technological feasibility
studies. Major elements in a feasibility study on production technology should
include, but are not limited to, the following:
An example of innovative design for operation and production is the use of
entropy concepts for the design of integrated chemical processes. Simple
calculations can be used to indicate the minimum energy requirements and the
least number of heat exchange units to achieve desired objectives. The result
is a new incentive and criterion for designers to achieve more effective
designs. Numerous applications of the new methodology has shown its efficacy
in reducing both energy costs and construction expenditures.[See Linnhoff, B.,
D.W. Townsend, D. Boland, G.F. Hewitt, B.E.A. Thomas, A.R. Guy, and R.H.
Marsland, User Guide on Process Integration for the Efficient Use of Energy,
Institution of Chemical Engineers, Rugby, Warks., England, 1982.] This is a
case in which innovative design is not a matter of trading-off operating and
capital costs, but better designs can simultaneously achieve improvements in
both objectives.
The choice of construction technology and method involves both strategic
and tactical decisions about appropriate technologies and the best sequencing
of operations. For example, the extent to which prefabricated facility
components will be used represents a strategic construction decision. In
turn, prefabrication of components might be accomplished off-site in existing
manufacturing facilities or a temporary, on-site fabrication plant might be
used. Another example of a strategic decision is whether to install mechanical
equipment in place early in the construction process or at an intermediate
stage. Strategic decisions of this sort should be integrated with the process
of facility design in many cases. At the tactical level, detailed decisions
about how to accomplish particular tasks are required, and such decisions can
often be made in the field.
Construction planning should be a major concern in the development of
facility designs, in the preparation of cost estimates, and in forming bids by
contractors. Unfortunately, planning for the construction of a facility is
often treated as an after thought by design professionals. This contrasts with
manufacturing practices in which the assembly of devices is a major concern in
design. Design to insure ease of assembly or construction should be a major
concern of engineers and architects. As the Business Roundtable noted, "All
too often chances to cut schedule time and costs are lost because construction
operates as a production process separated by a chasm from financial planning,
scheduling, and engineering or architectural design. Too many engineers,
separated from field experience, are not up to date about how to build what
they design, or how to design so structures and equipment can be erected most
efficiently."["More Construction for the Money," Summary Report of the
Construction Industry Cost Effectiveness Project, The Business Roundtable, New
York, 1983, pg. 30.]
Example 3-3: Innovative use of structural frames for buildings[See "The
Quiet Revolution in Skyscraper Design, " Civil Engineering, May 1983, pp.
54-59.]
The structural design of skyscrapers offers an example of innovation in
overcoming the barrier of high costs for tall buildings by making use of new
design capabilities. A revolutionary concept in skyscraper design was
introduced in the 1960's by Fazlur Khan who argued that, for a building of a
given height, there is an appropriate structural system which would produce the
most efficient use of the material.
Before 1965, most skyscrapers were steel rigid frames. However, Fazlur Khan
believed that it was uneconomical to construct all office buildings of rigid
frames, and proposed an array of appropriate structural systems for steel
buildings of specified heights as shown in Figure 3-0. By choosing an
appropriate structural system, an engineer can use structural materials more
efficiently. For example, the 60-story Chase Manhatten Building in New York
used about 60 pounds per square foot of steel in its rigid frame structure,
while the 100-story John Hancock Center in Chicago used only 30 pounds per
square foot for a trusted tube system. At the time the Chase Manhatten
Building was constructed, no bracing was used to stiffen the core of a rigid
frame building because design engineers did not have the computing tools to do
the complex mathematical analysis associated with core bracing.
Innovation is often regarded as the engine which can introduce construction
economies and advance labor productivity. This is obviously true for certain
types of innovations in industrial production technologies, design
capabilities, and construction equipment and methods. However, there are also
limitations due to the economic infeasibility of such innovations, particularly
in the segments of construction industry which are more fragmented and permit
ease of entry, as in the construction of residential housing.
Market demand and firm size play an important role in this regard. If a
builder is to construct a larger number of similar units of buildings, the cost
per unit may be reduced. This relationship between the market demand and the
total cost of production may be illustrated schematically as in Figure 3-0. An
initial threshold or fixed cost F is incurred to allow any production. Beyond
this threshold cost, total cost increases faster than the units of output but
at a decreasing rate. At each point on this total cost curve, the average cost
is represented by the slope of a line from the origin to the point on the
curve. At a point H, the average cost per unit is at a minimum. Beyond H to
the right, the total cost again increases faster than the units of output and
at an increasing rate. When the rate of change of the average cost slope is
decreasing or constant as between 0 and H on the curve, the range between 0 and
H is said to be increasing return to scale; when the rate of change of the
average cost slope is increasing as beyond H to the right, the region is said
to be decreasing return to scale. Thus, if fewer than h units are
constructed, the unit price will be higher than that of exactly h units. On
the other hand, the unit price will increase again if more than h units are
constructed.
Nowhere is the effect of market demand and total cost more evident than in
residential housing.[See J. Landis, "Why Homebuilders Don't Innovate," Built
Environment, Vol. 8, No. 1, 1982, pp. 46-53.] The housing segment in the
last few decades accepted many innovative technical improvements in building
materials which were promoted by material suppliers. Since material suppliers
provide products to a large number of homebuilders and others, they are in a
better position to exploit production economies of scale and to support new
product development. However, homebuilders themselves have not been as
successful in making the most fundamental form of innovation which encompasses
changes in the technological process of homebuilding by shifting the mixture of
labor and material inputs, such as substituting large scale off-site
prefabrication for on-site assembly.
There are several major barriers to innovation in the technological process
of homebuilding, including demand instability, industrial fragmentation, and
building codes. Since market demand for new homes follows demographic trends
and other socio-economic conditions, the variation in home building has been
anything but regular. The profitability of the homebuilding industry has
closely matched aggregate output levels. Since entry and exist from the
industry are relatively easy, it is not uncommon during periods of slack demand
to find builders leaving the market or suspending their operations until better
times. The inconsistent levels of retained earnings over a period of years,
even among the more established builders, are likely to discourage support for
research and development efforts which are required to nurture innovation.
Furthermore, because the homebuilding industry is fragmented with a vast
majority of homebuilders active only in local regions, the typical homebuilder
finds it excessively expensive to experiment with new designs. The potential
costs of a failure or even a moderately successful innovation would outweigh
the expected benefits of all but the most successful innovations. Variation in
local building codes has also caused inefficiencies although repeated attempts
have been made to standardize building codes.
In addition to the scale economies visible within a sector of the
construction market, there are also possibilities for scale economies in
individual facility. For example, the relationship between the size of a
building (expressed in square feet) and the input labor (expressed in
laborhours per square foot) varies for different types and sizes of buildings.
As shown in Figure 3-0, these relationships for several types of buildings
exhibit different characteristics.<See P.J. Cassimates, Economics of the
Construction Industry, National Industry Conference Board (SBE No. 111),
1969.> The labor hours per square foot decline as the size of facility
increases for houses, public housing and public buildings. However, the labor
hours per square foot almost remains constant for all sizes of school buildings
and increases as the size of a hospital facility increases.
Example 3-4: Use of new materials(See F. Moavenzadeh, "Construction's High
Technology Revolution," Technology Review, October, 1985, pp. 32-39.)
In recent years, an almost entirely new set of materials is emerging for
construction, largely from the aerospace and electronics industries. These
materials were developed from new knowledge about the structure and properties
of materials as well as new techniques for altering existing materials.
Additives to traditional materials such as concrete and steel are particularly
prominent. For example, it has been known for some time that polymers would
increase concrete strength, water resistance and ability to insulate when they
are added to the cement. However, their use has been limited by their costs
since they have had to replace as much as 10 percent of the cement to be
effective. However, Swedish researchers have helped reduce costs by using
polymer microspheres 8 millionths of an inch across, which occupy less than 1
percent of the cement. Concretes made with these microspheres meet even the
strict standards for offshore structures in the North Sea. Research on
micro-additives will probably produce useful concretes for repairing road and
bridges as well.
Example 3-5: Habitat(This example is based on a review of the project 20
years after its completion. See The New York Times, July 26, 1987, Sec. 8,
pg. 1.)
Habitat was an experimental residential complex designed by Moshe Safdie and
constructed in modules with an on-site factory for the 1967 Exposition in
Montreal, Canada. The original proposal called for a self-contained community
with 1000 to 2000 apartments, but was scaled down to a single 10-story complex
with 158 units built on Cite' du Havre, a landfill peninsula in Montreal's
inner harbor. The project was budgeted for $11.5 million, and almost half of
that was spent building the factories and acquiring special cranes. This
start-up cost was absurdly high for a single 10-story apartment complex, but
might have been justified in the original proposal for a whole community. As a
result of the small scale, development costs amounted to $85,500 for an
apartment at a time when average Montreal apartments were selling for $10,000
to $16,000. However, even if mass production was possible, steep increases in
urban land costs and interest rates in recent years would have overshadowed the
projected savings from production. Thus, an innovation which was hailed at one
time as the solution for urban housing has not materialized due to a
combination of economic factors.
While the conceptual design process may be formal or informal, it can be
characterized by a series of actions: formulation, analysis, search, decision,
specification, and modification. However, at the early stage in the
development of a new project, these actions are highly interactive as
illustrated in Figure 3-0.[See R.W. Jensen and C.C. Tonies (Editors), Software
Engineering, Prentice-Hall, Inc., Englewood Cliffs, NJ, 1979, p. 22.] Many
iterations of redesign are expected to refine the functional requirements,
design concepts and financial constraints, even though the analytic tools
applied to the solution of the problem at this stage may be very crude.
The series of actions taken in the conceptual design process may be
described as follows:
As the project moves from conceptual planning to detailed design, the design
process becomes more formal. In general, the actions of formulation, analysis,
search, decision, specification and modification still hold, but they represent
specific steps with less random interactions in detailed design. The design
methodology thus formalized can be applied to a variety of design problems.
For example, the analogy of the schematic diagrams of the structural design
process and of the computer program development process is shown in Figure
3-0.<See S.J. Fenves, "Computer Applications," in Structural Engineering
Handbook, (Gaylord, E. and C. Gaylord, Editors), McGraw-Hill Book Co., New
York, NY, 1979.>
The basic approach to design relies on decomposition and integration. Since
design problems are large and complex, they have to be decomposed to yield
subproblems that are small enough to solve. There are numerous alternative
ways to decompose design problems, such as decomposition by functions of the
facility, by spatial locations of its parts, or by links of various functions
or parts. Solutions to subproblems must be integrated into an overall
solution. The integration often creates conceptual conflicts which must be
identified and corrected. A hierarchical structure with an appropriate number
of levels may be used for the decomposition of a design problem to subproblems.
For example, in the structural design of a multistory building, the building
may be decomposed into floors, and each floor may in turn be decomposed into
separate areas. Thus, a hierarchy representing the levels of building, floor
and area is formed.
Different design styles may be used. The adoption of a particular style
often depends on factors such as time pressure or available design tools, as
well as the nature of the design problem. Examples of different styles are:
The objective of functional design for a proposed facility is to treat the
facility as a complex system of interrelated spaces which are organized
systematically according to the functions to be performed in these spaces in
order to serve a collection of needs. The arrangement of physical spaces can
be viewed as an iterative design process to find a suitable floor plan to
facilitate the movement of people and goods associated with the operations
intended.
A designer often relies on a heuristic approach, i.e., applying selected
rules or strategies serving to stimulate the investigation in search for a
solution. The heuristic approach used in arranging spatial layouts for
facilities is based generally on the following considerations:
Consider, for example, an integrated functional design for a proposed
hospital.[See T. Au, E.W. Parti and A.K.C. Wong, "Computer Applications for
Health Care Facility Design," Computers in Biology and Medicine, Vol. 1, No.
4, 1971, pp. 299-316.] Since the responsibilities for satisfying various needs
in a hospital are divided among different groups of personnel within the
hospital administrative structure, a hierarchy of functions corresponding to
different levels of responsibilities is proposed in the systematic organization
of hospital functions. In this model, the functions of a hospital system are
decomposed into a hierarchy of several levels:
In the integrated functional design of hospitals, the connection between
physical spaces and functions is most easily made at the lowest level of the
hierarchy, and then extended upward to the next higher level. For example, a
bed is a physical object immediately related to the activity of a patient. A
set of furniture consisting of a bed, a night table and an armchair arranged
comfortably in a zone indicates the sphere of private activities for a patient
in a room with multiple occupancy. Thus, the spatial representation of a
hospital can be organized in stages starting from the lowest level and moving
to the top. In each step of the organization process, an element (space or
function) under consideration can be related directly to the elements at the
levels above it, to those at the levels below it, and to those within the same
level.
Since the primary factor relating spaces is the movement of people and
supplies, the objective of arranging spaces is the minimization of movement
within the hospital. On the other hand, the internal environmental factors
such as atmospheric conditions (pressure, temperature, relative humidity, odor
and particle pollution), sound, light and fire protection produce constraining
effects on the arrangement of spaces since certain spaces cannot be placed
adjacent to other spaces because of different requirements in environmental
conditions. The consideration of logistics is important at all levels of the
hospital system. For example, the travel patterns between objects in a zone or
those between zones in a room are frequently equally important for devising an
effective design. On the other hand, the adjacency desirability matrix based
upon environmental conditions will not be important for organization of
functional elements below the room level since a room is the lowest level that
can provide a physical barrier to contain desirable environmental conditions.
Hence, the organization of functions for a new hospital can be carried out
through an interactive process, starting from the functional elements at the
lowest level that is regarded as stable by the designer, and moving step by
step up to the top level of the hierarchy. Due to the strong correlation
between functions and the physical spaces in which they are performed, the
arrangement of physical spaces for accommodating the functions will also follow
the same iterative process. Once a satisfactory spatial arrangement is
achieved, the hospital design is completed by the selection of suitable
building components which complement the spatial arrangement.
Example 3-6: Top-down design style
In the functional design of a hospital, the designer may begin with a
"reference model", i.e. the spatial layouts of existing hospitals of similar
size and service requirements. On the basis of past experience, spaces are
allocated to various divisions as shown schematically in Figure 3-0. The space
in each division is then divided further for various departments in the
division, and all the way down the line of the hierarchy. In every step along
the way, the pertinent information of the elements immediately below the level
under consideration will be assessed in order to provide input for making
necessary adjustments at the current level if necessary. The major drawback of
the top-down design style is that the connection between physical spaces and
functions at lower levels cannot be easily anticipated. Consequently, the new
design is essentially based on the intuition and experience of the designer
rather than an objective analysis of the functions and space needs of the
facility. Its greatest attraction is its simplicity which keeps the time and
cost of design relatively low.
Example 3-7: Bottom-up design style
A multi-purpose examination suite in a hospital is used as an illustration
of bottom-up design style. In Figure 3-0, the most basic elements (furniture)
are first organized into zones which make up the room. Thus the size of the
room is determined by spatial layout required to perform the desired services.
Finally, the suite is defined by the rooms which are parts of the multi-purpose
examination suite.
The structural design of complex engineering systems generally involves both
synthesis and analysis. Synthesis is an inductive process while analysis is a
deductive process. The activities in synthesis are often described as an art
rather than a science, and are regarded more akin to creativity than to
knowledge. The conception of a new structural system is by and large a matter
of subjective decision since there is no established procedure for generating
innovative and highly successful alternatives. The initial selection of a
workable system from numerous possible alternatives relies heavily on the
judicious judgment of the designer. Once a structural system is selected, it
must be subjected to vigorous analysis to insure that it can sustain the
demands in its environment. In addition, compatibility of the structural
system with mechanical equipment and piping must be assured.
For traditional types of structures such as office buildings, there are
standard systems derived from the past experience of many designers. However,
in many situations, special systems must be developed to meet the specified
requirements. The choice of materials for a structure depends not only on the
suitability of materials and their influence on the form of the structure. For
example, in the design of an airplane hangar, a steel skeleton frame may be
selected because a similar frame in reinforced concrete will limit the span of
the structure owing to its unfavorable ratio or resistance to weight. However,
if a thin-shelled roof is adopted, reinforced concrete may prove to be more
suitable than steel. Thus, the interplay of the structural forms and materials
affects the selection of a structural system, which in turn may influence the
method of construction including the use of falsework.
Example 3-8: Steel frame supporting a turbo-blower(The authors are
indebted to E. D'Appolonia for suggesting this example.)
The design of a structural frame supporting a turbo-blower supplying
pressurized air to a blast furnace in a steel mill can be used to illustrate
the structural design process. As shown in Figure 3-0, the turbo-blower
consists of a turbine and a blower linked to an air inlet stack. Since the
vibration of the turbo-blower is a major concern to its operation, a
preliminary investigation calls for a supporting frame which is separated from
the structural frame of the building. An analysis of the vibration
characteristics of the turbo-blower indicates that the lowest mode of vibration
consists of independent vibration of the turbine shaft and the blower shaft,
with higher modes for the coupled turbo-blower system when both shafts vibrate
either in-phase or out-of-phase. Consequently, a steel frame with separate
units for the blower side and the turbine side is selected. The columns of the
steel frame are mounted on pile foundation and all joints of the steel frame
are welded to reduce the vibration levels.
Since the structural steel frame also supports a condenser, an air inlet and
exhaust, and a steam inlet and exhaust in addition to the turbo-blower, a
static analysis is made to size its members to support all applied loads.
Then, a dynamic analysis is conducted to determine the vibration
characteristics of the system incorporating the structural steel frame and the
turbo-blower. When the limiting conditions for static loads and natural
frequencies of vibration are met, the design is accepted as satisfactory.
Example 3-9: Multiple hierarchy descriptions of projects
In the previous section, a hierarchy of functional spaces was suggested for
describing a facility. This description is appropriate for functional design
of spaces and processes within a building, but may be inadequate as a view of
the facility's structural systems. A hierarchy suitable for this purpose might
divide elements into structural functions such as slabs, walls, frames,
footings, piles or mats. Lower levels of the hierarchy would describe
individual design elements. For example, frames would be made up of column,
beam and diagonal groups which, in turn, are composed of individual structural
elements. These individual structural elements comprise the limits on
functional spaces such as rooms in a different hierarchical perspective.
Designers typically will initiate a view appropriate for their own concerns,
and these different hierarchical views must be synthesized to insure
consistency and adequacy of the overall design.
Since construction is site specific, it is very important to investigate the
subsurface conditions which often influence the design of a facility as well as
its foundation. The uncertainty in the design is particularly acute in
geotechnical engineering so that the assignment of risks in this area should be
a major concern. Since the degree of uncertainty in a project is perceived
differently by different parties involved in a project, the assignment of
unquantifiable risks arising from numerous unknowns to the owner, engineer and
contractor is inherently difficult. It is no wonder that courts or arbitrators
are often asked to distribute equitably a risk to parties who do not perceive
the same risks and do not want to assume a disproportionate share of such
risks.
Example 3-10: Design of a tie-back retaining wall(See E. D'Appolonia,
R. Alperstein and D.J. D'Appolonia, "Behavior of Colluvial Slope", ASCE Journal
of Soil Mechanics and Foundations Division, Vol. 93, No. SM4, 1967, pp.
447-473.)
This example describes the use of a tie-back retaining wall built in the
1960's when such construction was uncommon and posed a considerable risk. The
engineer designing it and the owner were aware of the risk because of
potentially extreme financial losses from both remedial and litigation costs in
the event that the retaining wall failed and permitted a failure of the slope.
But the benefits were perceived as being worth the risk--benefits to the owner
in terms of both lower cost and shorter schedule, and benefits to the engineer
in terms of professional satisfaction in meeting the owner's needs and solving
what appeared to be an insurmountable technical problem.
The tie-back retaining wall was designed to permit a cut in a hillside to
provide additional space for the expansion of a steel-making facility. Figure
3-0 shows a cross section of the original hillside located in an urban area.
Numerous residential dwellings were located on top of the hill which would have
been prohibitively costly or perhaps impossible to remove to permit regrading
of the hillside to push back the toe of the slope. The only realistic way of
accomplishing the desired goal was to attempt to remove the toe of the existing
slope and use a tie-back retaining wall to stabilize the slope as shown in
Figure 3-0.
A commitment was made by both the owner and the engineer to accomplish what
was a common goal. The engineer made a commitment to design and construct the
wall in a manner which permitted a real-time evaluation of problems and the
ability to take mitigating measures throughout the construction of the wall.
The owner made a commitment to give the engineer both the professional latitude
and resources required to perform his work. A design-construct contract was
negotiated whereby the design could be modified as actual conditions were
encountered during construction. But even with all of the planning,
investigation and design efforts, there still remained a sizable risk of
failure.
The wall was successfully built--not according to a pre-devised plan which
went smoothly, and not without numerous problems to be resolved as unexpected
groundwater and geological conditions were encountered. Estimated costs were
exceeded as each unexpected condition was addressed. But there were no
construction delays and their attendant costs as disputes over changed
conditions and contract terms were reconciled. There were no costs for legal
fees arising from litigation nor increased interest costs as construction
stopped while disputes were litigated. The owner paid more than was estimated,
but not more than was necessary and not as much as if he had to acquire the
property at the top of the hill to regrade the slope. In addition, the owner
was able to attain the desired facility expansion in far less time than by any
other method.
As a result of the success of this experience and others, the use of
tie-back retaining walls has become a routine practice.
While the general information about the construction site is usually
available at the planning stage of a project, it is important for the design
professionals and construction manager as well as the contractor to visit the
site. Each group will be benefited by first-hand knowledge acquired in the
field.
For design professionals, an examination of the topography may focus their
attention to the layout of a facility on the site for maximum use of space in
compliance with various regulatory restrictions. In the case of industrial
plants, the production or processing design and operation often dictate the
site layout. A poor layout can cause construction problems such as inadequate
space for staging, limited access for materials and personnel, and restrictions
on the use of certain construction methods. Thus, design and construction
inputs are important in the layout of a facility.
The construction manager and the contractor must visit the site to gain some
insight in preparing or evaluating the bid package for the project. They can
verify access roads and water, electrical and other service utilities in the
immediate vicinity, with the view of finding suitable locations for erecting
temporary facilities and the field office. They can also observe any
interferences of existing facilities with construction and develop a plan for
site security during construction.
In examining site conditions, particular attention must be paid to
environmental factors such as drainage, groundwater and the possibility of
floods. Of particular concern is the possible presence of hazardous waste
materials from previous uses. Cleaning up or controlling hazardous wastes can
be extremely expensive.
Example 3-11: Groundwater Pollution from a Landfill(The material in this
example is adapted from A.L. Tolman, A. P. Ballestero, W.W. Beck, G.H. Emrich,
"Guidance Manual for Minimizing Pollution from Waste Disposal Sites," Report to
the Municipal Environmental Research Laboratory, U.S. Environmental Protection
Agency, EPA-600/2-78-142, August 1978.)
The presence of waste deposits on a potential construction site can have
substantial impacts on the surrounding area. Under existing environmental
regulations in the United States, the responsibility for cleaning up or
otherwise controlling wastes generally resides with the owner of a facility in
conjunction with any outstanding insurance coverage.
A typical example of a waste problem is illustrated in Figure 3-0. In this
figure, a small pushover burning dump was located in a depression on a slope.
The landfill consisted of general refuse and was covered by a very sandy
material. The inevitable infiltration of water from the surface or from the
groundwater into the landfill will result in vertical or horizontal percolation
of leachable ions and organic contamination. This leachate would be odorous
and potentially hazardous in water. The pollutant would show up as seepage
downhill, as pollution in surface streams, or as pollution entering the
regional groundwater.
Before new construction could proceed, this landfill site would have to be
controlled or removed. Typical control methods might involve:
Value engineering may be broadly defined as an organized approach in
identifying unnecessary costs in design and construction and in soliciting or
proposing alternative design or construction technology to reduce costs without
sacrificing quality or performance requirements. It usually involves the steps
of gathering pertinent information, searching for creative ideas, evaluating
the promising alternatives, and proposing a more cost effective alternative.
This approach is usually applied at the beginning of the construction phase of
the project life cycle.
The use of value engineering in the public sector of construction has been
fostered by legislation and government regulation, but the approach has not
been widely adopted in the private sector of construction. One explanation may
lie in the difference in practice of engineering design services in the public
and private sectors. In the public sector, the fee for design services is
tightly monitored against the "market price," or may even be based on the
lowest bid for service. Such a practice in setting professional fees
encourages the design professionals to adopt known and tried designs and
construction technologies without giving much thought to alternatives that are
innovative but risky. Contractors are willing to examine such alternatives
when offered incentives for sharing the savings by owners. In the private
sector, the owner has the freedom to offer such incentives to design
professionals as well as the contractors without being concerned about the
appearance of favoritism in engaging professional services.
Another source of cost savings from value engineering is the ability of
contractors to take advantage of proprietary or unusual techniques and
knowledge specific to the contractor's firm. For example, a contractor may
have much more experience with a particular method of tunneling that is not
specified in the original design and, because of this experience, the
alternative method may be less expensive. In advance of a bidding competition,
a design professional does not know which contractor will undertake the
construction of a facility. Once a particular contractor is chosen, then
modifications to the construction technology or design may take advantage of
peculiar advantages of the contractor's organization.
As a final source of savings in value engineering, the contractor may offer
genuine new design or construction insights which have escaped the attention of
the design professional even if the latter is not restrained by the fee
structure to explore more alternatives. If the expertise of the contractor can
be utilized, of course, the best time to employ it is during the planning and
design phase of the project life cycle. That is why professional construction
management or integrated design/construction are often preferred by private
owners.
The development of a construction plan is very much analogous to the
development of a good facility design. The planner must weigh the costs and
reliability of different options while at the same time insuring technical
feasibility. Construction planning is more difficult in some ways since the
building process is dynamic as the site and the physical facility change over
time as construction proceeds. On the other hand, construction operations tend
to be fairly standard from one project to another, whereas structural or
foundation details might differ considerably from one facility to another.
Forming a good construction plan is an exceptionally challenging problem.
There are numerous possible plans available for any given project. While past
experience is a good guide to construction planning, each project is likely to
have special problems or opportunities that may require considerable ingenuity
and creativity to overcome or exploit. Unfortunately, it is quite difficult to
provide direct guidance concerning general procedures or strategies to form
good plans in all circumstances. There are some recommendations or issues that
can be addressed to describe the characteristics of good plans, but this does
not necessarily tell a planner how to discover a good plan. However, as in the
design process, strategies of decomposition in which planning is divided into
subproblems and hierarchical planning in which general activities are
repeatably subdivided into more specific tasks can be readily adopted in many
cases.
From the standpoint of construction contractors or the construction
divisions of large firms, the planning process for construction projects
consists of three stages that take place between the moment in which a planner
starts the plan for the construction of a facility to the moment in which the
evaluation of the final output of the construction process is finished.
The estimate stage involves the development of a cost and duration estimate
for the construction of a facility as part of the proposal of a contractor to
an owner. It is the stage in which assumptions of resource commitment to the
necessary activities to build the facility are made by a planner. A careful
and thorough analysis of different conditions imposed by the construction
project design and by site characteristics are taken into consideration to
determine the best estimate. The success of a contractor depends upon this
estimate, not only to obtain a job but also to construct the facility with the
highest profit. The planner has to look for the time-cost combination that
will allow the contractor to be successful in his commitment. The result of a
high estimate would be to lose the job, and the result of a low estimate could
be to win the job, but to lose money in the construction process. When changes
are done, they should improve the estimate, taking into account not only
present effects, but also future outcomes of succeeding activities. It is very
seldom the case in which the output of the construction process exactly echoes
the estimate offered to the owner.
In the monitoring and control stage of the construction process, the
construction manager has to keep constant track of both activities' durations
and ongoing costs. It is misleading to think that if the construction of the
facility is on schedule or ahead of schedule, the cost will also be on the
estimate or below the estimate, especially if several changes are made.
Constant evaluation is necessary until the construction of the facility is
complete. When work is finished in the construction process, and information
about it is provided to the planner, the third stage of the planning process
can begin.
The evaluation stage is the one in which results of the construction
process are matched against the estimate. A planner deals with this
uncertainty during the estimate stage. Only when the outcome of the
construction process is known is he/she able to evaluate the validity of the
estimate. It is in this last stage of the planning process that he or she
determines if the assumptions were correct. If they were not or if new
constraints emerge, he/she should introduce corresponding adjustments in future
planning.
Another approach to construction innovation is to apply the principles and
organizational solutions adopted for manufacturing. Industrialized
construction and pre-fabrication would involve transferring a significant
portion of construction operations from the construction site to more or less
remote sites where individual components of buildings and structures are
produced. Elements of facilities could be prefabricated off the erection site
and assembled by cranes and other lifting machinery.
There are a wide variety and degrees of introducing greater
industrialization to the construction process. Many components of constructed
facilities have always been manufactured, such as air conditioning units.
Lumber, piping and other individual components are manufactured to standard
sizes. Even temporary items such as forms for concrete can be assembled
off-site and transported for use. Reinforcing bars for concrete can also be
pre-cut and shaped to the desired configuration in a manufacturing plant or in
an automated plant located proximate to a construction site.
A major problem in extending the use of pre-fabricated units is the lack of
standardization for systems and building regulations.[For discussions of
industrialized building, see Bender, Richard, A Crack in the Rear View Mirror -
A View of Industrialized Building, Von Nostrand Reinhold Co., 1983;
Nutt-Powell, Thomas, E., Manufactured Homes: Making Sense of a Housing
Opportunity, Auburn House, 1982; or Warzawski, A., M. Avraham, and D. Carmel,
"Utilization of Precast Concrete Elements in Building," ASCE Journal of
Construction Engineering and Management, Vol. 110, No. CO4, 1984, pp.
476-485.] While designers have long adopted standard sizes for individual
components in designs, the adoption of standardized sub-assemblies is rarer.
Without standardization, the achievement of a large market and scale economies
of production in manufacturing may be impossible. An innovative and more
thorough industrialization of the entire building process may be a primary
source of construction cost savings in the future.
Example 3-12: Planning of pre-fabrication.
When might pre-fabricated components be used in preference to components
assembled on a construction site? A straightforward answer is to use
pre-fabricated components whenever their cost, including transportation, is
less than the cost of assembly on site. As an example, forms for concrete
panels might be transported to a construction site with reinforcing bars
already built in, necessary coatings applied to the forms, and even special
features such as electrical conduit already installed in the form. In some
cases, it might be less expensive to pre-fabricate and transport the entire
concrete panel to a manufacturing site. In contrast, traditional construction
practice would be to assemble all the different features of the panel on-site.
The relevant costs of these alternatives could be assessed during construction
planning to determine the lowest cost alternative.
In addition to the consideration of direct costs, a construction planner
should also consider some other aspects of this technology choice. First, the
planner must insure that pre-fabricated components will satisfy the relevant
building codes and regulations. Second, the relative quality of traditional
versus pre-fabricated components as experienced in the final facility should be
considered. Finally, the availability of components at the required time
during the construction process should also be considered.
Example 3-13: Impacts of building codes(See C.G. Field and S.R. Rivkin,
The Building Code Burden, Lexington Books, D.C. Heath and Co., Lexington, MA,
1975.)
Building codes originated as a part of the building regulatory process for
the safety and general welfare of the public. The source of all authority to
enact building codes is based on the police power of the state which may be
delegated by the state legislature to local government units. Consequently,
about 8,000 localities having their own building codes, either by following a
national model code or developing a local code. The lack of uniformity of
building codes may be attributed to a variety of reasons:
The lack of uniformity in building codes has serious impact on design and
construction as well as the regulatory process for buildings. Among the
significant factors are:
In the past twenty years, the computer has become an essential tool in
engineering, design, and accounting. The innovative designs of complicated
facilities cited in the previous sections would be impossible without the aid
of computer based analysis tools. By using general purpose analysis programs
to test alternative designs of complex structures such as petrochemical plants,
engineers are able to greatly improve initial designs. General purpose
accounting systems are also available and adopted in organizations to perform
routine bookkeeping and financial accounting chores. These applications
exploit the capability for computers to perform numerical calculations in a
pre-programmed fashion rapidly, inexpensively and accurately.
Despite these advances, the computer is often used as only an incidental
tool in the design, construction and project management processes. However,
new capabilities, systems and application programs are rapidly being adopted.
These are motivated in part by the remarkable improvement in computer hardware
capability coupled with a extraordinary decline in cost. New concepts in
computer design and in software are also contributing. For example, the
introduction of personal computers using microcircuitry has encouraged the
adoption of interactive programs because of the low cost and considerable
capability of the computer hardware. Personal computers available for several
thousand dollars in 1984 have essentially the same capability as expensive
mainframe computer systems of fifteen years earlier.
Computer graphics provide another pertinent example of a potentially
revolutionary mechanism for design and communication. Graphical
representations of both the physical and work activities on projects have been
essential tools in the construction industry for decades. However, manual
drafting of blueprints, plans and other diagrams is laborious and expensive.
Stand alone, computer aided drafting equipment has proved to be less expensive
and fully capable of producing the requiring drawings. More significantly, the
geometric information required for producing desired drawings might also be
used as a database for computer aided design and computer integrated
construction. Components of facilities can be represented as three dimensional
computer based solid models for this purpose. Geometric information forms
only one component of integrated design databases in which the computer can
assure consistency, completeness and compliance with relevant specifications
and constraints. Several approaches to integrated computer aided engineering
environments of this type have already been attempted.[See Rehak, Daniel R. and
L.A. Lopez, Computer Aided Engineering Problems and Prospects, Dept. of Civil
Engineering, University of Illinois, 1981.]
Computers are also being applied more and more extensively to non-analytical
and non-numerical tasks. For example, computer based specification writing
assistants are used to rapidly assemble sets of standard specifications or to
insert special clauses in the documentation of facility designs. As another
example, computerized transfer of information provides a means to avoid
laborious and error-prone transcription of project information. While most of
the traditional applications and research in computer aids have emphasized
numerical calculations, the use of computers will rapidly shift towards the
more prevalent and difficult problems of planning, communication, design and
management.
Knowledge based systems represent a prominent example of new software
approaches applicable to project management. These systems originally emerged
from research in artificial intelligence in which human cognitive processes
were modeled. In limited problem domains such as equipment configuration or
process control, knowledge based systems have been demonstrated to approach or
surpass the performance of human experts. The programs are marked by a
separation between the reasoning or "inference" engine program and the
representation of domain specific knowledge. As a result, system developers
need not specify complete problem solving strategies (or algorithms) for
particular problems. This characteristic of knowledge based systems make them
particularly useful in the ill-structured domains of design and project
management. Chapter 15 will discuss knowledge based systems in greater detail.
Computer program assistants will soon become ubiquitous in virtually all
project management organizations. The challenge for managers is to use the new
tools in an effective fashion. Computer intensive work environments should be
structured to aid and to amplify the capabilities of managers rather than to
divert attention from real problems such as worker motivation.
Good project management in construction must vigorously pursue the efficient
utilization of labor, material and equipment. Improvement of labor
productivity should be a major and continual concern of those who are
responsible for cost control of constructed facilities. Material handling,
which includes procurement, inventory, shop fabrication and field servicing,
requires special attention for cost reduction. The use of new equipment and
innovative methods has made possible wholesale changes in construction
technologies in recent decades. Organizations which do not recognize the
impact of various innovations and have not adapted to changing environments
have justifiably been forced out of the mainstream of construction activities.
Observing the trends in construction technology presents a very mixed and
ambiguous picture. On the one hand, many of the techniques and materials used
for construction are essentially unchanged since the introduction of
mechanization in the early part of the twentieth century. For example, a
history of the Panama Canal construction from 1904 to 1914 argues that:
The United States construction industry often points to factors which cannot
be controlled by the industry as a major explanatory factor in cost increases
and lack of technical innovation. These include the imposition of restrictions
for protection of the environment and historical districts, requirements for
community participation in major construction projects, labor laws which allow
union strikes to become a source of disruption, regulatory policies including
building codes and zoning ordinances, and tax laws which inhibit construction
abroad. However, the construction industry should bear a large share of blame
for not realizing earlier that the technological edge held by the large U.S.
construction firms has eroded in face of stiff foreign competition. Many past
practices, which were tolerated when U.S. contractors had a technological lead,
must now be changed in the face of stiff competition. Otherwise, the U.S.
construction industry will continue to find itself in trouble.
With a strong technological base, there is no reason why the construction
industry cannot catch up and reassert itself to meet competition wherever it
may be. Individual design and/or construction firms must explore new ways to
improve productivity for the future. Of course, operational planning for
construction projects is still important, but such tactical planning has
limitations and may soon reach the point of diminishing return because much
that can be wrung out of the existing practices have already been tried. What
is needed the most is strategic planning to usher in a revolution which can
improve productivity by an order of magnitude or more. Strategic planning
should look at opportunities and ask whether there are potential options along
which new goals may be sought on the basis of existing resources. No one can
be certain about the success of various development options for the design
professions and the construction industry. However, with the availability of
today's high technology, some options have good potential of success because of
the social and economic necessity which will eventually push barriers aside.
Ultimately, decisions for action, not plans, will dictate future outcomes.
Productivity in construction is often broadly defined as output per labor
hour. Since labor constitutes a large part of the construction cost and the
quantity of labor hours in performing a task in construction is more
susceptible to the influence of management than are materials or capital, this
productivity measure is often referred to as labor productivity. However, it
is important to note that labor productivity is a measure of the overall
effectiveness of an operating system in utilizing labor, equipment and capital
to convert labor efforts into useful output, and is not a measure of the
capabilities of labor alone. For example, by investing in a piece of new
equipment to perform certain tasks in construction, output may be increased for
the same number of labor hours, thus resulting in higher labor productivity.
Construction output may be expressed in terms of functional units or
constant dollars. In the former case, labor productivity is associated with
units of product per labor hour, such as cubic yards of concrete placed per
hour or miles of highway paved per hour. In the latter case, labor
productivity is identified with value of construction in constant dollars per
labor hour.
Contractors and owners are often concerned with the labor activity at job
sites. For this purpose, it is convenient to express labor productivity as
functional units per labor hour for each type of construction task. However,
even for such specific purposes, different levels of measure may be used. For
example, cubic yards of concrete placed per hour is a lower level of measure
than miles of highway paved per hour. Lower-level measures are more useful for
monitoring individual activities, while higher-level measures may be more
convenient for developing industry-wide standards of performance.
While each contractor or owner is free to use its own system to measure
labor productivity at a site, it is a good practice to set up a system which
can be used to track productivity trends over time and in varied locations.
Considerable efforts are required to collect information regionally or
nationally over a number of years to produce such results. The productivity
indices compiled from statistical data should include parameters such as the
performance of major crafts, effects of project size, type and location, and
other major project influences.
In order to develop industry-wide standards of performance, there must be a
general agreement on the measures to be useful for compiling data. Then, the
job site productivity data collected by various contractors and owners can be
correlated and analyzed to develop certain measures for each of the major
segment of the construction industry. Thus, a contractor or owner can compare
its performance with that of the industry average.
Because of the diversity of the construction industry, a single index for
the entire industry is neither meaningful nor reliable. Productivity indices
may be developed for major segments of the construction industry nationwide if
reliable statistical data can be obtained for separate industrial segments.
For this general type of productivity measure, it is more convenient to express
labor productivity as constant dollars per labor hours since dollar values are
more easily aggregated from a large amount of data collected from different
sources. The use of constant dollars allows meaningful approximations of the
changes in construction output from one year to another when price deflators
are applied to current dollars to obtain the corresponding values in constant
dollars. However, since most construction price deflators are obtained from a
combination of price indices for material and labor inputs, they reflect only
the change of price levels and do not capture any savings arising from improved
labor productivity. Such deflators tend to overstate increases in construction
costs over a long period of time, and consequently understate the physical
volume or value of construction work in years subsequent to the base year for
the indices.
Job-site productivity is influenced by many factors which can be
characterized either as project work conditions or as non-productive
activities. The project work conditions include among other factors:
The non-productive activities associated with a project may or may not be
paid by the owner, but they nevertheless take up potential labor resources
which can otherwise be directed to the project. The non-productive activities
include among other factors:
Both categories of factors affect the productive labor available to a
project as well as the on-site labor efficiency.
Job-site labor productivity can be estimated either for each craft
(carpenter, bricklayer, etc.) or each type of construction (residential
housing, processing plant, etc.) under a specific set of work conditions. A
base labor productivity may be defined for a set of work conditions specified
by the owner or contractor who wishes to observe and measure the labor
performance over a period of time under such conditions. A labor productivity
index may then be defined as the ratio of the job-site labor productivity
under a different set of work conditions to the base labor productivity, and is
a measure of the relative labor efficiency of a project under this new set of
work conditions.
The effects of various factors related to work conditions on a new project
can be estimated in advance, some more accurately than others. For example,
for very large construction projects, the labor productivity index tends to
decrease as the project size and/or complexity increase because of logistic
problems and the "learning" that the work force must undergo before adjusting
to the new environment. Job-site accessibility often may reduce the labor
productivity index if the workers must perform their jobs in round about ways,
such as avoiding traffic in repaving the highway surface or maintaining the
operation of a plant during renovation. Labor availability in the local market
is another factor. Shortage of local labor will force the contractor to bring
in non-local labor or schedule overtime work or both. In either case, the
labor efficiency will be reduced in addition to incurring additional expenses.
The degree of equipment utilization and mechanization of a construction project
clearly will have direct bearing on job-site labor productivity. The
contractual agreements play an important role in the utilization of union or
non-union labor, the use of subcontractors and the degree of field supervision,
all of which will impact job-site labor productivity. Since on-site
construction essentially involves outdoor activities, the local climate will
influence the efficiency of workers directly. In foreign operations, the
cultural characteristics of the host country should be observed in assessing
the labor efficiency.
The non-productive activities associated with a project should also be
examined in order to examine the productive labor yield, which is defined as
the ratio of direct labor hours devoted to the completion of a project to the
potential labor hours. The direct labor hours are estimated on the basis of
the best possible conditions at a job site by excluding all factors which may
reduce the productive labor yield. For example, in the repaving of highway
surface, the flagmen required to divert traffic represent indirect labor which
does not contribute to the labor efficiency of the paving crew if the highway
is closed to the traffic. Similarly, for large projects in remote areas,
indirect labor may be used to provide housing and infrastructure for the
workers hired to supply the direct labor for a project. The labor hours spent
on rework to correct unsatisfactory original work represent extra time taken
away from potential labor hours. The labor hours related to such activities
must be deducted from the potential labor hours in order to obtain the actual
productive labor yield.
Example 4-1: Effects of job size on productivity
A contractor has established that under a set of "standard" work conditions
for building construction, a job requiring 500,000 labor hours is considered
standard in determining the base labor productivity. All other factors being
the same, the labor productivity index will increase to 1.1 or 110% for a job
requiring only 400,000 labor-hours. Assuming that a linear relation exists for
the range between jobs requiring 300,000 to 700,000 labor hours as shown in
Figure 4-0, determine the labor productivity index for a new job requiring
650,000 labor hours under otherwise the same set of work conditions.
The labor productivity index I for the new job can be obtained by linear
interpolation of the available data as follows:
Example 4-2: Productive labor yield(This example was adapted with
permission from an unpublished paper "Managing Mega Projects" presented by G.R.
Desnoyers at the Project Management Symposium sponsored by the Exxon Research
and Engineering Company, Florham Park, NJ, November 12, 1980.)
In the construction of an off-shore oil drilling platform, the potential
labor hours were found to be L = 7.5 million hours. Of this total, the
non-productive activities expressed in thousand labor hours were as follows:
The percentages of time allocated to various non-productive activities, A,
B, C and D are:
Example 4-3: Utilization of on-site worker's time
An example illustrating the effects of indirect labor requirements which
limit productive labor by a typical craftsman on the job site was given by
R. Tucker with the following percentages of time allocation:(See R.L. Tucker,
"Perfection of the Buggy Whip," The Construction Advancement Address, ASCE,
Boston, MA, Oct. 29, 1986.)
The market demand in construction fluctuates greatly, often within short
periods and with uneven distributions among geographical regions. Even when
the volume of construction is relatively steady, some types of work may decline
in importance while other types gain. Under an unstable economic environment,
employers in the construction industry place great value on flexibility in
hiring and laying off workers as their volumes of work wax and wane. On the
other hand, construction workers sense their insecurity under such
circumstances and attempt to limit the impacts of changing economic conditions
through labor organizations.
There are many crafts in the construction labor forces, but most contractors
hire from only a few of these crafts to satisfy their specialized needs.
Because of the peculiar characteristics of employment conditions, employers and
workers are placed in a more intimate relationship than in many other
industries. Labor and management arrangements in the construction industry
include both unionized and non-unionized operations which compete for future
dominance. Most industrial and utility construction is union. In the
commercial building sector, non-union contractors have made inroads, while in
the housing sector, most contractors are non-union. The heavy construction
sector is primarily non-union.
The craft unions work with construction contractors using unionized labor
through various market institutions such as jurisdiction rules, apprenticeship
programs, and the referral system. Craft unions with specific jurisdiction
rules for different trades set uniform hourly wage rates for journeymen and
offer formal apprenticeship training to provide common and equivalent skill for
each trade. Contractors, through the contractors' associations, enter into
legally binding collective bargaining agreements with one or more of the craft
unions in the construction trades. The system which bind both parties to a
collective bargaining agreement is referred to as the "union shop". These
agreements obligate a contractor to observe the work jurisdictions of various
unions and to hire employees through a union operated referral system commonly
known as the hiring hall.
The referral systems operated by union organizations are required to observe
several conditions:
While these principles must prevail, referral systems operated by labor
organizations differ widely in the construction industry.
Contractors and craft unions must negotiate not only wage rates and working
conditions, but also hiring and apprentice training practices. The purpose of
trade jurisdiction is to encourage considerable investment in apprentice
training on the part of the union so that the contractor will be protected by
having only qualified workers perform the job even though such workers are not
permanently attached to the contractor and thus may have no sense of security
or loyalty. The referral system is often a rapid and dependable source of
workers, particularly for a contractor who moves into a new geographical
location or starts a new project which has high fluctuations in demand for
labor. By and large, the referral system has functioned smoothly in providing
qualified workers to contractors, even though some other aspects of union
operations are not as well accepted by contractors.
In recent years, non-union contractors have entered and prospered in an
industry which has a long tradition of unionization. Non-union operations in
construction are referred to as "open shops." However, in the absence of
collective bargaining agreements, many contractors operate under policies
adopted by non-union contractors' associations. This practice is referred to
as "merit shop", which follows substantially the same policies and procedures
as collective bargaining although under the control of a non-union contractors'
association without union participation. Other contractors may choose to be
totally "unorganized" by not following either union shop or merit shop
practices.
The operations of the merit shop are national in scope, except for the local
or state apprenticeship and training plans. The comprehensive plans of the
contractors' association apply to all employees and crafts of a contractor
regardless of their trades. Under such operations, workers have full rights to
move through the nation among member contractors of the association. Thus, the
non-union segment of the industry is organized by contractors' associations
into an integral part of the construction industry. However, since merit shop
workers are employed directly by the construction firms, they have a greater
loyalty to the firm, and recognize that their own interest will be affected by
the financial health of the firm.
Playing a significant role in the early growth and continued expansion of
merit shop construction is the Associated Builders and Contractors association.
By 1987, it had a membership of nearly 20,000 contractors and a network of 75
chapters through the nation. Among the merit shop contractors are large
construction firms such as Fluor Daniel, Blount International, and Brown & Root
Construction. The advantages of merit shops as claimed by its advocates are:
By shouldering the training responsibility for producing skill workers, the
merit shop contractors have deflected the most serious complaints of users and
labor that used to be raised against the open shop. On the other hand, the use
of mixed crews of skilled workers at a job site by merit shop contractors
enables them to remove a major source of inefficiencies caused by the exclusive
jurisdiction practiced in the union shop, namely the idea that only members of
a particular union should be permitted to perform any given task in
construction. As a result, merit shop contractors are able to exert a
beneficial influence on productivity and cost-effectiveness of construction
projects.
The unorganized form of open shop is found primarily in housing construction
where a large percentage of workers are characterized as unskilled helpers.
The skilled workers in various crafts are developed gradually through informal
apprenticeships while serving as helpers. This form of open shop is not
expected to expand beyond the type of construction projects in which highly
specialized skills are not required.
In the organized building trades in North American construction, the primary
unit is the international union, which is an association of local unions in the
United States and Canada. Although only the international unions have the
power to issue or remove charters and to organize or combine local unions, each
local union has considerable degrees of autonomy in the conduct of its affairs,
including the negotiation of collective bargaining agreements. The business
agent of a local union is an elected official who is the most important person
in handling the day to day operations on behalf of the union. The contractors'
associations representing the employers vary widely in composition and
structure, particularly in different geographical regions. In general, local
contractors' associations are considerably less well organized than the union
with which they deal, but they try to strengthen themselves through affiliation
with state and national organizations. Typically, collective bargaining
agreements in construction are negotiated between a local union in a single
craft and the employers of that craft as represented by a contractors'
association, but there are many exceptions to this pattern. For example, a
contractor may remain outside the association and negotiate independently of
the union, but it usually cannot obtain a better agreement than the
association.
Because of the great variety of bargaining structures in which the union and
contractors' organization may choose to stage negotiations, there are many
problems arising from jurisdictional disputes and other causes. Given the
traditional rivalries among various crafts and the ineffective organization of
some of contractors' associations, coupled with the lack of adequate mechanisms
for settling disputes, some possible solutions to these problems deserve
serious attention:<For more detailed discussion, see D.G. Mills: "Labor
Relations and Collective Bargaining" (Chapter 4) in The Construction Industry
(by J.E. Lang and D.Q. Mills), Lexington Books, D.C. Heath and Co., Lexington,
MA, 1979.>
Currently, the geographical area in a collective bargaining agreement does
not necessarily coincide with the territory of the union and contractors'
associations in the negotiations. There are overlapping of jurisdictions as
well as territories, which may create successions of contract termination dates
for different crafts. Most collective bargaining agreements are negotiated
locally, but regional agreements with more comprehensive coverage embracing a
number of states have been established. The role of national union negotiators
and contractors' representatives in local collective bargaining is limited.
The national agreement between international unions and a national contractor
normally binds the contractors' association and its bargaining unit.
Consequently, the most promising reform lies in the broadening of the
geographic region of an agreement in a single trade without overlapping
territories or jurisdictions.
The treatment of interrelationships among various craft trades in
construction presents one of the most complex issues in the collective
bargaining process. Past experience on project agreements has dealt with such
issues successfully in that collective bargaining agreements are signed by a
group of craft trade unions and a contractor for the duration of a project.
Project agreements may reference other agreements on particular points, such as
wage rates and fringe benefits, but may set their own working conditions and
procedures for settling disputes including a commitment of no-strike and
no-lockout. This type of agreement may serve as a starting point for
multicraft bargaining on a regional, non-project basis.
Although both sides of the bargaining table are to some degree responsible
for the success or failure of negotiation, contractors have often been
responsible for the poor performance of collective bargaining in construction
in recent years because local contractors' associations are generally less well
organized and less professionally staffed than the unions with which they deal.
Legislation providing for contractors' association accreditation as an
exclusive bargaining agent has now been provided in several provinces in
Canada. It provides a government board that could hold hearings and establish
an appropriate bargaining unit by geographic region or sector of the industry,
on a single-trade or multi-trade basis.
Materials management is an important element in project planning and
control. Materials represent a major expense in construction, so minimizing
procurement or purchase costs presents important opportunities for reducing
costs. Poor materials management can also result in large and avoidable costs
during construction. First, if materials are purchased early, capital may be
tied up and interest charges incurred on the excess inventory of materials.
Even worse, materials may deteriorate during storage or be stolen unless
special care is taken. For example, electrical equipment often must be stored
in waterproof locations. Second, delays and extra expenses may be incurred if
materials required for particular activities are not available. Accordingly,
insuring a timely flow of material is an important concern of project managers.
Materials management is not just a concern during the monitoring stage in
which construction is taking place. Decisions about material procurement may
also be required during the initial planning and scheduling stages. For
example, activities can be inserted in the project schedule to represent
purchasing of major items such as elevators for buildings. The availability of
materials may greatly influence the schedule in projects with a fast track or
very tight time schedule: sufficient time for obtaining the necessary materials
must be allowed. In some case, more expensive suppliers or shippers may be
employed to save time.
Materials management is also a problem at the organization level if central
purchasing and inventory control is used for standard items. In this case, the
various projects undertaken by the organization would present requests to the
central purchasing group. In turn, this group would maintain inventories of
standard items to reduce the delay in providing material or to obtain lower
costs due to bulk purchasing. This organizational materials management problem
is analogous to inventory control in any organization facing continuing demand
for particular items.
Materials ordering problems lend themselves particularly well to computer
based systems to insure the consistency and completeness of the purchasing
process. In the manufacturing realm, the use of automated materials
requirements planning systems is common. In these systems, the master
production schedule, inventory records and product component lists are merged
to determine what items must be ordered, when they should be ordered, and how
much of each item should be ordered in each time period. The heart of these
calculations is simple arithmetic: the projected demand for each material item
in each period is subtracted from the available inventory. When the inventory
becomes too low, a new order is recommended. For items that are non-standard
or not kept in inventory, the calculation is even simpler since no inventory
must be considered. With a materials requirement system, much of the detailed
record keeping is automated and project managers are alerted to purchasing
requirements.
Example 4-4: Examples of benefits for materials management systems.(This
example was adapted from Stukhart, G. and Bell, L.C. "Costs and Benefits of
Materials Management Systems,", ASCE Journal of Construction Engineering and
Management, Vol. 113, No. 2, June 1987, pp. 222-234.)
From a study of twenty heavy construction sites, the following benefits from
the introduction of materials management systems were noted:
The main sources of information for feedback and control of material
procurement are requisitions, bids and quotations, purchase orders and
subcontracts, shipping and receiving documents, and invoices. For projects
involving the large scale use of critical resources, the owner may initiate the
procurement procedure even before the selection of a constructor in order to
avoid shortages and delays. Under ordinary circumstances, the constructor will
handle the procurement to shop for materials with the best price/performance
characteristics specified by the designer. Some overlapping and rehandling in
the procurement process is unavoidable, but it should be minimized to insure
timely delivery of the materials in good condition.
The materials for delivery to and from a construction site may be broadly
classified as : (1) bulk materials, (2) standard off-the-shelf materials, and
(3) fabricated members or units. The process of delivery, including
transportation, field storage and installation will be different for these
classes of materials. The equipment needed to handle and haul these classes of
materials will also be different.
Bulk materials refer to materials in their natural or semi-processed state,
such as earthwork to be excavated, wet concrete mix, etc. which are usually
encountered in large quantities in construction. Some bulk materials such as
earthwork or gravels may be measured in bank (solid in situ) volume.
Obviously, the quantities of materials for delivery may be substantially
different when expressed in different measures of volume, depending on the
characteristics of such materials.
Standard piping and valves are typical examples of standard off-the-shelf
materials which are used extensively in the chemical processing industry.
Since standard off-the-shelf materials can easily be stockpiled, the delivery
process is relatively simple.
Fabricated members such as steel beams and columns for buildings are
pre-processed in a shop to simplify the field erection procedures. Welded or
bolted connections are attached partially to the members which are cut to
precise dimensions for adequate fit. Similarly, steel tanks and pressure
vessels are often partly or fully fabricated before shipping to the field. In
general, if the work can be done in the shop where working conditions can
better be controlled, it is advisable to do so, provided that the fabricated
members or units can be shipped to the construction site in a satisfactory
manner at a reasonable cost.
As a further step to simplify field assembly, an entire wall panel including
plumbing and wiring or even an entire room may be prefabricated and shipped to
the site. While the field labor is greatly reduced in such cases, "materials"
for delivery are in fact manufactured products with value added by another type
of labor. With modern means of transporting construction materials and
fabricated units, the percentages of costs on direct labor and materials for a
project may change if more prefabricated units are introduced in the
construction process.
In the construction industry, materials used by a specific craft are
generally handled by craftsmen, not by general labor. Thus, electricians
handle electrical materials, pipefitters handle pipe materials, etc. This
multiple handling diverts scarce skilled craftsmen and contractor supervision
into activities which do not directly contribute to construction. Since
contractors are not normally in the freight business, they do not perform the
tasks of freight delivery efficiently. All these factors tend to exacerbate
the problems of freight delivery for very large projects.
Example 4-5: Freight delivery for the Alaska Pipeline Project(The
information for this example was provided by Exxon Pipeline Company, Houston,
Texas, with permission from the Alyeska Pipeline Service Co., Anchorage,
Alaska.)
The freight delivery system for the Alaska pipeline project was set up to
handle 600,000 tons of materials and supplies. This tonnage did not include
the pipes which comprised another 500,000 tons and were shipped through a
different routing system.
The complexity of this delivery system is illustrated in Figure 4-0. The
rectangular boxes denote geographical locations. The points of origin
represent plants and factories throughout the US and elsewhere. Some of the
materials went to a primary staging point in Seattle and some went directly to
Alaska. There were five ports of entry: Valdez, Anchorage, Whittier, Seward
and Prudhoe Bay. There was a secondary staging area in Fairbanks and the
pipeline itself was divided into six sections. Beyond the Yukon River, there
was nothing available but a dirt road for hauling. The amounts of freight in
thousands of tons shipped to and from various locations are indicated by the
numbers near the network branches (with arrows showing the directions of
material flows) and the modes of transportation are noted above the branches.
In each of the locations, the contractor had supervision and construction labor
to identify materials, unload from transport, determine where the material was
going, repackage if required to split shipments, and then re-load material on
outgoing transport.
Example 4-6: Process plant equipment procurement[This example was adapted
from A.E. Kerridge, "How to Develop a Project Schedule," in A.E. Kerridge and
C. H. Vervalin (eds.), Engineering and Construction Project Management, Gulf
Publishing Company, Houston, 1986.]
The procurement and delivery of bulk materials items such as piping
electrical and structural elements involves a series of activities if such
items are not standard and/or in stock. The times required for various
activities in the procurement of such items might be estimated to be as
follows:
Once goods are purchased, they represent an inventory used during the
construction process. The general objective of inventory control is to
minimize the total cost of keeping the inventory while making tradeoffs among
the major categories of costs: (1) purchase costs, (2) order cost, (3) holding
costs, and (4) unavailable cost. These cost categories are interrelated since
reducing cost in one category may increase cost in others. The costs in all
categories generally are subject to considerable uncertainty.
The purchase cost of an item is the unit purchase price from an external
source including transportation and freight costs. For construction materials,
it is common to receive discounts for bulk purchases, so the unit purchase cost
declines as quantity increases. These reductions may reflect manufacturers'
marketing policies, economies of scale in the material production, or scale
economies in transportation. There are also advantages in having homogeneous
materials. For example, a bulk order to insure the same color or size of items
such as bricks may be desirable. Accordingly, it is usually desirable to make
a limited number of large purchases for materials. In some cases,
organizations may consolidate small orders from a number of different projects
to capture such bulk discounts; this is a basic saving to be derived from a
central purchasing office.
The cost of materials is based on prices obtained through effective
bargaining. Unit prices of materials depend on bargaining leverage, quantities
and delivery time. Organizations with potential for long-term purchase volume
can command better bargaining leverage. While orders in large quantities may
result in lower unit prices, they may also increase holding costs and thus
cause problems in cash flow. Requirements of short delivery time can also
adversely affect unit prices. Furthermore, design characteristics which
include items of odd sizes or shapes should be avoided. Since such items
normally are not available in the standard stockpile, purchasing them causes
higher prices.
The transportation costs are affected by shipment sizes and other factors.
Shipment by the full load of a carrier often reduces prices and assures quicker
delivery, as the carrier can travel from the origin to the destination of the
full load without having to stop for delivering part of the cargo at other
stations. Avoiding transshipment is another consideration in reducing shipping
cost. While the reduction in shipping costs is a major objective, the
requirements of delicate handling of some items may favor a more expensive mode
of transportation to avoid breakage and replacement costs.
The order cost reflects the administrative expense of issuing a purchase
order to an outside supplier. Order costs include expenses of making
requisitions, analyzing alternative vendors, writing purchase orders, receiving
materials, inspecting materials, checking on orders, and maintaining records of
the entire process. Order costs are usually only a small portion of total
costs for material management in construction projects, although ordering may
require substantial time.
The holding costs or carrying costs are primarily the result of capital
costs, handling, storage, obsolescence, shrinkage and deterioration. Capital
cost results from the opportunity cost or financial expense of capital tied up
in inventory. Once payment for goods is made, borrowing costs are incurred or
capital must be diverted from other productive uses. Consequently, a capital
carrying cost is incurred equal to the value of the inventory during a period
multiplied by the interest rate obtainable or paid during that period. Note
that capital costs only accumulate when payment for materials actually occurs;
many organizations attempt to delay payments as long as possible to minimize
such costs. Handling and storage represent the movement and protection charges
incurred for materials. Storage costs also include the disruption caused to
other project activities by large inventories of materials that get in the way.
Obsolescence is the risk that an item will lose value because of changes in
specifications. Shrinkage is the decrease in inventory over time due to theft
or loss. Deterioration reflects a change in material quality due to age or
environmental degradation. Many of these holding cost components are
difficult to predict in advance; a project manager knows only that there is
some chance that specific categories of cost will occur. In addition to these
major categories of cost, there may be ancillary costs of additional insurance,
taxes (many states treat inventories as taxable property), or additional fire
hazards. As a general rule, holding costs will typically represent 20 to 40%
of the average inventory value over the course of a year; thus if the average
material inventory on a project is $ 1 million over a year, the holding cost
might be expected to be $200,000 to $400,000.
The unavailability cost is incurred when a desired material is not
available at the desired time. In manufacturing industries, this cost is often
called the stockout or depletion cost. Shortages may delay work, thereby
wasting labor resources or delaying the completion of the entire project.
Again, it may be difficult to forecast in advance exactly when an item may be
required or when an shipment will be received. While the project schedule
gives one estimate, deviations from the schedule may occur during construction.
Moreover, the cost associated with a shortage may also be difficult to assess;
if the material used for one activity is not available, it may be possible to
assign workers to other activities and, depending upon which activities are
critical, the project may not be delayed.
To illustrate the type of trade-offs encountered in materials management,
suppose that a particular item is to be ordered for a project. The amount of
time required for processing the order and shipping the item is uncertain.
Consequently, the project manager must decide how much lead time to provide in
ordering the item. Ordering early and thereby providing a long lead time will
increase the chance that the item is available when needed, but it increases
the costs of inventory and the chance of spoilage on site.
Let T be the time for the delivery of a particular item, R be the time
required for process the order, and S be the shipping time. Then, the minimum
amount of time for the delivery of the item is T = R + S. In general, both R
and S are random variables; hence T is also a random variable. For the sake of
simplicity, we shall consider only the case of instant processing for an order,
i.e. R = 0. Then, the delivery time T equals the shipping time S.
Since T is a random variable, the chance that an item will be delivered on
day t is represented by the probability p(t). Then, the probability that the
item will be delivered on or before t day is given by: If a and b are the lower and upper bounds of possible delivery dates, the
expected delivery time is then given by:
The lead time L for ordering an item is the time period ahead of the
delivery time, and will depend on the tradeoff between holding costs and
unavailability costs. A project manager may want to avoid the unavailable cost
by requiring delivery on the scheduled date of use, or may be to lower the
holding cost by adopting a more flexible lead time based on the expected
delivery time. For example, the manager may make the tradeoff by specifying
the lead time to be D days more than the expected delivery time, i.e.,
where D may vary from 0 to the number of additional days required to produce
certain delivery on the desired date.
In a more realistic situation, the project manager would also contend with
the uncertainty of exactly when the item might be required. Even if the item
is scheduled for use on a particular date, the work progress might vary so
that the desired date would differ. In many cases, greater than expected work
progress may result in no savings because materials for future activities are
unavailable.
Example 4-7: : Lead time for ordering with no processing time.
Table 4-0 summarizes the probability of different delivery times for an
item. In this table, the first column lists the possible shipping times
(ranging from 10 to 16 days), the second column lists the probability or chance
that this shipping time will occur and the third column summarizes the chance
that the item arrives on or before a particular date. This table can be used
to indicate the chance that the item will arrive on a desired date for
different lead times. For example, if the order is placed 12 days in advance
of the desired date (so the lead time is 12 days), then there is a 15% chance
that the item will arrive exactly on the desired day and a 35% chance that the
item will arrive on or before the desired date. Note that this implies that
there is a 1 - 0.35 = 0.65 or 65% chance that the item will not arrive by the
desired date with a lead time of 12 days. Given the information in Table 4-0,
when should the item order be placed?
______________________________________________________________________________
!!!Delivery!!!Probability of!!!Cumulative Probability
!!!Date!!!Delivery on Day t!!!of Delivery by Day t
!!! t!!! p(t)!!! Pr{T L t}
!!!10 .10!!! .10!!!
!!!11 .10!!! .20!!!
!!!12 .15!!! .35!!!
!!!13 .20!!! .55!!!
!!!14 .30!!! .85!!!
!!!15 .10!!! .95!!!
!!!16 .05!!! 1.00!!!
______________________________________________________________________________
Suppose that the scheduled date of use for the item is in 16 days. To be
completely certain to have delivery by the desired day, the order should be
placed 16 days in advance. However, the expected delivery date with a 16 day
lead time would be:
Thus, the actual delivery date may be 16-13 = 3 days early, and this early
delivery might involve significant holding costs. A project manager might then
decide to provide a lead time so that the expected delivery date was equal to
the desired assembly date as long as the availability of the item was not
critical. Alternatively, the project manager might negotiate a more certain
delivery date from the supplier.
The selection of the appropriate type and size of construction equipment
often affects the required amount of time and effort and thus the job-site
productivity of a project. It is therefore important for site managers and
construction planners to be familiar with the characteristics of the major
types of equipment most commonly used in construction.(For further details on
equipment characteristics, see, for example, S.W. Nunnally, Construction
Methods and Management, Second Edition, Prentice-Hall, 1986)
One family of construction machines used for excavation is broadly
classified as a crane-shovel as indicated by the variety of machines in Figure
4-0. The crane-shovel consists of three major components:
The type of mounting for all machines in Figure 4-0 is referred to as
crawler mounting, which is particularly suitable for crawling over relatively
rugged surfaces at a job site. Other types of mounting include truck mounting
and wheel mounting which provide greater mobility between job sites, but
require better surfaces for their operation. The revolving deck includes a cab
to house the person operating the mounting and/or the revolving deck. The
types of front end attachments in Figure 4-0 might include a crane with hook,
claim shell, dragline, backhoe, shovel and piledriver.
A tractor consists of a crawler mounting and a non-revolving cab. When an
earth moving blade is attached to the front end of a tractor, the assembly is
called a bulldozer. When a bucket is attached to its front end, the assembly
is known as a loader or bucket loader. There are different types of loaders
designed to handle most efficiently materials of different weights and moisture
contents.
Scrapers are multiple-units of tractor-truck and blade-bucket assemblies
with various combinations to facilitate the loading and hauling of earthwork.
Major types of scrapers include single engine two-axle or three axle scrapers,
twin-engine all-wheel-drive scrapers, elevating scrapers, and push-pull
scrapers. Each type has different characteristics of rolling resistance,
maneuverability stability, and speed in operation.
The function of compaction equipment is to produce higher density in soil
mechanically. The basic forces used in compaction are static weight, kneading,
impact and vibration. The degree of compaction that may be achieved depends on
the properties of soil, its moisture content, the thickness of the soil layer
for compaction and the method of compaction. Some major types of compaction
equipment are shown in Figure 4-0, which includes rollers with different
operating characteristics.
The function of grading equipment is to bring the earthwork to the desired
shape and elevation. Major types of grading equipment include motor graders
and grade trimmers. The former is an all-purpose machine for grading and
surface finishing, while the latter is used for heavy construction because of
its higher operating speed.
Rock excavation is an audacious task requiring special equipment and
methods. The degree of difficulty depends on physical characteristics of the
rock type to be excavated, such as grain size, planes of weakness, weathering,
brittleness and hardness. The task of rock excavation includes loosening,
loading, hauling and compacting. The loosening operation is specialized for
rock excavation and is performed by drilling, blasting or rippling.
Major types of drilling equipment are percussion drills, rotary drills, and
rotary-percussion drills. A percussion drill penetrates and cuts rock by
impact while it rotates without cutting on the upstroke. Common types of
percussion drills include a jackhammer which is hand-held and others which are
mounted on a fixed frame or on a wagon or crawl for mobility. A rotary drill
cuts by turning a bit against the rock surface. A rotary-percussion drill
combines the two cutting movements to provide a faster penetration in rock.
Blasting requires the use of explosives, the most common of which is
dynamite. Generally, electric blasting caps are connected in a circuit with
insulated wires. Power sources may be power lines or blasting machines
designed for firing electric cap circuits. Also available are non-electrical
blasting systems which combine the precise timing and flexibility of electric
blasting and the safety of non-electrical detonation.
Tractor-mounted rippers are capable of penetrating and prying loose most
rock types. The blade or ripper is connected to an adjustable shank which
controls the angle at the tip of the blade as it is raised or lowered.
Automated ripper control may be installed to control ripping depth and tip
angle.
In rock tunneling, special tunnel machines equipped with multiple cutter
heads and capable of excavating full diameter of the tunnel are now available.
Their use has increasingly replaced the traditional methods of drilling and
blasting.
Derricks are commonly used to lift equipment of materials in industrial or
building construction. A derrick consists of a vertical mast and an inclined
boom sprouting from the foot of the mast. The mast is held in position by guys
or stifflegs connected to a base while a topping lift links the top of the mast
and the top of the inclined boom. A hook in the road line hanging from the top
of the inclined boom is used to lift loads. Guy derricks may easily be moved
from one floor to the next in a building under construction while stiffleg
derricks may be mounted on tracks for movement within a work area.
Tower cranes are used to lift loads to great heights and to facilitate the
erection of steel building frames. Horizon boom type tower cranes are most
common in highrise building construction. Inclined boom type tower cranes are
also used for erecting steel structures.
Basic types of equipment for paving include machines for dispensing concrete
and bituminous materials for pavement surfaces. Concrete mixers may also be
used to mix portland cement, sand, gravel and water in batches for other types
of construction other than paving.
A truck mixer refers to a concrete mixer mounted on a truck which is capable
of transporting ready mixed concrete from a central batch plant to construction
sites. A paving mixer is a self propelled concrete mixer equipped with a boom
and a bucket to place concrete at any desired point within a roadway. It can
be used as a stationary mixer or used to supply slipform pavers that are
capable of spreading, consolidating and finishing a concrete slab without the
use of forms.
A bituminous distributor is a truck-mounted plant for generating liquid
bituminous materials and applying them to road surfaces through a spray bar
connected to the end of the truck. Bituminous materials include both asphalt
and tar which have similar properties except that tar is not soluble in
petroleum products. While asphalt is most frequently used for road surfacing,
tar is used when the pavement is likely to be heavily exposed to petroleum
spills.
Air compressors and pumps are widely used as the power sources for
construction tools and equipment. Common pneumatic construction tools include
drills, hammers, grinders, saws, wrenches, staple guns, sandblasting guns, and
concrete vibrators. Pumps are used to supply water or to dewater at
construction sites and to provide water jets for some types of construction.
The introduction of new mechanized equipment in construction has had a
profound effect on the cost and productivity of construction as well as the
methods used for construction itself. An exciting example of innovation in
this regard is the introduction of computer microprocessors on tools and
equipment. As a result, the performance and activity of equipment can be
continually monitored and adjusted for improvement. In many cases, automation
of at least part of the construction process is possible and desirable. For
example, wrenches that automatically monitor the elongation of bolts and the
applied torque can be programmed to achieve the best bolt tightness. On
grading projects, laser controlled scrapers can produce desired cuts faster and
more precisely than wholly manual methods.[See Paulson, C., "Automation and
Robotics for Construction," ASCE Journal of Construction Engineering and
Management, Vol. 111, No. CO-3, 1985, pp. 190-207.] Possibilities for
automation and robotics in construction are explored more fully in Chapter 16.
Example 4-8: Tunneling Equipment(This example is adapted from Fred
Moavenzadeh, "Construction's High-Technology Revolution," Technology Review,
October, 1985, pg. 32.)
In the mid-1980's, some Japanese firms were successful in obtaining
construction contracts for tunneling in the United States by using new
equipment and methods. For example, the Japanese firm of Ohbayashi won the
sewer contract in San Francisco because of its advanced tunneling technology.
When a tunnel is dug through soft earth, as in San Francisco, it must be
maintained at a few atmospheres of pressure to keep it from caving in. Workers
must spend several hours in a pressure chamber before entering the tunnel and
several more in decompression afterwards. They can stay inside for only three
or four hours, always at considerable risk from cave-ins and asphyxiation.
Ohbayashi used the new Japanese "earth-pressure-balance" method, which
eliminates these problems. Whirling blades advance slowly, cutting the tunnel.
The loose earth temporarily remains behind to balance the pressure of the
compact earth on all sides. Meanwhile, prefabricated concrete segments are
inserted and joined with waterproof seals to line the tunnel. Then the loose
earth is conveyed away. This new tunneling method enabled Ohbayashi to bid $5
million below the engineer's estimate for a San Francisco sewer. The firm
completed the tunnel three months ahead of schedule. In effect, an innovation
involving new technology and method led to considerable cost and time savings.
Typically, construction equipment is used to perform essentially repetitive
operations, and can be broadly classified according to two basic functions:
(1) operators such as cranes, graders, etc. which stay within the confines of
the construction site, and (2) haulers such as dump trucks, ready mixed
concrete truck, etc. which transport materials to and from the site. In both
cases, the cycle of a piece of equipment is a sequence of tasks which is
repeated to produce a unit of output. For example, the sequence of tasks for a
crane might be to fit and install a wall panel (or a package of eight wall
panels) on the side of a building; similarly, the sequence of tasks of a ready
mixed concrete truck might be to load, haul and unload two cubic yards (or one
truck load) of fresh concrete.
In order to increase job-site productivity, it is beneficial to select
equipment with proper characteristics and a size most suitable for the work
conditions at a construction site. In excavation for building construction,
for examples, factors that could affect the selection of excavators include:
The choice of the type and size of haulers is based on the consideration
that the number of haulers selected must be capable of disposing of the
excavated materials expeditiously. Factors which affect this selection
include:
The cycle capacity C of a piece of equipment is defined as the number of
output units per cycle of operation under standard work conditions. The
capacity is a function of the output units used in the measurement as well as
the size of the equipment and the material to be processed. The cycle time T
refers to units of time per cycle of operation. The standard production rate R
of a piece of construction equipment is defined as the number of output units
per unit time. Hence: The daily standard production rate P@-(e) of an excavator can be obtained by
multiplying its standard production rate R@-(e) by the number of operating
hours H@-(e) per day. Thus: In determining the daily standard production rate of a hauler, it is
necessary to determine first the cycle time from the distance D to a dump site
and the average speed S of the hauler. Let T@-(t) be the travel time for the
round trip to the dump site, T@-(o) by the loading time and T@-(d) be the
dumping time. Then the travel time for the round trip is given by: The number of haulers required is also of interest. Let w denote the swell
factor of the soil such that wP@-(e) denotes the daily volume of loose
excavated materials resulting from the excavation volume P@-(e). Then the
approximate number of haulers required to dispose of the excavated materials is
given by: While the standard production rate of a piece of equipment is based on
"standard" or ideal conditions, equipment productivities at job sites are
influenced by actual work conditions and a variety of inefficiencies and work
stoppages. As one example, various factor adjustments can be used to account
in a approximate fashion for actual site conditions. If the conditions that
lower the standard production rate are denoted by n factors F@-(1), F@-(2),
..., F@-(n), each of which is smaller than 1, then the actual equipment
productivity R' at the job site can be related to the standard production rate
R as follows: In addition to the problem of estimating the various factors, F@-(1),
F@-(2), ..., F@-(n), it may also be important to account for interactions among
the factors and the exact influence of particular site characteristics.
Example 4-9: : Daily standard production rate of a power shovel[This and
the following examples in this section have been adapted from E. Baracco-Miller
and C.T. Hendrickson, Planning for Construction, Technical Report No.
R-87-162, Department of Civil Engineering, Carnegie Mellon University,
Pittsburgh, PA 1987.]
A power shovel with a dipper of one cubic yard capacity has a standard
operating cycle time of 30 seconds. Find the daily standard production rate of
the shovel.
For C@-(e) = 1 cu. yd., T@-(e) = 30 sec. and H@-(e) = 8 hours, the daily
standard production rate is found from Eq. (4.4.11) as follows:
Example 4-10: Daily standard production rate of a dump truck
A dump truck with a capacity of 6 cubic yards is used to dispose of
excavated materials at a dump site 4 miles away. The average speed of the dump
truck is 30 mph and the dumping time is 30 seconds. Find the daily standard
production rate of the truck. If a fleet of dump trucks of this capacity is
used to dispose of the excavated materials in Example 4-8 for 8 hours per day,
determine the number of trucks needed daily, assuming a swell factor of 1.1 for
the soil.
The daily standard production rate of a dump truck can be obtained by using
Equations (4.4.11) through (4.4.11):
Example 4-11: Job site productivity of a power shovel
A power shovel with a dipper of one cubic yard capacity (in Example 4-9) has
a standard production rate of 960 cubic yards for an 8-hour day. Determine the
job site productivity and the actual cycle time of this shovel under the work
conditions at the site that affects its productivity as shown below:
Example 4-12: Job site productivity of a dump truck
A dump truck with a capacity of 6 cubic yards (in Example 4-10) is used to
dispose of excavated materials. The distance from the dump site is 4 miles and
the average speed of the dump truck is 30 mph. The job site productivity of
the power shovel per day (in Example 4-11) is 504 cubic yards, which will be
modified by a swell factor of 1.1. The only factors affecting the job site
productivity of the dump truck are 0.80 for equipment idle time and 0.70 for
management efficiency. Determine the job site productivity of the dump truck.
If a fleet of such trucks is used to haul the excavated material, find the
number of trucks needed daily.
The actual cycle time T'@-(h) of the dump truck can be obtained by summing
the actual times for traveling, loading and dumping: The previous sections described the primary inputs of labor, material and
equipment to the construction process. At varying levels of detail, a project
manager must insure that these inputs are effectively coordinated to achieve an
efficient construction process. This coordination involves both strategic
decisions and tactical management in the field. For example, strategic
decisions about appropriate technologies or site layout are often made during
the process of construction planning. During the course of construction,
foremen and site managers will make decisions about work to be undertaken at
particular times of the day based upon the availability of the necessary
resources of labor, materials and equipment. Without coordination among these
necessary inputs, the construction process will be inefficient or stop
altogether.
Example 4-13: Steel erection
Erection of structural steel for buildings, bridges or other facilities is
an example of a construction process requiring considerable coordination.
Fabricated steel pieces must arrive on site in the correct order and quantity
for the planned effort during a day. Crews of steelworkers must be available
to fit pieces together, bolt joints, and perform any necessary welding. Cranes
and crane operators may be required to lift fabricated components into place;
other activities on a job site may also be competing for use of particular
cranes. Welding equipment, wrenches and other hand tools must be readily
available. Finally, ancillary materials such as bolts of the correct size must
be provided.
In coordinating a process such as steel erection, it is common to assign
different tasks to specific crews. For example, one crew may place members in
place and insert a few bolts in joints in a specific area. A following crew
would be assigned to finish bolting, and a third crew might perform necessary
welds or attachment of brackets for items such as curtain walls.
With the required coordination among these resources, it is easy to see how
poor management or other problems can result in considerable inefficiency. For
example, if a shipment of fabricated steel is improperly prepared, the crews
and equipment on site may have to wait for new deliveries.
Example 4-14: Construction process simulation models
Computer based simulation of construction operations can be a useful
although laborious tool in analyzing the efficiency of particular processes or
technologies. These tools tend to be either oriented toward modeling resource
processes or towards representation of spatial constraints and resource
movements. Later chapters will describe simulation in more detail, but a small
example of a construction operation model can be described here.[This model
used the INSIGHT simulation language and was described in B.C. Paulson, W.T.
Chan, and C.C. Koo, "Construction Operations Simulation by Microcomputer," ASCE
Journal of Construction Engineering and Management, Vol. 113, No. CO-2, June
1987, pp. 302-314.] The process involved placing concrete within existing
formwork for the columns of a new structure. A crane-and-bucket combination
with one cubic yard capacity and a flexible "elephant trunk" was assumed for
placement. Concrete was delivered in trucks with a capacity of eight cubic
yards. Because of site constraints, only one truck could be moved into the
delivery position at a time. Construction workers and electric immersion-type
concrete vibrators were also assumed for the process.
The simulation model of this process is illustrated in Figure 4-0. Node 2
signals the availability of a concrete truck arriving from the batch plant. As
with other circular nodes in Figure 4-0, the availability of a truck may result
in a resource waiting or queueing for use. If a truck (node 2) and the crane
(node 3) are both available, then the crane can load and hoist a bucket of
concrete (node 4). As with other rectangular nodes in the model, this
operation will require an appreciable period of time. On the completion of the
load and hoist operations, the bucket (node 5) is available for concrete
placement. Placement is accomplished by having a worker guide the bucket's
elephant trunk between the concrete forms and having a second worker operate
the bucket release lever. A third laborer operates a vibrator in the concrete
while the bucket (node 8) moves back to receive a new load. Once the concrete
placement is complete, the crew becomes available to place a new bucket load
(node 7). After two buckets are placed, then the column is complete (node 9)
and the equipment and crew can move to the next column (node 10). After the
movement to the new column is complete, placement in the new column can begin
(node 11). Finally, after a truck is emptied (nodes 12 and 13), the truck
departs and a new truck can enter the delivery stall (node 14) if one is
waiting.
Application of the simulation model consists of tracing through the time
required for these various operations. Events are also simulated such as the
arrival times of concrete trucks. If random elements are introduced, numerous
simulations are required to estimate the actual productivity and resource
requirements of the process. For example, one simulation of this process using
four concrete trucks found that a truck was waiting 83% of the time with an
average wait at the site of 14 minutes. This type of simulation can be used to
estimate the various productivity adjustment factors described in the previous
section.
A project manager needs to insure that resources required for and/or shared
by numerous activities are adequate. Problems in this area can be indicated in
part by the existence of queues of resource demands during construction
operations. A queue can be a waiting line for service. One can imagine a
queue as an orderly line of customers waiting for a stationary server such as a
ticket seller. However, the demands for service might not be so neatly
arranged. For example, we can speak of the queue of welds on a building site
waiting for inspection. In this case, demands do not come to the server, but a
roving inspector travels among the waiting service points. Waiting for
resources such as a particular piece of equipment or a particular individual is
an endemic problem on construction sites. If workers spend appreciable
portions of time waiting for particular tools, materials or an inspector, costs
increase and productivity declines. Insuring adequate resources to serve
expected demands is an important problem during construction planning and field
management.
In general, there is a trade-off between waiting times and utilization of
resources. Utilization is the proportion of time a particular resource is in
productive use. Higher amounts of resource utilization will be beneficial as
long as it does not impose undue costs on the entire operation. For example, a
welding inspector might have one hundred percent utilization, but workers
throughout the jobsite might be wasting inordinate time waiting for
inspections. Providing additional inspectors may be cost effective, even if
they are not utilized at all times.
A few conceptual models of queueing systems may be helpful to construction
planners in considering the level of adequate resources to provide. First, we
shall consider the case of time-varying demands and a server with a constant
service rate. This might be the situation for an elevator in which large
demands for transportation occur during the morning or at a shift change.
Second, we shall consider the situation of randomly arriving demands for
service and constant service rates. Finally, we shall consider briefly the
problems involving multiple serving stations.
Suppose that the cumulative number of demands for service or "customers" at
any time t is known and equal to the value of the function A(t). These
"customers" might be crane loads, weld inspections, or any other defined group
of items to be serviced. Suppose further that a single server is available to
handle these demands, such as a single crane or a single inspector. For this
model of queueing, we assume that the server can handle customers at some
constant, maximum rate denoted as x "customers" per unit of time. This is a
maximum rate since the server may be idle for periods of time if no customers
are waiting. This system is deterministic in the sense that both the arrival
function and the service process are assumed to have no random or unknown
component.
A cumulative arrival function of customers, A(t), is shown in Figure 4-0 in
which the vertical axis represents the cumulative number of customers, while
the horizontal axis represents the passage of time. The arrival of individual
customers to the queue would actually represent a unit step in the arrival
function A(t), but these small steps are approximated by a continuous curve in
the figure. The rate of arrivals for a unit time interval @g[D]t from t-1 to t
is given by:
While an hour or a minute is a natural choice as a unit time interval, other
time periods may also be used as long as the passage of time is expressed as
multiples of such time periods. For instance, if half an hour is used as unit
time interval for a process involving ten hours, then the arrivals should be
represented by 20 steps of half hour each. Hence, the unit time interval
between t-1 and t is @g[D] t = t - (t-1) = 1, and the slope of the cumulative
arrival function in the interval is given by:
The cumulative number of customers served over time is represented by the
cumulative departure function D(t). While the maximum service rate is x per
unit time, the actual service rate for a unit time interval @g[D]t from t-1 to
t is: Any time that the rate of arrivals to the queue exceeds the maximum service
rate, then a queue begins to form and the cumulative departures will occur at
the maximum service rate. The cumulative departures from the queue will
proceed at the maximum service rate of x "customers" per unit of time, so that
the slope of D(t) is x during this period. The cumulative departure function
D(t) can be readily constructed graphically by running a ruler with a slope of
x along the cumulative arrival function A(t). As soon as the function A(t)
climbs above the ruler, a queue begins to form. The maximum service rate will
continue until the queue disappears, which is represented by the convergence of
the cumulative arrival and departure functions A(t) and D(t).
With the cumulative arrivals and cumulative departure functions represented
graphically, a variety of service indicators can be readily obtained as shown
in Figure 4-0. Let A'(t) and D'(t) denote the derivatives of A(t) and D(t)
with respect to t, respectively. For 0 L t L t@-(i) in which A'(t) L x, there
is no queue. At t = t@-(i), when A'(t) > D'(t), a queue is formed. Then D'(t)
= x in the interval t@-(i) L t L t@-(k). As A'(t) continues to increase with
increasing t, the queue becomes longer since the service rate D'(t) = x cannot
catch up with the arrivals. However, when again A'(t) L D'(t) as t increases,
the queue becomes shorter until it reaches 0 at t = t@-(k). At any given time
t, the queue length is Generally, the arrival rates @g[D]A@-(t) = 1, 2, . . ., n periods of a
process as well as the maximum service rate x are known. Then the cumulative
arrival function and the cumulative departure function can be constructed
systematically together with other pertinent quantities as follows:
1. Starting with the initial conditions D(t-1)=0 and Q(t-1)=0 at t=1, find
the actual service rate at t=1:
2. Starting with A(t-1)=0 at t=1, find the cumulative arrival function for
t=2,3,. . .,n accordingly:
3. Compute the queue length for t=1,2, . . .,n.
4. Compute @g{D}D@-(t) for t=2,3,. . .,n after Q(t-1) is found first for
each t.
5. If A'(t) > x, find the cumulative departure function in the time period
between t@-(i) where a queue is formed and t@-(k) where the queue dissipates.
6. Compute the waiting time @g{D}w for the arrivals which are waiting for
service in interval @g{D}t.
7. Compute the total waiting time W over the time period between t@-(i) and
t@-(k).
8. Compute the average waiting time w for arrivals which are waiting for
service in the process.
This simple, deterministic model has a number of implications for operations
planning. First, an increase in the maximum service rate will result in
reductions in waiting time and the maximum queue length. Such increases might
be obtained by speeding up the service rate such as introducing shorter
inspection procedures or installing faster cranes on a site. Second, altering
the pattern of cumulative arrivals can result in changes in total waiting time
and in the maximum queue length. In particular, if the maximum arrival rate
never exceeds the maximum service rate, no queue will form, or if the arrival
rate always exceeds the maximum service rate, the bottleneck cannot be
dispersed. Both cases are shown in Figure 4-0.
A practical means to alter the arrival function and obtain these benefits is
to inaugurate a reservation system for customers. Even without drawing a graph
such as Figure 4-0, good operations planners should consider the effects of
different operation or service rates on the flow of work. Clearly, service
rates less than the expected arrival rate of work will result in resource
bottlenecks on a job.
Suppose that arrivals of "customers" to a queue are not deterministic or
known as in Figure 4-0. In particular, suppose that "customers" such as joints
are completed or crane loads arrive at random intervals. What are the
implications for the smooth flow of work? Unfortunately, bottlenecks and
queues may arise in this situation even if the maximum service rate is larger
than the average or expected arrival rate of customers. This occurs because
random arrivals will often bunch together, thereby temporarily exceeding the
capacity of the system. While the average arrival rate may not change over
time, temporary resource shortages can occur in this circumstance.
Let w be the average waiting time, a be the average arrival rate of
customers, and x be the deterministic constant service rate (in customers per
unit of time). Then, the expected average time for a customer in this situation
is given by:[In the literature of queueing theory, this formula represents an
M/D/1 queue, meaning that the arrival process is Markovian or random, the
service time is fixed, only one server exists, and the system is in "steady
state," implying that the service time and average arrival rate are constant.
Altering these assumptions would require changes in the waiting time formula;
for example, if service times were also random, the waiting time formula would
not have the 2 shown in the denominator of Eq. (4.4.13). For more details on
queueing systems, see Newell, G.F. Applications of Queueing Theory, Chapman
and Hall, London, 1982.]
If the average utilization rate of the service is defined as the ratio of the
average arrival rate and the constant service rate, i.e.,
Both of the simple models of service performance described above are limited
to single servers. In operations planning, it is commonly the case that
numerous operators are available and numerous stages of operations exist. In
these circumstances, a planner typically attempts to match the service rates
occurring at different stages in the process. For example, construction of a
high rise building involves a series of operations on each floor, including
erection of structural elements, pouring or assembling a floor, construction of
walls, installation of HVAC (Heating, ventilating and air conditioning)
equipment, installation of plumbing and electric wiring, etc. A smooth
construction process would have each of these various activities occurring at
different floors at the same time without large time gaps between activities on
any particular floor. Thus, floors would be installed soon after erection of
structural elements, walls would follow subsequently, and so on. From the
standpoint of a queueing system, the planning problem is to insure that the
productivity or service rate per floor of these different activities are
approximately equal, so that one crew is not continually waiting on the
completion of a preceding activity or interfering with a following activity.
In the realm of manufacturing systems, creating this balance among operations
is called assembly line balancing.
Example 4-15: Effect of a crane breakdown
Suppose that loads for a crane are arriving at a steady rate of one every
ten minutes. The crane has the capacity to handle one load every five minutes.
Suppose further that the crane breaks down for ninety minutes. How many loads
are delayed, what is the total delay, and how long will be required before the
crane can catch up with the backlog of loads?
The cumulative arrival and service functions are graphed in Figure 4-0.
Starting with the breakdown at time zero, nine loads arrive during the ninety
minute repair time. From Figure 4-0, an additional nine loads arrive before
the entire queue is served. Algebraically, the required time for service, t,
can be calculated by noted that the number of arrivals must equal the number of
loads served. Thus:
Example 4-16: Waiting time with random arrivals
Suppose that material loads to be inspected arrive randomly but with an
average of 5 arrivals per hour. Each load requires ten minutes for an
inspection, so an inspector can handle six loads per hour. Inspections must be
completed before the material can be unloaded from a truck. The cost per hour
of holding a material load in waiting is $ 30, representing the cost of a
driver and a truck. In this example, the arrival rate, a, equals 5 arrivals
per hour and the service rate, x, equals 6 material loads per hour. Then, the
average waiting time of any material load for u = 5/6 is: In contrast, if the possible service rate is x=10 material loads per hour,
then the expected waiting time of any material load for u = 5/10 = 0.5 is: Example 4-17: Delay of lift loads on a building site
Suppose that a single crane is available on a building site and that each
lift requires three minutes including the time for attaching loads. suppose
further that the cumulative arrivals of lift loads at different time periods
are as follows:
The maximum service rate x = 60 min/3 min per lift = 20 lifts per minute.
The detailed computation can be carried out in the Table 4-2, and the graph of
A(t) and D(t) is given in Figure 4-10.
The costs of a constructed facility to the owner include both the initial
capital cost and the subsequent operation and maintenance costs. Each of these
major cost categories consists of a number of cost components.
The capital cost for a construction project includes the expenses related to
the following activities:
It is important for design professionals and construction managers to
realize that while the construction cost may be the single largest component of
the capital cost, other cost components are not insignificant. For example,
land acquisition costs are a major expenditure for building construction in
high-density urban areas, and construction financing costs can reach the same
order of magnitude as the construction cost in large projects such as the
construction of nuclear power plants.
From the owner's perspective, it is equally important to estimate the
corresponding operation and maintenance cost of each alternative for a proposed
facility in order to analyze the life cycle costs. The large expenditures
needed for facility maintenance, especially for publicly owned infrastructure,
are reminders of the neglect in the past to consider fully the implications of
operation and maintenance cost in the design stage.
In this chapter, we shall focus on the estimation of construction cost, with
only occasional reference to other cost components. In Chapter 6, we shall
deal with the economic evaluation of a constructed facility on the basis of
both the capital cost and the operation and maintenance cost in the life cycle
of the facility. It is at this stage that tradeoffs between operating and
capital costs can be analyzed.
Example 5-1: Energy project resource demands(This example was adapted with
permission from a paper, "Forecasting Industry Resources," presented by A.R.
Crosby at the Institution of Chemical Engineers in London, November 4, 1981.)
The resources demands for three types of major energy projects investigated
during the energy crisis in the 1970's are shown in Table 5-0. These projects
are: (1) an oil shale project with a capacity of 50,000 barrels of oil product
per day; (2) a coal gasification project that makes gas with a heating value of
320 billions of British thermal units per day, or equivalent to about 50,000
barrels of oil product per day; and (3) a tar sand project with a capacity of
150,000 barrels of oil product per day.
For each project, the cost in billions of dollars, the engineering manpower
requirement for basic design in thousands of hours, the engineering manpower
requirement for detailed engineering in millions of hours, the skilled labor
requirement for construction in millions of hours and the material requirement
in billions of dollars are shown in Table 5-0. To build several projects of
such an order of magnitude concurrently could drive up the costs and strain the
availability of all resources required to complete the projects. Consequently,
cost estimation often represents an exercise in professional judgment instead
of merely compiling a bill of quantities and collecting cost data to reach a
total estimate mechanically.
______________________________________________________________________________
!!!Oil Shale!!! Coal Gasification!!! Tar Sands
!!! 50,000!!! 320 billions!!! 150,000
!!!barrels/day!!! BTU/day!!! barrels/day
Cost ($ billion)!!! 2.5!!! 4!!! 8 to 10
Basic Design !!!80!!! 200!!! 100
(Thousands of hours)
Detailed Engineering!!! 3 to 4!!! 4 to 5!!! 6 to 8
(Millions of hours)
Construction !!!20!!! 30!!! 40
(Millions of hours)
Materials ($ billion)!!! 1!!! 2!!! 2.5
Source: Exxon Research and Engineering Company, Florham Park, NJ
______________________________________________________________________________
Cost estimating is one of the most important steps in project management. A
cost estimate establishes the base line of the project cost at different stages
of development of the project. A cost estimate at a given stage of project
development represents a prediction provided by the cost engineer or estimator
on the basis of available data. According to the American Association of Cost
Engineers, cost engineering is defined as that area of engineering practice
where engineering judgment and experience are utilized in the application of
scientific principles and techniques to the problem of cost estimation, cost
control and profitability.
Virtually all cost estimation is performed according to one or some
combination of the following basic approaches:
Production function. In microeconomics, the relationship between the output
of a process and the necessary resources is referred to as the production
function. In construction, the production function may be expressed by the
relationship between the volume of construction and a factor of production such
as labor or capital. A production function relates the amount or volume of
output to the various inputs of labor, material and equipment. For example,
the amount of output Q may be derived as a function of various input factors
x@-(1), x@-(2), ..., x@-(n) by means of mathematical and/or statistical
methods. Thus, for a specified level of output, we may attempt to find a set
of values for the input factors so as to minimize the production cost. The
relationship between the size of a building project (expressed in square feet)
to the input labor (expressed in labor hours per square foot) is an example of
a production function for construction. Several such production functions are
shown in Figure 3-3 of Chapter 3.
Empirical cost inference. Empirical estimation of cost functions requires
statistical techniques which relate the cost of constructing or operating a
facility to a few important characteristics or attributes of the system. The
role of statistical inference is to estimate the best parameter values or
constants in an assumed cost function. Usually, this is accomplished by means
of regression analysis techniques.
Unit costs for bill of quantities. A unit cost is assigned to each of the
facility components or tasks as represented by the bill of quantities. The
total cost is the summation of the products of the quantities multiplied by the
corresponding unit costs. The unit cost method is straightforward in principle
but quite laborious in application. The initial step is to break down or
disaggregate a process into a number of tasks. Collectively, these tasks must
be completed for the construction of a facility. Once these tasks are defined
and quantities representing these tasks are assessed, a unit cost is assigned
to each and then the total cost is determined by summing the costs incurred in
each task. The level of detail in decomposing into tasks will vary
considerably from one estimate to another.
Allocation of joint costs. Allocations of cost from existing accounts may
be used to develop a cost function of a operation. The basic idea in this
method is that each expenditure item can be assigned to particular
characteristics of the operation. Ideally, the allocation of joint costs
should be causally related to the category of basic costs in an allocation
process. In many instances, however, a causal relationship between the
allocation factor and the cost item cannot be identified or may not exist. For
example, in construction projects, the accounts for basic costs may be
classified according to (1) labor, (2) material, (3) construction equipment,
(4) construction supervision, and (5) general office overhead. These basic
costs may then be allocated proportionally to various tasks which are
subdivisions of a project.
Construction cost constitutes only a fraction, though a substantial
fraction, of the total project cost. However, it is the part of the cost under
the control of the construction project manager. The required levels of
accuracy of construction cost estimates vary at different stages of project
development, ranging from ball park figures in the early stage to fairly
reliable figures for budget control prior to construction. Since design
decisions made at the beginning stage of a project life cycle are more
tentative than those made at a later stage, the cost estimates made at the
earlier stage are expected to be less accurate. Generally, the accuracy of a
cost estimate will reflect the information available at the time of estimation.
Construction cost estimates may be viewed from different perspectives
because of different institutional requirements. In spite of the many types of
cost estimates used at different stages of a project, cost estimates can best
be classified into three major categories according to their functions. A
construction cost estimate serves one of the three basic functions: design,
bid and control. For establishing the financing of a project, either a design
estimate or a bid estimate is used.
1. Design Estimates. For the owner or its designated design professionals,
the types of cost estimates encountered run parallel with the planning and
design as follows:
2. Bid Estimates. For the contractor, a bid estimate submitted to the owner
either for competitive bidding or negotiation consists of direct construction
cost including field supervision, plus a markup to cover general overhead and
profits. The direct cost of construction for bid estimates is usually derived
from a combination of the following approaches.
3. Control Estimates. For monitoring the project during construction, a
control estimate is derived from available information to establish:
In the planning and design stages of a project, various design estimates
reflect the progress of the design. At the very early stage, the screening
estimate or order of magnitude estimate is usually made before the facility
is designed, and must therefore rely on the cost data of similar facilities
built in the past. A preliminary estimate or conceptual estimate is based on
the conceptual design of the facility at the state when the basic technologies
for the design are known. The detailed estimate or definitive estimate is
made when the scope of work is clearly defined and the detailed design is in
progress so that the essential features of the facility are identifiable. The
engineer's estimate is based on the completed plans and specifications when
they are ready for the owner to solicit bids from construction contractors. In
preparing these estimates, the design professional will include expected
amounts for contractors' overhead and profits.
The costs associated with a facility may be decomposed into a hierarchy of
levels that are appropriate for the purpose of cost estimation. The level of
detail in decomposing the facility into tasks depends on the type of cost
estimate to be prepared. For conceptual estimates, for example, the level of
detail in defining tasks is quite coarse; for detailed estimates, the level of
detail can be quite fine.
As an example, consider the cost estimates for a proposed bridge across a
river. A screening estimate is made for each of the potential alternatives,
such as a tied arch bridge or a cantilever truss bridge. As the bridge type is
selected, e.g. the technology is chosen to be a tied arch bridge instead of
some new bridge form, a preliminary estimate is made on the basis of the layout
of the selected bridge form on the basis of the preliminary or conceptual
design. When the detailed design has progressed to a point when the essential
details are known, a detailed estimate is made on the basis of the well defined
scope of the project. When the detailed plans and specifications are
completed, an engineer's estimate can be made on the basis of items and
quantities of work.
The contractor's bid estimates often reflect the desire of the contractor to
secure the job as well as the estimating tools at its disposal. Some
contractors have well established cost estimating procedures while others do
not. Since only the lowest bidder will be the winner of the contract in most
bidding contests, any effort devoted to cost estimating is a loss to the
contractor who is not a successful bidder. Consequently, the contractor may
put in the least amount of possible effort for making a cost estimate if it
believes that its chance of success is not high.
If a general contractor intends to use subcontractors in the construction of
a facility, it may solicit price quotations for various tasks to be
subcontracted to specialty subcontractors. Thus, the general subcontractor
will shift the burden of cost estimating to subcontractors. If all or part of
the construction is to be undertaken by the general contractor, a bid estimate
may be prepared on the basis of the quantity takeoffs from the plans provided
by the owner or on the basis of the construction procedures devised by the
contractor for implementing the project. For example, the cost of a footing of
a certain type and size may be found in commercial publications on cost data
which can be used to facilitate cost estimates from quantity takeoffs.
However, the contractor may want to assess the actual cost of construction by
considering the actual construction procedures to be used and the associated
costs if the project is deemed to be different from typical designs. Hence,
items such as labor, material and equipment needed to perform various tasks may
be used as parameters for the cost estimates.
Both the owner and the contractor must adopt some base line for cost control
during the construction. For the owner, a budget estimate must be adopted
early enough for planning long term financing of the facility. Consequently,
the detailed estimate is often used as the budget estimate since it is
sufficient definitive to reflect the project scope and is available long before
the engineer's estimate. As the work progresses, the budgeted cost must be
revised periodically to reflect the estimated cost to completion. A revised
estimated cost is necessary either because of change orders initiated by the
owner or due to unexpected cost overruns or savings.
For the contractor, the bid estimate is usually regarded as the budget
estimate, which will be used for control purposes as well as for planning
construction financing. The budgeted cost should also be updated periodically
to reflect the estimated cost to completion as well as to insure adequate cash
flows for the completion of the project.
Example 5-2: Screening estimate of a grouting seal beneath a landfill(This
example is adapted from a cost estimate in A.L. Tolman, A.P. Ballestero, W.W.
Beck and G.H. Emrich, Guidance Manual for Minimizing Pollution from Waste
Disposal Sites, Municipal Environmental Research Laboratory, U.S.
Environmental Protection Agency, Cincinatti, Ohio, 1978.)
One of the methods of isolating a landfill from groundwater is to create a
bowl-shaped bottom seal beneath the site as shown in Figure 5-0. The seal is
constructed by pumping or pressure-injecting grout under the existing landfill.
Holes are bored at regular intervals throughout the landfill for this purpose
and the grout tubes are extended from the surface to the bottom of the
landfill. A layer of soil at a minimum of 5 ft. thick is left between the
grouted material and the landfill contents to allow for irregularities in the
bottom of the landfill. The grout liner can be between 4 and 6 feet thick. A
typical material would be Portland cement grout pumped under pressure through
tubes to fill voids in the soil. This grout would then harden into a
permanent, impermeable liner.
The work items in this project include (1) drilling exploratory bore holes
at 50 ft. intervals for grout tubes, and (2) pumping grout into the voids of a
soil layer between 4 and 6 feet thick. The quantities for these two items are
estimated on the basis of the landfill area:
The volume of the soil layer for grouting is estimated to be:
The unit cost for drilling exploratory bore holes is estimated to be between
$3 and $10 per foot (in 1978 dollars) including all expenses. Thus, the total
cost of boring will be between (2,880)(3) = $ 8,640 and (2,880)(10) = $ 28,800.
The unit cost of Portland cement grout pumped into place is between $ 4 and $
10 per cubic foot including overhead and profit. In addition to the variation
in the unit cost, the total cost of the bottom seal will depend upon the
thickness of the soil layer grouted and the proportion of voids in the soil.
That is:
The total cost of drilling bore holes is so small in comparison with the
cost of grouting that the former can be omitted in the screening estimate.
Furthermore, the range of unit cost varies greatly with soil characteristics,
and the engineer must exercise judgment in narrowing the range of the total
cost. Alternatively, additional soil tests can be used to better estimate the
unit cost of pumping grout and the proportion of voids in the soil. Suppose
that, in addition to ignoring the cost of bore holes, an average value of a 5
ft. soil layer with 25% voids is used together with a unit cost of $ 7 per cu.
ft. of Portland cement grouting. In this case, the total project cost is
estimated to be:
Example 5-3: Example of engineer's estimate and contractors' bids(See
"Utah Interstate Forges On," ENR, July 2, 1987, p. 39.)
The engineer's estimate for a project involving 14 miles of Interstate 70
roadway in Utah was $ 20,950,859. Bids were submitted on March 10, 1987 for
completing the project within 320 working days. The three low bidders were:
The unit prices for different items of work submitted for this project by
(1) Ball, Ball & Brosame, Inc. and (2) National Projects, Inc. are shown in
Table 5-0. The similarity of their unit prices for some items and the
disparity in others submitted by the two contractors can be noted.
Screening cost estimates are often based on a single variable representing
the capacity or some physical measure of the design such as floor area in
buildings, length of highways, volume of storage bins and production volumes of
processing plants. Costs do not always vary linearly with respect to different
facility sizes. Typically, scale economies or diseconomies exist. If the
average cost per unit of capacity is declining, then scale economies exist.
Conversely, scale diseconomies exist if average costs increase with greater
size. Empirical data are sought to establish the economies of scale for
various types of facility, if they exist, in order to take advantage of lower
costs per unit of capacity.
Let x be a variable representing the facility capacity, and y be the
resulting construction cost. Then, a linear cost relationship can be expressed
in the form:
A nonlinear cost relationship between the facility capacity x and
construction cost y can often be represented in the form:
A nonlinear cost relationship often used in estimating the cost of a new
industrial processing plant from the known cost of an existing facility of a
different size is known as the exponential rule. Let y@-(n) be the known cost
of an existing facility with capacity Q@-(n), and y be the estimated cost of
the new facility which has a capacity Q. Then, from the empirical data, it can
be assumed that: Example 5-4: Determination of m for the exponential rule
The empirical cost data from a number of sewage treatment plants are plotted
on a log-log scale for ln(Q/Q@-(n)) and ln(y/y@-(n)) and a linear relationship
between these logarithmic ratios is shown in Figure 5-0. For (Q/Q@-(n)) = 1 or
ln(Q/Q@-(n)) = 0, ln(y/y@-(n)) = 0; and for Q/Q@-(n) = 2 or ln(Q/Q@-(n)) =
0.301, ln(y/y@-(n)) = 0.1765. Since m is the slope of the line in the figure,
it can be determined from the geometric relation as follows:
Example 5-5: Cost exponents for water and wastewater treatment plants[This
and the next example have been adapted from P.M. Berthouex, "Evaluating
Economy of Scale," Journal of the Water Pollution Control Federation, Vol. 44,
No. 11, November 1972, pp. 2111-2118.]
The magnitude of the cost exponent m in the exponential rule provides a
simple measure of the economy of scale associated with building extra capacity
for future growth and system reliability for the present in the design of
treatment plants. When m is small, there is considerable incentive to provide
extra capacity since scale economies exist as illustrated in Figure 5-0. When
m is close to 1, the cost is directly proportional to the design capacity. The
value of m tends to increase as the number of duplicate units in a system
increases. The values of m for several types of treatment plants with
different plant components derived from statistical correlation of actual
construction costs are shown in Table 5--1.
Example 5-6: Cost data for the exponential rule
The exponential rule as represented by Equation (5.4) can be expressed in a
different form as: The estimated values of K and m for various water and sewage treatment plant
components are shown in Table 5--1. The K values are based on 1968 dollars.
The range of data from which the K and m values are derived in the primary
sources should be observed in order to use them in making cost estimates.
As an example, take K = $ 399 and m = 0.60 for a primary sedimentation
component in Table 5--1. For a proposed new plant with the primary
sedimentation process having a capacity of 15,000 sq. ft., the estimated cost
(in 1968 dollars) is:
If the design technology for a facility has been specified, the project can
be decomposed into elements at various levels of detail for the purpose of cost
estimation. The unit cost for each element in the bill of quantities must be
assessed in order to compute the total construction cost. This concept is
applicable to both design estimates and bid estimates, although different
elements may be selected in the decomposition.
For design estimates, the unit cost method is commonly used when the project
is decomposed into elements at various levels of a hierarchy as follows:
1. Preliminary Estimates. The project is decomposed into major structural
systems or production equipment items, e.g. the entire floor of a building or a
cooling system for a processing plant.
2. Detailed Estimates. The project is decomposed into components of
various major systems, i.e., a single floor panel for a building or a heat
exchanger for a cooling system.
3. Engineer's Estimates. The project is decomposed into detailed items of
various components as warranted by the available cost data. Examples of
detailed items are slabs and beams in a floor panel, or the piping and
connections for a heat exchanger.
For bid estimates, the unit cost method can also be applied even though the
contractor may choose to decompose the project into different levels in a
hierarchy as follows:
1. Subcontractor Quotations. The decomposition of a project into
subcontractor items for quotation involves a minimum amount of work for the
general contractor. However, the accuracy of the resulting estimate depends on
the reliability of the subcontractors since the general contractor selects one
among several contractor quotations submitted for each item of subcontracted
work.
2. Quantity Takeoffs. The decomposition of a project into items of
quantities that are measured (or taken off) from the engineer's plan will
result in a procedure similar to that adopted for a detailed estimate or an
engineer's estimate by the design professional. The levels of detail may vary
according to the desire of the general contractor and the availability of cost
data.
3. Construction Procedures. If the construction procedure of a proposed
project is used as the basis of a cost estimate, the project may be decomposed
into items such as labor, material and equipment needed to perform various
tasks in the projects.
Suppose that a project is decomposed into n elements for cost estimation.
Let Q@-(i) be the quantity of the i@+(th) element and u@-(i) be the
corresponding unit cost. Then, the total cost of the project is given by:
A special application of the unit cost method is the "factored estimate"
commonly used in process industries. Usually, an industrial process requires
several major equipment components such as furnaces, towers drums and pump in a
chemical processing plant, plus ancillary items such as piping, valves and
electrical elements. The total cost of a project is dominated by the costs of
purchasing and installing the major equipment components and their ancillary
items. Let C@-(i) be the purchase cost of a major equipment component i and
f@-(i) be a factor accounting for the cost of ancillary items needed for the
installation of this equipment component i. Then, the total cost of a project
is estimated by:
Consider the simple case for which costs of labor, material and equipment
are assigned to all tasks. Suppose that a project is decomposed into n tasks.
Let Q@-[i] be the quantity of work for task i, M@-[i] be the unit material cost
of task i, E@-(i) be the unit equipment rate for task i, L@-[i] be the units of
labor required per unit of Q@-[i], and W@-[i] be the wage rate associated with
L@-[i]. In this case, the total cost y is: Note that W@-(i)L@-(i) yields the labor cost per unit of Q@-(i), or the
labor unit cost of task i. Consequently, the units for all terms in Equation
(5.5.5) are consistent.
Example 5-7: Decomposition of a building foundation into design and
construction elements.
The concept of decomposition is illustrated by the example of estimating the
costs of a building foundation excluding excavation as shown in Table 5--1 in
which the decomposed design elements are shown on horizontal lines and the
decomposed contract elements are shown in vertical columns. For a design
estimate, the decomposition of the project into footings, foundation walls and
elevator pit is preferred since the designer can easily keep track of these
design elements; however, for a bid estimate, the decomposition of the project
into formwork, reinforcing bars and concrete may be preferred since the
contractor can get quotations of such contract items more conveniently from
specialty subcontractors.
Example 5-8: Cost estimate using labor, material and equipment rates.
For the given quantities of work Q@-(i) for the concrete foundation of a
building and the labor, material and equipment rates in Table 5--1, the cost
estimate is computed on the basis of Equation (5.5.5). The result is tabulated
in the last column of the same table.
The principle of allocating joint costs to various elements in a project is
often used in cost estimating. Because of the difficulty in establishing
casual relationship between each element and its associated cost, the joint
costs are often prorated in proportion to the basic costs for various elements.
One common application is found in the allocation of field supervision cost
among the basic costs of various elements based on labor, material and
equipment costs, and the allocation of the general overhead cost to various
elements according to the basic and field supervision cost. Suppose that a
project is decomposed into n tasks. Let y be the total basic cost for the
project and y@-(i) be the total basic cost for task i. If F is the total field
supervision cost and F@-(i) is the proration of that cost to task i, then a
typical proportional allocation is: Example 5-9: Prorated costs for field supervision and office overhead
If the field supervision cost is $ 13,245 for the project in Table 5-6
(Example 5-8) with a total direct cost of $ 88,300, find the prorated field
supervision costs for various elements of the project. Furthermore, if the
general office overhead charged to the project is 4% of the direct field cost
which is the sum of basic costs and field supervision cost, find the prorated
general office overhead costs for various elements of the project.
For the project, y = $ 88,300 and F = $13,245. Hence:
Example 5-10: A standard cost report for allocating overhead
The reliance on labor expenses as a means of allocating overhead burdens in
typical management accounting systems can be illustrated by the example of a
particular product's standard cost sheet.(See H.T. Johnson and R.S. Kaplan,
Relevance Lost: The Rise and Fall of Management Accounting, Harvard Business
School Press, Boston, MA 1987, p. 185.) Table 5--1 is an actual product's
standard cost sheet of a company following the procedure of using overhead
burden rates assessed per direct labor hour. The material and labor costs for
manufacturing a type of valve were estimated from engineering studies and from
current material and labor prices. These amounts are summarized in Columns 2
and 3 of Table 5--1. The overhead costs shown in Column 4 of Table 5--1 were
obtained by allocating the expenses of several departments to the various
products manufactured in these departments in proportion to the labor cost. As
shown in the last line of the table, the material cost represents 29% of the
total cost, while labor costs are 11% of the total cost. The allocated
overhead cost constitutes 60% of the total cost. Even though material costs
exceed labor costs, only the labor costs are used in allocating overhead.
Although this type of allocation method is common in industry, the arbitrary
allocation of joint costs introduces unintended cross subsidies among products
and may produce adverse consequences on sales and profits. For example, a
particular type of part may incur few overhead expenses in practice, but this
phenomenon would not be reflected in the standard cost report.
Preparing cost estimates normally requires the use of historical data on
construction costs. Historical cost data will be useful for cost estimation
only if they are collected and organized in a way that is compatible with
future applications. Organizations which are engaged in cost estimation
continually should keep a file for their own use. The information must be
updated with respect to changes that will inevitably occur. The format of cost
data, such as unit costs for various items, should be organized according to
the current standard of usage in the organization.
Construction cost data are published in various forms by a number of
organizations. These publications are useful as references for comparison.
Basically, the following types of information are available:
Historical cost data must be used cautiously. Changes in relative prices
may have substantial impacts on construction costs which have increased in
relative price. Unfortunately, systematic changes over a long period of time
for such factors are difficult to predict. Errors in analysis also serve to
introduce uncertainty into cost estimates. It is difficult, of course, to
foresee all the problems which may occur in construction and operation of
facilities. There is some evidence that estimates of construction and
operating costs have tended to persistently understate the actual costs. This
is due to the effects of greater than anticipated increases in costs, changes
in design during the construction process, or overoptimism.
Since the future prices of constructed facilities are influenced by many
uncertain factors, it is important to recognize that this risk must be borne to
some degree by all parties involved, i.e., the owner, the design professionals,
the construction contractors, and the financing institution. It is to the best
interest of all parties that the risk sharing scheme implicit in the
design-construct process adopted by the owner is fully understood by all. When
inflation adjustment provisions have very different risk implications to
various parties, the price level changes will also be treated differently for
various situations.
Example 5-11: Cost data from commercial publications
Cost data from commercial publications often provide useful information for
cost estimating. An example of cost data for earthwork (bulk excavation with a
backhoe) is shown in Figure 5-0, which is reproduced from Building Construction
Cost Data, 1987, by R.S. Means Company, Inc. These excavation costs assume
standard crews with the associated costs summarized in Figure 5-0. For
example, operation of a 2 cubic yard capacity hydraulic backhoe for bulk
excavation would require standard crew B-12C, would have a standard daily
output of (75 c.y./hr)(8 hr) = 600 cubic yards, and would require 0.027 labor
hours per cubic yard of excavation for a total of (600 c.y.)(0.027 hr/c.y.) =
16.2 labor hours. Costs exclusive of overhead and profit (i.e. "bare costs")
as well as total costs including standard overhead and profit rates are shown
in Figure 5-0. Thus, the total bare cost for a standard daily output of 600
cubic yards is (600 c.y.)($ 1.87/c.y.) = $ 1,122. The standard crew B-12C for
this task consists of two equipment operators as shown in Figure 5-0. Using a
daily total of 16 labor hours, the daily bare cost is seen to be $ 1,118, which
is essentially the same as the $ 1,122 obtained from Figure 5-0 except for the
difference due to truncation of decimals in the process of computation. Note
that costs would increase 15% if the excavated material must be loaded onto
trucks (Figure 5-0).
Since historical cost data are often used in making cost estimates, it is
important to note the price level changes over time. Trends in price changes
can also serve as a basis for forecasting future costs. The input price
indices of labor and/or material reflect the price level changes of such input
components of construction; the output price indices, where available, reflect
the price level changes of the completed facilities, thus to some degree also
measuring the productivity of construction.
A price index is a weighted aggregate measure of constant quantities of
goods and services selected for the package. The price index at a subsequent
year represents a proportionate change in the same weighted aggregate measure
because of changes in prices. Let l@-[t] be the price index in year t, and
l@-[t+1] be the price index in the following year t+1. Then, the percent
change in price index for year t+1 is: The best-known indicators of general price changes are the GNP deflators
compiled periodically by the U.S. Department of Commerce, and the consumer
price index (CPI) compiled periodically by the U.S. Department of Labor. They
are widely used as broad gauges of the changes in production costs and in
consumer prices for essential goods and services. Special price indices
related to construction are also collected by industry sources since some input
factors for construction and the outputs from construction may
disproportionately outpace or fall behind the general price indices. Examples
of special price indices for construction input factors are the wholesale
Building Material Price and Building Trades Union Wages, both compiled by the
U.S. Department of Labor. In addition, the construction cost index and the
building cost index are reported periodically in the Engineering News-Record
(ENR). Both ENR cost indices measure the effects of wage rate and material
price trends, but they are not adjusted for productivity, efficiency,
competitive conditions, or technology changes. Consequently, all these indices
measure only the price changes of respective construction input factors as
represented by constant quantities of material and/or labor. On the other
hand, the price indices of various types of completed facilities reflect the
price changes of construction output including all pertinent factors in the
construction process. The building construction output indices compiled by
Turner Construction Company and Handy-Whitman Utilities are compiled in the
U.S. Statistical Abstracts published each year.
Figure 5-0 shows the Gross National Product (GNP) price deflator and the ENR
building index from 1955 to 1985, using 1982 as the base year with an index of
100. Before 1976, the ENR building index rose more sharply than the GNP
deflator except in 1973, whereas from 1976 to 1985, both indices practically
coincide. The ENR building index is an input price index reflecting the cost
of inputs to the building construction process such as wage rates and standard
material costs. Figure 5-0 shows the Turner Construction Company building cost
index, also using 1982 as the base year for an index of 100. The Handy-Whitman
Utilities building cost index and the GNP price deflator are almost identical
to the Turner index, and therefore cannot be detected as separate curves if
plotted in Figure 5-0. Both the Turner and the Handy-Whitman indices are
referred to as output price indices because they represent the cost of
completed buildings. Before 1982, the Turner index runs very close to the ENR
building index, indicating no significant changes in productivity. However,
from 1982 to 1985, the Turner index increases slightly faster than the ENR
building index, suggesting a possible decline in productivity. In view of the
fact that the productivity of manufacturing industries has improved
significantly from 1955 to 1985, the performance of the construction industry
has been viewed as being stagnant by comparison. A summary of these indices
from 1970 to 1985 is also shown in Table 5--1 for illustration.
Since construction costs vary in different regions of the United States and
in all parts of the world, locational indices showing the construction cost at
a specific location relative to the national trend are useful for cost
estimation. ENR publishes periodically the indices of local construction
costs at the major cities in different regions of the United States as
percentages of local to national costs.
When the inflation rate is relatively small, i.e., less than 10%, it is
convenient to select a single price index to measure the inflationary
conditions in construction and thus to deal only with a single set of price
change rates in forecasting. Let j@-[t] be the price change rate in year t+1
over the price in year t. If the base year is denoted as year 0 (t=0), then
the price change rates at years 1,2,...t are j@-[1],j@-[2],...j@-[t],
respectively. Let A@-[t] be the cost in year t expressed in base-year dollars
and A@+[']@-[t] be the cost in year t expressed in then-current dollars. Then: If the prices of certain key items affecting the estimates of future
benefits and costs are expected to escalate faster than the general price
levels, it may become necessary to consider the differential price changes over
and above the general inflation rate. For example, during the period between
1973 through 1979, it was customary to assume that fuel costs would escalate
faster than the general price levels. With hindsight in 1983, the assumption
for estimating costs over many years would have been different. Because of the
uncertainty in the future, the use of differential inflation rates for special
items should be judicious.
Future forecasts of costs will be uncertain: the actual expenses may be much
lower or much higher than those forecasted. This uncertainty arises from
technological changes, changes in relative prices, inaccurate forecasts of
underlying socioeconomic conditions, analytical errors, and other factors. For
the purpose of forecasting, it is often sufficient to project the trend of
future prices by using a constant rate j for price changes in each year over a
period of t years, then Example 5-12: Changes in highway and building costs
Table 5--1 shows the change of standard highway costs from 1940 to 1980, and
Table 5--1 shows the change of residential building costs from 1970 to 1980.
For these series, the quality of the finished product was held roughly
equivalent. In each case, the rate of cost increase was substantially above
the rate of inflation after 1970. Indeed, the real cost increase between 1970
and 1980 was in excess of three percent per year in both cases. However, these
data also show some cause for optimism. For the case of the standard highway,
real cost decreases took place in the period from l940 to l980.
Unfortunately, comparable indices of outputs are not being compiled on a
nationwide basis for other types of construction.
In the screening estimate of a new facility, a single parameter is often
used to describe a cost function. For example, the cost of a power plant is a
function of electricity generating capacity expressed in megawatts, or the cost
of a sewage treatment plant as a function of waste flow expressed in million
gallons per day.
The general conditions for the application of the single parameter cost
function for screening estimates are:
Example 5-13: Screening estimate for a refinery
The total construction cost of a refinery with a production capacity of
200,000 bbl/day in Gary, Indiana, completed in 1981 was $100 million. It is
proposed that a similar refinery with a production capacity of 300,000 bbl/day
be built in Los Angeles, California, for completion in 1983. For the
additional information given below, make an order of magnitude estimate of the
cost of the proposed plant.
!!!!!!!!! Unit Price
Items!!!Unit!!!Qty.!!! 1!!! 2
Mobilization.!!!ls!!!1!!!115,000!!!569,554.!
Removal, berm.!!!lf!!!8,020!!!1.00!!!1.50.!!
Finish subgrade.!!!sy!!!1,207,500!!!0.50!!!0.30.!!!s
Surface ditches.!!!lf!!!525!!!2.00!!!1.00.!!
Excavation structures.!!!cy!!!7,000!!!3.00!!!5.00.!!
Base course, untreated, 3/4".!!!ton!!!362,200!!!4.50!!!5.00.!!!ton!!!362,200!!
Lean concrete, 4" thick.!!!sy!!!820,310!!!3.10!!!3.00.!!!sy!!!820,310!!!3.10
PCC, pavement, 10" thick.!!!sy!!!706,010!!!10.90!!!12.00.!!!sy!!!706,010!!!10.
Concrete, ci AA(AE).!!!ls!!!1!!!200,000!!!190,000.!!
Small structure.!!!cy!!!50!!!500!!!475.!!!
Barrier, precast.!!!lf!!!7,920!!!15.00!!!16.00.!!!
Flatwork, 4" thick.!!!sy!!!7,410!!!10.00!!!8.00.!!
10" thick.!!!sy!!!4,241!!!20.00!!!27.00.!!
Slope protection.!!!sy!!!2,104!!!25.00!!!30.00.!!!
Metal, end section, 15".!!!ea!!!39!!!100!!!125.!!!ea
18".!!!ea!!!3!!!150!!!200
Post, right-of-way, modification.!!!lf!!!4,700!!!3.00!!!2.50.!!!lf!!!4,700!!
Salvage & relay pipe.!!!lf!!!1,680!!!5.00!!!12.00.!!
Loose riprap.!!!cy!!!32!!!40.00!!!30.00.!!!c
Braced posts.!!!ea!!!54!!!100!!!110
Delineators, type I.!!!lb!!!1,330!!!12.00!!!12.00.!!
type II.!!!ea!!!140!!!15.00!!!12.00.!!!ea!
Constructive signs fixed.!!!sf!!!52,600!!!0.10!!!0.40.!!!sf!!!52,600!!!0.10!!!
Barricades, type III.!!!lf!!!29,500!!!0.20!!!0.20.
Warning lights.!!!day!!!6,300!!!0.10!!!0.50.
Pavement marking, epoxy material, black.!!!gal!!!475!!!90.00!!!100.!!!gal!!!47
Yellow.!!!gal!!!740!!!90.00!!!80.00.!!!gal
White.!!!gal!!!985!!!90.00!!!70.00.!!!gal!
Plowable, one way white.!!!ea!!!342!!!50.00!!!20.00.!!!ea!!!342!!!50.00!!!20
Topsoil, contractor furnished.!!!cy!!!260!!!10.00!!!6.00.!!!cy!!!260!!!10.00!!
Seedling, method A.!!!acr!!!103!!!150!!!200.
Excelsior blanket.!!!sy!!!500!!!2.00!!!2.00.
!!!!!!!!! Unit Price
Items!!!Unit!!!Qty.!!! 1!!! 2
Corrugated, metal pipe, 18".!!!lf!!!580!!!20.00!!!18.00.!!!lf!!!580!!!20.00!!!
Polyethylene pipe, 12".!!!lf!!!2,250!!!15.00!!!13.00.!!!lf!!!2,250!!!15.00!!
Catch basin grate & frame.!!!ea!!!35!!!350!!!280.!!!
Equal opportunity training.!!!hr!!!18,000!!!0.80!!!0.80.!!!hr!!!18,000!!!0.80!
Granular backfill borrow.!!!cy!!!274!!!10.00!!!16.00
Drill caisson, 2' x 6".!!!lf!!!722!!!100!!!80.00.!!!
Flagging.!!!hr!!!20,000!!!8.25!!!12.50.!!!hr
Prestressed concrete member
type IV, 141' x 4".!!!ea!!!7!!!12,000!!!16,000.!!!
132' x 4".!!!ea!!!6!!!11,000!!!14,000.!!!e
Reinforced steel.!!!lb!!!6,300!!!0.60!!!0.50
Epoxy coated.!!!lb!!!122,241!!!0.55!!!0.50
Structural steel.!!!ls!!!1!!!5,000!!!1,600.!
Sign, covering.!!!sf!!!16!!!10.00!!!4.00.!!!
type C-2, wood post.!!!sf!!!98!!!15.00!!!17.00.!!!
24".!!!ea!!!3!!!100!!!400
30".!!!ea!!!2!!!100!!!160
48".!!!ea!!!11!!!200!!!300.!!!ea!
Auxiliary.!!!sf!!!61!!!15.00!!!12.00.!!!sf
Steel post, 48" x 60".!!!ea!!!11!!!500!!!700.!!!ea
type 3, wood post.!!!sf!!!669!!!15.00!!!19.00.!!!s
24".!!!ea!!!23!!!100!!!125.!!!ea!
30".!!!ea!!!1!!!100!!!150
36".!!!ea!!!12!!!150!!!180.!!!ea!
42" x 60".!!!ea!!!8!!!150!!!220.!
48".!!!ea!!!7!!!200!!!270
Auxiliary.!!!sf!!!135!!!15.00!!!13.00.!!!s
Steel post.!!!sf!!!1,610!!!40.00!!!35.00.!
12" x 36".!!!ea!!!28!!!100!!!150.
Foundation, concrete.!!!ea!!!60!!!300!!!650.!!!ea!
Barricade, 48" x 42".!!!ea!!!40!!!100!!!100.
Wood post, road closed.!!!lf!!!100!!!30.00!!!36.00
Treatment Plant!!!Exponent!!!Capacity Range
Type!!! m!!!(millions of gallons per day)
1. Water treatment!!! 0.67!!! 1-100
2. Waste treatment!!!
Primary with digestion (small)!!! 0.55!!! 0.1-10
Primary with digestion (large)!!! 0.75!!! 0.7-100
Trickling filter!!! 0.60!!! 0.1-20
Activated sludge!!! 0.77!!! 0.1-100
Stabilization ponds!!! 0.57!!! 0.1-100
Note: Data are collected from various sources by P.M. Berthouex. See the
references in his article for the primary sources.
Processing!!!Unit of!!!K value!!! m
Unit!!!Capacity!!!(1968 $)!!!value
1. Liquid processing
Oil separation!!!mgd!!!58,000!!!0.84
Hydroclone degritter!!!mgd!!!3,820!!!0.35
Primary sedimentation!!!sq. ft.!!!399!!!0.60
Furial clarifier!!!sq. ft.!!!700!!!0.57
Sludge aeration basin!!!mil. gal.!!!170,000!!!0.50
Tickling filter!!!sq. ft.!!!21,000!!!0.71
Aerated lagoon basin!!!mil. gal.!!!46,000!!!0.67
Equalization!!!mil. gal.!!!72,000!!!0.52
Neutralization!!!mgd!!!60,000!!!0.70
2. Sludge handling
Digestion!!!cu. ft.!!!67,500!!!0.59
Vacuum filter!!!sq. ft.!!!9,360!!!0.84
Centrifuge!!!lbs dry !!!318!!!0.81
!!! solids/hr.
Note: Data are collected from various sources by P.M. Berthouex. See the
references in his article for the primary sources.
!!! !!! Material!!! Equipment!!!
Wage!!! Labor!!! Labor!!! Direct
!!! Quantity!!! Unit Cost!!! Unit Cost!!!
Rate!!! Input!!! Unit Cost!!! Cost
Description!!! Q@-(i)!!! M@-(i)!!! E@-(i)!!!
W@-(i)!!! L@-(i)!!! W@-(i)L@-(i)!!! y@-(i)
Formwork!!! 12,000 ft@+(2)!!! $ 0.4/ft@+(2)!!!
$ 0.8/ft@+(2)!!! $15/hr!!! 0.2 hr/ft
@+(2)!!!$ 3.0/ft@+(2)!!! $ 50,400
Re-bars!!! 4,000 lb!!! $ 0.2/lb!!!
$ 0.3/lb!!! $ 15/hr!!! 0.04 hr/lb!!!
$ 0.6/lb!!! $ 4,400
Concrete!!! 500 yd@+(3)!!! $ 5.0/yd@+(3)!!!
$ 50/yd@+(3)!!! $ 15/hr!!! 0.8 hr/yd@+(3)!!!
$12.0/yd@+(3)!!! $ 33,500
Total!!! !!!!!! !!!
!!! !!! !!! $ 88,300
!!!Material!!!Labor!!!Overhead!!!Total
!!! Cost!!! Cost!!! Cost!!!Cost
PURCHASED PART!!!$1.1980!!!!!!!!!$1.1980
OPERATION
Drill, face, tap (2)!!!!!!
$0.0438!!!$0.2404!!! 0.2842
Degrease!!!!!! 0.0031!!!
0.0337!!! 0.0368
Remove burs!!!!!! 0.0577!!!
0.3241!!! 0.3818
Total Cost, This Item!!! 1.1980!!!
0.1046!!! 0.5982!!! 1.9008
Other subassemblies!!! 0.3253!!!
0.2994!!! 1.8519!!!
2.4766
Total Cost,
Subassemblies!!! 1.5233!!! 0.4040!!!
2.4501!!! 4.3773
Assemble and test!!!!!! 0.1469!!!
0.4987!!! 0.6456
Pack without paper!!!!!! 0.0234!!!
0.1349!!! 0.1583
Total Cost, This Item!!!$1.5233!!!
$0.5743!!!$3.0837!!!$5.1813
COST COMPONENT %!!! 29%!!!
11%!!! 60%!!! 100%
From H. Thomas Johnson and Robert S. Kaplan, Relevance Lost: The Rise and
Fall of Management Accounting, Harvard Business School Press, Boston, MA.
Reprinted with permission.
______________________________________________________________________________
!!!!!!!!!Turner
!!!!!!ENR!!!Construction!!!Handy-Whitman
Year!!!GNP!!!Building!!!Co. Building!!!Utilities Building
!!!Deflator!!!Cost Index!!!Cost Index!!!Cost Index
1970!!!43!!!37!!!39!!!38
1971!!!45!!!43!!!44!!!41
1972!!!47!!!47!!!47!!!45
1973!!!50!!!51!!!49!!!49
1974!!!55!!!54!!!57!!!59
1975!!!60!!!58!!!61!!!66
1976!!!63!!!63!!!62!!!67
1977!!!67!!!67!!!64!!!70
1978!!!72!!!72!!!68!!!77
1979!!!79!!!79!!!76!!!86
1980!!!86!!!86!!!84!!!95
1981!!!94!!!94!!!93!!!100
1982!!!100!!!100!!!100!!!100
1983!!!104!!!104!!!105!!!103
1984!!!108!!!108!!!111!!!107
1985!!!112!!!112!!!115!!!110
Note: Index = 100 in base year of 1982.
______________________________________________________________________________
______________________________________________________________________________
!!! Standard Hgwy!!! Price Deflator!!!
Standard Hgwy!!! Percentage
Year!!! Cost !!! !!!
Real Cost !!! Change
!!!(1972=100) (1972=100)
(1972=100)!!! Per Year
1940!!! 26!!! --!!! 90
1950!!! 48!!! 54!!! 89!!! -0.1
1960!!! 58!!! 69!!! 84!!! -0.6
1970!!! 91!!! 92!!! 99!!! +1.8
1980!!! 255!!! 179!!! 143!!! +4.4
Source: Statistical Abstract of the United States. GNP Deflator is used
for the price deflator index.
______________________________________________________________________________
______________________________________________________________________________
!!! Standard Residence!!! Price Deflator!!!
Standard Residence!!! Percentage
Year!!! Cost !!! !!! Real Cost !!!
Change
!!!(1972=100) (1972=100) (1972=100)!!! Per Year
1970!!! 77!!! 92!!! 74
1980!!! 203!!! 179!!! 99!!! +3.4
Source: Statistical Abstract of the United States. The GNP deflator is
used for the price deflator index.
______________________________________________________________________________
On the basis of the above conditions, the estimate for the new project may
be obtained as follows:
Since there is no adjustment for the cost of construction financing, the
order of magnitude estimate for the new project is $209.5 million.
Example 5-14: Conceptual estimate for a chemical processing plant
In making a preliminary estimate of a chemical processing plant, several
major types of equipment are the most significant parameters in affecting the
installation cost. The cost of piping and other ancillary items for each type
of equipment can often be expressed as a percentage of that type of equipment
for a given capacity. The standard costs for the major equipment types for two
plants with different daily production capacities in 1972 are as shown in Table
5--1. It has been established that the installation cost of all equipment for
a plant with daily production capacity between 100,000 bbl and 400,000 bbl can
best be estimated by using linear interpolation of the standard data.
______________________________________________________________________________
Equipment!!!Equipment Cost ($1000)
!!!Cost of ancillary items as % of
Type!!!!!!!!! equipment cost ($1000)
!!!100,000 bbl!!!400,000 bbl!!!100,000 bbl!!!400,000 bbl
Furnace!!!3,000!!!10,000!!!40%!!!30%
Tower!!!2,000!!! 6,000!!!45%!!!35%
Drum!!!1,500!!! 5,000!!!50%!!!40%
Pump, etc.!!!1,000!!! 4,000!!!60%!!!50%
______________________________________________________________________________
A new chemical processing plant with a daily production capacity of 200,000
bbl was constructed in Memphis, TN in 1976. Determine the total preliminary
cost estimate of the plant including the building and the equipment on the
following basis:
(1) The costs of the equipment and ancillary items for a plant with a
capacity of 200,000 bbl can be estimated in 1972 dollars by linear
interpolation of the data in Table 5--1, and the results are shown in Table
5--1.
______________________________________________________________________________
.
Equipment!!! Equipment Cost!!! Percentage for
Type !!! (in $1,000)!!! ancillary items
Furnace!!!3,000 + (1/3)(10,000-3,000) = 5,333!!!40 - (1/3)(40-30) = 37
Tower!!!2,000 + (1/3)(6,000-2,000) = 3,333!!!45 - (1/3)(45-35) = 42
Drum!!!1,500 + (1/3)(5,000-1,500) = 2,667!!!50 - (1/3)(50-40) = 47
Pumps, etc.!!!1,000 + (1/3)(4,000-1,000) = 2,000!!!60 - (1/3)(60-50) = 57
______________________________________________________________________________
Hence, the total project cost in thousands of 1972 dollars is given by
Equation (5.8) as:
(2) The corresponding cost in thousands of 1976 dollars according to the ENR
building cost index in Table 5--1 and using Equation (5.16) is:
(3) The total cost of the project after adjustment for location is
The engineer's estimate is based on a list of items and the associated
quantities from which the total construction cost is derived. This same list
is also made available to the bidders if unit prices of the items on the list
are also solicited from the bidders. Thus, the itemized costs submitted by the
winning contractor may be used as the starting point for budget control.
In general, the progress payments to the contractor are based on the units
of work completed and the corresponding unit prices of the work items on the
list. Hence, the estimate based on the engineers' list of quanitities for
various work items essentially defines the level of detail to which subsequent
measures of progress for the project will be made.
Example 5-15: Bid estimate based on engineer's list of quantities
Using the unit prices in the bid of contractor 1 for the quantitites
specified by the engineer in Table 5-2 (Example 5-3), we can compute the total
bid price of contractor 1 for the roadway project. The itemized costs for
various work items as well as the total bid price are shown in Table 5--1.
Since construction costs are incurred over the entire construction phase of
a project, it is often necessary to determine the amounts to be spent in
various periods to derive the cash flow profile, especially for large projects
with long durations. Consequently, it is important to examine the percentage
of work expected to be completed at various time periods to which the costs
would be charged. More accurate estimates may be accomplished once the project
is scheduled as described in Chapter 10, but some rough estimate of the cash
flow may be required prior to this time.
Consider the basic problem in determining the percentage of work completed
during construction. One common method of estimating percentage of completion
is based on the amount of money spent relative to the total amount budgeted for
the entire project. This method has the obvious drawback in assuming that the
amount of money spent has been used efficiently for production. A more
reliable method is based on the concept of value of work completed which is
defined as the product of the budgeted labor hours per unit of production and
the actual number of production units completed, and is expressed in budgeted
labor hours for the work completed. Then, the percentage of completion at any
stage is the ratio of the value of work completed to date and the value of work
to be completed for the entire project. Regardless of the method of
measurement, it is informative to understand the trend of work progress during
construction for evaluation and control.
In general, the work on a construction project progresses gradually from the
time of mobilization until it reaches a plateau; then the work slows down
gradually and finally stops at the time of completion. The rate of work done
during various time periods (expressed in the percentage of project cost per
unit time) is shown schematically in Figure 5-0 in which ten time periods have
been assumed. The solid line A represents the case in which the rate of work
is zero at time t = 0 and increases linearly to 12.5% of project cost at t = 2,
while the rate begins to decrease from 12.5% at t = 8 to 0% at t = 10. The
dotted line B represents the case of rapid mobilization by reaching 12.5% of
project cost at t = 1 while beginning to decrease from 12.5% at t = 7 to 0% at
t = 10. The dash line C represents the case of slow mobilization by reaching
12.5% of project cost at t = 3 while beginning to decrease from 12.5% at t = 9
to 0% at t = 10.
The value of work completed at a given time (expressed as a cumulative
percentage of project cost) is shown schematically in Figure 5-0. In each case
(A, B or C), the value of work completed can be represented by an "S-shaped"
curve. The effects of rapid mobilization and slow mobilization are indicated
by the positions of curves B and C relative to curve A, respectively.
While the curves shown in Figures 5-0 and 5-0 represent highly idealized
cases, they do suggest the latitude for adjusting the schedules for various
activities in a project. While the rate of work progress may be changed quite
drastically within a single period, such as the change from rapid mobilization
to a slow mobilization in periods 1, 2 and 3 in Figure 5-0, the effect on the
value of work completed over time will diminish in significance as indicated by
the cumulative percentages for later periods in Figure 5-0. Thus, adjustment
of the scheduling of some activities may improve the utilization of labor,
material and equipment, and any delay caused by such adjustments for individual
activities is not likely to cause problems for the eventual progress toward the
completion of a project.
In addition to the speed of resource mobilization, another important
consideration is the overall duration of a project and the amount of resources
applied. Various strategies may be applied to shorten the overall duration of
a project such as overlapping design and construction activities (as described
in Chapter 2) or increasing the peak amounts of labor and equipment working on
a site. However, spatial, managerial and technical factors will typically
place a minimum limit on the project duration or cause costs to escalate with
shorter durations.
Example 5-16: Calculation of Value of Work Completed
From the area of work progress in Figure 5-0, the value of work completed at
any point in Figure 5-0 can be derived by noting the area under the curve up to
that point in Figure 5-0. The result for t = 0 through t = 10 is shown in
Table 5--2 and plotted in Figure 5-0.
In order to analyze the life cycle costs of a proposed facility, it is
necessary to estimate the operation and maintenance costs over time after the
start up of the facility. The stream of operating costs over the life of the
facility depends upon subsequent maintenance policies and facility use. In
particular, the magnitude of routine maintenance costs will be reduced if the
facility undergoes periodic repairs and rehabilitation at periodic intervals.
Since the tradeoff between the capital cost and the operating cost is an
essential part of the economic evaluation of a facility, the operating cost is
viewed not as a separate entity, but as a part of the larger parcel of life
cycle cost at the planning and design stage. The techniques of estimating life
cycle costs are similar to those used for estimating capital costs, including
empirical cost functions and the unit cost method of estimating the labor,
material and equipment costs. However, it is the interaction of the operating
and capital costs which deserve special attention.
As suggested earlier in the discussion of the exponential rule for
estimating, the value of the cost exponent may influence the decision whether
extra capacity should be built to accommodate future growth. Similarly, the
economy of scale may also influence the decision on rehabilitation at a given
time. As the rehabilitation work becomes extensive, it becomes a capital
project with all the implications of its own life cycle. Hence, the cost
estimation of a rehabilitation project may also involve capital and operating
costs.
While deferring the discussion of the economic evaluation of constructed
facilities to Chapter 6, it is sufficient to point out that the stream of
operating costs over time represents a series of costs at different time
periods which have different values with respect to the present. Consequently,
the cost data at different time periods must be converted to a common base line
if meaningful comparison is desired.
Example 5-17: Maintenance cost on a roadway[This example is adapted from
McNeil, S. and C. Hendrickson, "A Statistical Model of Pavement Maintenance
Expenditure," Transportation Research Record No. 846, 1982, pp. 71-76.]
Maintenance costs for constructed roadways tend to increase with both age
and use of the facility. As an example, the following empirical model was
estimated for maintenance expenditures on sections of the Ohio Turnpike:
For example, for V = 500,300 ESAL and A = 5 years, the annual cost of
routine maintenance per lane-mile is estimated to be:
Example 5-18: Time stream of costs over the life of a roadway[This example
is adapted from S. McNeil, Three Statistical Models of Road Management Based on
Turnpike Data, M.S. Thesis, Carnegie-Mellon University, Pittsburgh, PA, 1981.]
The time stream of costs over the life of a roadway depends upon the
intervals at which rehabilitation is carried out. If the rehabilitation
strategy and the traffic are known, the time stream of costs can be estimated.
Using a life cycle model which predicts the economic life of highway
pavement on the basis of the effects of traffic and other factors, an optimal
schedule for rehabilitation can be developed. For example, a time stream of
costs and resurfacing projects for one pavement section is shown in Figure 5-0.
As described in the previous example, the routine maintenance costs increase as
the pavement ages, but decline after each new resurfacing. As the pavement
continues to age, resurfacing becomes more frequent until the roadway is
completely reconstructed at the end of 35 years.
Facility investment decisions represent major commitments of corporate
resources and have serious consequences on the profitability and financial
stability of a corporation. In the public sector, such decisions also affect
the viability of facility investment programs and the credibility of the agency
in charge of the programs. It is important to evaluate facilities rationally
with regard to both the economic feasibility of individual projects and the
relative net benefits of alternative and mutually exclusive projects.
This chapter will present an overview of the decision process for economic
evaluation of facilities with regard to the project life cycle. The cycle
begins with the initial conception of the project and continues though
planning, design, procurement, construction, start-up, operation and
maintenance. It ends with the disposal of a facility when it is no longer
productive or useful. Four major aspects of economic evaluation will be
examined:
It is important to distinguish between the economic evaluation of
alternative physical facilities and the evaluation of alternative financing
plans for a project. The former refers to the evaluation of the cash flow
representing the benefits and costs associated with the acquisition and
operation of the facility, and this cash flow over the planning horizon is
referred to as the economic cash flow or the operating cash flow. The latter
refers to the evaluation of the cash flow representing the incomes and
expenditures as a result of adopting a specific financing plan for funding the
project, and this cash flow over the planning horizon is referred to as the
financial cash flow. In general, economic evaluation and financial evaluation
are carried out by different groups in an organization since economic
evaluation is related to design, construction, operations and maintenance of
the facility while financial evaluations require knowledge of financial assets
such as equities, bonds, notes and mortgages. The separation of economic
evaluation and financial evaluation does not necessarily mean one should ignore
the interaction of different designs and financing requirements over time which
may influence the relative desirability of specific design/financing
combinations. All such combinations can be duly considered. In practice,
however, the division of labor among two groups of specialists generally leads
to sequential decisions without adequate communication for analyzing the
interaction of various design/financing combinations because of the timing of
separate analyses.
As long as the significance of the interaction of design/financing
combinations is understood, it is convenient first to consider the economic
evaluation and financial evaluation separately, and then combine the results of
both evaluations to reach a final conclusion. Consequently, this chapter is
devoted primarily to the economic evaluation of alternative physical facilities
while the effects of a variety of financing mechanisms will be treated in the
next chapter. Since the methods of analyzing economic cash flows are equally
applicable to the analysis of financial cash flows, the techniques for
evaluating financing plans and the combined effects of economic and financial
cash flows for project selection are also included in this chapter.
A systematic approach for economic evaluation of facilities consists of the
following major steps:
The period of time to which the management of a firm or agency wishes to
look ahead is referred to as the planning horizon. Since the future is
uncertain, the period of time selected is limited by the ability to forecast
with some degree of accuracy. For capital investment, the selection of the
planning horizon is often influenced by the useful life of facilities, since
the disposal of usable assets, once acquired, generally involves suffering
financial losses.
In economic evaluations, project alternatives are represented by their cash
flow profiles over the n years or periods in the planning horizon. Thus, the
interest periods are normally assumed to be in years t = 0,1,2, ..., n with t =
0 representing the present time. Let B@-(t,x) be the annual benefit at the end
of year t for a investment project x where x = 1, 2, ... refer to projects No.
1, No. 2, etc., respectively. Let C@-(t,x) be the annual cost at the end of
year t for the same investment project x. The net annual cash flow is defined
as the annual benefit in excess of the annual cost, and is denoted by A@-(t,x)
at the end of year t for an investment project x. Then, for t = 0,1, . . .
,n: Once the management has committed funds to a specific project, it must
forego other investment opportunities which might have been undertaken by using
the same funds. The opportunity cost reflects the return that can be earned
from the best alternative investment opportunity foregone. The foregone
opportunities may include not only capital projects but also financial
investments or other socially desirable programs. Management should invest in
a proposed project only if it will yield a return at least equal to the minimum
attractive rate of return (MARR) from foregone opportunities as envisioned by
the organization.
In general, the MARR specified by the top management in a private firm
reflects the opportunity cost of capital of the firm, the market interest
rates for lending and borrowing, and the risks associated with investment
opportunities. For public projects, the MARR is specified by a government
agency, such as the Office of Management and Budget or the Congress of the
United States. The public MARR thus specified reflects social and economic
welfare considerations, and is referred to as the social rate of discount.
Regardless of how the MARR is determined by an organization, the MARR
specified for the economic evaluation of investment proposals is critically
important in determining whether any investment proposal is worthwhile from the
standpoint of the organization. Since the MARR of an organization often cannot
be determined accurately, it is advisable to use several values of the MARR to
assess the sensitivity of the potential of the project to variations of the
MARR value.
The basic principle in assessing the economic costs and benefits of new
facility investments is to find the aggregate of individual changes in the
welfare of all parties affected by the proposed projects. The changes in
welfare are generally measured in monetary terms, but there are exceptions,
since some effects cannot be measured directly by cash receipts and
disbursements. Examples include the value of human lives saved through safety
improvements or the cost of environmental degradation. The difficulties in
estimating future costs and benefits lie not only in uncertainties and
reliability of measurement, but also on the social costs and benefits generated
as side effects. Furthermore, proceeds and expenditures related to financial
transactions, such as interest and subsidies, must also be considered by
private firms and by public agencies.
To obtain an accurate estimate of costs in the cash flow profile for the
acquisition and operation of a project, it is necessary to specify the
resources required to construct and operate the proposed physical facility,
given the available technology and operating policy. Typically, each of the
labor and material resources required by the facility is multiplied by its
price, and the products are then summed to obtain the total costs. Private
corporations generally ignore external social costs unless required by law to
do so. In the public sector, externalities often must be properly accounted
for. An example is the cost of property damage caused by air pollution from a
new plant. In any case, the measurement of external costs is extremely
difficult and somewhat subjective for lack of a market mechanism to provide
even approximate answers to the appropriate value.
In the private sector, the benefits derived from a facility investment are
often measured by the revenues generated from the operation of the facility.
Revenues are estimated by the total of price times quantity purchased. The
depreciation allowances and taxes on revenues must be deducted according to the
prevailing tax laws. In the public sector, income may also be accrued to a
public agency from the operation of the facility. However, several other
categories of benefits may also be included in the evaluation of public
projects. First, private benefits can be received by users of a facility or
service in excess of costs such as user charges or price charged. After all,
individuals only use a service or facility if their private benefit exceeds
their cost. These private benefits or consumer surplus represent a direct
benefit to members of the public. In many public projects, it is difficult,
impossible or impractical to charge for services received, so direct revenues
equal zero and all user benefits appear as consumers surplus. Examples are a
park or roadways for which entrance is free. As a second special category of
public benefit, there may be external or secondary beneficiaries of public
projects, such as new jobs created and profits to private suppliers.
Estimating these secondary benefits is extremely difficult since resources
devoted to public projects might simply be displaced from private employment
and thus represent no net benefit.
Constructed facilities are inherently long-term investments with a deferred
pay-off. The cost of capital or MARR depends on the real interest rate (i.e.,
market interest rate less the inflation rate) over the period of investment.
As the cost of capital rises, it becomes less and less attractive to invest in
a large facility because of the opportunities foregone over a long period of
time.
In Figure 6-0, the changes in the cost of capital from 1955 to 1985 are
illustrated. This figure presents the market interest rate on a 20-year
treasury bond, and the corresponding real interest rate over this period. The
real interest rate is calculated as the market interest rate less the general
rate of inflation. During the last decade in this figure, the real interest
rate has varied substantially, ranging from 10% to -4%. The exceptional nature
of the 1980 to 1985 years is dramatically evident: the real rate of interest
reached remarkably high historic levels.
With these volatile interest rates, interest charges and the ultimate cost
of projects are uncertain. Organizations and institutional arrangements
capable of dealing with this uncertainty and able to respond to interest rate
changes effectively would be quite valuable. For example, banks offer both
fixed rate and variable rate mortgages. An owner who wants to limit its own
risk may choose to take a fixed rate mortgage even though the ultimate interest
charges may be higher. On the other hand, an owner who chooses a variable rate
mortgage will have to adjust its annual interest charges according to the
market interest rates.
In economic evaluation, a constant value of MARR over the planning horizon
is often used to simplify the calculations. The use of a constant value for
MARR is justified on the ground of long-term average of the cost of capital
over the period of investment. If the benefits and costs over time are
expressed in constant dollars, the constant value for MARR represents the
average real interest rate anticipated over the planning horizon; if the
benefits and costs over time are expressed in then-current dollars, the
constant value for MARR reflects the average market interest rate anticipated
over the planning horizon.
A profit measure is defined as an indicator of the desirability of a
project from the standpoint of a decision maker. A profit measure may or may
not be used as the basis for project selection. Since various profit measures
are used by decision makers for different purposes, the advantages and
restrictions for using these profit measures should be fully understood.
There are several profit measures that are commonly used by decision makers
in both private corporations and public agencies. Each of these measures is
intended to be an indicator of profit or net benefit for a project under
consideration. Some of these measures indicate the size of the profit at a
specific point in time; others give the rate of return per period when the
capital is in use or when reinvestments of the early profits are also included.
If a decision maker understands clearly the meaning of the various profit
measures for a given project, there is no reason why one cannot use all of them
for the restrictive purposes for which they are appropriate. With the
availability of computer based analysis and commercial software, it takes only
a few seconds to compute these profit measures. However, it is important to
define these measures precisely:
1. Net Future Value and Net Present Value. When an organization makes an
investment, the decision maker looks forward to the gain over a planning
horizon, against what might be gained if the money were invested elsewhere. A
minimum attractive rate of return (MARR) is adopted to reflect this opportunity
cost of capital. The MARR is used for compounding the estimated cash flows to
the end of the planning horizon, or for discounting the cash flow to the
present. The profitability is measured by the net future value (NFV) which is
the net return at the end of the planning horizon above what might have been
gained by investing elsewhere at the MARR. The net present value (NPV) of the
estimated cash flows over the planning horizon is the discounted value of the
NFV to the present. A positive NPV for a project indicates the present value
of the net gain corresponding to the project cash flows.
2. Equivalent Uniform Annual Net Value. The equivalent uniform annual net
value (NUV) is a constant stream of benefits less costs at equally spaced time
periods over the intended planning horizon of a project. This value can be
calculated as the net present value multiplied by an appropriate "capital
recovery factor." It is a measure of the net return of a project on an
annualized or amortized basis. The equivalent uniform annual cost (EUAC) can
be obtained by multiplying the present value of costs by an appropriate capital
recovery factor. The use of EUAC alone presupposes that the discounted
benefits of all potential projects over the planning horizon are identical and
therefore only the discounted costs of various projects need be considered.
Therefore, the EUAC is an indicator of the negative attribute of a project
which should be minimized.
3. Benefit Cost Ratio. The benefit-cost ratio (BCR), defined as the ratio
of discounted benefits to the discounted costs at the same point in time, is a
profitability index based on discounted benefits per unit of discounted costs
of a project. It is sometimes referred to as the savings-to-investment ratio
(SIR) when the benefits are derived from the reduction of undesirable effects.
Its use also requires the choice of a planning horizon and a MARR. Since some
savings may be interpreted as a negative cost to be deducted from the
denominator or as a positive benefit to be added to the numerator of the ratio,
the BCR or SIR is not an absolute numerical measure. However, if the ratio of
the present value of benefit to the present value of cost exceeds one, the
project is profitable irrespective of different interpretations of such
benefits or costs.
4. Internal Rate of Return. The internal rate of return (IRR) is defined
as the discount rate which sets the net present value of a series of cash flows
over the planning horizon equal to zero. It is used as a profit measure since
it has been identified as the "marginal efficiency of capital" or the "rate of
return over cost". The IRR gives the return of an investment when the capital
is in use as if the investment consists of a single outlay at the beginning
and generates a stream of net benefits afterwards. However, the IRR does not
take into consideration the reinvestment opportunities related to the timing
and intensity of the outlays and returns at the intermediate points over the
planning horizon. For cash flows with two or more sign reversals of the cash
flows in any period, there may exist multiple values of IRR; in such cases, the
multiple values are subject to various interpretations.
5. Adjusted Internal Rate of Return. If the financing and reinvestment
policies are incorporated into the evaluation of a project, an adjusted
internal rate of return (AIRR) which reflects such policies may be a useful
indicator of profitability under restricted circumstances. Because of the
complexity of financing and reinvestment policies used by an organization over
the life of a project, the AIRR seldom can reflect the reality of actual cash
flows. However, it offers an approximate value of the yield on an investment
for which two or more sign reversals in the cash flows would result in multiple
values of IRR. The adjusted internal rate of return is usually calculated as
the internal rate of return on the project cash flow modified so that all costs
are discounted to the present and all benefits are compounded to the end of the
planning horizon.
6. Return on Investment. When an accountant reports income in each year
of a multi-year project, the stream of cash flows must be broken up into annual
rates of return for those years. The return on investment (ROI) as used by
accountants usually means the accountant's rate of return for each year of the
project duration based on the ratio of the income (revenue less depreciation)
for each year and the undepreciated asset value (investment) for that same
year. Hence, the ROI is different from year to year, with a very low value at
the early years and a high value in the later years of the project.
7. Payback Period. The payback period (PBP) refers to the length of time
within which the benefits received from an investment can repay the costs
incurred during the time in question while ignoring the remaining time periods
in the planning horizon. Even the discounted payback period indicating the
"capital recovery period" does not reflect the magnitude or direction of the
cash flows in the remaining periods. However, if a project is found to be
profitable by other measures, the payback period can be used as a secondary
measure of the financing requirements for a project.
The objective of facility investment in the private sector is generally
understood to be profit maximization within a specific time frame. Similarly,
the objective in the public sector is the maximization of net social benefit
which is analogous to profit maximization in private organizations. Given this
objective, a method of economic analysis will be judged by the reliability and
ease with which a correct conclusion may be reached in project selection.
The basic principle underlying the decision for accepting and selecting
investment projects is that if an organization can lend or borrow as much money
as it wishes at the MARR, the goal of profit maximization is best served by
accepting all independent projects whose net present values based on the
specified MARR are nonnegative, or by selecting the project with the maximum
nonnegative net present value among a set of mutually exclusive proposals. The
net present value criterion reflects this principle and is most straightforward
and unambiguous when there is no budget constraint. Various methods of
economic evaluation, when properly applied, will produce the same result if the
net present value criterion is used as the basis for decision. For convenience
of computation, a set of tables for the various compound interest factors is
given in Appendix A.
Let BPV@-(x) be the present value of benefits of a project x and CPV@-(x) be
the present value of costs of the project x. Then, for MARR = i over a
planning horizon of n years, If there is no budget constraint, then all independent projects having net
present values greater than or equal to zero are acceptable. That is, project
x is acceptable as long as Since the cash flow profile of an investment can be represented by its
equivalent value at any specified reference point in time, the net future value
(NFV@-[x]) of a series of cash flows A@-(t,x) (for t=0,1,2,...,n) for project x
is as good a measure of economic potential as the net present value.
Equivalent future values are obtained by multiplying a present value by the
compound interest factor (F|P,i,n) which is (1+i)@+[n]. Specifically, !!!!!!!!!Unit!!!Item
Items!!!Unit!!!Qty.!!!Price!!!Cost
Mobilization.!!!ls!!!1!!!115,000!!!115,000..
Removal, berm.!!!lf!!!8,020!!!1.00!!!8,020..
Finish subgrade.!!!sy!!!1,207,500!!!0.50!!!603,750..
Surface ditches.!!!lf!!!525!!!2.00!!!1,050..
Excavation structures.!!!cy!!!7,000!!!3.00!!!21,000.
Base course, untreated, 3/4".!!!ton!!!362,200!!!4.50!!!1,629,900..!!!ton!!!362
Lean concrete, 4" thick.!!!sy!!!820,310!!!3.10!!!2,542,961..!!!sy!!!820,310!
PCC, pavement, 10" thick.!!!sy!!!706,010!!!10.90!!!7,695,509..!!!sy!!!706,010!
Concrete, ci AA(AE).!!!ls!!!1!!!200,000!!!200,000..!
Small structure.!!!cy!!!50!!!500!!!25,000.
Barrier, precast.!!!lf!!!7,920!!!15.00!!!118,800..
Flatwork, 4" thick.!!!sy!!!7,410!!!10.00!!!74,100.
10" thick.!!!sy!!!4,241!!!20.00!!!84,820..
Slope protection.!!!sy!!!2,104!!!25.00!!!52,600..!
Metal, end section, 15".!!!ea!!!39!!!100!!!3,900..!!
18".!!!ea!!!3!!!150!!!450..!!!ea!
Post, right-of-way, modification.!!!lf!!!4,700!!!3.00!!!14,100..!!!lf!!!4,70
Salvage & relay pipe.!!!lf!!!1,680!!!5.00!!!8,400..!
Loose riprap.!!!cy!!!32!!!40.00!!!1,280..!!!
Braced posts.!!!ea!!!54!!!100!!!5,400..!!!ea
Delineators, type I.!!!lb!!!1,330!!!12.00!!!15,960..
type II.!!!ea!!!140!!!15.00!!!2,100..!!!ea
Constructive signs fixed.!!!sf!!!52,600!!!0.10!!!5,260..!!!sf!!!52,600!!!0.10!
Barricades, type III.!!!lf!!!29,500!!!0.20!!!5,900..!!!lf!!!29,500!!!0.20!!!
Warning lights.!!!day!!!6,300!!!0.10!!!630..
Pavement marking, epoxy material, black.!!!gal!!!475!!!90.00!!!42,750..!!!gal!
Yellow.!!!gal!!!740!!!90.00!!!66,600..!!!g
White.!!!gal!!!985!!!90.00!!!88,650..!!!ga
Plowable, one way white.!!!ea!!!342!!!50.00!!!17,100..!!!ea!!!342!!!50.00!!!
Topsoil, contractor furnished.!!!cy!!!260!!!10.00!!!2,600..!!!cy!!!260!!!10.00
Seedling, method A.!!!acr!!!103!!!150!!!15,450..!!!a
Excelsior blanket.!!!sy!!!500!!!2.00!!!1,000..!!!sy!
!!!!!!!!!Unit!!!Item
Items!!!Unit!!!Qty.!!!Price!!!Cost
Corrugated, metal pipe, 18".!!!lf!!!580!!!20.00!!!11,600..!!!lf!!!580!!!20.00!
Polyethylene pipe, 12".!!!lf!!!2,250!!!15.00!!!33,750..!!!lf!!!2,250!!!15.00
Catch basin grate & frame.!!!ea!!!35!!!350!!!12,250.
Equal opportunity training.!!!hr!!!18,000!!!0.80!!!14,400..!!!hr!!!18,000!!!0.
Granular backfill borrow.!!!cy!!!274!!!10.00!!!2,740..!!!cy!!!274!!!10.00!!!2,
Drill caisson, 2' x 6".!!!lf!!!722!!!100!!!72,200..!
Flagging.!!!hr!!!20,000!!!8.25!!!165,000..!!
Prestressed concrete member
type IV, 141' x 4".!!!ea!!!7!!!12,000!!!84,000..!!
132' x 4".!!!ea!!!6!!!11,000!!!66,000..!!!
Reinforced steel.!!!lb!!!6,300!!!0.60!!!3,780..!!!lb
Epoxy coated.!!!lb!!!122,241!!!0.55!!!67,232.55.!!
Structural steel.!!!ls!!!1!!!5,000!!!5,000..
Sign, covering.!!!sf!!!16!!!10.00!!!160..!!!
type C-2, wood post.!!!sf!!!98!!!15.00!!!1,470.00.
24".!!!ea!!!3!!!100!!!300..!!!ea!
30".!!!ea!!!2!!!100!!!200..!!!ea!
48".!!!ea!!!11!!!200!!!2,200..!!!
Auxiliary.!!!sf!!!61!!!15.00!!!915..!!!sf!
Steel post, 48" x 60".!!!ea!!!11!!!500!!!5,500..!!
type 3, wood post.!!!sf!!!669!!!15.00!!!10,035..!!
24".!!!ea!!!23!!!100!!!2,300..!!!
30".!!!ea!!!1!!!100!!!100..!!!ea!
36".!!!ea!!!12!!!150!!!1,800..!!!
42" x 60".!!!ea!!!8!!!150!!!1,200..!!!ea!!
48".!!!ea!!!7!!!200!!!1,400..!!!e
Auxiliary.!!!sf!!!135!!!15.00!!!2,025..!!!
Steel post.!!!sf!!!1,610!!!40.00!!!64,400.
12" x 36".!!!ea!!!28!!!100!!!2,800..!!!ea!
Foundation, concrete.!!!ea!!!60!!!300!!!18,000..!!
Barricade, 48" x 42".!!!ea!!!40!!!100!!!4,000..!!!ea
Wood post, road closed.!!!lf!!!100!!!30.00!!!3,000..!!!lf!!!100!!!30.00!!!3,
Total.!!!$ 14,129,797.55.!!!$ 14,129,797.55.!!!$
The net equivalent uniform annual value (NUV@-[x]) refers to a uniform
series over a planning horizon of n years whose net present value is that of a
series of cash flow A@-(t,x) (for t= 1,2,...,n) representing project x. That
is, The benefit-cost ratio method is not as straightforward and unambiguous as
the net present value method but, if applied correctly, will produce the same
results as the net present value method. While this method is often used in
the evaluation of public projects, the results may be misleading if proper care
is not exercised in its application to mutually exclusive proposals.
The benefit-cost ratio is defined as the ratio of the discounted benefits
to the discounted cost at the same point in time. In view of Eqs. (6.6.6) and
(6.6.6), it follows that the criterion for accepting an independent project on
the basis of the benefit-cost ratio is whether or not the benefit-cost ratio is
greater than or equal to one: The term internal rate of return method has been used by different analysts
to mean somewhat different procedures for economic evaluation. The method is
often misunderstood and misused, and its popularity among analysts in the
private sector is undeserved even when the method is defined and interpreted in
the most favorable light. The method is usually applied by comparing the MARR
to the internal rate of return value(s) for a project or a set of projects.
A major difficulty in applying the internal rate of return method to
economic evaluation is the possible existence of multiple values of IRR when
there are two or more changes of sign in the cash flow profile A@-(t,x) (for
t=0,1,2,...,n). When that happens, the method is generally not applicable
either in determining the acceptance of independent projects or for selection
of the best among a group of mutually exclusive proposals unless a set of well
defined decision rules are introduced for incremental analysis. In any case,
no advantage is gained by using this method since the procedure is cumbersome
even if the method is correctly applied. This method is not recommended for
use either in accepting independent projects or in selecting the best among
mutually exclusive proposals.
Example 6-1: Evaluation of Four Independent Projects
The cash flow profiles of four independent projects are shown in Table 6-0.
Using a MARR of 20%, determine the acceptability of each of the projects on the
basis of the net present value criterion for accepting independent projects.
t!!!A@-(t,1)!!!A@-(t,2)!!!A@-(t,3)!!!A@-(t,4)
0!!!-77.0!!!-75.3!!!-39.9!!!18.0
1!!!0!!!28.0!!!28.0!!!10.0
2!!!0!!!28.0!!!28.0!!!-40.0
3!!!0!!!28.0!!!28.0!!!-60.0
4!!!0!!!28.0!!!28.0!!!30.0
5!!!235.0!!!28.0!!!-80.0!!!50.0
Using i = 20%, we can compute NPV for x = 1, 2, 3, and 4 from Eq. (6.5).
Then, the acceptability of each project can be determined from Eq. (6.6).
Thus,
It is interesting to note that if the four projects are mutually exclusive,
the net present value method can still be used to evaluate the projects and,
according to Eq. (6.7), the project (x = 1) which has the highest positive NPV
should be selected. The use of the net equivalent uniform annual value or the
net future value method will lead to the same conclusion. However, the project
with the highest benefit-cost ratio is not necessarily the best choice among a
group of mutually exclusive alternatives. Furthermore, the conventional
internal rate of return method cannot be used to make a meaningful evaluation
of these projects as the IRR for both x=1 and x=2 are found to be 25% while
multiple values of IRR exist for both the x=3 and x=4 alternatives.
For private corporations, the cash flow profile of a project is affected by
the amount of taxation. In the context of tax liability, depreciation is the
amount allowed as a deduction due to capital expenses in computing taxable
income and, hence, income tax in any year. Thus, depreciation results in a
reduction in tax liabilities.
It is important to differentiate between the estimated useful life used in
depreciation computations and the actual useful life of a facility. The former
is often an arbitrary length of time, specified in the regulations of the U.S.
Internal Revenue Service or a comparable organization. The depreciation
allowance is a bookkeeping entry that does not involve an outlay of cash, but
represents a systematic allocation of the cost of a physical facility over
time.
There are various methods of computing depreciation which are acceptable to
the U.S. Internal Revenue Service. The different methods of computing
depreciation have different effects on the streams of annual depreciation
charges, and hence on the stream of taxable income and taxes paid. Let P be
the cost of an asset, S its estimated salvage value, and N the estimated useful
life (depreciable life) in years. Furthermore, let D@-(t) denote the
depreciation amount in year t, T@-(t) denote the accumulated depreciation up to
year t, and B@-(t) denote the book value of the asset at the end of year t,
where t=1,2,..., or n refers to the particular year under consideration. Then, The depreciation methods most commonly used to compute D@-(t) and B@-(t) are
the straight line method, sum-of-the-years'-digits methods, and the double
declining balanced method. The U.S. Internal Revenue Service provides tables
of acceptable depreciable schedules using these methods. Under straight line
depreciation, the net depreciable value resulting from the cost of the facility
less salvage value is allocated uniformly to each year of the estimated useful
life. Under the sum-of-the-year's-digits (SOYD) method, the annual
depreciation allowance is obtained by multiplying the net depreciable value
multiplied by a fraction, which has as its numerator the number of years of
remaining useful life and its denominator the sum of all the digits from 1 to
n. The annual depreciation allowance under the double declining balance method
is obtained by multiplying the book value of the previous year by a constant
depreciation rate 2/n.
To consider tax effects in project evaluation, the most direct approach is
to estimate the after-tax cash flow and then apply an evaluation method such as
the net present value method. Since projects are often financed by internal
funds representing the overall equity-debt mix of the entire corporation, the
deductibility of interest on debt may be considered on a corporate-wide basis.
For specific project financing from internal funds, let after-tax cash flow in
year t be Y@-(t). Then, for t=0,1,2,...,n, Besides corporate income taxes, there are other provisions in the federal
income tax laws that affect facility investments, such as tax credits for
low-income housing. Since the tax laws are revised periodically, the
estimation of tax liability in the future can only be approximate.
Example 6-2: Effects of Taxes on Investment
A company plans to invest $55,000 in a piece of equipment which is expected
to produce a uniform annual net revenue before tax of $15,000 over the next
five years. The equipment has a salvage value of $5,000 at the end of 5 years
and the depreciation allowance is computed on the basis of the straight line
depreciation method. The marginal income tax rate for this company is 34%, and
there is no expectation of inflation. If the after-tax MARR specified by the
company is 8%, determine whether the proposed investment is worthwhile,
assuming that the investment will be financed by internal funds.
Using Equations (6.6.7) and (6.6.7), the after-tax cash flow can be computed
as shown in Table 6-0. Then, the net present value discounted at 8% is
obtained from Equation (6.6.6) as follows:
Year !!!Before-tax!!!Straight-line!!!
Taxable!!!Income!!!After-Tax
t !!!Cash Flow!!!Depreciation!!!
Income!!!Tax!!!Cash-Flow
!!! A@-(t)!!! D@-(t)!!!A@-(t) - D@-(t)!!!X@-(t)
(A@-[t] - D@-[t])!!! Y@-[t]
0!!!-55,000!!!!!!!!!!!!-55,000
1-5 each!!!+15,000!!!10,000!!!5,000!!!1,700!!!+13,300
5 only!!!+5,000!!!!!!!!!!!!+5,000
In the economic evaluation of investment proposals, two approaches may be
used to reflect the effects of future price level changes due to inflation or
deflation. The differences between the two approaches are primarily
philosophical and can be succinctly stated as follows:
Let i be the discount rate excluding inflation, i' be the discount rate
including inflation, and j be the annual inflation rate. Then, If A@-(t) denotes the cash flow in year t expressed in terms of constant
(base year) dollars, and A'@-(t) denotes the cash flow in year t expressed in
terms of inflated (then-current) dollars, then It can be shown that the results from these two equations are identical.
Furthermore, the relationship applies to after-tax cash flow as well as to
before-tax cash flow by replacing A@-(t) and A@-(t)@+(') with Y@-(t) and
Y@-(t)@+(') respectively in Equations (6.6.8) and (6.6.8).
Example 6-3: Effects of Inflation
Suppose that, in the previous example, the inflation expectation is 5% per
year, and the after-tax MARR specified by the company is 8% excluding
inflation. Determine whether the investment is worthwhile.
In this case, the before-tax cash flow A@-(t) in terms of constant dollars
at base year 0 is inflated at j = 5% to then-current dollars A@-(t)@+(') for
the computation of the taxable income (A@-[t]@+['] - D@-[t]) and income taxes. The
resulting after-tax flow Y@-(t)@+(') in terms of then-current dollars is
converted back to constant dollars. That is, for X@-(t) = 34% and D@-(t) =
$10,000. The annual depreciation charges D@-(t) are not inflated to current
dollars in conformity with the practice recommended by the U.S. Internal
Revenue Service. Thus:
!!! Constant $!!! Current $!!! Current $!!!
Current $!!! Current $!!! Current $!!! Constant $
Time!!!B-Tax CF!!! B-Tax CF!!! Depr.!!!
After Depr.!!! Income Tax!!! A-Tax CF!!! A-Tax CF
t!!! A@-(t)!!! A@-(t)@+(')!!! D@-(t)!!! A@-(t)
@+(')-D@-(t)!!! X@-[t](A@-(t)@+(')-D
@-[t])!!!Y@-(t)@+(')!!! Y@-(t)
0!!!-55,000!!!+55,000!!!!!!!!!!!!-55,000!!!-55,000
1!!!+15,000!!!+15,750!!!10,000!!!5,750!!!1,955!!!+13,795!!!+13,138
2!!!+15,000!!!+16,540!!!10,000!!!6,540!!!2,224!!!+14,316!!!+12,985
3!!!+15,000!!!+17,365!!!10,000!!!7,365!!!2,504!!!+14,861!!!+12,837
4!!!+15,000!!!+18,233!!!10,000!!!8,233!!!2,799!!!+15,434!!!+12,697
5!!!+15,000!!!+19,145!!!10,000!!!9,145!!!3,109!!!+16,036!!!12,564
5!!!+5,000!!!!!!!!!!!!!!!!!!+5,000
Note: B-Tax CF refers to Before-Tax Cash
Flow; A-Tax CF refers to After-Tax Cash Flow
Since future events are always uncertain, all estimates of costs and
benefits used in economic evaluation involve a degree of uncertainty.
Probabilistic methods are often used in decision analysis to determine expected
costs and benefits as well as to assess the degree of risk in particular
projects.
In estimating benefits and costs, it is common to attempt to obtain the
expected or average values of these quantities depending upon the different
events which might occur. Statistical techniques such as regression models can
be used directly in this regard to provide forecasts of average values.
Alternatively, the benefits and costs associated with different events can be
estimated and the expected benefits and costs calculated as the sum over all
possible events of the resulting benefits and costs multiplied by the
probability of occurrence of a particular event: For example, the average cost of a facility in an earthquake prone site
might be calculated as the sum of the cost of operation under normal conditions
(multiplied by the probability of no earthquake) plus the cost of operation
after an earthquake (multiplied by the probability of an earthquake). Expected
benefits and costs can be used directly in the cash flow calculations described
earlier.
In formulating objectives, some organizations wish to avoid risk so as to
avoid the possibility of losses. In effect, a risk avoiding organization
might select a project with lower expected profit or net social benefit as long
as it had a lower risk of losses. This preference results in a risk premium
or higher desired profit for risky projects. A rough method of representing a
risk premium is to make the desired MARR higher for risky projects. Let r@-[f]
be the risk free market rate of interest as represented by the average rate of
return of a safe investment such as U.S. government bonds. However, U.S.
government bonds do not protect from inflationary changes or exchange rate
fluctuations, but only insure that the principal and interest will be repaid.
Let r@-[p] be the risk premium reflecting an adjustment of the rate of return
for the perceived risk. Then, the risk-adjusted rate of return r is given by: More directly, a decision maker may be confronted with the subject choice
among alternatives with different expected benefits of levels of risk such that
at a given period t, the decision maker is willing to exchange an uncertain
A@-[t] with a smaller but certain return a@-[t]A@-[t] where a@-[t] is less than
one. Consider the decision tree in Figure 6-0 in which the decision maker is
confronted with a choice between the certain return of a@-(t)A@-(t) and a
gamble with possible outcomes (A@-<t>)@-(q) and respective probabilities Pr{q}
for q = 1,2,...,m. Then, the net present value for the series of "certainty
equivalents" over n years may be computed on the basis of the risk free rate.
Hence:
Selection of the best design and financing plans for capital projects is
typically done separately and sequentially. Three approaches to facility
investment planning most often adopted by an organization are:
Typically, different individuals or divisions of an organization conduct the
analysis for the operating and financing processes. Financing alternatives are
sometimes not examined at all since a single mechanism is universally adopted.
An example of a single financing plan in the public sector is the use of
pay-as-you-go highway trust funds. However, the importance of financial
analysis is increasing with the increase of private ownership and private
participation in the financing of public projects. The availability of a broad
spectrum of new financing instruments has accentuated the needs for better
financial analysis in connection with capital investments in both the public
and private sectors. While simultaneous assessment of all design and financing
alternatives is not always essential, more communication of information between
the two evaluation processes would be advantageous in order to avoid the
selection of inferior alternatives.
There is an ever increasing variety of borrowing mechanisms available.
First, the extent to which borrowing is tied to a particular project or asset
may be varied. Loans backed by specific, tangible and fungible assets and with
restrictions on that asset's use are regarded as less risky. In contrast,
specific project finance may be more costly to arrange due to transactions
costs than is general corporate or government borrowing. Also, backing by the
full good faith and credit of an organization is considered less risky than
investments backed by generally immovable assets. Second, the options of fixed
versus variable rate borrowing are available. Third, the repayment schedule
and time horizon of borrowing may be varied. A detailed discussion of
financing of constructed facilities will be deferred until the next chapter.
As a general rule, it is advisable to borrow as little as possible when
borrowing rates exceed the minimum attractive rate of return. Equity or
pay-as-you-go financing may be desirable in this case. It is generally
preferable to obtain lower borrowing rates, unless borrowing associated with
lower rates requires substantial transaction costs or reduces the flexibility
for repayment and refinancing. In the public sector, it may be that increasing
taxes or user charges to reduce borrowing involves economic costs in excess of
the benefits of reduced borrowing costs of borrowed funds. Furthermore, since
cash flow analysis is typically conducted on the basis of constant dollars and
loan agreements are made with respect to current dollars, removing the effects
of inflation will reduce the cost of borrowing. Finally, deferring investments
until pay-as-you-go or equity financing are available may unduly defer the
benefits of new investments.
It is difficult to conclude unambiguously that one financing mechanism is
always superior to others. Consequently, evaluating alternative financing
mechanisms is an important component of the investment analysis procedure. One
possible approach to simultaneously considering design and financing
alternatives is to consider each combination of design and financing options as
a specific, mutually exclusive alternative. The cash flow of this combined
alternative would be the sum of the economic or operating cash flow (assuming
equity financing) and the financial cash flow over the planning horizon.
A general approach for obtaining the combined effects of operating and
financing cash flows of a project is to make use of the additive property of
net present values by calculating an adjusted net present value. The adjusted
net present value (APV) is the sum of the net present value (NPV) of the
operating cash flow plus the net present value of the financial cash flow due
to borrowing or raising capital (FPV). Thus, To be specific, let A@-[t] be the net operating cash flow, @-[t] be the netA
financial cash flow resulting from debt financing, and AA@-<t> be the combined
net cash flow, all for year t before tax. Then: The tax shields for interest on borrowing (for t = 1, 2, ..., n) are usually
given by When MARR = i is applied to both the operating and the financial cash flows
in Eqs. (6.13) and (6.28), respectively, in computing the net present values,
the combined effect will be the same as the net present value obtained by
applying MARR = i to the combined cash flow in Eq. (6.29).
In many instances, a risk premium related to the specified type of operation
is added to the MARR for discounting the operating cash flow. On the other
hand, the MARR for discounting the financial cash flow for borrowing is often
regarded as relatively risk-free because debtors or holders of corporate bonds
must be paid first before stockholders in case financial difficulties are
encountered by a corporation. Then, the adjusted net present value is given by The evaluation of combined alternatives based on the adjusted net present
value method should also be performed in dollar amounts which either
consistently include or remove the effects of inflation. The MARR value used
would reflect the inclusion or exclusion of inflation accordingly.
Furthermore, it is preferable to use after-tax cash flows in the evaluation of
projects for private firms since different designs and financing alternatives
are likely to have quite different implications for tax liabilities and tax
shields.
In theory, the corporate finance process does not necessarily require a
different approach than that of the APV method discussed above. Rather than
considering single projects in isolation, groups or sets of projects along with
financing alternatives can be evaluated. The evaluation process would be to
select that group of operating and financing plans which has the highest total
APV. Unfortunately, the number of possible combinations to evaluate can become
very large even though many combinations can be rapidly eliminated in practice
because they are clearly inferior. More commonly, heuristic approaches are
developed such as choosing projects with the highest benefit/cost ratio within
a particular budget or financial constraint. These heuristic schemes will
often involve the separation of the financing and design alternative
evaluation. The typical result is design-driven or finance-driven planning in
which one or the other process is conducted first.
Example 6-4: Combined Effects of Operating and Financing Plans
A public agency plans to construct a facility and is considering two design
alternatives with different capacities. The operating net cash flows for both
alternatives over a planning horizon of 5 years are shown in Table 6-0. For
each design alternative, the project can be financed either through overdraft
on bank credit or by issuing bonds spanning over the 5-year period, and the
cash flow for each financing alternative is also shown in Table 6-0. The
public agency has specified a MARR of 10% for discounting the operating and
financing cash flows for this project. Determine the best combination of
design and financing plan if
The net present values (NPV) of all cash flows can be computed by
Eq.(6.6.6), and the results are given at the bottom of Table 6-0. The adjusted
net present value (APV) combining the operating cash flow of each design and an
appropriate financing is obtained according to Eq. (6.25), and the results are
also tabulated at the bottom of Table 6-0.
Under condition (a), design alternative 2 will be selected since NPV =
$767,000 is the higher value when only operating cash flows are considered.
Subsequently, bonds financing will be chosen because APV = $466,000 indicates
that it is the best financing plan for design alternative 2.
Under condition (b), however, the choice will be based on the highest value
of APV, i.e., APV = $484,000 for design alternative one in combination will
overdraft financing. Thus, the simultaneous decision approach will yield the
best results.
!!!Design Alternative One Design Alternative Two
Year!!!Operating!!!Overdraft!!!Bond!!!Operating!!!Overdraft!!!Bond
!!!Cash Flow!!!Financing!!!Financing!!!Cash Flow!!!Financing!!!Financing
0!!!-1,000!!!1,000!!!3,653!!!-2,500!!!2,500!!!3,805
1!!!-2,500!!!2,500!!!-418!!!-1,000!!!1,000!!!-435
2!!!1,000!!!-1,000!!!-418!!!1,000!!!-1,000!!!-435
3!!!1,500!!!-1,500!!!-418!!!1,500!!!-1,500!!!-435
4!!!1,500!!!-1,500!!!-418!!!1,500!!!-1,500!!!-435
5!!!1,700!!!-921!!!-4,217!!!1,930!!!-1,254!!!-4,392
NPV or FPV!!!761!!!-277!!!-290!!!767!!!-347!!!-301
at 10%
APV =!!!!!!484!!!471!!!!!!420!!!466
NPV + FPV
Note: All monetary values are in thousands of dollars
In recent years, various organizational ownership schemes have been proposed
to raise the level of investment in constructed facilities. For example,
independent authorities are assuming responsibility for some water and sewer
systems, while private entrepreneurs are taking over the ownership of public
buildings such as stadiums and convention centers in joint ventures with local
governments. Such ownership arrangements not only can generate the capital for
new facilities, but also will influence the management of the construction and
operation of these facilities. In this section, we shall review some of these
implications.
A particular organizational arrangement or financial scheme is not
necessarily superior to all others in each case. Even for similar facilities,
these arrangements and schemes may differ from place to place or over time.
For example, U.S. water supply systems are owned and operated both by
relatively large and small organizations in either the private or public
sector. Modern portfolio theory suggest that there may be advantages in using
a variety of financial schemes to spread risks. Similarly, small or large
organizations may have different relative advantages with respect to personnel
training, innovation or other activities.
A basic difference between public and private ownership of facilities is
that private organizations are motivated by the expectation of profits in
making capital investments. Consequently, private firms have a higher minimum
attractive rate of return (MARR) on investments than do public agencies. The
MARR represents the desired return or profit for making capital investments.
Furthermore, private firms often must pay a higher interest rate for borrowing
than public agencies because of the tax exempt or otherwise subsidized bonds
available to public agencies. International loans also offer subsidized
interest rates to qualified agencies or projects in many cases. With higher
required rates of return, we expect that private firms will require greater
receipts than would a public agency to make a particular investment desirable.
In addition to different minimum attractive rates of return, there is also
an important distinction between public and private organizations with respect
to their evaluation of investment benefits. For private firms, the returns and
benefits to cover costs and provide profit are monetary revenues. In
contrast, public agencies often consider total social benefits in evaluating
projects. Total social benefits include monetary user payments plus users'
surplus (e.g., the value received less costs incurred by users), external
benefits (e.g., benefits to local businesses or property owners) and
nonquantifiable factors (e.g., psychological support, unemployment relief,
etc.). Generally, total social benefits will exceed monetary revenues.
While these different valuations of benefits may lead to radically different
results with respect to the extent of benefits associated with an investment,
they do not necessarily require public agencies to undertake such investments
directly. First, many public enterprises must fund their investments and
operating expenses from user fees. Most public utilities fall into this
category, and the importance of user fee financing is increasing for many civil
works such as waterways. With user fee financing, the required returns for the
public and private firms to undertake the aforementioned investment are, in
fact, limited to monetary revenues. As a second point, it is always possible
for a public agency to contract with a private firm to undertake a particular
project.
All other things being equal, we expect that private firms will require
larger returns from a particular investment than would a public agency. From
the users or taxpayers point of view, this implies that total payments would be
higher to private firms for identical services. However, there are a number
of mitigating factors to counterbalance this disadvantage for private firms.
Another difference between public and private facility owners is in their
relative liability for taxes. Public entities are often exempt from taxes of
various kinds, whereas private facility owners incur a variety of income,
property and excise taxes. However, these private tax liabilities can be
offset, at least in part, by tax deductions of various kinds.
For private firms, income taxes represent a significant cost of operation.
However, taxable income is based on the gross revenues less all expenses and
allowable deductions as permitted by the prevalent tax laws and regulations.
The most significant allowable deductions are depreciation and interest. By
selecting the method of depreciation and the financing plan which are most
favorable, a firm can exert a certain degree of control on its taxable income
and, thus, its income tax.
Another form of relief in tax liability is the tax credit which allows a
direct deduction for income tax purposes of a small percentage of the value of
certain newly acquired assets. Although the provisions for investment tax
credit for physical facilities and equipment had been introduced at different
times in the US federal tax code, they were eliminated in the 1986 Tax
Reformation Act except a tax credit for low-income housing.
Of course, a firm must have profits to take direct advantage of such tax
shields, i.e., tax deductions only reduce tax liabilities if before-tax profits
exist. In many cases, investments in constructed facilities have net outlays
or losses in the early years of construction. Generally, these losses in early
years can be offset against profits occurred elsewhere or later in time.
Without such offsetting profits, losses can be carried forward by the firm or
merged with other firms' profits, but these mechanisms will not be reviewed
here.
Major investments in constructed facilities typically rely upon borrowed
funds for a large portion of the required capital investments. For private
organizations, these borrowed funds can be useful for leverage to achieve a
higher return on the organizations' own capital investment.
For public organizations, borrowing costs which are larger than the MARR
results in increased "cost" and higher required receipts. Incurring these
costs may be essential if the investment funds are not otherwise available:
capital funds must come from somewhere. But it is not unusual for the
borrowing rate to exceed the MARR for public organizations. In this case,
reducing the amount of borrowing lowers costs, whereas increasing borrowing
lowers costs whenever the MARR is greater than the borrowing rate.
Although private organizations generally require a higher rate of return
than do public bodies (so that the required receipts to make the investment
desirable are higher for the private organization than for the public body),
consideration of tax shields and introduction of a suitable financing plan may
reduce this difference. The relative levels of the MARR for each group and
their borrowing rates are critical in this calculation.
An important element in public investments is the availability of capital
grant subsidies from higher levels of government. For example, interstate
highway construction is eligible for federal capital grants for up to 90% of
the cost. Other programs have different matching amounts, with 50/50 matching
grants currently available for wastewater treatment plants and various
categories of traffic systems improvement in the U.S. These capital grants are
usually made available solely for public bodies and for designated purposes.
While the availability of capital grant subsidies reduces the local cost of
projects, the timing of investment can also be affected. In particular, public
subsidies may be delayed or spread over a longer time period because of limited
funds. To the extent that (discounted) benefits exceed costs for particular
benefits, these funding delays can be costly. Consequently, private financing
and investment may be a desirable alternative, even if some subsidy funds are
available.
Different perspectives and financial considerations also may have
implications for design and construction choices. For example, an important
class of design decisions arises relative to the trade-off between capital and
operating costs. It is often the case that initial investment or construction
costs can be reduced, but at the expense of a higher operating costs or more
frequent and extensive rehabilitation or repair expenditures. It is this
trade-off which has led to the consideration of "life cycle costs" of
alternative designs. The financial schemes reviewed earlier can profoundly
effect such evaluations.
For financial reasons, it would often be advantageous for a public body to
select a more capital intensive alternative which would receive a larger
capital subsidy and, thereby, reduce the project's local costs. In effect,
the capital grant subsidy would distort the trade-off between capital and
operating costs in favor of more capital intensive projects.
The various tax and financing considerations will also affect the relative
merits of relatively capital intensive projects. For example, as the borrowing
rate increases, more capital intensive alternatives become less attractive.
Tax provisions such as the investment tax credit or accelerated depreciation
are intended to stimulate investment and thereby make more capital intensive
projects relatively more desirable. In contrast, a higher minimum attractive
rate of return tends to make more capital intensive projects less attractive.
While it is difficult to conclude definitely that one or another
organizational or financial arrangement is always superior, different
organizations have systematic implications for the ways in which constructed
facilities are financed, designed and constructed. Moreover, the selection of
alternative investments for constructed facilities is likely to be affected by
the type and scope of the decision-making organization.
As an example of the perspectives of public and private organizations,
consider the potential investment on a constructed facility with a projected
useful life of n years. Let t = 0 be the beginning of the planning horizon and
t = 1, 2, ... n denote the end of each of the subsequent years. Furthermore,
let C@-(o) be the cost of acquiring the facility at t = 0, and C@-(t) be the
cost of operation in year t. Then, the net receipts A@-(t) in year t is given
by A@-(t) = B@-(t) - C@-(t) in which A@-(t) may be positive or negative for t =
0, 1, 2, ..., n.
Let the minimum attractive rate of return (MARR) for the owner of the
facility be denoted by i. Then, the net present value (NPV) of a project as
represented by the net cash flow discounted to the present time is given by Example 6-5: Different MARRs for Public and Private Organizations
For the facility cost stream of a potential investment with n = 7 in Table 6-5,
the required uniform annual gross receipts B are different for public and
private ownerships since these two types of organizations usually choose
different values of MARR. With a given value of MARR = i in each case, the
value of B can be obtained from Eq. (6.32). With a MARR of 10%, a public
agency requires at least B = $184,000. By contrast, a private firm using a 20%
MARR before tax while neglecting other effects such as depreciation and tax
deduction would require at least B = $219,000. Then, according to Eq. (6.31),
the gross receipt streams for both public and private ownerships in Table 6-0
will satisfy the condition NPV = 0 when each of them is netted from the cost
stream and discounted at the appropriate value of MARR, i.e., 10% for a public
agency and 20% (before tax) for a private firm. Thus, this case suggests that
public provision of the facility has lower user costs.
!!!!!!Public Ownership!!!!!!Private Ownership
Year!!!Facility!!!Gross!!!Net Receipt!!!Gross!!!Net Receipt
t!!!Cost, C@-(t)!!!Receipt, B@-(t)!!!A@-(t)=B
@-(t)=C@-(t)!!!receipt, B@-(t)!!!A
@-(t)=B@-(t)=C@-(t)
0!!!500!!!0!!!-500!!!0!!!-500
1!!!76!!!184!!!108!!!219!!!143
2!!!78!!!184!!!106!!!219!!!141
3!!!80!!!184!!!104!!!219!!!139
4!!!82!!!184!!!102!!!219!!!137
5!!!84!!!184!!!100!!!219!!!135
6!!!86!!!184!!!98!!!219!!!133
7!!!88!!!184!!!96!!!219!!!131
*All Monetary amounts are in thousands of dollars
Year!!!Net Receipt!!!Depreciation!!!Taxable!!!Income!!!After-tax
t!!!Before-tax !!!(SOYD)!!!Income!!!Tax!!!Cash Flow
!!! A@-(t)!!! D@-(t)!!!(A@-[t]-D@-[t])!!!X
-
@-[t](A@-[t]-D@-[t])!!! @-(t)Y
0!!!-500!!!0!!!0!!!0!!!-500
1!!!143!!!125!!!18!!!6!!!137
2!!!141!!!107!!!34!!!12!!!129
3!!!139!!!89!!!50!!!17!!!122
4!!!137!!!71!!!66!!!22!!!115
5!!!135!!!54!!!81!!!28!!!107
6!!!133!!!36!!!97!!!33!!!100
7!!!131!!!18!!!113!!!38!!!93
*All monetary amounts are in thousands of dollars.
Example 6-6: Effects of Depreciation and Tax Shields for Private Firms
Using the same data as in Example 6-5, we now consider the effects of
depreciation and tax deduction for private firms. Suppose that the marginal
tax rate of the firm is 34% in each year of operation, and losses can always be
offset by company-wide profits. Suppose further that the salvage value of the
facility is zero at the end of seven years so that the entire amount of cost
can be depreciated by means of the sum-of-the-years'-digits (SOYD) method.
Thus, for the sum of digits 1 through 7 equal to 28, the depreciation
allowances for years 1 to 7 are respectively 7/28, 6/28, ..., 1/28 of the total
depreciable value of $ 500,000, and the results are recorded in column 3 of
Table 6-0. For a uniform annual gross receipt B = $219,000, the net receipt
before tax in Column 6 of Table 6-0 in Example 6-5 can be used as the starting
point for computing the after-tax cash flow according to Equation (6.13) which
is carried out step-by-step in Table 6-6. (Dollar amounts are given to the
nearest $1,000). By trial and error, it is found that an after-tax MARR =
14.5% will produce a zero value for the net present value of the discounted
after-tax flow at t = 0. In other words, the required uniform annual gross
receipt for this project at 14.5% MARR after tax is also B = $219,000. It
means that the MARR of this private firm must specify a 20% MARR before tax in
order to receive the equivalent of 14.5% MARR after tax.
Example 6-7: Effects of Borrowing on Public Agencies
Suppose that the gross uniform annual receipt for public ownership is B =
$190,000 instead of $184,000 for the facility with cost stream given in Column
2 of Table 6-5. Suppose further that the public agency must borrow $400,000
(80% of the facility cost) at 12% annual interest, resulting in an annual
uniform payment of $88,000 for the subsequent seven years. This information
has been summarized in Table 6-0. The use of borrowed funds to finance a
facility is referred to as debt financing or leveraged financing, and the
combined cash flow resulting from operating and financial cash flows is
referred to as the levered cash flow.
To the net receipt A@-(t) in Column 4 of Table 6-0, which has been obtained
from a uniform annual gross receipt of $190,000, we add the financial cash flow
-
@-(t) which included a loan of $400,000 with an annual repayment of $88,000A
corresponding to an interest rate of 12%. Then the resulting combined cash
flow AA@-(t) as computed according to Equation (6.26) is shown in column 6 of
Table 6-7. Note that for a loan at 12% interest, the net present value of the
combined cash flow AA@-(t) is zero when discounted at a 10% MARR for the public
agency. This is not a coincidence, but several values of B have been tried
until B = $190,000 is found to satisfy NPV = 0 at 10% MARR. Hence, the minimum
required uniform annual gross receipt is B = $190,000.
!!!!!!!!!!!!Loan and!!!Combined
!!!Gross!!!Facility!!!Net Receipt!!!Payment!!!Cash Flow
Year!!!receipt!!!cost!!!(no loan)!!!(12% interest)!!!(12% interest)
t!!!B@-(t)!!!C@-(t)!!!A@-(t)!!!
-
@-[t]!!!AA@-[t]A
0!!!0!!!500!!!-500!!!+400!!!-100
1!!!190!!!76!!!114!!!-88!!!-26
2!!!190!!!78!!!112!!!-88!!!24
3!!!190!!!80!!!110!!!-88!!!22
4!!!190!!!82!!!108!!!-88!!!20
5!!!190!!!84!!!106!!!-88!!!18
6!!!190!!!86!!!104!!!-88!!!16
7!!!190!!!88!!!102!!!-88!!!14
*All monetary amounts are in thousands of dollars.
Example 6-8: Effects of Leverage and Tax Shields for Private Organizations
Suppose that the uniform annual gross receipt for a private firm is also B =
$190,000 (the same as that for the public agency in Example 6-7). The salvage
value of the facility is zero at the end of seven years so that the entire
amount of cost can be depreciated by means of the sum-of-the-years'-digit
(SOYD) method. The marginal tax rate of the firm is 34% in each year of
operation, and losses can always be offset by company-wide profits. Suppose
further that the firm must borrow $400,000 (80% of the facility cost) at a 12%
annual interest, resulting in an annual uniform payment of $88,000 for the
subsequent seven years. The interest charge each year can be computed as 12%
of the remaining balance of the loan in the previous year, and the interest
charge is deductible from the tax liability.
For B = $190,000 and a facility cost stream identical to that in Example
6-7, the net receipts before tax A@-(t) (operating cash flow with no loan) in
Table 6-7 can be used as the starting point for analyzing the effects of
financial leverage through borrowing. Thus, column 4 of Table 6-7 is
reproduced in column 2 of Table 6-8.
!!!Net Receipt!!!!!!Loan and!!!!!!After Tax
!!!Before Tax!!!Depreciation!!!Scheduled!!!Interest!!!Income Tax!!!Cash Flow
Year!!!(no loan)!!!(SOYD)!!!Payment!!!On Loan!!!(34% rate)!!!(levered)
-
t!!!A@-(t)!!!D@-(t)!!! A
@-(t)!!!I@-(t)!!!X@-(t)(A@-(t)-D@-(t)-I@-(t))!!!YY@-(t)
0!!!-500!!!0!!!400!!!0!!!0!!!-100
1!!!114!!!125!!!-88!!!48!!!-19!!!45
2!!!112!!!107!!!-88!!!43!!!-13!!!37
3!!!110!!!89!!!-88!!!38!!!-6!!!28
4!!!108!!!71!!!-88!!!32!!!2!!!
5!!!106!!!54!!!-88!!!25!!!9!!!45
6!!!104!!!36!!!-88!!!18!!!17!!!45
7!!!102!!!18!!!-88!!!9!!!26!!!45
*All monetary amounts are in thousands of dollars.
The computation of the after-tax cash flow of the private firm including the
effects of tax shields for interest is carried out in Table 6-8. The financial
-
cash stream @-(t) in Column 4 of Table 6-8 indicates a loan of $400,000 whichA
is secured at t = 0 for an annual interest of 12%, and results in a series of
uniform annual payments of $88,000 in order to repay the principal and
interest. The levered after-tax cash flow YY@-(t) can be obtained by Eq.
(6.29), using the same investment credit, depreciation method and tax rate, and
is recorded in Column 7 of Table 6-8. Since the net present value of YY@-[t]
in Column 7 of Table 6-8 discounted at 14.5% happens to be zero, the minimum
required uniform annual gross receipt for the potential investment is $190,000.
By borrowing $400,000 (80% of the facility cost) at 12% annual interest, the
investment becomes more attractive to the private firm. This is expected
because of the tax shield for the interest and the 12% borrowing rate which is
lower than the 14.5% MARR after-tax for the firm.
Example 6-9: Comparison of Public and Private Ownership.
In each of the analyses in Examples 6-5 through 6-8, a minimum required
uniform annual gross receipt B is computed for each given condition whether the
owner is a public agency or a private firm. By finding the value of B which
will lead to NPV = 0 for the specified MARR for the organization in each case,
various organizational effects with or without borrowing can be analyzed. The
results are summarized in Table 6-9 for comparison. In this example, public
ownership with a 80% loan and a 10% MARR has the same required benefit as
private ownership with an identical 80% loan and a 14.5% after-tax MARR.
Organizational!!!Financial!!!Minimum Benefit
Condition!!!Arrangement!!!Required
Public-No Tax!!!No loan!!!$184,000
(MARR = 10%)!!!80% loan at 12% interest!!!$190,000
Private-before Tax!!!No loan!!!$219,000
(MARR = 20%)!!!!!!$219,000
Private-after tax!!!No loan!!!$219,000
(MARR = 14.5%)!!!80% loan at 12% interest!!!$190,000
Investment in a constructed facility represents a cost in the short term
that returns benefits only over the long term use of the facility. Thus, costs
occur earlier than the benefits, and owners of facilities must obtain the
capital resources to finance the costs of construction. A project cannot
proceed without adequate financing, and the cost of providing adequate
financing can be quite large. For these reasons, attention to project finance
is an important aspect of project management. Finance is also a concern to the
other organizations involved in a project such as the general contractor and
material suppliers. Unless an owner immediately and completely covers the
costs incurred by each participant, these organizations face financing problems
of their own.
At a more general level, project finance is only one aspect of the general
problem of corporate finance. If numerous projects are considered and financed
together, then the net cash flow requirements constitutes the corporate
financing problem for capital investment. Whether project finance is performed
at the project or at the corporate level does not alter the basic financing
problem.
In essence, the project finance problem is to obtain funds to bridge the
time between making expenditures and obtaining revenues. Based on the
conceptual plan, the cost estimate and the construction plan, the cash flow of
costs and receipts for a project can be estimated. Normally, this cash flow
will involve expenditures in early periods. Covering this negative cash
balance in the most beneficial or cost effective fashion is the project finance
problem. During planning and design, expenditures of the owner are modest,
whereas substantial costs are incurred during construction. Only after the
facility is complete do revenues begin. In contrast, a contractor would
receive periodic payments from the owner as construction proceeds. However, a
contractor also may have a negative cash balance due to delays in payment and
retainage of profits or cost reimbursements on the part of the owner.
Plans considered by owners for facility financing typically have both long
and short term aspects. In the long term, sources of revenue include sales,
grants, and tax revenues. Borrowed funds must be eventually paid back from
these other sources. In the short term, a wider variety of financing options
exist, including borrowing, grants, corporate investment funds, payment delays
and others. Many of these financing options involve the participation of third
parties such as banks or bond underwriters. For private facilities such as
office buildings, it is customary to have completely different financing
arrangements during the construction period and during the period of facility
use. During the latter period, mortgage or loan funds can be secured by the
value of the facility itself. Thus, different arrangements of financing
options and participants are possible at different stages of a project, so the
practice of financial planning is often complicated.
On the other hand, the options for borrowing by contractors to bridge their
expenditures and receipts during construction are relatively limited. For
small or medium size projects, overdrafts from bank accounts are the most
common form of construction financing. Usually, a maximum limit is imposed on
an overdraft account by the bank on the basis of expected expenditures and
receipts for the duration of construction. Contractors who are engaged in
large projects often own substantial assets and can make use of other forms of
financing which have lower interest charges than overdrafting.
In this chapter, we will first consider facility financing from the owner's
perspective, with due consideration for its interaction with other
organizations involved in a project. Later, we discuss the problems of
construction financing which are crucial to the profitability and solvency of
construction contractors.
Financing arrangements differ sharply by type of owner and by the type of
facility construction. As one example, many municipal projects are financed in
the United States with tax exempt bonds for which interest payments to a
lender are exempt from income taxes. As a result, tax exempt municipal bonds
are available at lower interest charges. Different institutional arrangements
have evolved for specific types of facilities and organizations.
A private corporation which plans to undertake large capital projects may
use its retained earnings, seek equity partners in the project, issue bonds,
offer new stocks in the financial markets, or seek borrowed funds in another
fashion. Potential sources of funds would include pension funds, insurance
companies, investment trusts, commercial banks and others. Developers who
invest in real estate properties for rental purposes have similar sources, plus
quasi-governmental corporations such as urban development authorities.
Syndicators for investment such as real estate investment trusts (REITs) as
well as domestic and foreign pension funds represent relatively new entries to
the financial market for building mortgage money.
Public projects may be funded by tax receipts, general revenue bonds, or
special bonds with income dedicated to the specified facilities. General
revenue bonds would be repaid from general taxes or other revenue sources,
while special bonds would be redeemed either by special taxes or user fees
collected for the project. Grants from higher levels of government are also an
important source of funds for state, county, city or other local agencies.
As an indication of the potential sources of financing, Table 7-0 shows the
dollar amounts of borrowing in United States credit markets during 1985. Not
all of these funds are used for construction, of course. Compared to the one
trillion in borrowed funds shown in Table 7-0, the value of construction put in
place is slightly more than a quarter of the total. Also, some construction is
funded from other sources. Nevertheless, it is apparent that bonds, mortgages
and bank loans are all major sources of financing.
______________________________________________________________________________
!!! Type !!!Amount
!!!!!!($ billions)
!!!U.S. Government Securities 324!!!
!!!State and Local Obligations 183!!!
!!!Corporate and Foreign Bonds 108!!!
!!!Mortgages
!!!!!!Home Mortgages 156!!!
!!!!!!Multi-Family Residential Mortgages 26!!!
!!!!!!Commercial Mortgages 61!!!
!!!!!!Farm Mortgages -6!!!
!!!Mortgages (Total) 237!!!
!!!Consumer Credit 97!!!
!!!Bank Loans 42!!!
!!!Open Market Paper 53!!!
!!!Other 50!!!
!!!Total $ 1,094!!!
Source: Federal Reserve Bulletin, Table 1.57, pg. A42, August 1986.
______________________________________________________________________________
Despite the different sources of borrowed funds, there is a rough
equivalence in the actual cost of borrowing money for particular types of
projects. Because lenders can participate in many different financial markets,
they tend to switch towards loans that return the highest yield for a
particular level of risk. As a result, borrowed funds that can be obtained
from different sources tend to have very similar costs, including interest
charges and issuing costs.
As a general principle, however, the costs of funds for construction will
vary inversely with the risk of a loan. Lenders usually require security for a
loan represented by a tangible asset. If for some reason the borrower cannot
repay a loan, then the borrower can take possession of the loan security. To
the extent that an asset used as security is of uncertain value, then the
lender will demand a greater return and higher interest payments. Loans made
for projects under construction represent considerable risk to a financial
institution. If a lender acquires an unfinished facility, then it faces the
difficult task of re-assembling the project team. Moreover, a default on a
facility may result if a problem occurs such as foundation problems or
anticipated unprofitability of the future facility. As a result of these
uncertainties, construction lending for unfinished facilities commands a
premium interest charge of several percent compared to mortgage lending for
completed facilities.
Financing plans will typically include a reserve amount to cover unforeseen
expenses, cost increases or cash flow problems. This reserve can be
represented by a special reserve or a contingency amount in the project budget.
In the simplest case, this reserve might represent a borrowing agreement with a
financial institution to establish a line of credit in case of need. For
publicly traded bonds, specific reserve funds administered by a third party may
be established. The cost of these reserve funds is the difference between the
interest paid to bondholders and the interest received on the reserve funds
plus any administrative costs.
Finally, arranging financing may involve a lengthy period of negotiation and
review. Particularly for publicly traded bond financing, specific legal
requirements in the issue must be met. A typical seven month schedule to issue
revenue bonds would include the various steps outlined in Table 7-0.[This table
is adapted from A.J. Henkel, "The Mechanics of a Revenue Bond Financing: An
Overview," Infrastructure Financing, Kidder, Peabody & Co., New York, 1984.]
In many cases, the speed in which funds may be obtained will determine a
project's financing mechanism.
______________________________________________________________________________
!!! Activities!!!Time of Activities
!!!Analysis of financial alternatives!!!Weeks 0-4
!!!Preparation of legal documents!!!Weeks 1-17
!!!Preparation of disclosure documents!!!Weeks 2-20
!!!Forecasts of costs and revenues!!!Weeks 4-20
!!!Bond Ratings!!!Weeks 20-23
!!!Bond Marketing!!!Weeks 21-24
!!!Bond Closing and Receipt of Funds!!!Weeks 23-26
______________________________________________________________________________
Example 7-1: Example of financing options
Suppose that you represent a private corporation attempting to arrange
financing for a new headquarters building. These are several options that
might be considered:
Since there are numerous different sources and arrangements for obtaining
the funds necessary for facility construction, owners and other project
participants require some mechanism for evaluating the different potential
sources. The relative costs of different financing plans are certainly
important in this regard. In addition, the flexibility of the plan and
availability of reserves may be critical. As a project manager, it is
important to assure adequate financing to complete a project. Alternative
financing plans can be evaluated using the same techniques that are employed
for the evaluation of investment alternatives.
As described in Chapter 6, the availability of different financing plans can
affect the selection of alternative projects. A general approach for obtaining
the combined effects of operating and financing cash flows of a project is to
determine the adjusted net present value (APV) which is the sum of the net
present value of the operating cash flow (NPV) and the net present value of the
financial cash flow (FPV), discounted at their respective minimum attractive
rates of return (MARR), i.e., For the sake of simplicity, we shall emphasize in this chapter the
evaluation of financing plans, with occasional references to the combined
effects of operating and financing cash flows. In all discussions, we shall
present various financing schemes with examples limiting to cases of before-tax
cash flows discounted at a before-tax MARR of r = r@-(f) for both operating and
financial cash flows. Once the basic concepts of various financing schemes are
clearly understood, their application to more complicated situations involving
depreciation, tax liability and risk factors can be considered in combination
with the principles for dealing with such topics enunciated in Chapter 6.
In this section, we shall concentrate on the computational techniques
associated with the most common types of financing arrangements. More detailed
descriptions of various financing schemes and the comparisons of their
advantages and disadvantages will be discussed in later sections.
Typically, the interest rate for borrowing is stated in terms of annual
percentage rate (A.P.R.), but the interest is accrued according to the rate
for the interest period specified in the borrowing agreement. Let i@-(p) be
the nominal annual percentage rate, and i be the interest rate for each of the
p interest periods per year. By definition For a coupon bond, the face value of the bond denotes the amount borrowed
(called principal) which must be repaid in full at a maturity or due date,
while each coupon designates the interest to be paid periodically for the total
number of coupons covering all periods until maturity. Let Q be the amount
borrowed, and I@-(p) be the interest payment per period which is often six
months for coupon bonds. If the coupon bond is prescribed to reach maturity in
n years from the date of issue, the total number of interest periods will be pn
= 2n. The semi-annual interest payment is given by: An alternative loan arrangement is to make a series of uniform payments
including both interest and part of the principal for a pre-defined number of
repayment periods. In the case of uniform payments at an interest rate i for n
repayment periods, the uniform repayment amount U is given by: Usually, there is an origination fee associated with borrowing for legal and
other professional services which is payable upon the receipt of the loan.
This fee may appear in the form of issuance charges for revenue bonds or
percentage point charges for mortgages. The borrower must allow for such fees
in addition to the construction cost in determining the required original
amount of borrowing. Suppose that a sum of P@-(o) must be reserved at t=0 for
the construction cost, and K is the origination fee. Then the original loan
needed to cover both is: Because the borrowing rate i will generally exceed the investment rate h for
the running balance in the project account and since the origination fee
increases with the amount borrowed, the financial planner should minimize the
amount of money borrowed under this finance strategy. Thus, there is an
optimal value for Q such that all estimated shortfalls are covered, interest
payments and expenses are minimized, and adequate reserve funds are available
to cover unanticipated factors such as construction cost increases. This
optimal value of Q can either be identified analytically or by trial and error.
Finally, variations in ownership arrangements may also be used to provide at
least partial financing. Leasing a facility removes the need for direct
financing of the facility. Sale-leaseback involves sale of a facility to a
third party with a separate agreement involving use of the facility for a
pre-specified period of time. In one sense, leasing arrangements can be viewed
as a particular form of financing. In return for obtaining the use of a
facility or piece of equipment, the user (lesser) agrees to pay the owner
(lesser) a lease payment every period for a specified number of periods.
Usually, the lease payment is at a fixed level due every month, semi-annually,
or annually. Thus, the cash flow associated with the equipment or facility use
is a series of uniform payments. This cash flow would be identical to a cash
flow resulting from financing the facility or purchase with sufficient borrowed
funds to cover initial construction (or purchase) and with a repayment schedule
of uniform amounts. Of course, at the end of the lease period, the ownership
of the facility or equipment would reside with the lesser. However, the lease
terms may include a provision for transferring ownership to the lesser after a
fixed period.
Example 7-2: A coupon bond cash flow and cost
A private corporation wishes to borrow $10.5 million for the construction of
a new building by issuing a twenty-year coupon bond at an annual percentage
interest rate of 10% to be paid semi-annually, i.e. 5% per interest period of
six months. The principal will be repaid at the end of 20 years. The amount
borrowed will cover the construction cost of $10.331 million and an origination
fee of $169,000 for issuing the coupon bond.
The interest payment per period is (5%) (10.5) = $0.525 million over a life
time of (2) (20) = 40 interest periods. Thus, the cash flow of financing by
the coupon bond consists of a $10.5 million receipt at period 0, -$0.525
million each for periods 1 through 40, and an additional -$10.5 million for
period 40. Assuming a MARR of 5% per period, the net present value of the
financial cash flow is given by: Example 7-3: An example of leasing versus ownership analysis
Suppose that a developer offered a building to a corporation for an annual
lease payment of $ 10 million over a thirty year lifetime. For the sake of
simplicity, let us assume that the developer also offers to donate the building
to the corporation at the end of thirty years or, alternatively, the building
would then have no commercial value. Also, suppose that the initial cost of
the building was $ 65.66 million. For the corporation, the lease is equivalent
to receiving a loan with uniform payments over thirty years at an interest rate
of 15% since the present value of the lease payments is equal to the initial
cost at this interest rate: Example 7-4: Example evaluation of alternative financing plans.
Suppose that a small corporation wishes to build a headquarters building.
The construction will require two years and cost a total of $ 12 million,
assuming that $ 5 million is spent at the end of the first year and $7 million
at the end of the second year. To finance this construction, several options
are possible, including:
The first step in evaluation is to calculate the required amounts and cash
flows associated with these three alternative financing plans. First,
investment using retained earnings will require a commitment of $ 5 million in
year 1 and $ 7 million in year 2.
Second, borrowing from the local bank must yield sufficient funds to cover
both years of construction plus the issuing fee. With the unused fund
accumulating interest at a rate of 10%, the amount of dollars needed at the
beginning of the first year for future construction cost payments is: If this loan is to be repaid by annual uniform payments from corporate
earnings, the amount of each payment over the twenty year life time of the loan
can be calculated by Eq. (7.6) as follows: Finally, the twenty-year coupon bond would have to be issued in the amount
of $10.5 million which will reflect a higher origination fee of $169,000.
Thus, the amount for financing is: Table 7-0 summarizes the cash flows associated with the three alternative
financing plans. Note that annual incomes generated from the use of this
building have not been included in the computation. The adjusted net present
value of the combined operating and financial cash flows for each of the three
plans discounted at the corporate MARR of 15% is also shown in the table. In
this case, the coupon bond is the least expensive financing plan. Since the
borrowing rates for both the bank loan and the coupon bond are lower than the
corporate MARR, these results are expected.
______________________________________________________________________________
!!!!!! Retained!!! Bank!!! Coupon
Year!!! Source!!! Earnings!!! Loan!!! Bond
0!!!Principal!!! -!!! $ 10.409!!! $ 10.500
0!!!Issuing Cost!!! -!!! -0.078!!! -0.169
1!!!Earned Interest!!!-!!! 1.033!!! 1.033
1!!!Contractor Payment!!!$ -5.000!!! $ -5.000!!! $ -5.000
1!!!Loan Repayment!!!-!!! -1.324!!! - 1.076
2!!!Earned Interest!!!-!!! 0.636!!! 0.636
2!!!Contractor Payment!!!$ -7.000!!! $ -7.000!!! $ -7.000
2!!!Loan Repayment!!!-!!! - 1.324!!! - 1.076
3-19!!!Loan Repayment!!!-!!! - 1.324!!! - 1.076
20!!!Loan Repayment!!!-!!! -1.324!!! -11.576
[APV]@-(15%)!!!!!!-9.641!!! - 6.217!!! - 5.308
______________________________________________________________________________
Secured lending involves a contract between a borrower and lender, where the
lender can be an individual, a financial institution or a trust organization.
Notes and mortgages represent formal contracts between financial institutions
and owners. Usually, repayment amounts and timing are specified in the loan
agreement. Public facilities are often financed by bond issues for either
specific projects or for groups of projects. For publicly issued bonds, a
trust company is usually designated to represent the diverse bond holders in
case of any problems in the repayment. The borrowed funds are usually secured
by granting the lender some rights to the facility or other assets in case of
defaults on required payments. In contrast, corporate bonds such as debentures
can represent loans secured only by the good faith and credit worthiness of the
borrower.
Under the terms of many bond agreements, the borrower reserves the right to
repurchase the bonds at any time before the maturity date by repaying the
principal and all interest up to the time of purchase. The required repayment
R@-(c) at the end of period c is the net future value of the borrowed amount Q
-
less the payment @-(t) made at intermediate periods compounded at theA
borrowing rate i to period c as follows: Many types of bonds can be traded in a secondary market by the bond holder.
As interest rates fluctuate over time, bonds will gain or lose in value. The
actual value of a bond is reflected in the market discount or premium paid
relative to the original principal amount (the face value). Another indicator
of this value is the yield to maturity or internal rate of return of the
bond. This yield is calculated by finding the interest rate that sets the
(discounted) future cash flow of the bond equal to the current market price: Several other factors come into play in evaluation of bond values from the
lenders point of view, however. First, the lender must adjust for the
possibility that the borrower may default on required interest and principal
payments. In the case of publicly traded bonds, special rating companies
divide bonds into different categories of risk for just this purpose.
Obviously, bonds that are more likely to default will have a lower value.
Secondly, lenders will typically make adjustments to account for changes in the
tax code affecting their after-tax return from a bond. Finally, expectations
of future inflation or deflation as well as exchange rates will influence
market values.
Another common feature in borrowing agreements is to have a variable
interest rate. In this case, interest payments would vary with the overall
market interest rate in some pre-specified fashion. From the borrower's
perspective, this is less desirable since cash flows are less predictable.
However, variable rate loans are typically available at lower interest rates
because the lenders are protected in some measure from large increases in the
market interest rate and the consequent decrease in value of their expected
repayments. Variable rate loans can have floors and ceilings on the applicable
interest rate or on rate changes in each year.
Example 7-5: Example of a corporate promissory note
A corporation wishes to consider the option of financing the headquarters
building in Example 7-4 by issuing a five year promissory note which requires
an origination fee for the note is $25,000. Then a total borrowed amount needed
at the beginning of the first year to pay for the construction costs and
origination fee is 10.331 + 0.025 = $ 10.356 million. Interest payments are
made annually at an annual rate of 10.8% with repayment of the principal at the
end of the fifth year. Thus, the annual interest payment is (10.8%) (10.356) =
$1.118 million. With the data in Example 7-4 for construction costs and
accrued interests for the first two year, the combined operating and and
financial cash flows in million dollars can be obtained:
For this problem as well as for the financing arrangements in Example 7-4,
the project account is maintained to pay the construction costs only, while the
interest and principal payments are repaid from corporate earnings.
-
Consequently, the @-(t) terms in Eq. (7.10) will disappear when the accountA
balance in each period is computed for this problem:
Example 7-6: Bond financing mechanisms.
Suppose that the net operating expenditures and receipts of a facility
investment over a five year time horizon are as shown in column 2 of Table 7-0
in which each period is six months. This is a hypothetical example with a
deliberately short life time period to reduce the required number of
calculations. Consider two alternative bond financing mechanisms for this
project. Both involve borrowing $ 2.5 million at an issuing cost of five
percent of the loan with semi-annual repayments at a nominal annual interest
rate of ten percent i.e., 5% per period. Any excess funds can earn an interest
of four percent each semi-annual period. The coupon bond involves only
interest payments in intermediate periods, plus the repayment of the principal
at the end, whereas the uniform payment bond requires ten uniform payments to
cover both interests and the principal. Both bonds are subject to optional
redemption by the borrower before maturity.
The operating cash flow in column 2 of Table 7-4 represents the construction
expenditures in the early periods and rental receipts in later periods over the
lifetime of the facility. By trial and error with Eqs. (7.9) and (7.10), it
can be found that Q = $2.5 million (K = $0.125 or 5% of Q) is necessary to
insure a nonnegative balance in the project account for the uniform payment
bond, as shown in Column 6 of Table 7-4. For the purpose of comparison, the
same amount is borrowed for the coupon bond option even though a smaller loan
will be sufficient for the construction expenditures in this case.
The financial cash flow of the coupon bond can easily be derived from Q =
$2.5 million and K = $0.125 million. Using Eq. (7.5), I@-(p) = (5%) (2.5) =
$0.125 million, and the repayment in Period 10 is Q + I@-(p) = $2.625 million
as shown in Column 3 of Table 7-4. The account balance for the coupon bond in
Column 4 is obtained from Eqs. (7.9) and (7.10). On the other hand, the
uniform annual payment U = $0.324 million for the financial cash flow of the
uniform payment bond (Column 5) can be obtained from Eq. (7.6), and the bond
account for this type of balance is computed by Eqs. (7.9) and (7.10).
Because of the optional redemption provision for both types of bonds, it is
advantageous to gradually redeem both options at the end of period 3 to avoid
interest payments resulting from i = 5% and h = 4% unless the account balance
beyond period 3 is needed to fund other corporate investments. corporate
earnings are available for repurchasing the bonds at end of period 3, the
required repayment for coupon bond after redeeming the last coupon at the end
of period 3 is simply $2.625 million. In the case of the uniform payment bond,
the required payment after the last uniform payment at the end of period 3 is
obtained from Equation (7-12) as:
R@-(3) = (0.324) (P|U, 5%, 7) = (0.324) (5.7864) = $1.875 million.
______________________________________________________________________________
Period!!!Operating!!!Coupon!!!Account!!!Uniform!!!Account
!!!Cash Flow!!!Cash Flow!!!Balance!!!Cash Flow!!!Balance
0!!! -!!! 2,375.!!! 2,375!!! 2,375!!! 2,375!!!
1!!! -800!!! -125!!! 1545!!! -324!!! 1346!!!
2!!! -700!!! -125!!! 782!!! -324!!! 376!!!
3!!! -60!!! -125!!! 628!!! -324!!! 8!!!
4!!! 400!!! -125!!! 928!!! -324!!! 84!!!
5!!! 600!!! -125!!! 1,440!!! -324!!! 364!!!
6!!! 800!!! -125!!! 2,173!!! -324!!! 854!!!
7!!! 1,000!!! -125!!! 3,135!!! -324!!! 1,565!!!
8!!! 1,000!!! -125!!! 4,135!!! -324!!! 2,304!!!
9!!! 1,000!!! -125!!! 5,176!!! -324!!! 3,072!!!
10!!! 1,000!!! -2,625!!! 3,758!!! -324!!! 3,871!!!
Note: All numbers are in thousand dollars.
______________________________________________________________________________
Example 7-7: Provision of Reserve Funds
Typical borrowing agreements may include various required reserve funds.[The
calculations for this bond issue are adapted from a hypothetical example in
F. H. Fuller, "Analyzing Cash Flows for Revenue Bond Financing," Infrastructure
Financing, Kidder, Peabody & Co., Inc., New York, 1984, pp. 37-47.] Consider
an eighteen month project costing five million dollars. To finance this
facility, coupon bonds will be issued to generate revenues which must be
sufficient to pay interest charges during the eighteen months of construction,
to cover all construction costs, to pay issuance expenses, and to maintain a
debt service reserve fund. The reserve fund is introduced to assure
bondholders of payments in case of unanticipated construction problems. It is
estimated that a total amount of $ 7.4 million of bond proceeds is required,
including a two percent discount to underwriters and an issuance expense of
$100,000.
Three interest bearing accounts are established with the bond proceeds to
separate various categories of funds:
______________________________________________________________________________
Sources of Funds
!!!Bond Proceeds $ 7,400,000!!!
!!!Interest Earnings on Construction Fund 278,400!!!
!!!Interest Earnings of Capitalized Interest Fund 77,600!!!
!!!Interest Earnings on Debt Service Reserve Fund 287,640!!!
!!!Total Sources of Funds $ 8,043,640!!!
Uses of Funds
!!!Construction Costs $ 5,000,000!!!
!!!Interest Payments 904,100!!!
!!!Debt Service Reserve Fund 1,891,540!!!
!!!Bond Discount (2.0%) 148,000!!!
!!!Issuance Expense 100,000!!!
!!!Total Uses of Funds $ 8,043,640!!!
______________________________________________________________________________
First Series of 1987: $12,000,000
Date: December 1, 1987 Due: November 1, 2017
Example 7-8: Variable rate revenue bonds prospectus
The information in Table 7-6 is abstracted from the Prospectus for a new
issue of revenue bonds for the Atwood City. This prospectus language is
typical for municipal bonds. Notice the provision for variable rate after the
initial interest periods. The borrower reserves the right to repurchase the
bond before the date for conversion to variable rate takes effect in order to
protect itself from declining market interest rates in the future so that the
borrower can obtain other financing arrangements at lower rates.
Overdrafts can be arranged with a banking institution to allow accounts to
have either a positive or a negative balance. With a positive balance,
interest is paid on the account balance, whereas a negative balance incurs
interest charges. Usually, an overdraft account will have a maximum overdraft
limit imposed. Also, the interest rate h available on positive balances is
less than the interest rate i charged for borrowing.
Clearly, the effects of overdraft financing depends upon the pattern of cash
flows over time. Suppose that the net cash flow for period t in the account is
denoted by A@-(t) which is the difference between the receipt P@-(t) and the
payment E@-(t) in period t. Hence, A@-(t) can either be positive or negative.
The amount of overdraft at the end of period t is the cumulative net cash flow
N@-(t) which may also be positive or negative. If N@-(t) is positive, a
surplus is indicated and the subsequent interest would be paid to the borrower.
Most often, N@-(t) is negative during the early time periods of a project and
becomes positive in the later periods when the borrower has received payments
exceeding expenses.
If the borrower uses overdraft financing and pays the interest per period on
the accumulated overdraft at a borrowing rate i in each period, then the
interest per period for the accumulated overdraft N@-(t-1) from the previous
period (t-1) is I@-(t) = iN@-(t-1) where I@-(t) would be negative for a
negative account balance N@-(t-1). For a positive account balance, the
interest received is I@-(t) = hN@-(t-1) where I@-(t) would be positive for a
positive account balance.
The account balance N@-(t) at each period t is the sum of receipts P@-(t),
payments E@-(t), interest I@-(t) and the account balance from the previous
period N@-(t-1). Thus, For the purpose of separating project finances with other receipts and
payments in an organization, it is convenient to establish a credit account
into which receipts related to the project must be deposited when they are
received, and all payments related to the project will be withdrawn from this
account when they are needed. Since receipts typically lag behind payments for
a project, this credit account will have a negative balance until such time
when the receipts plus accrued interests are equal to or exceed payments in the
period. When that happens, any surplus will not be deposited in the credit
account, and the account is then closed with a zero balance. In that case, for
negative N@-(t-1), Eq. (7.7.5) can be expressed as: Example 7-9: Overdraft Financing with Grants to a Local Agency
A public project which costs $ 61,525,000 is funded eighty percent by a
federal grant and twenty percent from a state grant. The anticipated duration
of the project is six years with receipts from grant funds allocated at the end
of each year to a local agency to cover partial payments to contractors for
that year while the remaining payments to contractors will be allocated at the
end of the sixth year. The end-of-year payments are given in Table 7-0 in
which t=0 refers to the beginning of the project, and each period is one year.
If this project is financed with an overdraft at an annual interest rate i =
10%, then the account balance are computed by Eq. (7.7.5) and the results are
shown in Table 7-0.
In this project, the total grant funds to the local agency covered the cost
of construction in the sense that the sum of receipts equaled the sum of
construction payments of $ 61,525,000. However, the timing of receipts lagged
payments, and the agency incurred a substantial financing cost, equal in this
plan to the overdraft amount of $ 1,780,000 at the end of year 6 which must be
paid to close the credit account. Clearly, this financing problem would be a
significant concern to the local agency.
______________________________________________________________________________
Period!!!Receipts!!!Payments!!!Interest!!!Account!!!
t!!! P@-(t)!!! E@-(t)!!! I@-(t)!!! N@-(t)!!!
0!!! 0!!! 0!!! 0!!! 0!!!
1!!! 5.826!!! 6.473!!! 0!!! -0.647!!!
2!!! 8.401!!! 9.334!!! -0.065!!! -1.645!!!
3!!! 12.013!!! 13.348!!! -0.165!!! -3.145!!!
4!!! 15.149!!! 16.832!!! 0.315!!! -5.143!!!
5!!! 13.984!!! 15.538!!! -0.514!!! -7.211!!!
6!!! 6.152!!! 0!!! -0.721!!! -1.780!!!
Total!!! 61.525!!! 61.525!!! -1.780!!!
______________________________________________________________________________
Example 7-10: Use of overdraft financing for a facility
A corporation is contemplating an investment in a facility with the
following before-tax operating net cash flow (in thousands of dollars) at year
ends: The results of the analysis of this project is shown in Table 7-0 as
follows:
Refinancing of debts has two major advantages for an owner. First, they
allow re-financing at intermediate stages to save interest charges. If a
borrowing agreement is made during a period of relatively high interest
charges, then a repurchase agreement allows the borrower to re-finance at a
lower interest rate. Whenever the borrowing interest rate declines such that
the savings in interest payments will cover any transaction expenses (for
purchasing outstanding notes or bonds and arranging new financing), then it is
advantageous to do so.
Another reason to repurchase bonds is to permit changes in the operation of
a facility or new investments. Under the terms of many bond agreements, there
may be restrictions on the use of revenues from a particular facility while any
bonds are outstanding. These restrictions are inserted to insure bondholders
that debts will be repaid. By repurchasing bonds, these restrictions are
removed. For example, several bridge authorities had bonds that restricted any
diversion of toll revenues to other transportation services such as transit.
By repurchasing these bonds, the authority could undertake new operations.
This type of repurchase may occur voluntarily even without a repurchase
agreement in the original bond. The borrower may give bondholders a premium to
retire bonds early.
Example 7-11: Refinancing a loan.
Suppose that the bank loan shown in Example 7-4 had a provision permitting
the borrower to repay the loan without penalty at any time. Further, suppose
that interest rates for new loans dropped to nine percent at the end of year
six of the loan. Issuing costs for a new loan would be $ 50,000. Would it be
advantageous to re-finance the loan at that time?
To repay the original loan at the end of year six would require a payment of
the remaining principal plus the interest due at the end of year six. This
amount R@-(6) is equal to the present value of remaining fourteen payments
discounted at the loan interest rate 11.2% to the end of year 6 as given in
Equation (7-13) as follows: We have focused so far on problems and concerns at the project level. While
this is the appropriate viewpoint for project managers, it is always worth
bearing in mind that projects must fit into broader organizational decisions
and structures. This is particularly true for the problem of project finance,
since it is often the case that financing is planned on a corporate or agency
level, rather than a project level. Accordingly, project managers should be
aware of the concerns at this level of decision making.
A construction project is only a portion of the general capital budgeting
problem faced by an owner. Unless the project is very large in scope relative
to the owner, a particular construction project is only a small portion of the
capital budgeting problem. Numerous construction projects may be lumped
together as a single category in the allocation of investment funds.
Construction projects would compete for attention with equipment purchases or
other investments in a private corporation.
Financing is usually performed at the corporate level using a mixture of
long term corporate debt and retained earnings. A typical set of corporate
debt instruments would include the different bonds and notes discussed in this
chapter. Variations would typically include different maturity dates,
different levels of security interests, different currency denominations, and,
of course, different interest rates.
Grouping projects together for financing influences the type of financing
that might be obtained. As noted earlier, small and large projects usually
involve different institutional arrangements and financing arrangements. For
small projects, the fixed costs of undertaking particular kinds of financing
may be prohibitively expensive. For example, municipal bonds require fixed
costs associated with printing and preparation that do not vary significantly
with the size of the issue. By combining numerous small construction projects,
different financing arrangements become more practical.
While individual projects may not be considered at the corporate finance
level, the problems and analysis procedures described earlier are directly
relevant to financial planning for groups of projects and other investments.
Thus, the net present values of different financing arrangements can be
computed and compared. Since the net present values of different sub-sets of
either investments or financing alternatives are additive, each project or
finance alternative can be disaggregated for closer attention or aggregated to
provide information at a higher decision making level.
Example 7-12: Basic types of repayment schedules for loans.
Coupon bonds are used to obtain loans which involve no payment of principal
until the maturity date. By combining loans of different maturities, however,
it is possible to achieve almost any pattern of principal repayments. However,
the interest rates charged on loans of different maturities will reflect market
forces such as forecasts of how interest rates will vary over time. As an
example, Table 7-0 illustrates the cash flows of debt service for a series of
coupon bonds used to fund a municipal construction project; for simplicity not
all years of payments are shown in the table.
In this financing plan, a series of coupon bonds were sold with maturity
dates ranging from June 1988 to June 2012. Coupon interest payments on all
outstanding bonds were to be paid every six months, on December 1 and June 1 of
each year. The interest rate or "coupon rate" was larger on bonds with longer
maturities, reflecting an assumption that inflation would increase during this
period. The total principal obtained for construction was $ 26,250,000 from
sale of these bonds. This amount represented the gross sale amount before
subtracting issuing costs or any sales discounts; the amount available to
support construction would be lower. The maturity dates for bonds were
selected to require relative high repayment amounts until December 1995, with a
declining repayment amount subsequently. By shifting the maturity dates and
amounts of bonds, this pattern of repayments could be altered. The initial
interest payment (of $ 819,760 on December 1, 1987), reflected a payment for
only a portion of a six month period since the bonds were issued in late June
of 1987.
Date!!! Maturing!!! Corresponding
!!! Interest!!! Annual
!!! Principal!!! Interest Rate
!!! Due!!! Debt Service
Dec. 1, 1987!!!!!!!!! $ 819,760!!! $ 819,760
June 1, 1988!!! 1,350,000!!! 5.00!!! 894,429!!!
Dec. 1, 1988!!!!!!!!! 860,540!!! 3,184,830
June 1, 1989!!! 1,450,000!!! 5.25!!! 860,540!!!
Dec. 1, 1989!!! !!!!!! 822,480!!! 3,133,010
June 1, 1990!!! 1,550,000!!! 5.50!!! 822,480!!!
Dec. 1, 1990!!!!!!!!! 779,850!!! 3,152,330
June 1, 1991!!! 1,600,000!!! 5.80!!! 779,850!!!
Dec. 1, 1991!!!!!!!!! 733,450!!! 3,113,300
June 1, 1992!!! 1,700,000!!! 6.00!!! 73,3450!!!
Dec. 1, 1992!!!!!!!!! 682,450!!! 3,115,900
June 1, 1993!!! 1,800,000!!! 6.20!!! 682,450!!!
Dec. 1, 1993!!!!!!!!! 626,650!!! 3,109,100
.!!! .!!! .!!! .!!! .
.!!! .!!! .!!! .!!! .
.!!! .!!! .!!! .!!! .
June 1, 2011!!! 880,000!!! 8.00!!! 68,000!!!
Dec. 1, 2011!!!!!!!!! 36,000!!! 964,000
June 1, 2012!!! 96,000!!! 8.00!!! 36,000!!!
Dec. 1, 2012!!!!!!!!!!!! 936,000
The different participants in the construction process have quite distinct
perspectives on financing. In the realm of project finance, the revenues to
one participant represent an expenditure to some other participant. Payment
delays from one participant result in a financial burden and a cash flow
problem to other participants. It is common occurrence in construction to
reduce financing costs by delaying payments in just this fashion. Shifting
payment times does not eliminate financing costs, however, since the financial
burden still exists.
Traditionally, many organizations have used payment delays both to shift
financing expenses to others or to overcome momentary shortfalls in financial
resources. From the owner's perspective, this policy may have short term
benefits, but it certainly has long term costs. Since contractors do not have
large capital assets, they typically do not have large amounts of credit
available to cover payment delays. Contractors are also perceived as credit
risks in many cases, so loans often require a premium interest charge.
Contractors faced with large financing problems are likely to add premiums to
bids or not bid at all on particular work. For example, A. Maevis
noted:[Maevis, Alfred C., "Construction Cost Control by the Owner," ASCE
Journal of the Construction Division, Vol. 106, No. 4, December, 1980, pg.
444.]
The owner of a constructed facility usually has a better credit rating and
can secure loans at a lower borrowing rate, but there are some notable
exceptions to this rule, particularly for construction projects in developing
countries. Under certain circumstances, it is advisable for the owner to
advance periodic payments to the contractor in return for some concession in
the contract price. This is particularly true for large-scale construction
projects with long durations for which financing costs and capital requirements
are high. If the owner is willing to advance these amounts to the contractor,
the gain in lower financing costs can be shared by both parties through prior
agreement.
Unfortunately, the choice of financing during the construction period is
often left to the contractor who cannot take advantage of all available options
alone. The owner is often shielded from participation through the traditional
method of price quotation for construction contracts. This practice merely
exacerbates the problem by excluding the owner from participating in decisions
which may reduce the cost of the project.
Under conditions of economic uncertainty, a premium to hedge the risk must
be added to the estimation of construction cost by both the owner and the
contractor. The larger and longer the project is, the greater is the risk.
For an unsophisticated owner who tries to avoid all risks and to place the
financing burdens of construction on the contractor, the contract prices for
construction facilities are likely to be increased to reflect the risk premium
charged by the contractors. In dealing with small projects with short
durations, this practice may be acceptable particularly when the owner lacks
any expertise to evaluate the project financing alternatives or the financial
stability to adopt innovative financing schemes. However, for large scale
projects of long duration, the owner cannot escape the responsibility of
participation if it wants to avoid catastrophes of run-away costs and expensive
litigation. The construction of nuclear power plants in the private sector and
the construction of transportation facilities in the public sector offer ample
examples of such problems. If the responsibilities of risk sharing among
various parties in a construction project can be clearly defined in the
planning stage, all parties can be benefited to take advantage of cost saving
and early use of the constructed facility.
Example 7-13: Effects of payment delays
Table 7-0 shows an example of the effects of payment timing on the general
contractor and subcontractors. The total contract price for this project is $
5,100,000 with scheduled payments from the owner shown in Column 2. The
general contractor's expenses in each period over the lifetime of the project
are given in Column 3 while the subcontractor's expenses are shown in Column 4.
If the general contractor must pay the subcontractor's expenses as well as its
own at the end of each period, the net cash flow of the general contractor is
obtained in Column 5, and its cumulative cash flow in Column 6.
In this example, the owner withholds a five percent retainage on cost as
well as a payment of $ 100,000 until the completion of the project. This $
100,000 is equal to the expected gross profit of the contractor without
considering financing costs or cash flow discounting. Processing time and
contractual agreements with the owner result in a delay of one period in
receiving payments. The actual construction expenses from the viewpoint of the
general contractor consist of $ 100,000 in each construction period plus
payments due to subcontractors of $ 900,000 in each period. While the net cash
flow without regard to discounting or financing is equal to a $ 100,000 profit
for the general contractor, financial costs are likely to be substantial. With
immediate payment to subcontractors, over $ 1,000,000 must be financed by the
contractor throughout the duration of the project. If the general contractor
uses borrowing to finance its expenses, a maximum borrowing amount of $
1,200,000 in period five is required even without considering intermediate
interest charges. Financing this amount is likely to be quite expensive and
may easily exceed the expected project profit.
______________________________________________________________________________
!!! !!! General!!! Sub-!!! General!!!
!!!Owner!!! Contractor's!!! Contractor's!!!
Contractor's!!! Cumulative!!!
Period!!! Payments!!! Expenses!!! Expenses!!!
Net Cash Flow!!! Cash Flow
1!!! -!!! $ 100,000.!!! $ 900,000.!!!
$ -1,000,000.!!! $ -1,000,000.!!!
2!!! $ 950,000.!!! 100,000.!!! 900,000.!!!
-50,000.!!! -1,050,000.!!!
3!!! 950,000.!!! 100,000.!!! 900,000.!!!
-50,000.!!! -1,100,000.!!!
4!!! 950,000.!!! 100,000.!!! 900,000.!!!
-50,000.!!! -1,150,000.!!!
5!!! 950,000.!!! 100,000.!!! 900,000.!!!
-50,000.!!! -1,200,000.!!!
6!!! 1,300,000.!!! - !!! - !!!
1,300,000.!!! 100,000.!!!
Totals!!! $ 5,100,000.!!! $ 500,000.!!!
$ 4,500,000.!!! $ 100,000.!!!
Note: Cumulative cash flow includes no financing charges.
______________________________________________________________________________
By delaying payments to subcontractors, the general contractor can
substantially reduce its financing requirement. For example, Table 7-0 shows
the resulting cash flows from delaying payments to subcontractors for one
period and for two periods, respectively. With a one period delay, a maximum
amount of $ 300,000 (plus intermediate interest charges) would have to be
financed by the general contractor. That is, from the data in Table 7-0, the
net cash flow in period 1 is -$ 100,000, and the net cash flow for each of the
periods 2 through 5 is given by:
______________________________________________________________________________
!!! One Period Payment Delay!!!
Two Period Payment Delay!!!
!!! Net!!! Cumulative!!! Net!!! Cumulative!!!
Period!!! Cash Flow!!! Cash Flow!!!
Cash Flow!!! Cash Flow!!!
1!!! $ -100,000.!!! $ -100,000.!!!
$ -100,000.!!! $ -100,000.!!!
2!!! $ -50,000.!!! $ -150,000.!!! $ 850,000.!!! $ 750,000.!!!
3!!! $ -50,000.!!! $ -200,000.!!! $ -50,000.!!! $ 700,000.!!!
4!!! $ -50,000.!!! $ -250,000.!!! $ -50,000.!!! $ 650,000.!!!
5!!! $ -50,000.!!! $ -300,000.!!! $ -50,000.!!! $ 600,000.!!!
6!!! $ 400,000.!!! $ 100,000.!!!
$ 400,000.!!! $ 1,000,000.!!!
7!!! !!! !!! $ -900,000.!!! $ 100,000.!!!
______________________________________________________________________________
For a general contractor or subcontractor, the cash flow profile of expenses
and incomes for a construction project typically follows the work in progress
for which the contractor will be paid periodically. The markup by the
contractor above the estimated expenses is included in the total contract price
and the terms of most contracts generally call for monthly reimbursements of
work completed less retainage. At time period 0, which denotes the beginning
of the construction contract, a considerable sum may have been spent in
preparation. The contractor's expenses which occur more or less continuously
for the project duration are depicted by a piecewise continuous curve while the
receipts (such as progress payments from the owner) are represented by a step
function as shown in Fig. 7-1. The owner's payments for the work completed are
assumed to lag one period behind expenses except that a withholding proportion
or remainder is paid at the end of construction. This method of analysis is
applicable to realistic situations where a time period is represented by one
month and the number of time periods is extended to cover delayed receipts as a
result of retainage.
While the cash flow profiles of expenses and receipts are expected to vary
for different projects, the characteristics of the curves depicted in Fig. 7-1
are sufficiently general for most cases. Let E@-(t) represent the contractor's
expenses in period t, and P@-(t) represent owner's payments in period t, for
t=0,1,2,...,n for n=5 in this case. The net operating cash flow at the end of
period t for t G 0 is given by: The cumulative operating cash flow at the end of period t just before
receiving payment P@-(t) (for t G 1) is: The gross operating profit G for a n-period project is defined as net
operating cash flow at t=n and is given by: Since the net cash flow A@-(t) (for t=0,1,...,n) for a construction project
represents the amount of cash required or accrued after the owner's payment is
plowed back to the project at the end of period t, the internal rate of return
(IRR) of this cash flow is often cited in the traditional literature in
construction as a profit measure. To compute IRR, let the net present value
(NPV) of A@-(t) discounted at a discount rate i per period be zero, i.e., The resulting i (if it is unique) from the solution of Eq. (7.7.9) is the
IRR of the net cash flow A@-(t). Aside from the complications that may be
involved in the solution of Eq. (7.7.9), the resulting i = IRR has a meaning to
the contractor only if the firm finances the entire project from its own
equity. This is seldom if ever the case since most construction firms are
highly leveraged, i.e. they have relatively small equity in fixed assets such
as construction equipment, and depend almost entirely on borrowing in financing
individual construction projects. The use of the IRR of the net cash flows as
a measure of profit for the contractor is thus misleading. It does not
represent even the IRR of the bank when the contractor finances the project
through overdraft since the gross operating profit would not be given to the
bank.
Since overdraft is the most common form of financing for small or medium
size projects, we shall consider the financing costs and effects on profit of
-
the use of overdrafts. Let @-(t) be the cumulative cash flow before theF
-
owner's payment in period t including interest and @-(t) be the cumulativeN
net cash flow in period t including interest. At t = 0 when there is no
- -
accrued interest, @-(o) = F@-(o) and @-(o) = N@-(o). For t G 1, the interestF N
-
@-(t) in period t can be obtained by considering the contractor's expensesI
E@-(t) to be dispersed uniformly during the period.
The inclusion of enterest on contractor's expenses E@-(t) during period t
(for G 1) is based on the rationale that the S-shaped curve depicting the
contractor's expenses in Figure 7-1 is fairly typical of actual situations,
where the owner's payments are typically made at the end of well defined
periods. Hence, interest on expenses during period t is approximated by one
half of the amount as if the expenses were paid at the beginning of the period.
In fact, E@-(t) is the accumulation of all expenses in period t and is treated
-
as an expense at the end of the period. Thus, the interest per period @-(t)I
(for t> 1) is the combination of interest charge for N@-(t-1) in period t and
-
that for one half of E@-(t) in the same period t. If @-(t) is negative and iN
is the borrowing rate for the shortfall,
Hence, if the cumulative net cash flow @-(t) is negative, the interest onN
the overdraft for each period t is paid by the contractor at the end of each
period. If N@-(t) is positive, a surplus is indicated and the subsequent
interest would be paid to the contractor. Most often, N@-(t) is negative
during the early time periods of a project and becomes positive in the later
periods when the contractor has received payments exceeding expenses.
Including the interest accrued in period t, the cumulative cash flow at the
end of period t just before receiving payment P@-(t) (for t G 1) is:
Furthermore, the cumulative net cash flow after receiving payment P@-(t) at the
end of period t (for t G 1) is:
The gross operating profit at the end of a n-period project includingG
interest charges is:
where @-(n) is the cumulative net cash flow for t = n.N
Example 7-14: Contractor's gross profit from a project
The contractor's expenses and owner's payments for a multi-year construction
project are given in Columns 2 and 3 respectively of Table 7-12. Each time
period is represented by one year, and the annual interest rate i is for
borrowing 11%. The computation has been carried out in Table 7-0, and the
contractor's gross profit G is found to be N@-(5) = $8.025 million in the last
column of the table.
Period!!!Contractor's!!!Owner's!!!Net!!!Cumulative Cash!!!Cumulative
t!!!Expenses!!!Payments!!!Cash Flow!!!Before Payments!!!Net Cash
!!!E@-(t)!!!P@-(t)!!!A@-(t)!!!F@-(t)!!!N@-(t)
0!!!3.782!!!0!!!-3.782!!!-3.782!!!-3.782
1!!!7.458!!!6.473!!!-0.985!!!-11.240!!!-4.767
2!!!10.425!!!9.334!!!-1.091!!!-15.192!!!-5.858
3!!!14.736!!!13.348!!!-1.388!!!-20.594!!!-7.246
4!!!11.420!!!16.832!!!+5.412!!!-18.666!!!-1.834
5!!!5.679!!!15.538!!!+9.859!!!-7.513!!!+8.025
Total!!!53.500!!!61.525!!!+8.025
Example 7-15: : Effects of Construction Financing
The computation of the cumulative cash flows including interest charges at i
- -
= 11% for Example 7-14 is shown in Table 7-0 with gross profit = @-(5) =G N
$1.384 Million. The results of computation are also shown in Figure 7-0.
Period!!!Construction!!!Owner's!!!Annual!!!Cumulative!!!Cumulative
(year)!!!Expenses!!!Payments!!!Interest!!!Net Cash!!!Net Cash
!!!!!!!!!!!!Flow!!!Flow
- - -
t!!!E@-(t)!!!P@-(t)!!! @-(t)!!! @-(t)!!! @-(t)I F N
0!!!3.782!!!0!!!0!!!-3.782!!!-3.782
1!!!7.458!!!6.473!!!-0.826!!!-12.066!!!-5.593
2!!!10.425!!!9.334!!!-1.188!!!-17.206!!!-7.872
3!!!14.736!!!13.348!!!-1.676!!!-24.284!!!-10.936
4!!!11.420!!!16.832!!!-1.831!!!-24.187!!!-7.354
5!!!5.679!!!15.538!!!-1.121!!!-14.154!!!+1.384
In times of economic uncertainty, the fluctuations in inflation rates and
market interest rates affect profits significantly. The total contract price
is usually a composite of expenses and payments in then-current dollars at
different payment periods. In this case, estimated expenses are also expressed
in then-current dollars.
During periods of high inflation, the contractor's profits are particularly
vulnerable to delays caused by uncontrollable events for which the owner will
not be responsible. Hence, the owner's payments will not be changed while the
contractor's expenses will increase with inflation.
Example 7-16: Effects of Inflation
Suppose that both expenses and receipts for the construction project in the
Example 7-14 are now expressed in then-current dollars (with annual inflation
rate of 4%) in Table 7-0. The market interest rate reflecting this inflation
is now 15%. In considering these expenses and receipts in then-current dollars
and using an interest rate of 15% including inflation, we can recompute the
cumulative net cash flow (with interest). Thus, the gross profit less
- -
financing costs becomes = @-(5) = $0.4 million. There will be a loss ratherG N
than a profit after deducting financing costs and adjusting for the effects of
inflation with this project.
!!!Period!!!Construction!!!Owner's!!!Annual!!!Cumulative!!!Cumulative
!!!(Year)!!!Expenses!!!Payments!!!Interest!!!Before!!!Net Cash
!!!!!!!!!!!!!!!Payments!!!Flow
- - -
!!!t!!!E@-(t)!!!P@-(t)!!! @-(t)!!! @-(t)!!! @-(t)I F N
!!!0!!!3.782!!!0!!!0!!!-3.782!!!-3.782
!!!1!!!7.756!!!6.732!!!-1.149!!!-12.687!!!-5.955
!!!2!!!11.276!!!10.096!!!-1.739!!!-18.970!!!-8.874
!!!3!!!16.576!!!15.015!!!-2.574!!!-28.024!!!-13.009
!!!4!!!13.360!!!19.691!!!-2.953!!!-29.322!!!-9.631
!!!5!!!6.909!!!18.904!!!-1.964!!!-18.504!!!+0.400
Example 7-17: Effects of Work Stoppage at Periods of Inflation
Suppose further that besides the inflation rate of 4%, the project in
Example 7-16 is suspended at the end of year 2 due to a labor strike and
resumed after one year. Also, assume that while the contractor will incur
higher interest expenses due to the work stoppage, the owner will not increase
the payments to the contractor. The cumulative net cash flows for the case and
of operation and financing expenses are recomputed and tabulated in Table 7-0.
The construction expenses and receipts in then-current dollars resulting from
the work stopping and the corresponding net cash flow of the project including
financing (with annual interest accumulated in the overdraft to the end of the
project) is shown in Fig. 7-3. It is noteworthy that, with or without the work
stoppage, the gross operating profit declines in value at the end of the
project as a result of inflation, but with the work stoppage it has eroded
-
further to a loss of $ 3.524 million as indicated by @-(6) = -3.524 in TableN
7-0.
!!!Period!!!Construction!!!Owner's!!!Annual!!!Cumulative!!!Cumulative
!!!(Year)!!!Expenses!!!Payments!!!Interest!!!Before!!!Net Cash
!!!!!!!!!!!!!!!Payments!!!Flow
- - -
!!!t!!!E@-(t)!!!P@-(t)!!! @-(t)!!! @-(t)!!! @-(t)I F N
!!!0!!!3.782!!!0!!!0!!!-3.782!!!-3.782
!!!1!!!7.756!!!6.732!!!-1.149!!!-12.687!!!-5.955
!!!2!!!11.276!!!10.096!!!-1.739!!!-18.970!!!-8.874
!!!3!!!0!!!0!!!-1.331!!!-10.205!!!-10.205
!!!4!!!17.239!!!15.015!!!-2.824!!!-30.268!!!-15.253
!!!5!!!13.894!!!19.691!!!-3.330!!!-32.477!!!-12.786
!!!6!!!7.185!!!18.904!!!-2.457!!!-22.428!!!-3.524
Because of the unique nature of constructed facilities, it is almost
imperative to have a separate price for each facility. The construction
contract price includes the direct project cost including field supervision
expenses plus the markup imposed by contractors for general overhead expenses
and profit. The factors influencing a facility price will vary by type of
facility and location as well. Within each of the major categories of
construction such as residential housing, commercial buildings, industrial
complexes and infrastructure, there are smaller segments which have very
different environments with regard to price setting. However, all pricing
arrangements have some common features in the form of the legal documents
binding the owner and the supplier(s) of the facility. Without addressing
special issues in various industry segments, the most common types of pricing
arrangements can be described broadly to illustrate the basic principles.
The basic structure of the bidding process consists of the formulation of
detailed plans and specifications of a facility based on the objectives and
requirements of the owner, and the invitation of qualified contractors to bid
for the right to execute the project. The definition of a qualified contractor
usually calls for a minimal evidence of previous experience and financial
stability. In the private sector, the owner has considerable latitude in
selecting the bidders, ranging from open competition to the restriction of
bidders to a few favored contractors. In the public sector, the rules are
carefully delineated to place all qualified contractors on an equal footing for
competition, and strictly enforced to prevent collusion among contractors and
unethical or illegal actions by public officials.
Detailed plans and specifications are usually prepared by an
architectural/engineering firm which oversees the bidding process on behalf of
the owner. The final bids are normally submitted on either a lump sum or unit
price basis, as stipulated by the owner. A lump sum bid represents the total
price for which a contractor offers to complete a facility according to the
detailed plans and specifications. Unit price bidding is used in projects for
which the quantity of materials or the amount of labor involved in some key
tasks is particularly uncertain. In such cases, the contractor is permitted to
submit a list of unit prices for those tasks, and the final price used to
determine the lowest bidder is based on the lump sum price computed by
multiplying the quoted unit price for each specified task by the corresponding
quantity in the owner's estimates for quantities. However, the total payment
to the winning contractor will be based on the actual quantities multiplied by
the respective quoted unit prices.
Instead of inviting competitive bidding, private owners often choose to
award construction contracts with one or more selected contractors. A major
reason for using negotiated contracts is the flexibility of this type of
pricing arrangement, particularly for projects of large size and great
complexity or for projects which substantially duplicate previous facilities
sponsored by the owner. An owner may value the expertise and integrity of a
particular contractor who has a good reputation or has worked successfully for
the owner in the past. If it becomes necessary to meet a deadline for
completion of the project, the construction of a project may proceed without
waiting for the completion of the detailed plans and specifications with a
contractor that the owner can trust. However, the owner's staff must be highly
knowledgeable and competent in evaluating contractor proposals and monitoring
subsequent performance.
Generally, negotiated contracts require the reimbursement of direct project
cost plus the contractor's fee as determined by one of the following methods:
In residential construction, developers often build houses and condominiums
in anticipation of the demand of home buyers. Because the basic needs of home
buyers are very similar and home designs can be standardized to some degree,
the probability of finding buyers of good housing units within a relatively
short time is quite high. Consequently, developers are willing to undertake
speculative building and lending institutions are also willing to finance such
construction. The developer essentially set the price for each housing unit as
the market will bear, and can adjust the prices of remaining units at any given
time according to the market trend.
Some owners use in-house labor forces to perform a substantial amount of
construction, particularly for addition, renovation and repair work. Then, the
total of the force-account charges including in-house overhead expenses will be
the pricing arrangement for the construction.
Provisions for the allocation of risk among parties to a contract can appear
in numerous areas in addition to the total construction price. Typically,
these provisions assign responsibility for covering the costs of possible or
unforeseen occurances. A partial list of responsibilities with concomitant
risk that can be assigned to different parties would include:
The language used for specifying the risk assignments in these areas must
conform to legal requirements and past interpretations which may vary in
different jurisdictions or over time. Without using standard legal language,
contract provisions may be unenforceable. Unfortunately, standard legal
language for this purpose may be difficult to understand. As a result, project
managers often have difficulty in interpreting their particular
responsibilities. Competent legal counsel is required to advise the different
parties to an agreement about their respective responsibilities.
Standard forms for contracts can be obtained from numerous sources, such as
the American Institute of Architects (AIA) or the Associated General
Contractors (AGC). These standard forms may include risk and responsibility
allocations which are unacceptable to one or more of the contracting parties.
In particular, standard forms may be biased to reduce the risk and
responsibility of the originating organization or group. Parties to a contract
should read and review all contract documents carefully.
The three examples appearing below illustrate contract language resulting in
different risk assignments between a contractor (CONTRACTOR) and an owner
(COMPANY). Each contract provision allocates different levels of
indemnification risk to the contractor.(These examples are taken directly from
A Construction Industry Cost Effectiveness Project Report, "Contractual
Arrangements," The Business Roundtable, New York, Appendix D, 1982. Permission
to quote this material from the Business Roundtable is gratefully
acknowledged.)
Example 8-1: A Contract Provision Example with High Contractor Risk
"Except where the sole negligence of COMPANY is involved or alleged,
CONTRACTOR shall indemnify and hold harmless COMPANY, its officers, agents and
employees, from and against any and all loss, damage, and liability and from
any and all claims for damages on account of or by reason of bodily injury,
including death, not limited to the employees of CONTRACTOR, COMPANY, and of
any subcontractor or CONTRACTOR, and from and against any and all damages to
property, including property of COMPANY and third parties, direct and/or
consequential, caused by or arising out of, in while or in part, or claimed to
have been caused by or to have arisen out of, in whole or in part, an act of
omission of CONTRACTOR or its agents, employees, vendors, or subcontractors, of
their employees or agents in connection with the performance of the Contract
Documents, whether or not insured against; and CONTRACTOR shall, at its own
cost and expense, defend any claim, suit, action or proceeding, whether
groundless or not, which may be commenced against COMPANY by reason thereof or
in connection therewith, and CONTRACTOR shall pay any and all judgments which
may be recovered in such action, claim, proceeding or suit, and defray any and
all expenses, including costs and attorney's fees which may be incurred by
reason of such actions, claims, proceedings, or suits."
Comment: This is a very burdensome provision for the contractor. It makes
the contractor responsible for practically every conceivable occurrence and
type of damage, except when a claim for loss or damages is due to the sole
negligence of the owner. As a practical matter, sole negligence on a
construction project is very difficult to ascertain because the work is so
inter-twined. Since there is no dollar limitation to the contractor's
exposure, sufficient liability coverage to cover worst scenario risks will be
difficult to obtain. The best the contractor can do is to obtain as complete
and broad excess liability insurance coverage as can be purchased. This
insurance is costly, so the contractor should insure the contract price is
sufficiently high to cover the expense.
Example 8-2: An Example Contract Provision with Medium Risk Allocation to
Contractor
"CONTRACTOR shall protect, defend, hold harmless, and indemnify COMPANY from
and against any loss, damage, claim, action, liability, or demand whatsoever
(including, with limitation, costs, expenses, and attorney's fees, whether for
appeals or otherwise, in connection therewith), arising out of any personal
injury (including, without limitation, injury to any employee of COMPANY,
CONTRACTOR or any subcontractor), arising out of any personal injury
(including, without limitation, injury to any employee of COMPANY, CONTRACTOR,
or any subcontractor), including death resulting therefrom or out of any damage
to or loss or destruction of property, real and or personal (including property
of COMPANY, CONTRACTOR, and any subcontractor, and including tools and
equipment whether owned, rented, or used by CONTRACTOR, any subcontractor, or
any workman) in any manner based upon, occasioned by , or attributable or
related to the performance, whether by the CONTRACTOR or any subcontractor, of
the Work or any part thereof, and CONTRACTOR shall at its own expense defend
any and all actions based thereon, except where said personal injury or
property damage is caused by the negligence of COMPANY or COMPANY'S employees.
Any loss, damage, cost expense or attorney's fees incurred by COMPANY in
connection with the foregoing may, in addition to other remedies, be deducted
from CONTRACTOR'S compensation, then due or thereafter to become due. COMPANY
shall effect for the benefit of CONTRACTOR a waiver of subrogation on the
existing facilities, including consequential damages such as, but not by way of
limitation, loss of profit and loss of product or plant downtime but excluding
any deductibles which shall exist as at the date of this CONTRACT; provided,
however, that said waiver of subrogation shall be expanded to include all said
deductible amounts on the acceptance of the Work by COMPANY."
Comment: This clause provides the contractor considerable relief. He still
has unlimited exposure for injury to all persons and third party property but
only to the extent caused by the contractor's negligence. The "sole"
negligence issue does not arise. Furthermore, the contractor's liability for
damages to the owner's property--a major concern for contractors working in
petrochemical complexes, at times worth billions--is limited to the owner's
insurance deductible, and the owner's insurance carriers have no right of
recourse against the contractor. The contractor's limited exposure regarding
the owner's facilities ends on completion of the work.
Example 8-3: An Example Contract Provision with Low Risk Allocation to
Contractor
"CONTRACTOR hereby agrees to indemnify and hold COMPANY and/or any parent,
subsidiary, or affiliate, or COMPANY and/or officers, agents, or employees of
any of them, harmless from and against any loss or liability arising directly
or indirectly out of any claim or cause of action for loss or damage to
property including, but not limited to, CONTRACTOR'S property and COMPANY'S
property and for injuries to or death of persons including but not limited to
CONTRACTOR'S employees, caused by or resulting from the performance of the work
by CONTRACTOR, its employees, agents, and subcontractors and shall, at the
option of COMPANY, defend COMPANY at CONTRACTOR'S sole expense in any
litigation involving the same regardless of whether such work is performed by
CONTRACTOR, its employees, or by its subcontractors, their employees, or all or
either of them. In all instances, CONTRACTOR'S indemnity to COMPANY shall be
limited to the proceeds of CONTRACTOR'S umbrella liability insurance
coverage."
Comment: With respect to indemnifying the owner, the contractor in this
provision has minimal out-of-pocket risk. Exposure is limited to whatever can
be collected from the contractor's insurance company.
All owners want quality construction with reasonable costs, but not all are
willing to share risks and/or provide incentives to enhance the quality of
construction. In recent years, more owners recognize that they do not get the
best quality of construction by squeezing the last dollar of profit from the
contractor, and they accept the concept of risk sharing/risk assignment in
principle in letting construction contracts. However, the implementation of
such a concept in the past decade has received mixed results.
Many public owners have been the victims of their own schemes, not only
because of the usual requirement in letting contracts of public works through
competitive bidding to avoid favoritism, but at times because of the sheer
weight of entrenched bureaucracy. Some contractors steer away from public
works altogether; others submit bids at higher prices to compensate for the
restrictive provisions of contract terms. As a result, some public authorities
find that either there are few responsible contractors responding to their
invitations to submit bids or the bid prices far exceed their engineers'
estimates. Those public owners who have adopted the federal government's risk
sharing/risk assignment contract concepts have found that while initial bid
prices may have decreased somewhat, claims and disputes on contracts are more
frequent than before, and notably more so than in privately funded
construction. Some of these claims and disputes can no doubt be avoided by
improving the contract provisions.(See C.D. Sutliff and J.G. Zack, Jr.
"Contract Provisions that Ensure Complete Cost Disclosures", Cost Engineering,
Vol. 29, No. 10, October 1987, pp. 10-14.)
Since most claims and disputes arise most frequently from lump sum contracts
for both public and private owners, the following factors associated with lump
sum contracts are particularly noteworthy:
An unbalanced bid refers to raising the unit prices on items to be completed
in the early stage of the project and lowering the unit prices on items to be
completed in the later stages. The purpose of this practice on the part of the
contractor is to ease its burden of construction financing. It is better for
owners to offer explicit incentives to aid construction financing in exchange
for lower bid prices than to allow the use of hidden unbalanced bids.
Unbalanced bids may also occur if a contractor feels some item of work was
underestimated in amount, so that a high unit price on that item would increase
profits. Since lump sum contracts are awarded on the basis of low bids, it is
difficult to challenge the low bidders on the validity of their unit prices
except for flagrant violations. Consequently remedies should be sought by
requesting the contractor to submit pertinent records of financial transactions
to substantiate the expenditures associated with its monthly billings for
payments of work completed during the period.
One of the most contentious issues in contract provisions concerns the
payment for change orders. The owner and its engineer should have an
appreciation of the effects of changes for specific items of work and negotiate
with the contractor on the identifiable cost of such items. The owner should
require the contractor to submit the price quotation within a certain period of
time after the issuance of a change order and to assess whether the change
order may cause delay damages. If the contract does not contain specific
provisions on cost disclosures for evaluating change order costs, it will be
difficult to negotiate payments for change orders and claim settlements later.
In some projects, the contract provisions may allow the contractor to
provide alternative design and/or construction technology. The owner may
impose different mechanisms for pricing these changes. For example, a
contractor may suggest a design or construction method change that fulfills the
performance requirements. Savings due to such changes may accrue to the
contractor or the owner, or may be divided in some fashion between the two.
The contract provisions must reflect the owners risk-reward objectives in
calling for alternate design and/or construction technology. While innovations
are often sought to save money and time, unsuccessful innovations may require
additional money and time to correct earlier misjudgment. At worse, a failure
could have serious consequences.
In spite of admonitions and good intentions for better planning before
initiating a construction project, most owners want a facility to be in
operation as soon as possible once a decision is made to proceed with its
construction. Many construction contracts contain provisions of penalties for
late completion beyond a specified deadline; however, unless such provisions
are accompanied by similar incentives for early completion, they may be ruled
unenforceable in court. Early completion may result in significant savings,
particularly in rehabilitation projects in which the facility users are
inconvenienced by the loss of the facility and the disruption due to
construction operations.
Example 8-4: Arkansas Rice Growers Cooperative Association v. Alchemy
Industries
A 1986 court case can illustrate the assumption of risk on the part of
contractors and design professionals.(Arkansas Rice Growers v. Alchemy
Industries, Inc., United States Court of Appeals, Eighth Circuit, 1986. The
court decision appears in 797 Federal Reporter, 2d Series, pp. 565-574.) The
Arkansas Rice Growers Cooperative contracted with Alchemy Industries, Inc. to
provide engineering and construction services for a new facility intended to
generate steam by burning rice hulls. Under the terms of the contract, Alchemy
Industries guaranteed that the completed plant would be capable of "reducing a
minimum of seven and one-half tons of rice hulls per hour to an ash and
producing a minimum of 48 million BTU's per hour of steam at 200 pounds
pressure." Unfortunately, the finished plant did not meet this performance
standard, and the Arkansas Rice Growers Cooperative Association sued Alchemy
Industries and its subcontractors for breach of warranty. Damages of almost $
1.5 million were awarded to the Association.
While construction contracts serve as a means of pricing construction, they
also structure the allocation of risk to the various parties involved. The
owner has the sole power to decide what type of contract should be used for a
specific facility to be constructed and to set forth the terms in a contractual
agreement. It is important to understand the risks of the contractors
associated with different types of construction contracts.
In a lump sum contract, the owner has essentially assigned all the risk to
the contractor, who in turn can be expected to ask for a higher markup in order
to take care of unforeseen contingencies. Beside the fixed lump sum price,
other commitments are often made by the contractor in the form of submittals
such as a specific schedule, the management reporting system or a quality
control program. If the actual cost of the project is underestimated, the
underestimated cost will reduce the contractor's profit by that amount. An
overestimate has an opposite effect, but may reduce the chance of being a low
bidder for the project.
In a unit price contract, the risk of inaccurate estimation of uncertain
quantities for some key tasks has been removed from the contractor. However,
some contractors may submit an "unbalanced bid" when it discovers large
discrepancies between its estimates and the owner's estimates of these
quantities. Depending on the confidence of the contractor on its own estimates
and its propensity on risk, a contractor can slightly raise the unit prices on
the underestimated tasks while lowering the unit prices on other tasks. If the
contractor is correct in its assessment, it can increase its profit
substantially since the payment is made on the actual quantities of tasks; and
if the reverse is true, it can lose on this basis. Furthermore, the owner may
disqualify a contractor if the bid appears to be heavily unbalanced. To the
extent that an underestimate or overestimate is caused by changes in the
quantities of work, neither error will effect the contractor's profit beyond
the markup in the unit prices.
For certain types of construction involving new technology or extremely
pressing needs, the owner is sometimes forced to assume all risks of cost
overruns. The contractor will receive the actual direct job cost plus a fixed
percentage, and have little incentive to reduce job cost. Furthermore, if
there are pressing needs to complete the project, overtime payments to workers
are common and will further increase the job cost. Unless there are compelling
reasons, such as the urgency in the construction of military installations, the
owner should not use this type of contract.
Under this type of contract, the contractor will receive the actual direct
job cost plus a fixed fee, and will have some incentive to complete the job
quickly since its fee is fixed regardless of the duration of the project.
However, the owner still assumes the risks of direct job cost overrun while the
contractor may risk the erosion of its profits if the project is dragged on
beyond the expected time.
For this type of contract, the contractor agrees to a penalty if the actual
cost exceeds the estimated job cost, or a reward if the actual cost is below
the estimated job cost. In return for taking the risk on its own estimate, the
contractor is allowed a variable percentage of the direct job-cost for its fee.
Furthermore, the project duration is usually specified and the contractor must
abide by the deadline for completion. This type of contract allocates
considerable risk for cost overruns to the owner, but also provides incentives
to contractors to reduce costs as much as possible.
This is another form of contract which specifies a penalty or reward to a
contractor, depending on whether the actual cost is greater than or less than
the contractor's estimated direct job cost. Usually, the percentages of
savings or overrun to be shared by the owner and the contractor are
predetermined and the project duration is specified in the contract. Bonuses
or penalties may be stipulated for different project completion dates.
When the project scope is well defined, an owner may choose to ask the
contractor to take all the risks, both in terms of actual project cost and
project time. Any work change orders from the owner must be extremely minor if
at all, since performance specifications are provided to the owner at the
outset of construction. The owner and the contractor agree to a project cost
guaranteed by the contractor as maximum. There may be or may not be additional
provisions to share any savings if any in the contract. This type of contract
is particularly suitable for turnkey operation.
Regardless of the type of construction contract selected by the owner, the
contractor recognizes that the actual construction cost will never be identical
to its own estimate because of imperfect information. Furthermore, it is
common for the owner to place work change orders to modify the original scope
of work for which the contractor will receive additional payments as stipulated
in the contract. The contractor will use different markups commensurate with
its market circumstances and with the risks involved in different types of
contracts, leading to different contract prices at the time of bidding or
negotiation. The type of contract agreed upon may also provide the contractor
with greater incentives to try to reduce costs as much as possible. The
contractor's gross profit at the completion of a project is affected by the
type of contract, the accuracy of its original estimate, and the nature of work
change orders. The owner's actual payment for the project is also affected by
the contract and the nature of work change orders.
In order to illustrate the relative costs of several types of construction
contracts, the pricing mechanisms for such construction contracts are
formulated on the same direct job cost plus corresponding markups reflecting
the risks. Let us adopt the following notation:
At the time of a contract award, the contract price is given by:
!!! Type of Contract!!! Markup!!! Contract Price
!!!1. Lump sum!!!M = (R +R@-[1])E!!!B = (1 + R + R@-[1])E
!!!2. Unit price!!!M = (R + R@-[2])E!!!B = (1 + R + R@-[2])E
!!!3. Cost plus fixed %!!!M = RA = RE!!!B = (1 + R)E
!!!4. Cost plus fixed fee!!!M = RE!!!B = (1 + R)E
!!!5. Cost plus variable %!!!M = R (2E - A) = RE!!!B = (1 + R)E
!!!6. Target estimate!!!M = RE + N (E-A) = RE!!!B = (1 + R)E
!!!7. Guaranteed max cost!!!M = (R + R@-[3])E!!!B = (1 + R + R@-[3])E
Payments of change orders are also different in contract provisions for
different types of contracts. Suppose that payments for change orders agreed
upon for various types of contracts are as shown in column 2 of Table 8-0. The
owner's actual payments based on these provisions as well as the incentive
provisions for various types of contracts are given in column 3 of Table 8-0.
The corresponding contractor's profits under various contractual arrangements
are shown in Table 8-0.
______________________________________________________________________________
!!! Type of Contract!!!Change Order!!! Owner's Payment
!!!!!! Payment
!!!1. Lump sum!!! C (1 + R + R@-(1))!!!P = B + C(1 + R + R@-(1))
!!!2. Unit price!!! C(1 + R + R@-(2))!!!P = (1 + R + R@-[2])A + C
!!!3. Cost plus fixed %!!! C(1 + R)!!!P = (1 + R) (A + C)
!!!4. Cost plus fixed fee!!! C!!!P = RE + A + C
!!!5. Cost plus variable %!!! C(1 + R)!!!P = R (2E - A + C) + A + C
!!!6. Target estimate!!! C!!!P = RE + N (E - A) + A + C
!!!7. Guaranteed max cost!!! 0!!!P = B
______________________________________________________________________________
!!! Type of Contract!!!Profit from!!! Contractor's
!!!!!!Change Order!!! Gross Profit
!!!1. Lump sum!!! C (R + R@-[1])!!!F = E - A + (R + R@-[1]) (E + C)
!!!2. Unit price!!! C (R + R@-[2]!!!F = (R + R@-[2]) (A + C)
!!!3. Cost plus fixed %!!! CR!!!F = R (A + C)
!!!4. Cost plus fixed fee!!! 0!!!F = RE
!!!5. Cost plus variable %!!! CR!!!F = R (2E - A + C)
!!!6. Target estimate!!! 0!!!F = RE + N (E - A)
!!!7. Guaranteed max cost!!! - C!!!F = (1 + R + R@-[3])E - A - C
It is important to note that the equations in Tables 8-0 through 8-0 are
illustrative, subject to the simplified conditions of payments assumed under
the various types of contracts. When the negotiated conditions of payment are
different, the equations must also be modified.
Example 8-5: Contractor's Gross Profits under Different Contract
Arrangements
Consider a construction project for which the contractor's original estimate
is $6,000,000. For various types of contracts, R = 10%, R@-[1] = 2%, R@-[2] =
1%, R@-[3] = 5% and N = 0.5. The contractor is not compensated for change
orders under the guaranteed maximum cost contract if the total cost for the
change orders is within 6% ($360,000) of the original estimate. Determine the
contractor's gross profit for each of the seven types of construction contracts
for each of the following conditions.
In this example, the percentage markup for the cost plus fixed percentage
contract is 10% which is used as the bench mark for comparison. The percentage
markup for the lump sum contract is 12% while that for the unit price contract
is 11%, reflecting the degrees of higher risk. The fixed fee for the cost plus
fixed fee is based on 10% of the estimated cost, which is comparable to the
cost plus fixed percentage contract if there is no overestimate or
underestimate in cost. The basic percentage markup is 10% for both the cost
plus variable percentage contract and the target estimator contract, but they
are subject to incentive bonuses and penalties that are built in the formulas
for owners' payments. The percentage markup for the guaranteed maximum cost
contract is 15% to account for the high risk undertaken by the contractor. The
results of computation for all seven types of contracts under different
conditions of underestimation U and change order C are shown in Table 8-0
Type of!!!U=0!!!U=0!!!U=4%E!!!U=4%E!!!U=-4%E!!!U=-4%E
Contract!!!C=0!!!C=6%E!!!C=0!!!C=6%E!!!C= 0!!!C= 6%E
1. lump sum!!!720!!!763!!!480!!!523!!! 960!!!1,003
2. unit price!!!660!!!700!!!686!!!726!!! 634!!!674
3. cost + fixed %!!!600!!!636!!!624!!!660!!! 576!!!612
4. cost + fixed fee!!!600!!!600!!!600!!!600!!! 600!!!600
5. cost + Var %!!!600!!!636!!!576!!!616!!! 624!!!660
6. target estimate!!!600!!!600!!!480!!!480!!! 720!!!720
7. guar. max. cost!!!900!!!540!!!660!!!300!!!1,140!!!780
Example 8-6: Owner's Payments under Different Contract Arrangements
Using the data in Example 7-1, determine the owner's actual payment for each
of the seven types of construction contracts for the same conditions of U and
C. The results of computation are shown in Table 8-0.
!!!Type of!!!U=0!!!U=0!!!U=4%E!!!U=4%E!!!U=-4%E!!!U=-4%E
!!!Contract!!!C=0!!!C=6%E!!!C=0!!!C=6%E!!!C= 0!!!C= 6%E
!!!1. lump sum!!!6,720!!!7,123!!!6,720!!!7,123!!!6,720!!!7,123
!!!2. unit price!!!6,660!!!7,060!!!6,926!!!7,326!!!6,394!!!6,794
!!!3. cost + fixed %!!!6,600!!!6,996!!!6,864!!!7,260!!!6,336!!!6,732
!!!4. cost + fixed fee!!!6,600!!!6,960!!!6,840!!!7,200!!!6,360!!!6,720
!!!5. cost + var %!!!6,600!!!6,996!!!6,816!!!7,212!!!6,384!!!6,780
!!!6. target estimate!!!6,600!!!6,960!!!6,720!!!7,080!!!6,480!!!6,840
!!!7. guar. max. cost!!!6,900!!!6,900!!!6,900!!!6,900!!!6,900!!!6,900
Competitive bidding on construction projects involves decision making under
uncertainty where one of the greatest sources of the uncertainty for each
bidder is due to the unpredictable nature of his competitors. Each bid
submitted for a particular job by a contractor will be determined by a large
number of factors, including an estimate of the direct job cost, the general
overhead, the confidence that the management has in this estimate, and the
immediate and long-range objectives of management. So many factors are
involved that it is impossible for a particular bidder to attempt to predict
exactly what the bids submitted by its competitors will be.
It is useful to think of a bid as being made up of two basic elements: (1)
the estimate of direct job cost, which includes direct labor costs, material
costs, equipment costs, and direct filed supervision; and (2) the markup or
return, which must be sufficient to cover a portion of general overhead costs
and allow a fair profit on the investment. A large return can be assured
simply by including a sufficiently high markup. However, the higher the
markup, the less chance there will be of getting the job. Consequently a
contractor who includes a very large markup on every bid could become bankrupt
from lack of business. Conversely, the strategy of bidding with very little
markup in order to obtain high volume is also likely to lead to bankruptcy.
Somewhere in between the two extreme approaches to bidding lies an "optimum
markup" which considers both the return and the likelihood of being low bidder
in such a way that, over the long run, the average return is maximized.
From all indications, most contractors confront uncertain bidding conditions
by exercising a high degree of subjective judgment, and each contractor may
give different weights to various factors. The decision on the bid price, if a
bid is indeed submitted, reflects the contractor's best judgment on how well
the proposed project fits into the overall strategy for the survival and growth
of the company, as well as the contractor's propensity to risk greater profit
versus the chance of not getting a contract.
Contractors generally tend to specialize in a submarket of construction and
concentrate their work in particular geographic locations. The level of demand
in a submarket at a particular time can influence the number of bidders and
their bid prices. When work is scarce in the submarket, the average number of
bidders for projects will be larger than at times of plenty. The net result of
scarcity is likely to be the increase in the number of bidders per project and
downward pressure on the bid price for each project in the submarket. At times
of severe scarcity, some contractors may cross the line between segments to
expand their activities, or move into new geographic locations to get a larger
share of the existing submarket. Either action will increase the risks
incurred by such contractors as they move into less familiar segments or
territories. The trend of market demand in construction and of the economy at
large may also influence the bidding decisions of a contractor in other ways.
If a contractor perceives drastic increases in labor wages and material prices
as a result of recent labor contract settlements, it may take into
consideration possible increases in unit prices for determining the direct
project cost. Furthermore, the perceptions of increase in inflation rates and
interest rates may also cause the contractor to use a higher markup to hedge
the uncertainty. Consequently, at times of economic expansion and/or higher
inflation rate, contractors are reluctant to commit themselves to long-term
fixed price contracts.
All other things being equal, the probability of winning a contract
diminishes as more bidders participate in the competition. Consequently, a
contractor tries to find out as much information as possible about the number
and identities of potential bidders on a specific project. Such information is
often available in the Dodge Bulletin<Dodge Bulletin (daily publication),
F. W. Dodge Corp., New York, NY.> or similar publications which provide data of
potential projects and names of contractors who have taken out plans and
specifications. For certain segments, potential competitors may be identified
through private contacts, and bidders often confront the same competitor's
project after project since they have similar capabilities and interests in
undertaking the same type of work, including size, complexity and geographical
location of the projects. A general contractor may also obtain information of
potential subcontractors from publications such as Credit Reports(Credit
Reports, Building Construction Division, and Bradstreet, Inc., New York, N.Y.)
published by Dun and Bradstreet, Inc. However, most contractors form an
extensive network with a group of subcontractors with whom they have had
previous business transactions. They usually rely on their own experience in
soliciting subcontract bids before finalizing a bid price for the project.
The bidding strategy of some contractors are influenced by a policy of
minimum percentage markup for general overhead and profit. However, the
percentage markup may also reflect additional factors stipulated by the owner
such as high retention and slow payments for completed work, or perceptions of
uncontrollable factors in the economy. The intensity of a contractor's efforts
in bidding a specific project is influenced by the contractor's desire to
obtain additional work. The winning of a particular project may be potentially
important to the overall mix of work in progress or the cash flow implications
for the contractor. The contractor's decision is also influenced by the
availability of key personnel in the contractor organization. The company
sometimes wants to reserve its resources for future projects, or commits itself
to the current opportunity for different reasons.
Contractor's Comparative Advantages
A final important consideration in forming bid prices on the part of
contractors are the possible special advantages enjoyed by a particular firm.
As a result of lower costs, a particular contractor may be able to impose a
higher profit markup yet still have a lower total bid than competitors. These
lower costs may result from superior technology, greater experience, better
management, better personnel or lower unit costs. A comparative cost advantage
is the most desirable of all circumstances in entering a bid competition.
An example of simulating the bidding process is illustrated by a
construction management game which has been programmed for use on a
computer.(See Au, T., Bostleman, R. L., and Parti, E.W., "Construction
Management Game -- Deterministic Model," ASCE Journal of Construction
Division, Vol. 95, 1969, pp.25-38. A current version for operation on an IBM
personal computer with the R-Base database package is available from the Dept.
of Civil Engr., Carnegie Mellon Univ., Pittsburgh, PA 15213, and was developed
by D.R. George in 1987.) Teams of players are cast in the roles of managers
in construction companies. Each company is a general contractor which
subcontracts and coordinates all portions of a building construction project
either to individual subcontractors or to its own operational divisions when
awarded a general contract.
Each of the construction companies begin with a different amount of assets
in the game. The simulated time of 3 years is divided into 12 three-month
periods. At the beginning of each time period, a list of jobs available for
bidding is produced by a mathematical equation depicting the market demand
which is stored in the computer. Each general contractor will then make the
necessary decisions to submit to the owner as represented by the computer. In
some periods, the general contractor may request additional information at a
cost. At the end of each time period the computer will process the input
decisions according to the programmed game model and output a statement to each
company indicating all contract awards, the cost of performing work and its
earnings. The company which shows the largest relative gain at the end of
three years will be declared the winner.
Market Demands - The number of jobs available for bidding during various
time periods 1 through 12 is given by a demand equation which can be modified
easily if the administrator should desire to change the demand pattern of the
game. The demand equation reflects the seasonal variation in construction
activities, and yet is not symmetrical or easily predictable. A typical
example is shown in Figure 8-0.
Geographical Region of Operation - The construction companies in this game
operate in a geographical region consisting of nine districts identified by
consecutive numbers 1 through 9 as shown in Figure 8-0. The unit prices of
labor and materials in a district are different from those in other districts,
but within each one, the labor and material rates are constant.
The subcontractors and the proposed jobsites are distributed throughout the
region with each subcontractor and each job site located in a particular
district. The distance units between districts are defined as follows: (1)
zero units when both the subcontractor and the jobsite are in the same
district; (2) one unit when the subcontractor's district is adjacent to the
district of the jobsite; and (3) two units when there is one district between
the subcontractor and the jobsite.
Subcontracting Firms. - Four types of subcontractors, representing the four
phases of the project (e.g., foundation excavation, foundation structure,
superstructure framing, and building closure), are required to complete any
job. When a general contractor bids on a general contract, he must select one
subcontractor of each type to perform the work. All behavior of the
sub-contractors is controlled by the computer.
Determination of Bid Prices
Subcontractor Selection. - For every job specified by the demand equation,
four different subcontractors of each type will be selected internally by the
computer from a pool of 40 subcontractors (10 of each type). Each job has its
own requirement of labor and material units of each of the four types of work.
The difference in bid prices submitted by the subcontractors for the same job
is affected by (1) unit prices of labor and material in the different district;
(2) transportation costs; (3) reliability factor; and (4) the desire for work.
The unit prices used in any subcontract bid are those of the district in which
the subcontractor is located. The relative transportation cost of a
subcontractor is based on the distance between the jobsite and the location of
the subcontractor. A reliability factor has been internally assigned to gauge
each subcontractor on his performance at the end of each period. In general,
other factors being equal, an unreliable subcontractor will be able to submit a
bid lower than that of a reliable one because he is more willing to take risks.
Finally, depending on his inclination to work, a variable factor representing a
subcontractor's desire to work will be assigned by the computer. An upper
limit is also placed on the work load that a subcontractor can take at any
given time. If such a limit is reached, this subcontractor will be eliminated
from the pool of subcontractors to be selected by the computer.
Information Services. - Two consulting services, the Construction Reports,
Incorporated, and the Subcontractor Rating Service, are provided for obtaining
additional information at a cost. These services are included to simulate
existing services for the construction industry. An information request can be
made only by the players during time period 1, period 4, period 7, and period
10. Therefore, a company must plan ahead and request any information it will
need for the next three time periods.
Construction Reports, Incorporated surveys the anticipated construction
activities for each time period in three areas each comprising three districts,
i.e., districts 1-2-3, districts 4-5-6, and districts 7-8-9. At each of the
time periods, period 1, period 4, period 7, and period 10, information may be
requested for any of these areas in any of the next three successive time
periods. Included in each report is a list of jobs anticipated to be let for
bidding in the area specified during that time period requested, the location
of each jobsite, and the approximate scope of each job in thousands of dollars.
The Subcontractor Rating Service rates any subcontractor on his overall
reliability. The ratings are A = excellent, B = good, C = fair, and D = poor.
At the beginning of the game, each general contractor is assumed to possess a
backlog of information for some of the subcontractors available in the game.
This backlog is simulated by providing each contractor with a partial set of
the subcontractor's ratings prior to the start of game play. The information
supplied to each contractor may or may not be the same. At the end of each
period, the rating of each subcontractor will be reevaluated internally by the
computer. Generally, a subcontractor's rating will improve if his work load
has increased during the period, reflecting the confidence that has been placed
upon this subcontractor by the general contractors. Since the Sub-contractor
Rating Services can be requested only in period 1, period 4, period 7, and
period 10, the outputs represent the ratings at the beginning of the game and
at the end of period 3, period 6, and period 9, respectively. In each
consultation, the general contractor may request any number of individual
ratings up to the entire list of 40 subcontractors.
Chance Factors. - In any competitive game, risk and uncertainty play a
major role in shaping the character of the environment. Generally speaking,
the more that is known of a given situation, the less risky is a strategy for
decision and the more certain is the outcome. Regardless of the precautions
taken, however, there is always the chance that an undesirable event may occur.
Many chance factors are therefore included in this game in order to produce a
resemblance of reality. Each bid made by a general contractor will be
influenced by the subcontractors allowed to bid on a job and by the magnitude
of their bids. Both of those factors are, to some extent, randomly controlled
by the computer. Although the information services are expected to be
generally helpful, their forecasts nevertheless are not perfect and must be
viewed with a certain amount of distrust.
Factors Influencing Bidding Behavior: In this game, the most important
internal constraint on bidding behavior is a company's cash-on-hand which is
comprised of liquid assets plus any outstanding loans. The cash-on-hand
reflects the capacity of the general contractor to do work, since the
cash-on-hand may be converted or transformed into other resources such as new
equipment and personnel are both necessary to expand the company's operational
base.
At the end of each time period when the bids are submitted, each general
contractor's proposed work load is compared to his maximum allowable work load.
The proposed work load is defined as the sum of the company's pending work from
previously awarded construction contracts and the bids submitted at the current
time period; the maximum allowable work load is defined as that work load which
is equal to 40 times the cash-on-hand. If the proposed work load exceeds the
maximum allowable work load, the general contractor will not be awarded any new
contracts in spite of the fact that he may be the low bidder. In addition,
bidding costs will be assessed for all attempted bids.
Should a general contractor wish to expand his operating base immediately,
the only alternative within the framework of this game is to seek a loan. The
contractor's capacity to do work will be increased by an amount which is 40
times the amount of the loan. However, the total amount of outstanding loans
cannot exceed twice the company's liquid assets at a particular time period;
otherwise the request for loan will be denied. All loans are one-year notes at
6% interest per year. When a loan is approved, the company's account will be
credited with the amount of the loan, and charged 1.5% interest in each of the
four succeeding time periods. At the end of the four time periods, repayment
of the loan is due and thus the amount is deducted from the company's account.
Contract Awards, Costs and Payments: Upon the submission of bids for the
available jobs at the end of each time period, the contracts will be awarded.
The cost of performing each job will be determined for the successful bidder,
and a statement of earnings for each general contractor will be prepared. All
general contractors will be notified of the successful bidder on each job and
the amount of the contract; in addition each successful bidder will be notified
of the actual cost of his work.
In general the contract for each job will be awarded to the low bidder.
However, this rule will be nullified should all bids exceed the maximum
allowable bid for the particular job which is prestored in the computer, or
should the low bidder exceed the maximum allowable work load. In the first
case all bids will be rejected and in the second case the individual bidder
will be rejected.
The actual cost charged to the general contractor for performing work is
computed by adjusting the base cost for the general contractor which is the sum
of the subcontractors bids. This base cost is then modified according to the
reliability of the subcontractors. Generally speaking, the probability of
making a profit is directly related to the reliability of subcontractors
selected.
Although the relation between the size of a job and its duration is not
well-defined, it is assumed that the number of time periods needed to complete
a job is related to the size of the job, and that the rate of progress of work
is constant for these time periods. The general contractor will be reimbursed
at the end of each time period for work done during that period. For example,
if a job takes three time periods to complete, the contractor will be paid
one-third of the total cost and realize one-third of his profit or loss in each
of the next three time periods.
The performance of a company at the end of each time period is indicated by
a statement of earnings output by the computer. The items in the statement
refer to the transactions in the time period under consideration. The last
item indicated the percentage of gain or loss up to the end of the period,
which is the ratio of gain or loss to the amount of assets at the beginning of
the game. The which has the highest percentage of gain at the end of period 12
is the winner of the game.
Example 8-7: A company's performance in the bidding game.
The bidding game described in this section has been programmed on a personal
computer. Upon the submission of the required inputs, the corresponding
outputs will be generated automatically. As an example, the measure of
performance generated at period 4 for a team of players representing a
construction company is shown in Table 8-0.
Negotiation is another important mechanism for arranging construction
contracts. Project managers often find themselves as participants in
negotiations, either as principal negotiators or as expert advisors. These
negotiations can be complex and often present important opportunities and risks
for the various parties involved. For example, negotiation on work contracts
can involve issues such as completion date, arbitration procedures, special
work item compensation, contingency allowances as well as the overall price.
As a general rule, exogenous factors such as the history of a contractor and
the general economic climate in the construction industry will determine the
results of negotiations. However, the skill of a negotiator can affect the
possibility of reaching an agreement, the profitability of the project, the
scope of any eventual disputes, and the possibility for additional work among
the participants. Thus, negotiations are an important task for many project
managers. Even after a contract is awarded on the basis of competitive
bidding, there are many occasions in which subsequent negotiations are required
as conditions change over time.
In conducting negotiations between two parties, each side will have a series
of objectives and constraints. The overall objective of each party is to
obtain the most favorable, acceptable agreement. A two party, one issue
negotiation illustrates this fundamental point. Suppose that a developer is
willing to pay up to $ 500,000 for a particular plot of land, whereas the owner
would be willing to sell the land for $ 450,000 or more. These maximum and
minimum sales prices represent constraints on any eventual agreement. In this
example, any purchase price between $ 450,000 and $ 500,000 is acceptable to
both of the involved parties. This range represents a feasible agreement
space. Successful negotiations would conclude in a sales price within this
range. Which party receives the $ 50,000 in the middle range between $ 450,000
and $ 500,000 would typically depend upon the negotiating skills and special
knowledge of the parties involved. For example, if the developer was a better
negotiator, then the sales price would tend to be close to the minimum $
450,000 level.
With different constraints, it might be impossible to reach an agreement.
For example, if the owner was only willing to sell at a price of $ 550,000
while the developer remains willing to pay only $ 500,000, then there would be
no possibility for an agreement between the two parties. Of course, the two
parties typically do not know at the beginning of negotiations if agreements
will be possible. But it is quite important for each party to the negotiation
to have a sense of their own reservation price, such as the owner's minimum
selling price or the buyer's maximum purchase price in the above example. This
reservation price is equal to the value of the best alternative to a negotiated
agreement.
Poor negotiating strategies adopted by one or the other party may also
preclude an agreement even with the existence of a feasible agreement range.
For example, one party may be so demanding that the other party simply breaks
off negotiations. In effect, negotiations are not a well behaved solution
methodology for the resolution of disputes.
The possibility of negotiating failures in the land sale example highlights
the importance of negotiating style and strategy with respect to revealing
information. Style includes the extent to which negotiators are willing to
seem reasonable, the type of arguments chosen, the forcefulness of language
used, etc. Clearly, different negotiating styles can be more or less
effective. Cultural factors are also extremely important. American and
Japanese negotiating styles differ considerably, for example. Revealing
information is also a negotiating decision. In the land sale case, some
negotiators would readily reveal their reserve or constraint prices, whereas
others would conceal as much information as possible (i.e. "play their cards
close to the vest") or provide misleading information.
In light of these tactical problems, it is often beneficial to all parties
to adopt objective standards in determining appropriate contract provisions.
These standards would prescribe a particular agreement or a method to arrive at
appropriate values in a negotiation. Objective standards can be derived from
numerous sources, including market values, precedent, professional standards,
what a court would decide, etc. By using objective criteria of this sort,
personalities and disruptive negotiating tactics do not become impediments to
reaching mutually beneficial agreements.
With additional issues, negotiations become more complex both in procedure
and in result. With respect to procedure, the sequence in which issues are
defined or considered can be very important. For example, negotiations may
proceed on an issue-by-issue basis, and the outcome may depend upon the exact
sequence of issues considered. Alternatively, the parties may proceed by
proposing complete agreement packages and then proceed to compare packages.
With respect to outcomes, the possibility of the parties having different
valuations or weights on particular issues arises. In this circumstance, it is
possible to trade-off the outcomes on different issues to the benefit of both
parties. By yielding on an issue of low value to himself but high value to the
other party, concessions on other issues may be obtained.
The notion of Pareto optimal agreements can be introduced to identify
negotiated agreements in which no change in the agreement can simultaneously
make both parties better off. Figure 8-0 illustrates Pareto optimal agreements
which can be helpful in assessing the result of multiple issue negotiations.
In this figure, the axes represent the satisfaction or desirability of
agreements to the parties, denoted I and II. This representation assumes that
one can place a dollar or utility value on various agreements reached in a
multiple-issue negotiation between two parties. Points in the graph represent
particular agreements on the different issues under consideration. A
particular point may be obtained by more than one contract agreement. The
curved line encloses the set of all feasible agreements; any point in this area
is an acceptable agreement. Each party has a minimum acceptable satisfaction
level in this graph. Points on the interior of this feasible area represent
inferior agreements since some other agreement is possible that benefits both
parties. For example, point B represents a more desirable agreement than point
A. In the previous example, point B might represent a purchase price of $
490,000 and an immediate purchase, whereas point A might represent a $ 475,000
sale price and a six month delay. The feasible points that are not inferior
constitute the set of Pareto optimal or efficient agreements; these points lie
on the north-east quadrant of the feasible region as marked on the figure.
The definition of Pareto optimal agreements allows one to assess at least
one aspect of negotiated outcomes. If two parties arrive at an inferior
agreement (such as point A in Figure 8-0), then the agreement could be improved
to the benefit of both parties. In contrast, different Pareto optimal
agreements (such as points B and C in Figure 8-0) can represent widely
different results to the individual parties but do not have the possibility for
joint improvement.
Of course, knowledge of the concept of Pareto optimal agreements does not
automatically give any guidance on what might constitute the best agreements.
Much of the skill in contract negotiation comes from the ability to invent new
options that represent mutual gains. For example, devising contract incentives
for speedier completion of projects may result in benefits to both contractors
and the owner.
Example 8-8: Effects of different value perceptions.
Suppose that the closing date for sale of the land in the previous case must
also be decided in negotiation. The current owner would like to delay the sale
for six months, which would represent rental savings of $ 10,000. However, the
developer estimates that the cost of a six month delay would be $ 20,000.
After negotiation, suppose that a purchase price of $ 475,000 and a six month
purchase delay are agreed upon. This agreement is acceptable but not optimal
for both parties. In particular, both sides would be better off if the
purchase price was increased by $ 15,000 and immediate closing instituted. The
current owner would receive an additional payment of $ 15,000, incur a cost of
$ 10,000, and have a net gain of $ 5,000. Similarly, the developer would pay $
15,000 more for the land but save $ 20,000 in delay costs. While this superior
result may seem obvious and easily achievable, recognizing such opportunities
during a negotiation becomes increasingly difficult as the number and
complexity of issues increases.
This construction negotiation game simulates a contract negotiation between
a utility, "CMG Gas" and a design/construct firm, "Pipeline Constructors,
Inc."[This game is further described in W. Dudziak and C. Hendrickson, "A
Negotiation Simulation Game," ASCE Journal of Management in Engineering, Vol.
4, No. 2, 1988.] The negotiation involves only two parties but multiple issues.
Participants in the game are assigned to represent one party or the other and
to negotiate with a designated partner. In a class setting, numerous
negotiating partners are created. The following overview from the CMG Gas
participants' instructions describes the setting for the game:
To focus the negotiations, the issues to be decided in the contract are
already defined:
As a further aid, each participant is provided with additional information
and a scoring system to indicate the relative desirability of different
contract agreements. Additional information includes items such as estimated
construction cost and expected duration as well as company policies such as
desired reporting formats or work arrangements. This information may be
revealed or withheld from the other party depending upon an individual's
negotiating strategy. The numerical scoring system includes point totals for
different agreements on specific issues, including interactions among the
various issues. For example, the amount of points received by Pipeline
Constructors, Inc. for a bonus for early completion increases as the
completion date become later. An earlier completion becomes more likely with a
later completion date, and hence the probability of receiving a bonus
increases, so the resulting point total likewise increases.
The two firms have differing perceptions of the desirability of different
agreements. In some cases, their views will be directly conflicting. For
example, increases in a flat fee imply greater profits for Pipeline
Constructors, Inc. and greater costs for CMG Gas. In some cases, one party may
feel strongly about a particular issue, whereas the other is not particularly
concerned. For example, CMG Gas may want a clerk on site, while Pipeline
Constructors, Inc. may not care. As described in the previous section, these
differences in the evaluation of an issue provide opportunities for
negotiators. By conceding an unimportant issue to the other party, a
negotiator may trade for progress on an issue that is more important to his or
her firm. Examples of instructions to the negotiators appear below.
After examining the project site, your company's estimators are convinced
that the project can be completed in thirty-six weeks. In bargaining for the
duration, keep two things in mind; the longer past thirty-six weeks the
contract duration is, the more money that can be made off the "bonuses for
being early" and the chances of being late are reduced. That reduces the risk
of paying a "penalty for lateness".
Throughout the project the gas company will want progress reports. These
reports take time to compile and therefore the fewer you need to submit, the
better. In addition, State law dictates that the Required Standard Report be
used unless the contractor and the owner agree otherwise. These standard
reports are even more time consuming to produce than more traditional reports.
The State Legislature is considering a law that requires accurate drawings
and markers of all pipelines by all utilities. You would prefer not to conform
to this uncertain set of requirements, but this is negotiable.
What type of contract and the amount your company will be paid are two of
the most important issues in negotiations. In the Flat Fee contract, your
company will receive an agreed amount from CMG Gas. Therefore, when there are
any delay or cost overruns, it will be the full responsibility of your company.
with this type of contract, your company assumes all the risk and will in turn
want a higher price. Your estimators believe a cost and contingency amount of
4,500,000 dollars. You would like a higher fee, of course.
With the Cost Plus Contract, the risk is shared by the gas company and your
company. With this type of contract, your company will bill CMG Gas for all
of its costs, plus a specified percentage of those costs. In this case, cost
overruns will be paid by the gas company. Not only does the percentage above
cost have to be decided upon but also whether or not your company will allow a
Field Clerk from the gas company to be at the job site to monitor reported
costs. Whether or not he is around is of no concern to your company since its
policy is not to inflate costs. this point can be used as a bargaining weapon.
Finally, your company is worried whether the gas company will obtain the
land rights to lay the pipe. Therefore, you should demand a penalty for the
potential delay of the project starting date.
Instructions to the CMG Gas Company Representative
In order to satisfy the auto manufacturer, the pipeline must be completed in
forty weeks. An earlier completion date will not result in receiving revenue
any earlier. Thus, the only reason to bargain for shorter duration is to feel
safer about having the project done on time. If the project does exceed the
forty week maximum, a penalty will have to be paid to the auto manufacturer.
Consequently, if the project exceeds the agreed upon duration, the contractor
should pay you a penalty. The penalty for late completion might be related to
the project duration. For example, if the duration is agreed to be thirty-six
weeks, then the penalty for being late need not be so severe. Also, it is
normal that the contractor get a bonus for early completion. Of course,
completion before forty weeks doesn't yield any benefit other than your own
peace of mind. Try to keep the early bonus as low as possible.
Throughout the project you will want progress reports. The more often these
reports are received, the better to monitor the progress. State law dictates
that the Required Standard Report be used unless the contractor and the owner
agree otherwise. These reports are very detailed and time consuming to review.
You would prefer to use the traditional CMG Gas reports.
The state legislature is considering a law that requires accurate drawings
and markers of all pipelines by all utilities. For this project it will cost
an additional 250,000 dollars to do this now, or 750,000 dollars to do this
when the law is passed.
One of the most important issues is the type of contract, and the amount of
be paid. The Flat Fee contract means that CMG Gas will pay the contractor a
set amount. Therefore, when there are delays and cost overruns, the contractor
assumes full responsibility for the individual costs. However, this evasion of
risk has to be paid for and results in a higher price. If Flat Fee is chosen,
only the contract price is to be determined. Your company's estimators have
determined that the project should cost about 5,000,000 dollars.
The Cost Plus Percent contract may be cheaper, but the risk is shared. With
this type of contract, the contractor will bill the gas company for all costs,
plus a specified percentage of those costs. In this case, cost overruns will
be paid by the gas company. If this type of contract is chosen, not only must
the profit percentage be chosen, but also whether or not a gas company
representative will be allowed on site all of the time acting as a Field Clerk,
to ensure that a proper amount of material and labor is billed. The usual
percentage agreed upon is about ten percent.
Contractors also have a concern whether or not they will receive a penalty
if the gas right-of-way is not obtained in time to start the project. In this
case, CMG Gas has already secured the right-of-ways. But, if the penalty is
too high, this is a dangerous precedent for future negotiations. However, you
might try to use this as a bargaining tool.
Example 8-9: An example of a negotiated contract
A typical contract resulting from a simulation of the negotiation between
CMG Gas and Pipeline Constructors, Inc. appears in Table 8-9. An agreement
with respect to each pre-defined issue is included, and the resulting contract
signed by both negotiators.
Example 8-10: Scoring systems for the negotiated contract games
To measure the performance of the negotiators in the previous example, a
scoring system is needed for the representative of Pipeline Constructors, Inc.
and another scoring system for the representative of CMG Gas. These scoring
systems for the companies associated with the issues described in Example 8-7
are designated as system A.
In order to make the negotiating game viable for classroom use, another set
of instructions for each company is described in this example, and the
associated scoring systems for the two companies are designated as System B. In
each game play, the instructor may choose a different combination of
instructions and negotiating teams, leading to four possible combinations of
scoring systems for Pipeline Constructors, Inc. and CMG Gas. (To undertake
this exercise, the instructor needs to divide students into negotiating teams,
with each individual assigned scoring system A or B. Negotiators will represent
Pipeline Constructors, Inc. or CMG Gas. Negotiating pairs should not be told
which scoring system their counterpart is assigned.)
In order to help you, your boss has left you with a scoring table for all
the issues and alternatives. Two different scoring systems are listed here;
you will be assigned to use one or the other. Instructions for scoring system
A are included in Section 8.9. The instructions for scoring system B are as
follows:
After examining the site, your estimator believes that the project will
require 38 weeks. You are happy to conform with any reporting or pipeline
marking system, since your computer based project control and design systems
can easily produce these submissions. You would prefer to delay the start of
the contract as long as possible, since your forces are busy on another job;
hence, you do not want to impose a penalty for late start. Try to maximize the
amount of points, as they reflect profit brought into your company, or a cost
savings. In Parts 3 and 4, be sure to use the project duration agreed upon to
calculate your score. Finally, do not discuss your scoring system with the CMG
Gas representative; this is proprietary information!
SCORING FOR PIPELINE CONSTRUCTORS, INC. NOTE: NA means not acceptable and the deal will not be approved by your
boss with any of these provisions. also, the alternatives listed are the only
ones in the context of this problem; no other alternatives are acceptable.
1. COMPLETION DATE
In order to help you, your boss has left you with a scoring table for all
the issues and alternatives. Two different scoring systems are listed here;
you will be assigned to use one or the other. Instructions for scoring system
A are included in Section 8.9. The instructions for scoring system B are
described as follows:
Your contract with the automobile company provides an incentive for
completion of the pipeline earlier than 38 weeks and a penalty for completion
after 38 weeks. To insure timely completion of the project, you would like to
receive detailed project reports as often as possible.
Try to maximize the number of points from the final contract provisions;
this corresponds to minimizing costs. Do not discuss your scoring systems with
Pipeline Constructors, Inc.
SCORING SYSTEM FOR CMG GAS NOTE: NA means not acceptable and the deal will not be approved by your
boss with any of these provisions. If you can't negotiate a contract, your
score will be +450. Also, the alternatives listed are the only ones in the
context of this problem no other alternatives are acceptable.
Once a contract is reached, a variety of problems may emerge during the
course of work. Disputes may arise over quality of work, over responsibility
for delays, over appropriate payments due to changed conditions, or a multitude
of other considerations. Resolution of contract disputes is an important task
for project managers. The mechanism for contract dispute resolution can be
specified in the original contract or, less desireably, decided when a dispute
arises.
The most prominent mechanism for dispute resolution is adjudication in a
court of law. This process tends to be expensive and time consuming since it
involves legal representation and waiting in queues of cases for available
court times. Any party to a contract can bring a suit. In adjudication, the
dispute is decided by a neutral, third party with no necessary specialized
expertise in the disputed subject. After all, it is not a prerequisite for
judges to be familiar with construction procedures! Legal procedures are
highly structured with rigid, formal rules for presentations and fact finding.
On the positive side, legal adjudication strives for consistency and
predictability of results. The results of previous cases are published and can
be used as precedents for resolution of new disputes.
Negotiation among the contract parties is a second important dispute
resolution mechanism. These negotiations can involve the same sorts of
concerns and issues as with the original contracts. Negotiation typically does
not involve third parties such as judges. The negotiation process is usually
informal, unstructured and relatively inexpensive. If an agreement is not
reached between the parties, then adjudication is a possible remedy.
A third dispute resolution mechanism is the resort to arbitration or
mediation and conciliation. In these procedures, a third party serves a
central role in the resolution. These outside parties are usually chosen by
mutually agreement of the parties involved and will have specialized knowledge
of the dispute subject. In arbitration, the third party may make a decision
which is binding on the participants. In mediation and conciliation, the third
party serves only as a facilitator to help the participants reach a mutually
acceptable resolution. Like negotiation, these procedures can be informal and
unstructured.
Finally, the high cost of adjudication has inspired a series of
non-traditional dispute resolution mechanisms that have some of the
characteristics of judicial proceedings. These mechanisms include:
While these various disputes resolution mechanisms involve varying costs, it
is important to note that the most important mechanism for reducing costs and
problems in dispute resolution is the reasonableness of the initial contract
among the parties as well as the competence of the project manager.
Construction planning is a fundamental and challenging activity in the
management and execution of construction projects. It involves the choice of
technology, the definition of work tasks, the estimation of the required
resources and durations for individual tasks, and the identification of any
interactions among the different work tasks. A good construction plan is the
basis for developing the budget and the schedule for work. Developing the
construction plan is a critical task in the management of construction, even if
the plan is not written or otherwise formally recorded. In addition to these
technical aspects of construction planning, it may also be necessary to make
organizational decisions about the relationships between project participants
and even which organizations to include in a project. For example, the extent
to which sub-contractors will be used on a project is often determined during
construction planning.
Forming a construction plan is a highly challenging task. As Sherlock
Holmes noted:
In developing a construction plan, it is common to adopt a primary emphasis
on either cost control or on schedule control as illustrated in Fig. 9-0.
Some projects are primarily divided into expense categories with associated
costs. In these cases, construction planning is cost or expense oriented.
Within the categories of expenditure, a distinction is made between costs
incurred directly in the performance of an activity and indirectly for the
accomplishment of the project. For example, borrowing expenses for project
financing and overhead items are commonly treated as indirect costs. For other
projects, scheduling of work activities over time is critical and is emphasized
in the planning process. In this case, the planner insures that the proper
precedences among activities are maintained and that efficient scheduling of
the available resources prevails. Traditional scheduling procedures emphasize
the maintenance of task precedences (resulting in critical path scheduling
procedures) or efficient use of resources over time (resulting in job shop
scheduling procedures). Finally, most complex projects require consideration
of both cost and scheduling over time, so that planning, monitoring and record
keeping must consider both dimensions. In these cases, the integration of
schedule and budget information is a major concern.
In this chapter, we shall consider the functional requirements for
construction planning such as technology choice, work breakdown, and budgeting.
Construction planning is not an activity which is restricted to the period
after the award of a contract for construction. It should be an essential
activity during the facility design. Also, if problems arise during
construction, re-planning is required.
As in the development of appropriate alternatives for facility design,
choices of appropriate technology and methods for construction are often
ill-structured yet critical ingredients in the success of the project. For
example, a decision whether to pump or to transport concrete in buckets will
directly affect the cost and duration of tasks involved in building
construction. A decision between these two alternatives should consider the
relative costs, reliabilities, and availability of equipment for the two
transport methods. Unfortunately, the exact implications of different methods
depend upon numerous considerations for which information may be sketchy during
the planning phase, such as the experience and expertise of workers or the
particular underground condition at a site.
In selecting among alternative methods and technologies, it may be necessary
to formulate a number of construction plans based on alternative methods or
assumptions. Once the full plan is available, then the cost, time and
reliability impacts of the alternative approaches can be reviewed. This
examination of several alternatives is often made explicit in bidding
competitions in which several alternative designs may be proposed or value
engineering for alternative construction methods may be permitted. In this
case, potential constructors may wish to prepare plans for each alternative
design using the suggested construction method as well as to prepare plans for
alternative construction methods which would be proposed as part of the value
engineering process.
In forming a construction plan, a useful approach is to simulate the
construction process either in the imagination of the planner or with a formal
computer based simulation technique.[See, for example, Paulson, B.C., S.A.
Douglas, A. Kalk, A. Touran and G.A. Victor, "Simulation and Analysis of
Construction Operations," ASCE Journal of Technical Topics in Civil
Engineering, 109(2), August, 1983, pp. 89, or Carr, R.I., "Simulation of
Construction Project Duration," ASCE Journal of the Construction Division,
105(2), June 1979, 117-128.] By observing the result, comparisons among
different plans or problems with the existing plan can be identified. For
example, a decision to use a particular piece of equipment for an operation
immediately leads to the question of whether or not there is sufficient access
space for the equipment. Three dimensional geometric models in a computer
aided design (CAD) system may be helpful in simulating space requirements for
operations and for identifying any interferences. Similarly, problems in
resource availability identified during the simulation of the construction
process might be effectively forestalled by providing additional resources as
part of the construction plan.
Example 9-1: A roadway rehabilitation
An example from a roadway rehabilitation project in Pittsburgh, PA can serve
to illustrate the importance of good construction planning and the effect of
technology choice. In this project, the decks on overpass bridges as well as
the pavement on the highway itself were to be replaced. The initial
construction plan was to work outward from each end of the overpass bridges
while the highway surface was replaced below the bridges. As a result, access
of equipment and concrete trucks to the overpass bridges was a considerable
problem. However, the highway work could be staged so that each overpass
bridge was accessible from below at prescribed times. By pumping concrete up
to the overpass bridge deck from the highway below, costs were reduced and the
work was accomplished much more quickly.
Example 9-2: Laser Leveling
An example of technology choice is the use of laser leveling equipment to
improve the productivity of excavation and grading.<For a description of a
laser leveling system, see Paulson, B.C., Jr., "Automation and Robotics for
Construction," ASCE Journal of Construction Engineering and Management,
(111)3, pp. 190-207, Sept. 1985.> In these systems, laser surveying equipment
is erected on a site so that the relative height of mobile equipment is known
exactly. This height measurement is accomplished by flashing a rotating laser
light on a level plane across the construction site and observing exactly where
the light shines on receptors on mobile equipment such as graders. Since laser
light does not disperse appreciably, the height at which the laser shines
anywhere on the construction site gives an accurate indication of the height of
a receptor on a piece of mobile equipment. In turn, the receptor height can be
used to measure the height of a blade, excavator bucket or other piece of
equipment. Combined with electro-hydraulic control systems mounted on mobile
equipment such as bulldozers, graders and scrapers, the height of excavation
and grading blades can be precisely and automatically controlled in these
systems. This automation of blade heights has reduced costs in some cases by
over 80% and improved quality in the finished product, as measured by the
desired amount of excavation or the extent to which a final grade achieves the
desired angle. These systems also permit the use of smaller machines and less
skilled operators. However, the use of these semi-automated systems require
investments in the laser surveying equipment as well as modification to
equipment to permit electronic feedback control units. Still, laser leveling
appears to be an excellent technological choice in many instances.
At the same time that the choice of technology and general method are
considered, a parallel step in the planning process is to define the various
work tasks that must be accomplished. These work tasks represent the necessary
framework to permit scheduling of construction activities, along with
estimating the resources required by the individual work tasks, and any
necessary precedences or required sequence among the tasks. The terms work
"tasks" or "activities" are often used interchangeably in construction plans to
refer to specific, defined items of work. In job shop or manufacturing
terminology, a project would be called a "job" and an activity called an
"operation", but the sense of the terms is equivalent.[See Baker, K.R.,
Introduction to Sequencing and Scheduling, John-Wiley and Sons, New York,
1974, for an introduction to scheduling in manufacturing.] The scheduling
problem is to determine an appropriate set of activity start time, resource
allocations and completion times that will result in completion of the project
in a timely and efficient fashion. Construction planning is the necessary
fore-runner to scheduling. In this planning, defining work tasks, technology
and construction method is typically done either simultaeously or in a series
of iterations.
The definition of appropriate work tasks can be a laborious and tedious
process, yet it represents the necessary information for application of formal
scheduling procedures. Since construction projects can involve thousands of
individual work tasks, this definition phase can also be expensive and time
consuming. Fortunately, many tasks may be repeated in different parts of the
facility or past facility construction plans can be used as general models for
new projects. For example, the tasks involved in the construction of a
building floor may be repeated with only minor differences for each of the
floors in the building. Also, standard definitions and nomenclatures for most
tasks exist. As a result, the individual planner defining work tasks does not
have to approach each facet of the project entirely from scratch.
While repetition of activities in different locations or reproduction of
activities from past projects reduces the work involved, there are very few
computer aids for the process of defining activities. Databases and
information systems can assist in the storage and recall of the activities
associated with past projects as described in Chapter 14. For the scheduling
process itself, numerous computer programs are available. But for the
important task of defining activities, reliance on the skill, judgment and
experience of the construction planner is likely to continue. In the next few
decades, however, more powerful computer aids may become available for this
problem; an example is described in Chapter 15.
More formally, an activity is any subdivision of project tasks. The set of
activities defined for a project should be comprehensive or completely
exhaustive so that all necessary work tasks are included in one or more
activities. Typically, each design element in the planned facility will have
one or more associated project activities. Execution of an activity requires
time and resources, including manpower and equipment, as described in the next
section. The time required to perform an activity is called the duration of
the activity. The beginning and the end of activities are signposts or
milestones, indicating the progress of the project. Occasionally, it is
useful to define activities which have no duration to mark important events.
For example, receipt of equipment on the construction site may be defined as an
activity since other activities would depend upon the equipment availability
and the project manager might appreciate formal notice of the arrival.
Similarly, receipt of regulatory approvals would also be specially marked in
the project plan.
The extent of work involved in any one activity can vary tremendously in
construction project plans. Indeed, it is common to begin with fairly coarse
definitions of activities and then to further sub-divide tasks as the plan
becomes better defined. As a result, the definition of activities evolves
during the preparation of the plan. A result of this process is a natural
hierarchy of activities with large, abstract functional activities repeatedly
sub-divided into more and more specific sub-tasks. For example, the problem of
placing concrete on site would have sub-activities associated with placing
forms, installing reinforcing steel, pouring concrete, finishing the concrete,
removing forms and others. Even more specifically, sub-tasks such as removal
and cleaning of forms after concrete placement can be defined. Even further,
the sub-task "clean concrete forms" could be subdivided into the various
operations:
It is generally advantageous to introduce an explicit hierarchy of work
activities for the purpose of simplifying the presentation and development of a
schedule. For example, the initial plan might define a single activity
associated with "site clearance." Later, this single activity might be
sub-divided into "re-locating utilities," "removing vegetation," "grading",
etc. However, these activities could continue to be identified as
sub-activities under the general activity of "site clearance." This
hierarchical structure also facilitates the preparation of summary charts and
reports in which detailed operations are combined into aggregate or
"super"-activities.
More formally, a hierarchical approach to work task definition decomposes
the work activity into component parts in the form of a tree. Higher levels in
the tree represent decision nodes or summary activities, while branches in the
tree lead to smaller components and work activities. A variety of constraints
among the various nodes may be defined or imposed, including precedence
relationships among different tasks as defined below. Technology choices may
be decomposed to decisions made at particular nodes in the tree. For example,
choices on plumbing technology might be made without reference to choices for
other functional activities.
Of course, numerous different activity hierarchies can be defined for each
construction plan. For example, upper level activities might be related to
facility components such as foundation elements, and then lower level activity
divisions into the required construction operations might be made.
Alternatively, upper level divisions might represent general types of
activities such as electrical work, while lower work divisions represent the
application of these operations to specific facility components. As a third
alternative, initial divisions might represent different spatial locations in
the planned facility. The choice of a hierarchy depends upon the desired
scheme for summarizing work information and on the convenience of the planner.
In computerized databases, multiple hierarchies can be stored so that different
aggregations or views of the work breakdown structure can be obtained.
The number and detail of the activities in a construction plan is a matter
of judgment or convention. Construction plans can easily range between less
than a hundred to many thousand defined tasks, depending on the planner's
decisions and the scope of the project. If subdivided activities are too
refined, the size of the network becomes unwieldy and the cost of planning
excessive. Sub-division yields no benefit if reasonably accurate estimates of
activity durations and the required resources cannot be made at the detailed
work breakdown level. On the other hand, if the specified activities are too
coarse, it is impossible to develop realistic schedules and details of resource
requirements during the project. More detailed task definitions permit better
control and more realistic scheduling. It is useful to define separate work
tasks for:
In practice, the proper level of detail will depend upon the size,
importance and difficulty of the project as well as the specific scheduling and
accounting procedures which are adopted. However, it is generally the case
that most schedules are prepared with too little detail than too much. It is
important to keep in mind that task definition will serve as the basis for
scheduling, for communicating the construction plan and for construction
monitoring. Completion of tasks will also often serve as a basis for progress
payments from the owner. Thus, more detailed task definitions can be quite
useful. But more detailed task breakdowns are only valuable to the extent that
the resources required, durations and activity relationships are realistically
estimated for each activity. Providing detailed work task breakdowns is not
helpful without a commensurate effort to provide realistic resource requirement
estimates. As more powerful, computer-based scheduling and monitoring
procedures are introduced, the ease of defining and manipulating tasks will
increase, and the number of work tasks can reasonably be expected to expand.
Example 9-3: Task Definition for a Road Building Project
As an example of construction planning, suppose that we wish to develop a
plan for a road construction project including two culverts.(This example is
adapted from Aras, R. and J. Surkis, "PERT and CPM Techniques in Project
Management," ASCE Journal of the Construction Division, Vol. 90, No. CO1,
March, 1964.) Initially, we divide project activities into three categories as
shown in Figure 9-0: structures, roadway, and general. This division is based
on the major types of design elements to be constructed. Within the roadway
work, a further sub-division is into earthwork and pavement. Within these
subdivisions, we identify clearing, excavation, filling and finishing
(including seeding and sodding) associated with earthwork, and we define
watering, compaction and paving sub-activities associated with pavement.
Finally, we note that the roadway segment is fairly long, and so individual
activities can be defined for different physical segments along the roadway
path. In Figure 9-0, we divide each paving and earthwork activity into
activities specific to each of two roadway segments. For the culvert
construction, we define the sub-divisions of structural excavation, concreting,
and reinforcing. Even more specifically, structural excavation is divided into
excavation itself and the required backfill and compaction. Similarly,
concreting is divided into placing concrete forms, pouring concrete, stripping
forms, and curing the concrete. As a final step in the structural planning,
detailed activities are defined for reinforcing each of the two culverts.
General work activities are defined for move in, general supervision, and clean
up. As a result of this planning, over thirty different detailed activities
have been defined.
At the option of the planner, additional activities might also be defined
for this project. For example, materials ordering or lane striping might be
included as separate activities. It might also be the case that a planner
would define a different hierarchy of work breakdowns than that shown in Figure
9-0. For example, placing reinforcing might have been a sub-activity under
concreting for culverts. One reason for separating reinforcement placement
might be to emphasize the different material and resources required for this
activity. Also, the division into separate roadway segments and culverts might
have been introduced early in the hierarchy. With all these potential
differences, the important aspect is to insure that all necessary activities
are included somewhere in the final plan.
Once work activities have been defined, the relationships among the
activities can be specified. Precedence relations between activities signify
that the activities must take place in a particular sequence. Numerous natural
sequences exist for construction activities due to requirements for structural
integrity, regulations, and other technical requirements. For example, design
drawings cannot be checked before they are drawn. Diagramatically, precedence
relationships can be illustrated by a network or graph in which the
activities are represented by arrows as in Figure 9-0. The arrows in Figure
9-0 are called branches or links in the activity network, while the circles
marking the beginning or end of each arrow are called nodes or events. In
this figure, links represent particular activities, while the nodes represent
milestone events.
More complicated precedence relationships can also be specified. For
example, one activity might not be able to start for several days after the
completion of another activity. As a common example, concrete might have to
cure (or set) for several days before formwork is removed. This restriction on
the removal of forms activity is called a lag between the completion of one
activity (i.e., pouring concrete in this case) and the start of another
activity (i.e., removing formwork in this case). Many computer based
scheduling programs permit the use of a variety of precedence relationships.
Three mistakes should be avoided in specifying predecessor relationships for
construction plans. First, a circle of activity precedences will result in an
impossible plan. For example, if activity A precedes activity B, activity B
precedes activity C, and activity C precedes activity A, then the project can
never be started or completed! Figure 9-0 illustrates the resulting activity
network. Fortunately, formal scheduling methods and good computer scheduling
programs will find any such errors in the logic of the construction plan.
Forgetting a necessary precedence relationship can be more insidious. For
example, suppose that installation of dry wall should be done prior to floor
finishing. Ignoring this precedence relationship may result in both activities
being scheduled at the same time. Corrections on the spot may result in
increased costs or problems of quality in the completed project.
Unfortunately, there are few ways in which precedence omissions can be found
other than with checks by knowledgeable managers or by comparison to comparable
projects. One other possible but little used mechanism for checking
precedences is to conduct a physical or computer based simulation of the
construction process and observe any problems.
Finally, it is important to realize that different types of precedence
relationships can be defined and that each has different implications for the
schedule of activities:
Example 9-4: Precedence Definition for Site Preparation and Foundation
Work
Suppose that a site preparation and concrete slab foundation construction
project consists of nine different activities:
Activities A (site clearing) and B (tree removal) do not have preceding
activities since they depend on none of the other activities. We assume that
activities C (general excavation) and D (general grading) are preceded by
activity A (site clearing). It might also be the case that the planner wished
to delay any excavation until trees were removed, so that B (tree removal)
would be a precedent activity to C (general excavation) and D (general
grading). Activities E (trench excavation) and F (concrete preparation) cannot
begin until the completion of general excavation and grading, since they
involve subsequent excavation and trench preparation. Activities G (install
lines) and H (install utilities) represent installation in the utility trenches
and cannot be attempted until the trenches are prepared, so that activity E
(trench excavation) is a preceding activity. We also assume that the utilities
should not be installed until grading is completed to avoid equipment
conflicts, so activity D (general grading) is also preceding activities G
(install sewers) and H (install utilities). Finally, activity I (pour
concrete) cannot begin until the sewer line is installed and formwork and
reinforcement are ready, so activities F and G are preceding. Other utilities
may be routed over the slab foundation, so activity H (install utilities) is
not necessarily a preceding activity for activity I (pour concrete). The
result of our planning are the immediate precedences shown in Table 9-0.
______________________________________________________________________________
Activity!! Description!! Predecessors!!
A!!Site clearing !! -!!
B!!Removal of trees!! -!!
C!!General excavation!! A!!
D!!Grading general area!! A!!
E!!Excavation for utility trenches!! B,C!!
F!!Placing formwork and reinforcement!! B,C!!
!! for concrete
G!!Installing sewer lines!! D,E!!
H!!Installing other utilities!! D,E!!
I!!Pouring concrete!! F,G!!
______________________________________________________________________________
With this information, the next problem is to represent the activities in a
network diagram and to determine all the precedence relationships among the
activities. One network representation of these nine activities is shown in
Figure 9-0, in which the activities appear as branches or links between nodes.
The nodes represent milestones of possible beginning and starting times. This
representation is called an activity-on-branch diagram. Note that an initial
event beginning activity is defined (Node 0 in Figure 9-0), while node 5
represents the completion of all activities.
Alternatively, the nine activities could be represented by nodes and
predecessor relationships by branches or links, as in Figure 9-0. The result
is an activity-on-node diagram. In Figure 9-0, new activity nodes
representing the beginning and the end of construction have been added to mark
these important milestones.
These network representations of activities can be very helpful in
visualizing the various activities and their relationships for a project.
Whether activities are represented as branches (as in Figure 9-0) or as nodes
(as in Figure 9-0) is largely a matter of organizational or personal choice.
Some considerations in choosing one form or another are discussed in Chapter
10.
It is also notable that Table 9-0 lists only the immediate predecessor
relationships. Clearly, there are other precedence relationships which involve
more than one activity. For example, "installing sewer lines" (activity G)
cannot be undertaken before "site clearing" (Activity A) is complete since the
activity "grading general area" (Activity D) must precede activity G and must
follow activity A. Table 9-0 is an implicit precedence list since only
immediate predecessors are recorded. An explicit predecessor list would
include all of the preceding activities for activity G. Table 9-0 shows all
such predecessor relationships implied by the project plan. This table can be
produced by tracing all paths through the network back from a particular
activity and can be performed algorithmically.(For a discussion of network
reachability and connectivity computational algorithms, see Chapters 2 and 7 in
N. Christofides, Graph Theory: An Algorithmic Approach, London: Academic
Press, 1975, or any other text on graph theory.) For example, inspecting
Figure 9-0 reveals that each activity except for activity B depends upon the
completion of activity A.
______________________________________________________________________________
Predecessor!! Direct Successor!! All Successor!! All Predecessor
Activity!! Activities!! Activities!! Activities
A!! C,D!! E,F,G,H,I!! -
B!! E,F!! G,H,I!! -
C!! E,F!! G,H,I!! A
D!! G,H!! I!! A
E!! G,H!! I!! A,B,C
F!! I!! -!! A,B,C
G!! I!! -!! A,B,C,D,E
H!! -!! -!! A,B,C,D,E
I!! -!! -!! A,B,C,D,E,F,G
______________________________________________________________________________
In most scheduling procedures, each work activity has an associated time
duration. These durations are used extensively in preparing a schedule. For
example, suppose that the durations shown in Table 9-0 were estimated for the
project diagrammed in Figure 9-0. The entire set of activities would then
require at least 3 days, since the activities follow one another directly and
require a total of 1.0 + 0.5 + 0.5 + 1.0 = 3 days. If another activity
proceeded in parallel with this sequence, the 3 day minimum duration of these
four activities is unaffected. More than 3 days would be required for the
sequence if there was a delay or a lag between the completion of one activity
and the start of another.
______________________________________________________________________________
Activity!!Predecessor!!Duration (Days)
Excavate trench!!-!!1.0
Place formwork!!Excavate trench!!0.5
Place reinforcing!!Place formwork!!0.5
Pour concrete!!Place reinforcing!!1.0
______________________________________________________________________________
All formal scheduling procedures rely upon estimates of the durations of the
various project activities as well as the definitions of the predecessor
relationships among tasks. The variability of an activity's duration may also
be considered. Formally, the probability distribution of an activity's
duration as well as the expected or most likely duration may be used in
scheduling. A probability distribution indicates the chance that a particular
activity duration will occur. In advance of actually doing a particular task,
we cannot be certain exactly how long the task will require.
A straightforward approach to the estimation of activity durations is to
keep historical records of particular activities and rely on the average
durations from this experience in making new duration estimates. Since the
scope of activities are unlikely to be identical between different projects,
unit productivity rates are typically employed for this purpose. For example,
the duration of an activity D@-(ij) such as concrete formwork assembly might be
estimated as: A formula such as Eq. (9.9.5) can be used for nearly all construction
activities. Typically, the required quantity of work, A@-(ij) is determined
from detailed examination of the final facility design. This
quantity-take-off to obtain the required amounts of materials, volumes, and
areas is a very common process in bid preparation by contractors. In some
countries, specialized quantity surveyors provide the information on required
quantities for all potential contractors and the owner. The number of crews
working, N@-(ij), is decided by the planner. In many cases, the number or
amount of resources applied to particular activities may be modified in light
of the resulting project plan and schedule. Finally, some estimate of the
expected work productivity, P@-(ij) must be provided to apply Equation (9.9.5).
As with cost factors, commercial services can provide average productivity
figures for many standard activities of this sort. Historical records in a
firm can also provide data for estimation of productivities.
The calculation of a duration as in Equation (9.9.5) is only an
approximation to the actual activity duration for a number of reasons. First,
it is usually the case that peculiarities of the project make the
accomplishment of a particular activity more or less difficult. For example,
access to the forms in a particular location may be difficult; as a result, the
productivity of assembling forms may be lower than the average value for a
particular project. Often, adjustments based on engineering judgment are made
to the calculated durations from Equation (9.9.5) for this reason.
In addition, productivity rates may vary in both systematic and random
fashions from the average. An example of systematic variation is the effect of
learning on productivity. As a crew becomes familiar with an activity and the
work habits of the crew, their productivity will typically improve. Figure 9-0
illustrates the type of productivity increase that might occur with experience;
this curve is called a learning curve. The result is that productivity
P@-(ij) is a function of the duration of an activity or project. A common
construction example is that the assembly of floors in a building might go
faster at higher levels due to improved productivity even though the
transportation time up to the active construction area is longer. Again,
historical records or subjective adjustments might be made to represent
learning curve variations in average productivity.[See H.R. Thomas, C.T.
Matthews and J.G. Ward, "Learning Curve Models of Construction Productivity,"
ASCE Journal of Construction Engineering and Management, Vol. 112, No. 2, June
1986, pp. 245-258.]
Random factors will also influence productivity rates and make estimation of
activity durations uncertain. For example, a scheduler will typically not know
at the time of making the initial schedule how skillful the crew and manager
will be that are assigned to a particular project. The productivity of a
skilled designer may be many times that of an unskilled engineer. In the
absence of specific knowledge, the estimator can only use average values of
productivity.
Weather effects are often very important and thus deserve particular
attention in estimating durations. Weather has both systematic and random
influences on activity durations. Whether or not a rainstorm will come on a
particular day is certainly a random effect that will influence the
productivity of many activities. However, the likelihood of a rainstorm is
likely to vary systematically from one month or one site to the next.
Adjustment factors for inclement weather as well as meteorological records can
be used to incorporate the effects of weather on durations. As a simple
example, an activity might require ten days in perfect weather, but the
activity could not proceed in the rain. Furthermore, suppose that rain is
expected ten percent of the days in a particular month. In this case, the
expected activity duration is eleven days including one expected rain day.
Finally, the use of average productivity factors themselves cause problems
in the calculation presented in Equation (9.9.5). The expected value of the
multiplicative reciprocal of a variable is not exactly equal to the reciprocal
of the variable's expected value. For example, if productivity on an activity
is either six in good weather (ie., P=6) or two in bad weather (ie., P=2) and
good or bad weather is equally likely, then the expected productivity is P =
(6)(0.5) + (2)(0.5) = 4, and the reciprocal of expected productivity is 1/4.
However, the expected reciprocal of productivity is E[1/P] = (0.5)/6 + (0.5)/2
= 1/3. The reciprocal of expected productivity is 33% greater than the
expected value of the reciprocal in this case! By representing only two
possible productivity values, this example represents an extreme case, but it
is always true that the use of average productivity factors in Equation (9.9.5)
will result in optimistic estimates of activity durations. The use of actual
averages for the reciprocals of productivity or small adjustment factors may be
used to correct for this non-linearity problem.
The simple duration calculation shown in Equation (9.9.5) also assumes an
inverse linear relationship between the number of crews assigned to an activity
and the total duration of work. While this is a reasonable assumption in
situations for which crews can work independently and require no special
coordination, it need not always be true. For example, design tasks may be
divided among numerous architects and engineers, but delays to insure proper
coordination and communication increase as the number of workers increase. As
another example, insuring a smooth flow of material to all crews on a site may
be increasingly difficult as the number of crews increase. In these latter
cases, the relationship between activity duration and the number of crews is
unlikely to be inversely proportional as shown in Equation (9.9.5). As a
result, adjustments to the estimated productivity from Equation (9.9.5) must be
made. Alternatively, more complicated functional relationships might be
estimated between duration and resources used in the same way that nonlinear
preliminary or conceptual cost estimate models are prepared.
One mechanism to formalize the estimation of activity durations is to employ
a hierarchical estimation framework. This approach decomposes the estimation
problem into component parts in which the higher levels in the hierarchy
represent attributes which depend upon the details of lower level adjustments
and calculations. For example, Figure 9-0 represents various levels in the
estimation of the duration of masonry construction.[For a more extension
discussion and description of this estimation procedure, see Hendrickson, C.,
D. Martinelli, and D. Rehak, "Hierarchical Rule-based Activity Duration
Estimation," ASCE Journal of Construction Engineering and Management, Vol 113,
No. 2, 1987,pp. 288-301.] At the lowest level, the maximum productivity for
the activity is estimated based upon general work conditions. Table 9-0
illustrates some possible maximum productivity values that might be employed in
this estimation. At the next higher level, adjustments to these maximum
productivities are made to account for special site conditions and crew
compositions; table 9-0 illustrates some possible adjustment rules. At the
highest level, adjustments for overall effects such as weather are introduced.
Also shown in Figure 9-0 are nodes to estimate down or unproductive time
associated with the masonry construction activity. The formalization of the
estimation process illustrated in Figure 9-0 permits the development of
computer aids for the estimation process (as described in Chapter 15) or can
serve as a conceptual framework for a human estimator.
In addition to the problem of estimating the expected duration of an
activity, some scheduling procedures explicitly consider the uncertainty in
activity duration estimates by using the probabilistic distribution of activity
durations. That is, the duration of a particular activity is assumed to be a
random variable that is distributed in a particular fashion. For example, an
activity duration might be assumed to be distributed as a normal or a beta
distributed random variable as illustrated in Figure 9-0. This figure shows
the probability or chance of experiencing a particular activity duration based
on a probabilistic distribution. The beta distribution is often used to
characterize activity durations, since it can have an absolute minimum and an
absolute maximum of possible duration times. The normal distribution is a good
approximation to the beta distribution in the center of the distribution and is
easy to work with, so it is often used as an approximation.
If a standard random variable is used to characterize the distribution of
activity durations, then only a few parameters are required to calculate the
probability of any particular duration. Still, the estimation problem is
increased considerably since more than one parameter is required to
characterize most of the probabilistic distribution used to represent activity
durations. For the beta distribution, three or four parameters are required
depending on its generality, whereas the normal distribution requires two
parameters.
As an example, the normal distribution is characterized by two parameters,
@g(m) and @g(s) representing the average duration and the standard deviation of
the duration, respectively. Alternatively, the variance of the distribution
@g(s)@+(2) could be used to describe or characterize the variability of
duration times; the variance is the value of the standard deviation multiplied
by itself. From historical data, these two parameters can be estimated as: In addition to precedence relationships and time durations, resource
requirements are usually estimated for each activity. Since the work
activities defined for a project are comprehensive, the total resources
required for the project are the sum of the resources required for the various
activities. By making resource requirement estimates for each activity, the
requirements for particular resources during the course of the project can be
identified. Potential bottlenecks can thus be identified, and schedule,
resource allocation or technology changes made to avoid problems.
Many formal scheduling procedures can incorporate constraints imposed by the
availability of particular resources. For example, the unavailability of a
specific piece of equipment or crew may prohibit activities from being
undertaken at a particular time. Another type of resource is space. A planner
typically will schedule only one activity in the same location at the same
time. While activities requiring the same space may have no necessary
technical precedence, simultaneous work might not be possible. Computational
procedures for these various scheduling problems will be described in Chapters
10 and 11. In this section, we shall discuss the estimation of required
resources.
The initial problem in estimating resource requirements is to decide the
extent and number of resources that might be defined. At a very aggregate
level, resources categories might be limited to the amount of labor (measured
in man-hours or in dollars), the amount of materials required for an activity,
and the total cost of the activity. At this aggregate level, the resource
estimates may be useful for purposes of project monitoring and cash flow
planning. For example, actual expenditures on an activity can be compared with
the estimated required resources to reveal any problems that are being
encountered during the course of a project. Monitoring procedures of this sort
are described in Chapter 12. However, this aggregate definition of resource
use would not reveal bottlenecks associated with particular types of equipment
or workers.
More detailed definitions of required resources would include the number and
type of both workers and equipment required by an activity as well as the
amount and types of materials. Standard resource requirements for particular
activities can be recorded and adjusted for the special conditions of
particular projects. As a result, the resources types required for particular
activities may already be defined. Reliance on historical or standard activity
definitions of this type requires a standard coding system for activities.
In making adjustments for the resources required by a particular activity,
most of the problems encountered in forming duration estimations described in
the previous section are also present. In particular, resources such as labor
requirements will vary in proportion to the work productivity, P@-(ij), used to
estimate activity durations in Equation (9.9.5). Mathematically, a typical
estimating equation would be: From the planning perspective, the important decisions in estimating
resource requirements are to determine the type of technology and equipment to
employ and the number of crews to allocate to each task. Clearly, assigning
additional crews might result in faster completion of a particular activity.
However, additional crews might result in congestion and coordination problems,
so that work productivity might decline. Further, completing a particular
activity earlier might not result in earlier completion of the entire project,
as discussed in Chapter 10.
Example 9-5: Resource Requirements for Block Foundations
In placing concrete block foundation walls, a typical crew would consist of
three bricklayers and two bricklayer helpers. If sufficient space was
available on the site, several crews could work on the same job at the same
time, thereby speeding up completion of the activity in proportion to the
number of crews. In more restricted sites, multiple crews might interfere with
one another. For special considerations such as complicated scaffolding or
large blocks (such as twelve inch block), a bricklayer helper for each
bricklayer might be required to insure smooth and productive work. In general,
standard crew composition depends upon the specific construction task and the
equipment or technology employed. These standard crews are then adjusted in
response to special characteristics of a particular site.
Example 9-6: Pouring Concrete Slabs
For large concrete pours on horizontal slabs, it is important to plan the
activity so that the slab for a full block can be completed continuously in a
single day. Resources required for pouring the concrete depend upon the
technology used. For example, a standard crew for pumping concrete to the slab
might include a foreman, five laborers, one finisher, and one equipment
operator. Related equipment would be vibrators and the concrete pump itself.
For delivering concrete with a chute directly from the delivery truck, the
standard crew might consist of a foreman, four laborers and a finisher. The
number of crews would be chosen to insure that the desired amount of concrete
could be placed in a single day. In addition to the resources involved in the
actual placement, it would also be necessary to insure a sufficient number of
delivery trucks and availability of the concrete itself.
One objective in many construction planning efforts is to define the plan
within the constraints of a universal coding system for identifying
activities. Each activity defined for a project would be identified by a
pre-defined code specific to that activity. The use of a common nomenclature
or identification system is basically motivated by the desire for better
integration of organizational efforts and improved information flow. In
particular, coding systems are adopted to provide a numbering system to replace
verbal descriptions of items. These codes reduce the length or complexity of
the information to be recorded. A common coding system within an organization
also aids consistency in definitions and categories between projects and among
the various parties involved in a project. Common coding systems also aid in
the retrieval of historical records of cost, productivity and duration on
particular activities. Finally, electronic data storage and retrieval
operations are much more efficient with standard coding systems, as described
in Chapter 14.
In North America, the most widely used standard coding system for
constructed facilities is the MASTERFORMAT system developed by the Construction
Specifications Institute (CSI) of the United States and Construction
Specifications of Canada.(Information on the MASTERFORMAT coding system can be
obtained from: The Construction Specifications Institute, 601 Madison St.,
Alexandria VA 22314.) After development of separate systems, this combined
system was originally introduced as the Uniform Construction Index (UCI) in
1972 and was subsequently adopted for use by numerous firms, information
providers, professional societies and trade organizations. The term
MASTERFORMAT was introduced with the 1978 revision of the UCI codes.
MASTERFORMAT provides a standard identification code for nearly all the
elements associated with building construction.
MASTERFORMAT involves a hierarchical coding system with multiple levels plus
keyword text descriptions of each item. In the numerical coding system, the
first two digits represent one of the sixteen divisions for work; a seventeenth
division is used to code conditions of the contract for a constructor. In the
latest version of the MASTERFORMAT, a third digit is added to indicate a
subdivision within each division. Each division is further specified by a
three digit extension indicating another level of subdivisions. In many cases,
these subdivisions are further divided with an additional three digits to
identify more specific work items or materials. For example, the code
16-950-960, "Electrical Equipment Testing" are defined as within Division 16
(Electrical) and Sub-Division 950 (Testing). The keywords "Electrical
Equipment Testing" is a standard description of the activity. The seventeen
major divisions in the UCI/CSI MASTERFORMAT system are shown in Table 9-0. As
an example, site work second level divisions are shown in Table 9-0.
While MASTERFORMAT provides a very useful means of organizing and
communicating information, it has some obvious limitations as a complete
project coding system. First, more specific information such as location of
work or responsible organization might be required for project cost control.
Code extensions are then added in addition to the digits in the basic
MASTERFORMAT codes. For example, a typical extended code might have the
following elements:
As a second problem, the MASTERFORMAT system was originally designed for
building construction activities, so it is difficult to include various
construction activities for other types of facilities or activities associated
with planning or design. Different coding systems have been provided by other
organizations in particular sub-fields such as power plants or roadways.
Nevertheless, MASTERFORMAT provides a useful starting point for organizing
information in different construction domains.
In devising organizational codes for project activities, there is a
continual tension between adopting systems that are convenient or expedient for
one project or for one project manager and systems appropriate for an entire
organization. As a general rule, the record keeping and communication
advantages of standard systems are excellent arguments for their adoption.
Even in small projects, however, ad hoc or haphazard coding systems can lead to
problems as the system is revised and extended over time.
In addition to assigning dates to project activities, project scheduling is
intended to match the resources of equipment, materials and labor with project
work tasks over time. Good scheduling can eliminate problems due to production
bottlenecks, facilitate the timely procurement of necessary materials, and
otherwise insure the completion of a project as soon as possible. In contrast,
poor scheduling can result in considerable waste as laborers and equipment wait
for the availability of needed resources or the completion of preceding tasks.
Delays in the completion of an entire project due to poor scheduling can also
create havoc for owners who are eager to start using the constructed
facilities.
Attitudes toward the formal scheduling of projects are often extreme. Many
owners require detailed construction schedules to be submitted by contractors
as a means of monitoring the work progress. The actual work performed is
commonly compared to the schedule to determine if construction is proceeding
satisfactorily. After the completion of construction, similar comparisons
between the planned schedule and the actual accomplishments may be performed to
allocate the liability for project delays due to changes requested by the
owner, worker strikes or other unforeseen circumstances.
In contrast to these instances of reliance upon formal schedules, many field
supervisors disdain and dislike formal scheduling procedures. In particular,
the critical path method of scheduling is commonly required by owners and has
been taught in universities for over two decades, but is often regarded in the
field as irrelevant to actual operations and a time consuming distraction. The
result is "seat-of-the-pants" scheduling that can be good or that can result in
grossly inefficient schedules and poor productivity. Progressive construction
firms use formal scheduling procedures whenever the complexity of work tasks is
high and the coordination of different workers is required.
With the continued development of easy to use computer programs and improved
methods of presenting schedules, many of the practical problems associated with
formal scheduling mechanisms are being overcome. But problems with the use of
scheduling techniques will continue until managers understand their proper use
and limitations.
A basic distinction exists between resource oriented and time oriented
scheduling techniques. For resource oriented scheduling, the focus is on using
and scheduling particular resources in an effective fashion. For example, the
project manager's main concern on a high-rise building site might be to insure
that cranes are used effectively for moving materials; without effective
scheduling in this case, delivery trucks might queue on the ground and workers
wait for deliveries on upper floors. For time oriented scheduling, the
emphasis is on determining the completion time of the project given the
necessary precedence relationships among activities. Hybrid techniques for
resource leveling or resource constrained scheduling in the presence of
precedence relationships also exist.
This chapter will introduce the fundamentals of scheduling methods. Our
discussion will generally assume that computer based scheduling programs will
be applied. Consequently, the wide variety of manual or mechanical scheduling
techniques will not be discussed in any detail. These manual methods are not
as capable or as convenient as computer based scheduling. With the
availability of these computer based scheduling programs, it is important for
managers to understand the basic operations performed by scheduling programs.
Moreover, even if formal methods are not applied in particular cases, the
conceptual framework of formal scheduling methods provides a valuable reference
for a manager. Accordingly, examples involving hand calculations will be
provided throughout the chapter to facilitate understanding.
The most widely used scheduling technique is the critical path method (CPM)
for scheduling, often referred to as critical path scheduling. This method
calculates the minimum completion time for a project along with the possible
start and finish times for the project activities. Indeed, many texts and
managers regard critical path scheduling as the only usable and practical
scheduling procedure. Computer programs and algorithms for critical path
scheduling are widely available and can efficiently handle projects with
thousands of activities.
The critical path itself represents the set or sequence of
predecessor/successor activities which will take the longest time to complete.
The duration of the critical path is the sum of the activities' durations along
the path. Thus, the critical path can be defined as the longest possible path
through the "network" of project activities, as described in Chapter 9. The
duration of the critical path represents the minimum time required to complete
a project. Any delays along the critical path would imply that additional time
would be required to complete the project. There may be more than one critical
path among all the project activities, so completion of the entire project
could be delayed by delaying activities along any one of the critical paths.
Formally, critical path scheduling assumes that a project has been divided
into activities of fixed duration and well defined predecessor relationships.
No resource constraints other than those implied by precedence relationships
are recognized. To use critical path scheduling in practice, construction
planners often attempt to represent a resource constraint by a precedence
relation. A constraint is simply a restriction on the options available to a
manager, and a resource constraint is a constraint deriving from the limited
availability of some resource of equipment, material, space or labor. For
example, one of two activities requiring the same piece of equipment might be
arbitrarily assumed to precede the other activity. This artificial precedence
constraint insures that the two activities requiring the same resource will not
be scheduled at the same time. Also, most critical path scheduling algorithms
impose restrictions on the generality of the activity relationships or network
geometries which are used. In essence, these restrictions imply that the
construction plan can be represented by a network plan in which activities
appear as links or "branches" in a network, as in Figure 9-0, or activities
appear as nodes in a network, as in Figure 9-0. In the first representation,
nodes in the network represent events or milestones. Nodes are numbered, and
no two nodes can have the same number or designation. Activities themselves
are usually referenced by their predecessor and successor node numbers. Two
nodes are introduced to represent the start and completion of the project
itself.
The actual computer representation of the project schedule generally
consists of a list of activities along with their associated durations,
required resources and predecessor activities. Graphical network
representations rather than a list are helpful for visualization of the plan
and to insure that mathematical requirements are met. The actual input of the
data to a computer program may be accomplished by filling in blanks on a screen
menu, reading an existing datafile, or typing data directly to the program with
identifiers for the type of information being provided.
With an activity-on-branch network, dummy activities may be introduced for
the purposes of providing unique activity designations and maintaining the
correct sequence of activities. A dummy activity is assumed to have no time
duration and can be graphically represented by a dashed line in a network.
Several cases in which dummy activities are useful are illustrated in Fig.
10-0. In Fig. 10-0(a), the elimination of activity C would mean that both
activities B and D would be identified as being between nodes 1 and 3.
However, if a dummy activity X is introduced, as shown in part (b) of the
figure, the unique designations for activity B (node 1 to 2) and D (node 2 to
3) will be preserved. Furthermore, if the problem in part (a) is changed so
that activity E cannot start until both C and D are completed but that F can
start after D alone is completed, the order in the new sequence can be
indicated by the addition of a dummy activity Y, as shown in part (c). In
general, dummy activities may be necessary to meet the requirements of specific
computer scheduling algorithms, but it is important to limit the number of such
dummy link insertions to the extent possible.
Example 10-1: Formulating a network diagram
Suppose that we wish to form an activity network for a seven activity
network with the following precedences:
With the background provided by the previous sections, we can formulate the
critical path scheduling mathematically. We shall present an algorithm or set
of instructions for critical path scheduling assuming an activity-on-branch
project network. We also assume that all precedences are of a finish-to-start
nature, so that a succeeding activity cannot start until the completion of a
preceding activity. In a later section, we present a comparable algorithm for
activity-on-node representations with multiple precedence types.
Suppose that our project network has n+1 nodes, the initial event being 0
and the last event being n. Let the time at which node events occur be x@-(1),
x@-(2), @+(...), x@-(n), respectively. The start of the project at x@-(0) will
be defined as time 0. Nodal event times must be consistent with activity
durations, so that an activity's successor node event time must be larger than
an activity's predecessor node event time plus its duration. For an activity
defined as starting from event i and ending at event j, this relationship can
be expressed as the inequality constraint, x@-(j) G x@-(i) + D@-(ij) where
D@-(ij) is the duration of activity (i,j). This same expression can be written
for every activity and must hold true in any feasible schedule.
Mathematically, then, the critical path scheduling problem is to minimize the
time of project completion (x@-[n]) subject to the constraints that each node
completion event cannot occur until each of the predecessor activities have
been completed: Rather than solving the critical path scheduling problem with a linear
programming algorithm (such as the Simplex method), more efficient techniques
are available that take advantage of the network structure of the problem.
These solution methods are very efficient with respect to the required
computations, so that very large networks can be treated even with small
micro-computers. These methods also give some very useful information about
possible activity schedules. The programs can compute the earliest and latest
possible starting times for each activity which are consistent with completing
the project in the shortest possible time. This calculation is of particular
interest for activities which are not on the critical path (or paths), since
these activities might be slightly delayed or re-scheduled over time as a
manager desires without delaying the entire project.
An efficient solution process for critical path scheduling based upon node
labeling is shown in Table 10-0. Three algorithms appear in the table. The
event numbering algorithm numbers the nodes (or events) of the project such
that the beginning event has a lower number than the ending event for each
activity. Technically, this algorithm accomplishes a "topological sort" of the
activities. The project start node is given number 0. As long as the project
activities fulfill the conditions for an activity-on-branch network, this type
of numbering system is always possible. Some software packages for critical
path scheduling do not have this numbering algorithm programmed, so that the
construction project planners must insure that appropriate numbering is done.
The earliest event time algorithm computes the earliest possible time,
E(i), at which each event, i, in the network can occur. Earliest event times
are computed as the maximum of the earliest start times plus activity durations
for each of the activities immediately preceding an event. The earliest start
time for each activity (i,j) is equal to the earliest possible time for the
preceding event E(i):
Activities are identified in this algorithm by the predecessor node (or event)
i and the successor node j. The algorithm simply requires that each event in
the network should be examined in turn beginning with the project start (node
0).
The latest event time algorithm computes the latest possible time, L(j), at
which each event j in the network can occur, given the desired completion time
of the project, L(n) for the last event n. Usually, the desired completion
time will be equal to the earliest possible completion time, so that E(n) =
L(n) for the final node n. The procedure for finding the latest event time is
analogous to that for the earliest event time except that the procedure begins
with the final event and works backwards through the project activities. Thus,
the earliest event time algorithm is often called a forward pass through the
network, whereas the latest event time algorithm is the the backward pass
through the network. The latest finish time consistent with completion of the
project in the desired time frame of L(n) for each activity (i,j) is equal to
the latest possible time L(j) for the succeeding event: The earliest start and latest finish times for each event are useful pieces
of information in developing a project schedule. Events which have equal
earliest and latest times, E(i) = L(i), lie on the critical path or paths. An
activity (i,j) is a critical activity if it satisfies all of the following
conditions:
Hence, activities between critical events are also on a critical path as long
as the activity's earliest start time equals its latest start time, ES(i,j) =
LS(i,j). To avoid delaying the project, all the activities on a critical path
should begin as soon as possible, so each critical activity (i,j) must be
scheduled to begin at the earliest possible start time, E(i).
Example 10-2: Critical path scheduling calculations
Consider the network shown in Figure 10-0 in which the project start is
given number 0. Then, the only event that has each predecessor numbered is the
successor to activity A, so it receives number 1. After this, the only event
that has each predecessor numbered is the successor to the two activities B and
C, so it receives number 2. The other event numbers resulting from the
algorithm are also shown in the figure. For this simple project network, each
stage in the numbering process found only one possible event to number at any
time. With more than one feasible event to number, the choice of which to
number next is arbitrary. For example, if activity C did not exist in the
project for Figure 10-0, the successor event for activity A or for activity B
could have been numbered 1.
For the network in Figure 10-0 with activity durations in Table 10-0, the
earliest event time calculations proceed as follows:
For the "backward pass," the latest event time calculations are:
In this example, E(0) = L(0), E(1) = L(1), E(2) = L(2), E(4) = L(4),and E(5)
= L(5). As a result, all nodes but node 3 are in the critical path.
Activities on the critical path include C (1,2), F (2,4) and I (4,5) as shown
in Table 10-0.
A number of different activity schedules can be developed from the critical
path scheduling procedure described in the previous section. An earliest time
schedule would be developed by starting each activity as soon as possible, at
ES(i,j). Similarly, a latest time schedule would delay the start of each
activity as long as possible but still finish the project in the minimum
possible time. This late schedule can be developed by setting each activity's
start time to LS(i,j).
Activities that have different early and late start times (i.e., ES(i,j) <
LS(i,j)) can be scheduled to start anytime between ES(i,j) and LS(i,j) as shown
in Figure 10-0. The concept of float is to use part or all of this allowable
range to schedule an activity without delaying the completion of the project.
An activity that has the earliest time for its predecessor and successor nodes
differing by more than its duration possesses a window in which it can be
scheduled. That is, if E(i) + D@-(ij) < L(j) then some float is available in
which to schedule this activity.
Float is a very valuable concept since it represents the scheduling
flexibility or "maneuvering room" available to complete particular tasks.
Activities on the critical path do not provide any flexibility for scheduling
nor leeway in case of problems. For activities with some float, the actual
starting time might be chosen to balance work loads over time, to correspond
with material deliveries, or to improve the project's cash flow.
Of course, if one activity is allowed to float or change in the schedule,
then the amount of float available for other activities may decrease. Three
separate categories of float are defined in critical path scheduling:
The various categories of activity float are illustrated in Figure 10-0 in
which the activity is represented by a bar which can move back and forth in
time depending upon its scheduling start. Three possible scheduled starts are
shown, corresponding to the cases of starting each activity at the earliest
event time, E(i), the latest activity start time LS(i,j), and at the latest
event time L(i). The three categories of float can be found directly from this
figure. Finally, a fourth bar is included in the figure to illustrate the
possibility that an activity might start, be temporarily halted, and then
re-start. In this case, the temporary halt was sufficiently short that it was
less than the independent float time and thus would not interfere with other
activities. Whether or not such work splitting is possible or economical
depends upon the nature of the activity.
As shown in Table 10-0, activity D (1,3) has free and independent floats of
10 for the project shown in Figure 10-0. Thus, the start of this activity
could be scheduled anytime between time 4 and 14 after the project began
without interfering with the schedule of other activities or with the earliest
completion time of the project. As the total float of 11 units indicates, the
start of activity D could also be delayed until time 15, but this would require
that the schedule of other activities be restricted. For example, starting
activity D at time 11 would required that activity G would begin as soon as
activity D was completed. However, if this schedule was maintained, the
overall completion date of the project would not be changed.
Example 10-3: Critical path for a fabrication project
As another example of critical path scheduling, consider the seven
activities associated with the fabrication of a steel component shown in Table
10-0. Figure 10-0 shows the network diagram associated with these seven
activities. Note that an additional dummy activity X has been added to insure
that the correct precedence relationships are maintained for activity E. A
simple rule to observe is that if an activity has more than one immediate
predecessor and another activity has at least one but not all of these
predecessor activity as a predecessor, a dummy activity will be required to
maintain precedence relationships. Thus, in the figure, activity E has
activities B and C as predecessors, while activity D has only activity C as a
predecessor. Hence, a dummy activity is required. Node numbers have also been
added to this figure using the procedure outlined in Table 10-0. Note that the
node numbers on nodes 1 and 2 could have been exchanged in this numbering
process since after numbering node 0, either node 1 or node 2 could be numbered
next.
The results of the earliest and latest event time algorithms (appearing in
Table 10-0) are shown in Table 10-0. The minimum completion time for the
project is 32 days. In this small project, all of the event nodes except node
1 are on the critical path. Table 10-0 shows the earliest and latest start
times for the various activities including the different categories of float.
Activities C,E,F,G and the dummy activity X are seen to lie on the critical
path.
Communicating the project schedule is a vital ingredient in successful
project management. A good presentation will greatly ease the manager's
problem of understanding the multitude of activities and their
inter-relationships. Moreover, numerous individuals and parties are involved
in any project, and they have to understand their assignments. Graphical
presentations of project schedules are particularly useful since it is much
easier to comprehend a graphical display of numerous pieces of information than
to sift through a large table of numbers. Early computer scheduling systems
were particularly poor in this regard since they produced pages and pages of
numbers without aids to the manager for understanding them. A short example
appears in Tables 10-0 and 10-0; in practice, a project summary table would be
much longer. It is extremely tedious to read a table of activity numbers,
durations, schedule times, and floats and thereby gain an understanding and
appreciation of a project schedule. In practice, producing diagrams manually
has been a common prescription to the lack of automated drafting facilities.
Indeed, it has been common to use computer programs to perform critical path
scheduling and then to produce bar charts of detailed activity schedules and
resource assignments manually. With the availability of computer graphics, the
cost and effort of producing graphical presentations has been significantly
reduced and the production of presentation aids can be automated.
Network diagrams for projects have already been introduced. These diagrams
provide a powerful visualization of the precedences and relationships among the
various project activities. They are a basic means of communicating a project
plan among the participating planners and project monitors. Project planning
is often conducted by producing network representations of greater and greater
refinement until the plan is satisfactory.
A useful variation on project network diagrams is to draw a time-scaled
network. The activity diagrams shown in the previous section were topological
networks in that only the relationship between nodes and branches were of
interest. The actual diagram could be distorted in any way desired as long as
the connections between nodes were not changed. In time-scaled network
diagrams, activities on the network are plotted on a horizontal axis measuring
the time since project commencement. Figure 10-0 gives an example of a
time-scaled activity-on-branch diagram for the nine activity project in Figure
10-0. In this time-scaled diagram, each node is shown at its earliest possible
time. By looking over the horizontal axis, the time at which activity can
begin can be observed. Obviously, this time scaled diagram is produced as a
display after activities are initially scheduled by the critical path method.
Another useful graphical representation tool is a bar or Gantt chart
illustrating the scheduled time for each activity. The bar chart lists
activities and shows their scheduled start, finish and duration. An
illustrative bar chart for the nine activity project appearing in Figure 10-0
is shown in Figure 10-0. Activities are listed in the vertical axis of this
figure, while time since project commencement is shown along the horizontal
axis. During the course of monitoring a project, useful additions to the
basic bar chart include a vertical line to indicate the current time plus small
marks to indicate the current state of work on each activity. In Figure 10-0,
a hypothetical project state after 4 periods is shown. The small "v" marks on
each activity represent the current state of each activity.
Bar charts are particularly helpful for communicating the current state and
schedule of activities on a project. As such, they have found wide acceptance
as a project representation tool in the field. For planning purposes, bar
charts are not as useful since they do not indicate the precedence
relationships among activities. Thus, a planner must remember or record
separately that a change in one activity's schedule may require changes to
successor activities. There have been various schemes for mechanically linking
activity bars to represent precedences, but it is now easier to use computer
based tools to represent such relationships.
Other graphical representations are also useful in project monitoring. Time
and activity graphs are extremely useful in portraying the current status of a
project as well as the existence of activity float. For example, Figure 10-0
shows two possible schedules for the nine activity project described in Table
9-0 and shown in the previous figures. The first schedule would occur if each
activity was scheduled at its earliest start time, ES(i,j) consistent with
completion of the project in the minimum possible time. With this schedule,
Figure 10-0 shows the percent of project activity completed versus time. The
second schedule in Figure 10-0 is based on latest possible start times for each
activity, LS(i,j). The horizontal time difference between the two feasible
schedules gives an indication of the extent of possible float. If the project
goes according to plan, the actual percentage completion at different times
should fall between these curves. In practice, a vertical axis representing
cash expenditures rather than percent completed is often used in developing a
project representation of this type. For this purpose, activity cost estimates
are used in preparing a time versus completion graph. Separate "S-curves" may
also be prepared for groups of activities on the same graph, such as separate
curves for the design, procurement, foundation or particular sub-contractor
activities.
Time versus completion curves are also useful in project monitoring. Not
only the history of the project can be indicated, but the future possibilities
for earliest and latest start times. For example, Figure 10-0 illustrates a
project that is forty percent complete after eight days for the nine activity
example. In this case, the project is well ahead of the original schedule;
some activities were completed in less than their expected durations. The
possible earliest and latest start time schedules from the current project
status are also shown on the figure.
Graphs of resource use over time are also of interest to project planners
and managers. An example of resource use is shown in Figure 10-0 for the
resource of total employment on the site of a project. This graph is prepared
by summing the resource requirements for each activity at each time period for
a particular project schedule. With limited resources of some kind, graphs of
this type can indicate when the competition for a resource is too large to
accommodate; in cases of this kind, resource constrained scheduling may be
necessary as described in Section 10.9. Even without fixed resource
constraints, a scheduler tries to avoid extreme fluctuations in the demand for
labor or other resources since these fluctuations typically incur high costs
for training, hiring, transportation, and management. Thus, a planner might
alter a schedule through the use of available activity floats so as to level or
smooth out the demand for resources. Resource graphs such as Figure 10-0
provide an invaluable indication of the potential trouble spots and the success
that a scheduler has in avoiding them.
A common difficulty with project network diagrams is that too much
information is available for easy presentation in a network. In a project
with, say, five hundred activities, drawing activities so that they can be seen
without a microscope requires a considerable expanse of paper. A large project
might require the wall space in a room to include the entire diagram. On a
computer display, a typical restriction is that less than twenty activities can
be successfully displayed at the same time. The problem of displaying numerous
activities becomes particularly acute when accessory information such as
activity identifying numbers or phrases, durations and resources are added to
the diagram.
One practical solution to this representation problem is to define sets of
activities that can be represented together as a single activity. That is, for
display purposes, network diagrams can be produced in which one "activity"
would represent a number of real sub-activities. For example, an activity such
as "foundation design" might be inserted in summary diagrams. In the actual
project plan, this one activity could be sub-divided into numerous tasks with
their own precedences, durations and other attributes. These sub-groups are
sometimes termed fragnets for fragments of the full network. The result of
this organization is the possibility of producing diagrams that summarize the
entire project as well as detailed representations of particular sets of
______________________________________________________________________________
Masonry
Unit Size!!Condition(s)!!Maximum Productivity
!!!!Achievable
8 inch Block!!None!!400 Units/Day/Mason
6 inch!!Wall is "long"!!430 Units/Day/Mason
6 inch!!Wall is not "long"!!370 Units/Day/Mason
12 inch!!Non-union labor!!300 Units/Day/Mason
4 inch!!Wall is "long"!!480 Units/Day/Mason
!!Weather is "warm and dry"
!!or high strength mortar is used
4 inch!!Wall is not "long"!!430 Units/Day/Mason
!!Weather is "warm and dry"
!!or high strength mortar is used
4 inch!!Wall is "long"!!370 Units/Day/Mason
!!Weather is not "warm and dry"
!!or high strength mortar is not used
4 inch!!Wall is not "long"!!320 Units/Day/Mason
!!Weather is not "warm and dry"
!!or high strength mortar is not used
8 inch!!Support from existing wall!!1000 Units/Day/Mason
8 inch!!No support from existing wall!!750 Units/Day/Mason
12 inch!!Support from existing wall!!700 Units/Day/Mason
12 inch!!No support from existing wall!!550 Units/Day/Mason
______________________________________________________________________________
______________________________________________________________________________
Impact!!Condition(s)!!Adjustment Magnitude
!!!!(% of Maximum)
Crew type!!Crew type is non-union!! 15%
!!Job is "large"
Crew type!!Crew type is union!! 10%
!!Job is "small"
Supporting labor!!Less than 2 laborers per crew!! 20%
Supporting labor!!More than 2 masons/laborer!! 10%
Elevation!!Steel frame building!! 10%
!!Exterior wall
!!"Insufficient" support labor
Elevation!!Solid-masonry building!! 12%
!!Exterior wall
!!Non-union labor
Visibility!!Block is not covered!! 7%
Temperature!!Temperature is below 45@+(o) F.!! 15%
Temperature!!Temperature is above 85@+(o) F.!! 10%
Brick texture!!Bricks are baked high!! 10%
!!Weather is cold or moist
______________________________________________________________________________
______________________________________________________________________________
0 Conditions of the Contract!!9 Finishes
1 General requirements!!10 Specialties
2 Site Work!!11 Equipment
3 Concrete!!12 Furnishings
4 Masonry!!13 Special Construction
5 Metals!!14 Conveying system
6 Carpentry!!15 Mechanical
7 Moisture prevention!!16 Electrical
8 Doors, windows and glass
______________________________________________________________________________
02-010!!Subsurface Exploration!!02-600!!Paving and Surfacing
!!02-011!!!!Borings!!!!02-610!!!!Paving
!!02-012!!!!Core Drilling!!!!02-620!!!!Curbs and Gutters
!!02-013!!!!Standard Penetration Tests!!!!02-630!!!!Walks
!!02-014!!!!Seismic Exploration!!!!02-640!!!!Synthetic Surfacing
02-100!!Clearing!!02-700!!Site Improvements
!!02-101!!!!Structure Moving!!02-710!!!!Fences and Gates
!!02-102!!!!Clearing and Grubbing!!!!02-720!!!!Road and Pkg Misc.
!!02-103!!!!Tree Pruning!!!!02-730!!!!Playing Fields
!!02-104!!!!Shrub and Tree Relocation!!!!02-740!!!!Fountains
!!!!!!!!02-750!!!!Irrigation Systems
02-100!!Demolition!!!!02-760!!!!Site Furnishings
02-200!!Earthwork!!02-800!!Landscaping
!!02-210!!!!Site Grading!!!!02-810!!!!Soil Preparation
!!02-211!!!!Rock Removal!!!!02-820!!!!Lawns
!!02-212!!!!Embankment!!!!02-830!!!!Other vegetation
!!02-220!!!!Excavating and Backfilling
!!02-221!!!!Trenching!!02-850!!Railroad Work
!!02-222!!!!Structure Excavation!!!!02-851!!!!Trackwork
!!02-223!!!!Roadway Excavation!!!!02-852!!!!Ballasting
!!02-224!!!!Pipe Boring and Jacking
!!02-227!!!!Waste Material Disposal!!02-900!!Marine Work
!!02-230!!!!Soil Compaction Control!!!!02-910!!!!Docks
!!02-240!!!!Soil Stabilization!!!!02-920!!!!Boat Facilities
!!!!!!!!!!02-930!!!!Prot. Marine Strucs.
!!02-250!! Soil Treatment!!!!02-931!!!!Fenders
!!02-251!!!!Termite Control!!!!02-932!!!!Seawalls
!!02-252!!!!Vegetation Control!!!!02-933!!!!Groins
!!!!!!!!!!02-934!!!!Jettys
02-300!!Pile Foundations!!!!02-940!!!!Dredging
02-350!!Caissons!!02-950!!Tunneling
!!02-351!!!!Drilled Caissons!!!!02-960!!!!Tunnel Excavation
!!02-352!!!!Excavated Caissons!!!!02-970!!!!Tunnel Grouting
02-400!!Shoring!!02-980!!!!Support Systems
!!02-402!!!!Underpinning
02-500!!Site Drainage
02-550!!Site Utilities
______________________________________________________________________________
Event Numbering Algorithm
Step 1: Give the starting event number 0.
Step 2: Give the next number to any unnumbered event whose
predecessor events are each already numbered.
Repeat Step 2 until all events are numbered.
Earliest Event Time Algorithm
Step 1: Let E(0) = 0.
Step 2: For j = 1,2,3,@+(...),n (where n is the last event), let
E(j) = maximum {E(i) + D@-(ij)}
where the maximum is computed over all activities
(i,j) that have j as the ending event.
Latest Event Time Algorithm
Step 1: Let L(n) equal the required completion time of the project.
Note: L(n) must equal or exceed E(n).
Step 2: For i = n-1, n-2, ..., 0, let
L(i) = minimum {L(j) - D@-(ij)}
where the minimum is computed over all activities
(i,j) that have i as the starting event.
______________________________________________________________________________
______________________________________________________________________________
Activity!!! Description!!! Predecessors!!!
A!!!Site clearing !!! -!!!
B!!!Removal of trees!!! -!!!
C!!!General excavation!!! A!!!
D!!!Grading general area!!! A!!!
E!!!Excavation for trenches!!! B,C!!!
F!!!Placing formwork and reinforcement!!!
B,C!!!
!!! for concrete
G!!!Installing sewer lines!!! D,E!!!
H!!!Installing other utilities!!! D,E!!!
I!!!Pouring concrete!!! F,G!!!
______________________________________________________________________________
______________________________________________________________________________
Activity!!! Duration!!!
Earliest Start!!! Latest Finish!!!
Latest Start
!!!D@-(i,j)!!! Time E(i)=ES(ij)!!!
Time L(j)=LF(ij)!!! Time LS(i,j)
A (0,1)!!! 4!!! 0!!! 4*!!! 0*
B (0,2)!!! 3!!! 0!!! 12!!! 9
C (1,2)!!! 8!!! 4!!! 12*!!! 4*
D (1,3)!!! 7!!! 4!!! 22!!! 15
E (2,3)!!! 9!!! 12!!! 22!!! 13
F (2,4)!!! 12!!! 12!!! 24*!!! 12*
G (3,4)!!! 2!!! 21!!! 24!!! 22
H (3,5)!!! 5!!! 21!!! 30!!! 25
I (4,5)!!! 6!!! 24!!! 30*!!! 24*
*Activity on a critical path since E(i) + D@-(i,j) = L(j).
______________________________________________________________________________
______________________________________________________________________________
Activity!!! Description!!!
Predecessors!!! Duration
A!!!Preliminary design!!! -!!! 6
B!!!Evaluation of design!!! A!!! 1
C!!!Contract negotiation!!! -!!! 8
D!!!Preparation of fabrication plant!!! C!!! 5
E!!!Final design!!! B,C!!! 9
F!!!Fabrication of Product!!! D,E!!! 12
G!!!Shipment of Product to owner!!! F!!! 3
____________________________________________________________________________
______________________________________________________________________________
Node!!! Earliest Time E(i)!!! Latest Time L(j)
0!!! 0!!! 0
1!!! 6!!! 7
2!!! 8!!! 8
3!!! 8!!! 8
4!!! 17!!! 17
5!!! 29!!! 29
6!!! 32!!! 32
______________________________________________________________________________
______________________________________________________________________________
!!! Earliest Start!!! Latest Start!!!
Free!!! Independent!!! Total
Activity!!! Time ES(i,j)!!!
Time LS(i,j)!!! Float!!! Float!!! Float
A (0,1)!!! 0!!! 1!!! 0!!! 1!!! 1
B (1,3)!!! 6!!! 7!!! 1!!! 1!!! 1
C (0,2)!!! 0!!! 0!!! 0!!! 0!!! 0
D (2,4)!!! 8!!! 12!!! 4!!! 4!!! 4
E (3,4)!!! 8!!! 8!!! 0!!! 0!!! 0
F (4,5)!!! 17!!! 17!!! 0!!! 0!!! 0
G (5,6)!!! 29!!! 29!!! 0!!! 0!!! 0
X (2,3)!!! 8!!! 8!!! 0!!! 0!!! 0
______________________________________________________________________________
An example figure of a sub-network appears in Figure 10-0. Summary displays
would include only a single node A to represent the set of activities in the
sub-network. Note that precedence relationships shown in the master network
would have to be interpreted with care since a particular precedence might be
due to an activity that would not commence at the start of activity on the
sub-network.
The use of graphical project representations is an important and extremely
useful aid to planners and managers. Of course, detailed numerical reports may
also be required to check the peculiarities of particular activities. But
graphs and diagrams provide an invaluable means of rapidly communicating or
understanding a project schedule. With computer based storage of basic project
data, graphical output is readily obtainable and should be used whenever
possible.
Finally, the scheduling procedure described in Section 10.3 simply counted
days from the initial starting point. Practical scheduling programs include a
calendar conversion to provide calendar dates for scheduled work as well as the
number of days from the initiation of the project. This conversion can be
accomplished by establishing a one-to-one correspondence between project dates
and calendar dates. For example, project day 2 would be May 4 if the project
began at time 0 on May 2 and no holidays intervened. In this calendar
conversion, weekends and holidays would be excluded from consideration for
scheduling, although the planner might overrule this feature. Also, the number
of work shifts or working hours in each day could be defined, to provide
consistency with the time units used is estimating activity durations. Project
reports and graphs would typically use actual calendar days.
Building on the critical path scheduling calculations described in the
previous sections, some additional capabilities are useful. Desirable
extensions include the definition of allowable windows for activities and the
introduction of more complicated precedence relationships among activities.
For example, a planner may wish to have an activity of removing formwork from a
new building component follow the concrete pour by some pre-defined lag period
to allow setting. This delay would represent a required gap between the
completion of a preceding activity and the start of a successor. The
scheduling calculations to accommodate these complications will be described in
this section. Again, the standard critical path scheduling assumptions of
fixed activity durations and unlimited resource availability will be made here,
although these assumptions will be relaxed in later sections.
A capability of many scheduling programs is to incorporate types of activity
interactions in addition to the straightforward predecessor finish to successor
start constraint used in Section 10.3. Incorporation of additional categories
of interactions is often called precedence diagramming.[See K.C. Crandall,
"Project Planning with Precedence Lead/Lag Factors," Project Management
Quarterly, Vol. 4, No. 3, Sept. 1973, pp. 18-27, or J.J. Moder, C.R.
Phillips, and E.W. Davis, Project Management with CPM, PERT and Precedence
Diagramming, New York: Van Nostrand Reinhold Company, third edition, 1983,
chapter 4.] For example, it may be the case that installing concrete forms in
a foundation trench might begin a few hours after the start of the trench
excavation. This would be an example of a start-to-start constraint with a
lead: the start of the trench-excavation activity would lead the start of the
concrete-form-placement activity by a few hours. Eight separate categories of
precedence constraints can be defined, representing greater than (leads) or
less than (lags) time constraints for each of four different inter-activity
relationships. These relationships are summarized in Table 10-0. Typical
precedence relationships would be:
!!! Relationship!!! Explanation
!!!Finish-to-start Lead
!!!!!!Latest Finish of Predecessor G Earliest Start of Successor + FS
!!!Finish-to-start Lag
!!!!!!Latest Finish of Predecessor L Earliest Start of Successor + FS
!!!Start-to-start Lead
!!!!!!Earliest Start of Predecessor G Earliest Start of Successor + SS
!!!Start-to-start Lag
!!!!!!Earliest Start of Predecessor L Earliest Start of Successor + SS
!!!Finish-to-finish Lead
!!!!!!Latest Finish of Predecessor G Earliest Finish of Successor + FF
!!!Finish-to-finish Lag
!!!!!!Latest Finish of Predecessor L Earliest Finish of Successor + FF
!!!Start-to-finish Lead
!!!!!!Earliest Start of Predecessor G Earliest Finish of Successor + SF
!!!Start-to-finish Lag
!!!!!!Earliest Start of Predecessor L Earliest Finish of Successor + SF
The computations with these lead and lag constraints are somewhat more
complicated variations on the basic calculations defined in Table 10-0 for
critical path scheduling. For example, a start-to-start lead would modify the
calculation of the earliest start time to consider whether or not the necessary
lead constraint was met: The possibility of interrupting or splitting activities into two work
segments can be particularly important to insure feasible schedules in the case
of numerous lead or lag constraints. With activity splitting, an activity is
divided into two sub-activities with a possible gap or idle time between work
on the two subactivities. The computations for scheduling treat each
sub-activity separately after a split is made. Splitting is performed to
reflect available scheduling flexibility or to allow the development of a
feasible schedule. For example, splitting may permit scheduling the early
finish of a successor activity at a date later than the earliest start of the
successor plus its duration. In effect, the successor activity is split into
two segments with the later segment scheduled to finish after a particular
time. Most commonly, this occurs when a constraint involving the finish time
of two activities determines the required finish time of the successor. When
this situation occurs, it is advantageous to split the successor activity into
two so the first part of the successor activity can start earlier but still
finish in accordance with the applicable finish-to-finish constraint.
Finally, the definition of activity windows can be extremely useful. An
activity window defines a permissible period in which a particularly activity
may be scheduled. To impose a window constraint, a planner could specify an
earliest possible start time for an activity (WES) or a latest possible
completion time (WLF). Latest possible starts (WLS) and earliest possible
finishes (WEF) might also be imposed. In the extreme, a required start time
might be insured by setting the earliest and latest window start times equal
(WES = WLS). These window constraints would be in addition to the time
constraints imposed by precedence relationships among the various project
activities. Window constraints are particularly useful in enforcing milestone
completion requirements on project activities. For example, a milestone
activity may be defined with no duration but a latest possible completion time.
Any activities preceding this milestone activity cannot be scheduled for
completion after the milestone date. Window constraints are actually a special
case of the other precedence constraints summarized above: windows are
constraints in which the precedecessor activity is the project start. Thus, an
earliest possible start time window (WES) is a start-to-start lead.
One related issue is the selection of an appropriate network representation.
Generally, the activity-on-branch representation will lead to a more compact
diagram and is also consistent with other engineering network representations
of structures or circuits.[See C.T. Hendrickson and B.N. Janson, "A Common
Network Formulation of Several Civil Engineering Problems," Civil Engineering
Systems, Vol. 1, No. 4, 1984, pp. 195-203.] For example, the nine activities
shown in Figure 10-0 result in an activity-on-branch network with six nodes and
nine branches. In contrast, the comparable activity-on-node network shown in
Figure 9-0 has eleven nodes (with the addition of a node for project start and
completion) and fifteen branches. The activity-on-node diagram is more
complicated and more difficult to draw, particularly since branches must be
drawn crossing one another. Despite this larger size, an important practical
reason to select activity-on-node diagrams is that numerous types of precedence
relationships are easier to represent in these diagrams. For example,
different symbols might be used on each of the branches in Figure 9-0 to
represent direct precedences, start-to-start precedences, start-to-finish
precedences, etc. Alternatively, the beginning and end points of the
precedence links can indicate the type of lead or lag precedence relationship.
Another advantage of activity-on-node representations is that the introduction
of dummy links as in Figure 10-0 is not required. Either representation can be
used for the critical path scheduling computations described earlier. In the
absence of lead and lag precedence relationships, it is more common to select
the compact activity-on-branch diagram, although a unified model for this
purpose is described in Chapter 11. Of course, one reason to pick
activity-on-branch or activity-on-node representations is that particular
computer scheduling programs available at a site are based on one
representation or the other. Since both representations are in common use,
project managers should be familiar with either network representation.
Many commercially available computer scheduling programs include the
necessary computational procedures to incorporate windows and many of the
various precedence relationships described above. Indeed, the term "precedence
diagramming" and the calculations associated with these lags seems to have
first appeared in the user's manual for a computer scheduling program.[See IBM,
Project Management System, Application Description Manual, (H20-0210), IBM,
1968.] If the construction plan suggests that such complicated lags are
important, then these scheduling algorithms should be adopted. In the next
section, the various computations associated with critical path scheduling with
several types of leads, lags and windows are presented.
Table 10-0 contains an algorithmic description of the calculations required
for critical path scheduling with leads, lags and windows. This description
assumes an activity-on-node project network representation, since this
representation is much easier to use with complicated precedence relationships.
The possible precedence relationships accomadated by the procedure contained in
Table 10-0 are finish-to-start leads, start-to-start leads, finish-to-finish
lags and start-to-finish lags. Windows for earliest starts or latest finishes
are also accomadated. Incorporating other precedence and window types in a
scheduling procedure is also possible as described in Chapter 11. With an
activity-on-node representation, we assume that an initiation and a termination
activity are included to mark the beginning and end of the project. The set of
procedures described in Table 10-0 does not provide for automatic splitting of
activities.
The first step in the scheduling algorithm is to sort activities such that
no higher numbered activity precedes a lower numbered activity. With numbered
activities, durations can be denoted D(k), where k is the number of an
activity. Other activity information can also be referenced by the activity
number. Note that node events used in activity-on-branch representations are
not required in this case.
The forward pass calculations compute an earliest start time (ES(k)) and an
earliest finish time (EF(k)) for each activity in turn (Table 10-0). In
computing the earliest start time of an activity k, the earliest start window
time (WES), the earliest finish window time (WEF), and each of the various
precedence relationships must be considered. Constraints on finish times are
included by identifying minimum finish times and then subtracting the activity
duration. A default earliest start time of day 0 is also insured for all
activities. A second step in the procedure is to identify each activity's
earliest finish time (EF(k)).
The backward pass calculations proceed in a manner very similar to those of
the forward pass (Table 10-0). In the backward pass, the latest finish and the
latest start times for each activity are calculated. In computing the latest
finish time, the latest start time is identified which is consistent with
precedence constraints on an activity's starting time. This computation
requires a minimization over applicable window times and all successor
activities. A check for a feasible activity schedule can also be imposed at
this point: if the late start time is less than the early start time (LS(k) <
ES(k)), then the activity schedule is not possible.
The result of the forward and backward pass calculations are the earliest
start time, the latest start time, the earliest finish time, and the latest
finish time for each activity. The activity float is computed as the latest
start time less the earliest start time. Note that window constraints may be
instrumental in setting the amount of float, so that activities without any
float may either lie on the critical path or be constrained by an allowable
window.
To consider the possibility of activity splitting, the various formulas for
the forward and backward passes in Table 10-0 must be modified. For example,
the possibility of activity splitting due to finish-to-start (FS) and
start-to-start lead (SS) precedences must be considered. Considering
start-to-start precedence relationships is somewhat complicated since it is
important to insure that the preceding activity has been underway for at least
the required lead period of SF(i,k). If the preceding activity was split and
the first sub-activity was not underway for a sufficiently long period, then
the following activity cannot start until the first plus the second
sub-activities have been underway for a period equal to SF(i,k). Thus, in
setting the earliest start time for an activity, the calculation takes into
account the duration of the first subactivity (DA(i)) for preceding activities
involving a start-to-start lead. Algebraically, the term in the earliest start
time calculation pertaining to start-to-start precedence constraints (ES(i) +
SS(i,k)) has two parts with the possibility of activity splitting: The computation of earliest finish time involves similar considerations,
except that the finish-to-finish and start-to-finish lag constraints are
involved. In this case, a maximization over the following terms is required: Another possible extension of the scheduling computations in Table 10-0
would be to include a duration modification capability during the forward and
backward passes. This capability would permit alternative work calendars for
different activities or for modifications to reflect effects of time of the
year on activity durations. For example, the duration of outside work during
winter months would be increased. As another example, activities with weekend
work permitted might have their weekday durations shortened to reflect weekend
work accomplishments.
Example 10-4: Impacts of precedence relationships and windows
To illustrate the impacts of different precedence relationships and windows,
consider a project consisting of only two activities in addition to the start
and finish. The start is numbered activity 0, the first activity is number 1,
the second activity is number 2, and the finish is activity 3. Each activity
is assumed to have a duration of five days. With a direct finish-to-start
precedence relationship without a lag, the critical path calculations reveal:
With a start-to-start precedence constraint with a two day lead, the
scheduling calculations are:
Finally, suppose that a finish-to-finish precedence relationship exists
between activity 1 and activity 2 with a two day lag. The scheduling
calculations are:
Example 10-5: Scheduling in the presence of leads, lags and windows.
As a second example of the scheduling computations involved in the presence
of leads, lags and windows, we shall perform the calculations required for the
project shown in Figure 10-0. Start and end activities are included in the
project diagram, making a total of eleven activities. The various windows and
durations for the activities are summarized in Table 10-0; and the precedence
relationships appear in Table 10-0. Only earliest start (WES) and latest
finish (WLF) window constraints are included in this example problem. All four
types of precedence relationships are included in this project. Note that two
activities may have more than one type of precedence relationship at the same
time; in this case, activities 2 and 5 have both S-S and F-F precedences. In
Figure 10-0, the different precedence relationships are shown by links
connecting the activity nodes. The type of precedence relationship is
indicated by the beginning or end point of each arrow. For example,
start-to-start precedences go from the left portion of the preceding activity
to the left portion of the following activity. Application of the activity
sorting algorithm (Table 10-0) reveals that the existing activity numbers are
appropriate for the critical path algorithm. These activity numbers will be
used in the forward and backward pass calculations.
During the forward pass calculations (Table 10-0), the earliest start and
earliest finish times are computed for each activity. The relevant
calculations are:
The backward pass computations result in the latest finish and latest start
times for each activity. These calculations are:
The earliest and latest start times for each of the activities are
summarized in Table 10-0. Activities without float are 0, 1, 6, 9 and 10.
These activities also constitute the critical path in the project. Note that
activities 6 and 9 are related by a finish-to-finish precedence with a 4 day
lag. Decreasing this lag would result in a reduction in the overall project
duration.
Resource constrained scheduling should be applied whenever there are limited
resources available for a project and the competition for these resources among
the project activities is keen. In effect, delays are liable to occur in such
cases as activities must wait until common resources become available. To the
extent that resources are limited and demand for the resource is high, this
waiting may be considerable. In turn, the congestion associated with these
waits represents increased costs, poor productivity and, in the end, project
delays. Schedules made without consideration for such bottlenecks can be
completely unrealistic.
Resource constrained scheduling is of particular importance in managing
multiple projects with fixed resources of staff or equipment. For example, a
design office has an identifiable staff which must be assigned to particular
projects and design activities. When the workload is heavy, the designers may
fall behind on completing their assignments. Government agencies are
particularly prone to the problems of fixed staffing levels, although some
flexibility in accomplishing tasks is possible through the mechanism of
contracting work to outside firms. Construction activities are less
susceptible to this type of problem since it is easier and less costly to hire
additional personnel for the (relatively) short duration of a construction
project. Overtime or double shift work also provide some flexibility.
Resource oriented scheduling also is appropriate in cases in which unique
resources are to be used. For example, scheduling excavation operations when
one only excavator is available is simply a process of assigning work tasks or
job segments on a day by day basis while insuring that appropriate precedence
relationships are maintained. Even with more than one resource, this manual
assignment process may be quite adequate. However, a planner should be careful
to insure that necessary precedences are maintained.
Resource constrained scheduling represents a considerable challenge and
source of frustration to researchers in mathematics and operations research.
While algorithms for optimal solution of the resource constrained problem
exist, they are generally too computationally expensive to be practical for all
but small networks (of less than about 100 nodes).(A variety of mathematical
programming techniques have been proposed for this problem. For a review and
comparison, see J.H. Patterson, "A Comparison of Exact Approaches for Solving
the Multiple Constrained Resource Project Scheduling Problem," Management
Science, Vol. 30, No. 7, 1984, pp. 854-867.) The difficulty of the resource
constrained project scheduling problem arises from the combinatorial explosion
of different resource assignments which can be made and the fact that the
decision variables are integer values representing all-or-nothing assignments
of a particular resource to a particular activity. In contrast, simple
critical path scheduling deals with continuous time variables. Construction
projects typically involve many activities, so optimal solution techniques for
resource allocation are not practical.
One possible simplification of the resource oriented scheduling problem is
to ignore precedence relationships. In some applications, it may be impossible
or unnecessary to consider precedence constraints among activities. In these
cases, the focus of scheduling is usually on efficient utilization of project
resources. To insure minimum cost and delay, a project manager attempts to
minimize the amount of time that resources are unused and to minimize the
waiting time for scarce resources. This resource oriented scheduling is often
formalized as a problem of "job shop" scheduling in which numerous tasks are to
be scheduled for completion and a variety of discrete resources need to perform
operations to complete the tasks. Reflecting the original orientation towards
manufacturing applications, tasks are usually referred to as "jobs" and
resources to be scheduled are designated "machines." In the provision of
constructed facilities, an analogy would be an architectural/engineering design
office in which numerous design related tasks are to be accomplished by
individual professionals in different departments. The scheduling problem is
to insure efficient use of the individual professionals (i.e. the resources)
and to complete specific tasks in a timely manner.
The simplest form of resource oriented scheduling is a reservation system
for particular resources. In this case, competing activities or users of a
resource pre-arrange use of the resource for a particular time period. Since
the resource assignment is known in advance, other users of the resource can
schedule their activities more effectively. The result is less waiting or
"queuing" for a resource. It is also possible to inaugurate a preference
system within the reservation process so that high-priority activities can be
accomadated directly.
In the more general case of multiple resources and specialized tasks,
practical resource constrained scheduling procedures rely on heuristic
procedures to develop good but not necessarily optimal schedules. While this
is the occasion for considerable anguish among researchers, the heuristic
methods will typically give fairly good results. An example heuristic method
is provided in the next section. Manual methods in which a human scheduler
revises a critical path schedule in light of resource constraints can also work
relatively well. Given that much of the data and the network representation
used in forming a project schedule are uncertain, the results of applying
heuristic procedures may be quite adequate in practice.
Example 10-6: A Reservation System[This example is adapted from
H. Smallowitz, "Construction by Computer," Civil Engineering, June, 1986, pp.
71-73.]
A recent construction project for a high-rise building complex in New York
City was severely limited in the space available for staging materials for
hauling up the building. On the four building site, thirty-eight separate
cranes and elevators were available, but the number of movements of men,
materials and equipment was expected to keep the equipment very busy. With
numerous sub-contractors desiring the use of this equipment, the potential for
delays and waiting in the limited staging area was considerable. By
implementing a crane reservation system, these problems were nearly entirely
avoided. The reservation system required contractors to telephone one or more
days in advance to reserve time on a particular crane. Time were available on
a first-come, first-served basis (i.e. first call, first choice of available
slots). Penalties were imposed for making an unused reservation. The
reservation system was also computerized to permit rapid modification and
updating of information as well as the provision of standard reservation
schedules to be distributed to all participants.
Example 10-7: Heuristic Resource Allocation
Suppose that a project manager has eleven pipe sections for which necessary
support structures and materials are available in a particular week. To work
on these eleven pipe sections, five crews are available. The allocation
problem is to assign the crews to the eleven pipe sections. This allocation
would consist of a list of pipe sections allocated to each crew for work plus a
recommendation on the appropriate sequence to undertake the work. The project
manager might make assignments to minimize completion time, to insure
continuous work on the pipeline (so that one section on a pipeline run is not
left incomplete), to reduce travel time between pipe sections, to avoid
congestion among the different crews, and to balance the workload among the
crews. Numerous trial solutions could be rapidly generated, especially with
the aid of an electronic spreadsheet. For example, if the nine sections had
estimated work durations for each of the fire crews as shown in Table 10-0,
then the allocations shown in Figure 10-0 would result in a minimum completion
time.
Example 10-8: Algorithms for Resource Allocation with Bottleneck Resources
In the previous example, suppose that a mathematical model and solution was
desired. For this purpose, we define a binary (i.e. 0 or 1 valued) decision
variable for each pipe section and crew, x@-(ij), where x@-(ij) = 1 implies
that section i was assigned to crew j and x@-(ij) = 0 implied that section i
was not assigned to crew j. The time required to complete each section is
t@-(i). The overall time to complete the nine sections is denoted z. In this
case, the problem of minimizing overall completion time is:
The previous section outlined resource oriented approaches to the scheduling
problem. In this section, we shall review some general approaches to
integrating both concerns in scheduling.
Two problems arise in developing a resource constrained project schedule.
First, it is not necessarily the case that a critical path schedule is
feasible. Because one or more resources might be needed by numerous
activities, it can easily be the case that the shortest project duration
identified by the critical path scheduling calculation is impossible. The
difficulty arises because critical path scheduling assumes that no resource
availability problems or bottlenecks will arise. Finding a feasible or
possible schedule is the first problem in resource constrained scheduling. Of
course, there may be a numerous possible schedules which conform with time and
resource constraints. As a second problem, it is also desirable to determine
schedules which have low costs or, ideally, the lowest cost.
Numerous heuristic methods have been suggested for resource constrained
scheduling. Many begin from critical path schedules which are modified in
light of the resource constraints. Others begin in the opposite fashion by
introducing resource constraints and then imposing precedence constraints on
the activities. Still others begin with a ranking or classification of
activities into priority groups for special attention in scheduling.[For
discussions and comparisons of alternative heuristic algorithms, see E.M.
Davies, "An experimental investigation of resource allocation in multiactivity
projects," Operational Research Quarterly Vol. 24, No. 11, July 1976, pp.
1186-1194; J.D. Wiest and F.K. Levy, A Management Guide to PERT/CPM,
Prentice-Hall, New Jersey, 1977; or S.R. Lawrence, A Computational Comparison
of Heuristic Scheduling Techniques, Technical Report, Graduate School of
Industrial Administration, Carnegie-Mellon University, 1985.] One type of
heuristic may be better than another for different types of problems.
Certainly, projects in which only an occasional resource constraint exists
might be best scheduled starting from a critical path schedule. At the other
extreme, projects with numerous important resource constraints might be best
scheduled by considering critical resources first. A mixed approach would be
to proceed simultaneously considering precedence and resource constraints.
A simple modification to critical path scheduling has been shown to be
effective for a number of scheduling problems and is simple to implement. For
this heuristic procedure, critical path scheduling is applied initially. The
result is the familiar set of possible early and late start times for each
activity. Scheduling each activity to begin at its earliest possible start
time may result in more than one activity requiring a particular resource at
the same time. Hence, the initial schedule may not be feasible. The heuristic
proceeds by identifying cases in which activities compete for a resource and
selecting one activity to proceed. The start time of other activities are then
shifted later in time. A simple rule for choosing which activity has priority
is to select the activity with the earliest CPM late start time (calculated as
LS(i,j) = L(j)-D@-(ij)) among those activities which are both feasible (in that
all their precedence requirements are satisfied) and competing for the
resource. This decision rule is applied from the start of the project until
the end for each type of resource in turn.
The order in which resources are considered in this scheduling process may
influence the ultimate schedule. A good heuristic to employ in deciding the
order in which resources are to be considered is to consider more important
resources first. More important resources are those that have high costs or
that are likely to represent an important bottleneck for project completion.
Once important resources are scheduled, other resource allocations tend to be
much easier. The resulting scheduling procedure is described in Table 10-0.
The late start time heuristic described in Table 10-0 is only one of many
possible scheduling rules. It has the advantage of giving priority to
activities which must start sooner to finish the project on time. However, it
is myopic in that it doesn't consider trade-offs among resource types nor the
changes in the late start time that will be occurring as activities are shifted
later in time. More complicated rules can be devised to incorporate broader
knowledge of the project schedule. These complicated rules require greater
computational effort and may or may not result in scheduling improvements in
the end.
Example 10-9: Resource constrained scheduling with nine activities.
As an example of resource constrained scheduling, we shall re-examine the
nine activity project discussed in Section 10.3. To begin with, suppose that
four workers and two pieces of equipment such as backhoes are available for the
project. The required resources for each of the nine project activities are
summarized in Table 10-0. Graphs of resource requirements over the 30 day
project duration are shown in Figure 10-0. Equipment availability in this
schedule is not a problem. However, on two occasions, more than the 4
available workers are scheduled for work. Thus, the existing project schedule
is infeasible and should be altered.
The first resource problem occurs on day 21 when activity F is underway and
activities G and H are scheduled to start. Applying the latest start time
heuristic to decide which activity should start, the manager should re-schedule
activity H since it has a later value of LS(i,j), i.e., day 25 versus day 22 as
seen in Table 10-0. Two workers become available on day 23 after the
completion of activity G. Since activity H is the only activity which is
feasible at that time, it is scheduled to begin. Two workers also become
available on day 24 at the completion of activity F. At this point, activity I
is available for starting. If possible, it would be scheduled to begin with
only two workers until the completion of activity H on day 28. If all 4
workers were definitely required, then activity I would be scheduled to begin
on day 28. In this latter case, the project duration would be 34 days,
representing a 4 day increase due to the limited number of workers available.
Example 10-10: Additional resource constraints.
As another example, suppose that only one piece of equipment was available
for the project. As seen in Figure 10-0, the original schedule would have to
be significantly modified in this case. Application of the resource
constrained scheduling heuristic proceeds as follows as applied to the original
project schedule:
P10-1 to P10-4. Construct an activity-on-branch network from the precedence
relationships of activities in the project given in the table for the problem,
Tables P10-1 to P10-4.
P10-5 to P10-8. Determine the critical path and all slacks for the projects
in Tables P10-1 to P10-4.
P10-9. Suppose that the precedence relationships for Problem P10-1 in Table
P10-1 are all direct finish-to-start relationships with no lags except for the
following:
P10-10. Suppose that the precedence relationships for Problem P10-2 in
Table P10-2 are all direct finish-to-start relationships with no lags except
for the following:
P10-11 to P10-12. For the projects described in Tables P10-11 and P10-12,
respectively, suggest a project schedule that would complete the project in
minimum time and result in relatively constant or level requirements for labor
over the course of the project.
P10-13. Develop a spreadsheet template that lists activity name, duration,
required resources, earliest possible start, latest possible start, and
scheduled start in separate columns for a maximum of twenty activities. By
means of formulas, also develop the required resources for each day of the
project, based on the activities' scheduled start, expected durations, and
required resources. Use the spreadsheet graphics facility to plot the required
resources over time. Use your template to solve Problems P10-11 and P10-12 by
altering scheduled start times. (Hint: One way to prepare such a template is
to use a column to represent a single day with each cell in the column
indicating resources required by a particular activity on the particular day).
P10-14. Develop an example of a project network with three critical paths.
P10-15. For the project defined in Table P10-11, suppose that you are
limited to a maximum of 20 workers at any given time. Determine a desirable
schedule for the project, using the late start time heuristic described in
Section 10.9.
P10-16. For the project defined in Table P10-12, suppose that you are
limited to a maximum of 15 workers at any given time. Determine a desirable
schedule for the project, using the late start time heuristic described in
Section 10.9.
P10-17. The examples and problems presented in this chapter generally make
use of activity duration and project durations as measured in working days from
the beginning of the project. Outline the procedures by which time measured in
working days would be converted into calendar days with single- or double-shift
work. Could your procedure be modified to allow some but not all activities to
be underway on weekends?
Construction project scheduling is a topic that has received extensive
research over a number of decades. The previous chapter described the
fundamental scheduling techniques widely used and supported by numerous
commercial scheduling systems. A variety of special techniques have also been
developed to address specific circumstances or problems. With the availability
of more powerful computers and software, the use of advanced scheduling
techniques is becoming easier and of greater relevance to practice. In this
chapter, we survey some of the techniques that can be employed in this regard.
These techniques address some important practical problems, such as:
As descriped in Chapter 10, the activity-on-node (or precedence diagram) and
the activity-on-branch (or arrow diagram) network models are alternative
activity network representations. Numerous commercial scheduling software
systems allow users to input network information and to view network graphs
employing either representation. Virtually any graphic illustration of an
activity network (arrow diagram, bar chart, etc.) can be generated from either
network model, as described in Section 10.5. However, solution methods,
network topology, and types of allowable precedences differ in the two methods.
In this section, a unified activity network model is presented in which each
activity is represented by a start node, a finish node and an intervening link.
Precedence relationships and activity window constraints are also represented
by links. Project milestones can be modelled as nodes in the activity network.
This representation originated in work supporting the generation of project
plans so that partial plans and plans at different levels of abstraction could
be more easily represented. Even without consideration of the plan generation
problem, the unified representation model has some distinct advantages.
The basic unified activity network method is identical in form to a basic
critical path model (CPM) with activities on branches. Nodes represent events,
including a project start and a project completion node. Links are
characterized by a duration and the preceding event time plus the duration must
be less than the succeeding event time for each link.
While the CPM and unified model structures are similar, the interpretation
of network elements is different. Figure 11-0 illustrates a small unified
network with two activities i and j. In this model, nodes represent project
milestone events (such as the project start PS and project finish PF nodes).
Links represent activity durations (such as i and j), activity precedences, or
window constraints (which are precedences defined with respect to project
milestones). In particular, the precedences in Figure 11-0 are:
Permitting negative link durations allows an additional eight constraint
types to be represented. With a negative link duration, a maximum precedence
lead is imposed. If event k must occur within a prescribed time period (|#D#|)
time units after event h, then a link from k to h with negative duration
D@-(kh) requires that the time of event k, E@-(k), must be less that or equal
to the time of event h plus a prespecified lead
!!!!EQUATION USED TO BE HERE!!!!!!
As shown in the partial network in Figure 11-0, the additional links 9 to 16
represent the following constraints:
The possibility of activity splitting also deserves mention. In Figure
11-0, activities are implicitly assumed to be amenable to splitting: the only
constraint is that the activity start time does not precede the start node
event time and the activity finish occurs by the finish node event time.
Activity splitting implies that an activity can be started, stopped and then
re-started without penalty. To prohibit the possibility of splitting, an
activity can be represented by a positive and a negative link as in Figure
11-0. In this case, the activity start and finish node event times are
separated by exactly the activity duration so that no splitting can occur.
In the absence of negative link durations, the unified model can be solved
with the familiar CPM longest path algorithms involving both forward and
backward passes. Applying a node labelling algorithm such as the algorithm in
Table 10-0 yields the critical path and float times for all nodes (including
activity start and finishes).
Allowing negative link durations permits a greater variety of precedence
relationships, but also complicates the scheduling calculations. For this
situation, a variety of solution algorithms are possible. Table 11-0
summarizes one such algorithm based on a modification of the shortest path
algorithm due originally to Dijkstra.[See, E. Minieka, Optimization Algoirthms
for Networks and Graphs, Marcel Dekker, Inc., 1978, pp. 41-51.] This
algorithm makes a distinction between the longest path to a node found during
the course of the algorithm and the actual longest path to a particular node.
The longest path to a node can be altered during the application of the
algorithm, so the same node may be evaluated numerous times.
The use of a solution method such as the algorithm in Table 11-0 imposes a
considerable additional computational burden. As a result, it may be efficient
to apply a longest path algorithm initially without considering negative
duration links. If the resulting schedule is feasible with respect to the
maximum lead constraints (i.e. links with negative duration), then a more
complicated solution algorithm is not required.
In the unified model, node and link floats may be computed directly. Node
floats represent the amount of time that an event (e.g., the start or finish
of an activity) can be delayed without affecting the total duration of the
project and are computed by subtracting latest event times L(i) from their
corresponding earliest event times E(i). Link floats for both activities and
constraints are obtained by using the following definitions (see Chapter 10):
______________________________________________________________________________
____________________________________________________________________________
______________________________________________________________________________
Activity!!!!!!!!!Earliest Start!!!Latest Finish!!!Activity!!!
Number!!!Predecessors!!!Successors!!!Window!!!Window!!!Duration!!!
0!!!-!!!1,2,4!!!-!!!-!!!0!!!
1!!!0!!!3,4,6!!!-!!!-!!!2!!!
2!!!0!!!3,4,6!!!-!!!-!!!5!!!
3!!!1!!!6!!!2!!!-!!!4!!!
4!!!0!!!7,8!!!-!!!-!!!3!!!
5!!!2,2!!!7,8!!!-!!!16!!!5!!!
6!!!1,3!!!9!!!6!!!16!!!6!!!
7!!!4,5!!!9!!!-!!!-!!!2!!!
8!!!4,5!!!10!!!-!!!-!!!4!!!
9!!!6,7!!!10!!!-!!!16!!!5!!!
10!!!8,9!!!-!!!-!!!-!!!0!!!
______________________________________________________________________________
______________________________________________________________________________
Predecessor!!!Successor!!!Type!!!Lead or Lag!!!
0!!!1!!!F-S!!!0!!!
0!!!2!!!F-S!!!0!!!
0!!!4!!!F-S!!!0!!!
1!!!3!!!S-S!!!1!!!
1!!!4!!!S-F!!!1!!!
1!!!6!!!F-S!!!2!!!
2!!!5!!!S-S!!!2!!!
2!!!5!!!F-F!!!2!!!
3!!!6!!!F-S!!!0!!!
4!!!7!!!S-S!!!2!!!
4!!!8!!!F-S!!!0!!!
5!!!7!!!F-S!!!1!!!
5!!!8!!!S-S!!!3!!!
6!!!9!!!F-F!!!4!!!
7!!!9!!!F-S!!!0!!!
8!!!10!!!F-S!!!0!!!
9!!!10!!!F-S!!!0!!!
______________________________________________________________________________
______________________________________________________________________________
Activity!!! Earliest Start!!! Latest Start!!! Float!!!
0!!! 0!!! 0!!! 0!!!
1!!! 0!!! 0!!! 0!!!
2!!! 0!!! 1!!! 1!!!
3!!! 0!!! 2!!! 2!!!
4!!! 0!!! 6!!! 6!!!
5!!! 2!!! 3!!! 1!!!
6!!! 6!!! 6!!! 0!!!
7!!! 8!!! 9!!! 1!!!
8!!! 5!!! 12!!! 7!!!
9!!! 11!!! 11!!! 0!!!
10!!! 16!!! 16!!! 0!!!
______________________________________________________________________________
!!! Section!!! Work Duration
!!! A !!! 9
!!! B !!! 9
!!! C !!! 8
!!! D !!! 8
!!! E !!! 7
!!! F !!! 7
!!! G !!! 6
!!! H !!! 6
!!! I !!! 5
!!! J !!! 5
!!! K !!! 5
______________________________________________________________________________
____________________________________________________________________________
______________________________________________________________________________
Activity!!! Workers!!! Equipment!!! Earliest!!! Latest!!! Duration
!!! Required!!! Required!!! Start Time!!! Start Time!!!
A!!! 2!!! 0!!! 0!!! 0!!! 4
B!!! 2!!! 1!!! 0!!! 9!!! 3
C!!! 2!!! 1!!! 4!!! 4!!! 8
D!!! 2!!! 1!!! 4!!! 15!!! 7
E!!! 2!!! 1!!! 12!!! 13!!! 9
F!!! 2!!! 0!!! 12!!! 12!!! 12
G!!! 2!!! 1!!! 21!!! 22!!! 2
H!!! 2!!! 1!!! 21!!! 25!!! 5
I!!! 4!!! 1!!! 24!!! 24!!! 6
______________________________________________________________________________
______________________________________________________________________________
Activity!!! Predecessors!!! Duration
A!!! -!!! 6
B!!! A!!! 7
C!!! A!!! 1
D!!! -!!! 14
E!!! B!!! 5
F!!! C,D!!! 8
G!!! C,D!!! 9
H!!! D!!! 3
I!!! H!!! 5
J!!! F!!! 3
K!!! E,J!!! 4
L!!! F!!! 12
M!!! G,I!!! 6
N!!! G,I!!! 2
O!!! L,N!!! 7
______________________________________________________________________________
______________________________________________________________________________
Activity!!! Predecessors!!! Duration
A!!! -!!! 5
B!!! A!!! 6
C!!! B!!! 3
D!!! C!!! 4
E!!! D,G!!! 5
F!!! A!!! 8
G!!! F,J!!! 3
H!!! -!!! 3
I!!! H!!! 2
J!!! I!!! 7
K!!! F,J!!! 2
L!!! H!!! 7
M!!! L!!! 4
N!!! K,M!!! 3
______________________________________________________________________________
______________________________________________________________________________
Activity!!! Predecessors!!! Duration
A!!! -!!! 6
B!!! -!!! 12
C!!! -!!! 16
D!!! A!!! 5
E!!! B!!! 3
F!!! C!!! 10
G!!! B,D!!! 9
H!!! C,E!!! 4
I!!! F!!! 5
J!!! F!!! 3
K!!! E,G,I!!! 10
L!!! H,J!!! 6
______________________________________________________________________________
______________________________________________________________________________
Activity!!! Predecessors!!! Duration
A!!! -!!! 3
B!!! -!!! 6
C!!! -!!! 2
D!!! C!!! 3
E!!! C!!! 8
F!!! B,E!!! 5
G!!! A,F!!! 7
H!!! B,E!!! 10
I!!! B,E!!! 6
J!!! B,E!!! 6
K!!! D,J!!! 8
L!!! G,H!!! 3
M!!! I,K,L!!! 4
______________________________________________________________________________
______________________________________________________________________________
Activity!!! Predecessors!!! Duration!!! Workers
!!!!!!!!! Per Day
A!!! -!!! 3!!! 9
B!!! -!!! 5!!! 6
C!!! -!!! 1!!! 4
D!!! A!!! 1!!! 10
E!!! B!!! 7!!! 16
F!!! B!!! 6!!! 9
G!!! C!!! 4!!! 5
H!!! C!!! 3!!! 8
I!!! D,E!!! 6!!! 2
J!!! F,G!!! 4!!! 3
K!!! H!!! 3!!! 7
______________________________________________________________________________
______________________________________________________________________________
Activity!!! Predecessors!!! Duration!!! Workers
!!!!!!!!! Per Day
A!!! -!!! 5!!! 0
B!!! -!!! 1!!! 3
C!!! -!!! 7!!! 0
D!!! A!!! 2!!! 9
E!!! A!!! 6!!! 5
F!!! A!!! 4!!! 4
G!!! B!!! 3!!! 2
H!!! B!!! 2!!! 14
I!!! C!!! 6!!! 10
J!!! F,G!!! 4!!! 4
K!!! H,I,L!!! 5!!! 1
L!!! F,G!!! 1!!! 2
M!!! D,J!!! 4!!! 7
N!!! E,K!!! 5!!! 3
______________________________________________________________________________
Forward Pass:
Step 1: Set PL(i) = -I and TL(i)
= -I where I is a number
larger than any link duration.
Set TL(PS) = 0.
where PS is the project start node,
PL(i) will be the maximum distance
from PS to node i, and
TL(i) will be the maximum distance
from PS to node i found at intermediate stages.
Step 2: Select node i for which TL(i) is
the maximum among all nodes.
Set PL(i) = TL(i) and TL(i) = -I
For each link originating at node i:
If PL(j) = -I and
PL(i) + D(i,j) > TL(j),
then set TL(j) = PL(i) + D(i,j)
If PL(j) = -I and PL(i)
+ D(i,j) L TL(j),
then do not change the labels on j.
If PL(j) > - I
and PL(i) + D(I,j) > PL(j),
then set PL(j) = -I
and TL(j) = PL(i) + D(i,j)
If PL(j) > -I
and PL(i) + D(i,j) > PL(j),
then do not change the labels on j.
Step 3: Repeat Step 2 until PL(PF)
> -I
where PF is the project finish node.
Step 4: Set the earliest event time
for each node, E(i) = PL(i)
Backward Pass: Repeat application of
the algorithm with the following changes:
l. Reverse each link direction.
2. Start with the project finish node PF with TL(PF) = 0.
3. At the end of step 3, set the
latest event time, L(i) = E(PF) - PL(i) for all nodes i.
(i,j) is equal to the maximum of zero or the value of E(j) - L(i) -
D@-(i,j).
By reducing the number of required link types and special computational
rules, the unified model of activity networks can be a useful simplification.
The network representation also makes activity relationships immediately
apparent. Sixteen different window or precedence relationships can be
accommodated in the model with only one link type. The disadvantages of the
unified model stem from the increased network model size. Nevertheless, the
increasing computational speed and memory capacity of computers used for
project management reduces the effective cost of this size increase.
Example 11-1: Scheduling for a Small Unified Network Model with All
Positive Durations
Figure 11-0 shows an application of the basic unified model to a project
with five activities and twelve precedence links. In the absence of negative
link durations and assuming that all activities are amenable to splitting, the
unified model can be solved with the familiar CPM longest path algorithms
involving both forward and backward passes shown in Table 10-0.
The critical path for this example is: PS##R##SC##R##FC##R##SE##R##PF. The
following observations are directly obtained from the results of the solution
algorithms:
Table 11-0 shows the values of the three floats for constraints and
activities. Some observations are the following:
Example 11-2: Application of the Unifed Model with Some Negative Link
Durations
A common example application of the unified model with maximum durations
occurs when activity splitting is restricted. Figure 11-0 shows the solution
to a modified version of the example of Figure 11-0 for the case in which no
activities are amenable to splitting (e.g. their durations are fixed). In this
second example, the start of activity D has been constrained to be exactly
equal to the finish of activity A. With these assumptions, the total
duration of the project is seventeen time units, and critical path becomes:
PS##R##SD##R##FA##R##FCR##SER##PF. The early start of activity A has been set
to two units even though there is no window constraint imposed on this event.
The reason is that the finish time of activity A is critical and its duration
is fixed.
Section 10.3 described the application of critical path scheduling for the
situation in which activity durations are fixed and known. Unfortunately,
activity durations are estimates of the actual time required, and there is
liable to be a significant amount of uncertainty associated with the actual
durations. During the preliminary planning stages for a project, the
uncertainty in activity durations is particularly large since the scope and
obstacles to the project are still undefined. Activities that are outside of
the control of the owner are likely to be more uncertain. For example, the
time required to gain regulatory approval for projects may vary tremendously.
Other external events such as adverse weather, trench collapses, or labor
strikes make duration estimates particularly uncertain.
Two simple approaches to dealing with the uncertainty in activity durations
warrant some discussion before introducing more formal scheduling procedures to
deal with uncertainty. First, the uncertainty in activity durations may simply
be ignored and scheduling done using the expected or most likely time duration
for each activity. Since only one duration estimate needs to be made for each
activity, this approach reduces the required work in setting up the original
schedule. Formal methods of introducing uncertainty into the scheduling
process require more work and assumptions. While this simple approach might be
defended, it has two drawbacks. First, the use of expected activity durations
typically results in overly optimistic schedules for completion; a numerical
example of this optimism appears below. Second, the use of single activity
durations often produces a rigid, inflexible mindset on the part of schedulers.
As field managers appreciate, activity durations vary considerable and can be
influenced by good leadership and close attention. As a result, field managers
may loose confidence in the realism of a schedule based upon fixed activity
durations. Clearly, the use of fixed activity durations in setting up a
schedule makes a continual process of monitoring and updating the schedule in
light of actual experience imperative. Otherwise, the project schedule is
rapidly outdated.
A second simple approach to incorporation uncertainty also deserves mention.
Many managers recognize that the use of expected durations may result in overly
optimistic schedules, so they include a contingency allowance in their estimate
of activity durations. For example, an activity with an expected duration of
two days might be scheduled for a period of 2.2 days, including a ten percent
contingency. Systematic application of this contingency would result in a ten
percent increase in the expected time to complete the project. While the use
of this rule-of-thumb or heuristic contingency factor can result in more
accurate schedules, it is likely that formal scheduling methods that
incorporate uncertainty more formally are useful as a means of obtaining
greater accuracy or in understanding the effects of activity delays.
The most common formal approach to incorporate uncertainty in the scheduling
process is to apply the critical path scheduling process (as described in
Section 10.3) and then analyze the results from a probabilistic perspective.
This process is usually referred to as the PERT scheduling or evaluation
method.(See D. G. Malcolm, J.H. Rosenbloom, C.E. Clark, and W. Fazar,
"Applications of a Technique for R and D Program Evaluation," Operations
Research, Vol. 7, No. 5, 1959, pp. 646-669.) As noted earlier, the duration
of the critical path represents the minimum time required to complete the
project. Using expected activity durations and critical path scheduling, a
critical path of activities can be identified. This critical path is then used
to analyze the duration of the project incorporating the uncertainty of the
activity durations along the critical path. The expected project duration is
equal to the sum of the expected durations of the activities along the critical
path. Assuming that activity durations are independent random variables, the
variance or variation in the duration of this critical path is calculated as
the sum of the variances along the critical path. With the mean and variance
of the identified critical path known, the distribution of activity durations
can also be computed.
The mean and variance for each activity duration are typically computed from
estimates of "optimistic" (a@-(ij)), "most likely" (m@-(ij)), and "pessimistic"
(b@-(ij)) activity durations using the formulas:
Since absolute limits on the optimistic and pessimistic activity durations
are extremely difficult to estimate from historical data, a common practice is
to use the ninety-fifth percentile of activity durations for these points.
Thus, the optimistic time would be such that there is only a one in twenty
(five percent) chance that the actual duration would be less than the estimated
optimistic time. Similarly, the pessimistic time is chosen so that there is
only a five percent chance of exceeding this duration. Thus, there is a ninety
percent chance of having the actual duration of an activity fall between the
optimistic and pessimistic duration time estimates. With the use of
ninety-fifth percentile values for the optimistic and pessimistic activity
duration, the calculation of the expected duration according to Eq. (11.11.3)
is unchanged but the formula for calculating the activity variance becomes: While the PERT method has been made widely available, it suffers from three
major problems. First, the procedure focuses upon a single critical path, when
many paths might become critical due to random fluctuations. For example,
suppose that the critical path with longest expected time happened to be
completed early. Unfortunately, this does not necessarily mean that the
project is completed early since another path or sequence of activities might
take longer. Similarly, a longer than expected duration for an activity not on
the critical path might result in that activity suddenly becoming critical. As
a result of the focus on only a single path, the PERT method typically
underestimates the actual project duration.
As a second problem with the PERT procedure, it is incorrect to assume that
most construction activity durations are independent random variables. In
practice, durations are correlated with one another. For example, if problems
are encountered in the delivery of concrete for a project, this problem is
likely to influence the expected duration of numerous activities involving
concrete pours on a project. Positive correlations of this type between
activity durations imply that the PERT method underestimates the variance of
the critical path and thereby produces over-optimistic expectations of the
probability of meeting a particular project completion deadline.
Finally, the PERT method requires three duration estimates for each activity
rather than the single estimate developed for critical path scheduling. Thus,
the difficulty and labor of estimating activity characteristics is multiplied
threefold.
As an alternative to the PERT procedure, a straightforward method of
obtaining information about the distribution of project completion times (as
well as other schedule information) is through the use of Monte Carlo
simulation. This technique calculates sets of artificial (but realistic)
activity duration times and then applies a deterministic scheduling procedure
to each set of durations. Numerous calculations are required in this process
since simulated activity durations must be calculated and the scheduling
procedure applied many times. For realistic project networks, 40 to 1,000
separate sets of activity durations might be used in a single scheduling
simulation. The calculations associated with Monte Carlo simulation are
described in the following section.
A number of different indicators of the project schedule can be estimated
from the results of a Monte Carlo simulation:
The disadvantage of Monte Carlo simulation results from the additional
information about activity durations that is required and the computational
effort involved in numerous scheduling applications for each set of simulated
durations. For each activity, the distribution of possible durations as well
as the parameters of this distribution must be specified. For example,
durations might be assumed or estimated to be uniformly distributed between a
lower and upper value. In addition, correlations between activity durations
should be specified. For example, if two activities involve assembling forms
in different locations and at different times for a project, then the time
required for each activity is likely to be closely related. If the forms pose
some problems, then assembling them on both occasions might take longer than
expected. This is an example of a positive correlation in activity times. In
application, such correlations are commonly ignored, leading to errors in
results. As a final problem and discouragement, easy to use software systems
for Monte Carlo simulation of project schedules are not generally available.
This is particularly the case when correlations between activity durations are
desired.
Another approach to the simulation of different activity durations is to
develop specific scenarios of events and determine the effect on the overall
project schedule. This is a type of "what-if" problem solving in which a
manager simulates events that might occur and sees the result. For example,
the effects of different weather patterns on activity durations could be
estimated and the resulting schedules for the different weather patterns
compared. One method of obtaining information about the range of possible
schedules is to apply the scheduling procedure using all optimistic, all most
likely, and then all pessimistic activity durations. The result is three
project schedules representing a range of possible outcomes. This process of
"what-if" analysis is similar to that undertaken during the process of
construction planning or during analysis of project crashing.
Example 11-3: Scheduling activities with uncertain time durations.
Suppose that the nine activity example project shown in Table 10-0 and
Figure 10-0 of Chapter 10 was thought to have very uncertain activity time
durations. As a result, project scheduling considering this uncertainty is
desired. All three methods (PERT, Monte Carlo simulation, and "What-if"
simulation) will be applied.
Table 11-0 shows the estimated optimistic, most likely and pessimistic
durations for the nine activities. From these estimates, the mean, variance
and standard deviation are calculated. In this calculation, ninety-fifth
percentile estimates of optimistic and pessimistic duration times are assumed,
so that Equation (11.11.3) is applied. The critical path for this project
ignoring uncertainty in activity durations consists of activities A, C, F and I
as found in Table 10-3 (Section 10.3). Applying the PERT analysis procedure
suggests that the duration of the project would be approximately normally
distributed. The sum of the means for the critical activities is 4.0 + 8.0 +
12.0 + 6.0 = 30.0 days, and the sum of the variances is 0.4 + 1.6 + 1.6 + 1.6 =
5.2 leading to a standard deviation of 2.3 days.
With a normally distributed project duration, the probability of meeting a
project deadline is equal to the probability that the standard normal
PD-@g[m]@-{D}
distribution is less than or equal to where PD is the project-------------
@g{s}@-(D)
deadline, @g[m]@-(D) is the expected duration and @g[s]@-(D) is the standard
deviation of project duration. For example, the probability of project
completion within 35 days is:
PD-@g(m)@-(D) 35-30.0
Pr{D L PD} = Pr{z L } = Pr{z L } = Pr{z L 2.17}------------- -------
@g(s)@-(D) 2.3
where z is the standard normal distribution tabulated value of the cumulative
standard distribution appears in Table B.1 of Appendix B.
!!!! Most!!
!! Optimistic!! Likely!! Pessimistic!!
Activity!! Duration!! Duration!! Duration!! Mean!! Variance
A!! 3!! 4!! 5!! 4.0!! 0.4
B!! 2!! 3!! 5!! 3.2!! 0.9
C!! 6!! 8!! 10!! 8.0!! 1.6
D!! 5!! 7!! 8!! 6.8!! 0.9
E!! 6!! 9!! 14!! 9.3!! 6.4
F!! 10!! 12!! 14!! 12.0!! 1.6
G!! 2!! 2!! 4!! 2.3!! 0.4
H!! 4!! 5!! 8!! 5.3!! 1.6
I!! 4!! 6!! 8!! 6.0!! 1.6
Monte Carlo simulation results provide slightly different estimates of the
project duration characteristics. Assuming that activity durations are
independent and approximately normally distributed random variables with the
mean and variances shown in Table 11-0, a simulation can be performed by
obtaining simulated duration realization for each of the nine activities and
applying critical path scheduling to the resulting network. Applying this
procedure 500 times, the average project duration is found to be 30.9 days with
a standard deviation of 2.5 days. The PERT result is less than this estimate
by 0.9 days or three percent. Also, the critical path considered in the PERT
procedure (consisting of activities A, C, F and I) is found to be the critical
path in the simulated networks less than half the time.
If there are correlations among the activity durations, then significantly
different results can be obtained. For example, suppose that activities C, E,
G and H are all positively correlated random variables with a correlation of
0.5 for each pair of variables. Applying Monte Carlo simulation using 500
activity network simulations results in an average project duration of 36.5
days and a standard deviation of 4.9 days. This estimated average duration is
6.5 days or 20 percent longer than the PERT estimate or the estimate obtained
ignoring uncertainty in durations. If correlations like this exist, these
methods can seriously underestimate the actual project duration.
Finally, the project durations obtained by assuming all optimistic and all
pessimistic activity durations are 23 and 41 days respectively. Other
"what-if" simulations might be conducted for cases in which peculiar soil
characteristics might make excavation difficult; these soil peculiarities might
be responsible for the correlations of excavation activity durations described
above.
Results from the different methods are summarized in Table 11-0. Note that
positive correlations among some activity durations results in relatively large
increases in the expected project duration and variability.
Procedure !! Project !! Standard Deviation
and Assumptions!! Duration!! of Project Duration
!! (days)!! (days)
Critical Path Method!! 30.0!! NA
PERT Method!!30.0!! 2.3
Monte Carlo Simulation
No Duration Correlations!! 30.9!! 2.5
Positive Duration Correlations!!36.5!! 4.9
"What-if" Simulations
Optimistic!!23.0!! NA
Most Likely!!30.0!! NA
Pessimistic!!41.0!! NA
In this section, we outline the procedures required to perform Monte Carlo
simulation for the purpose of schedule analysis. These procedures presume that
the various steps involved in forming a network plan and estimating the
characteristics of the probability distributions for the various activities
have been completed. Given a plan and the activity duration distributions, the
heart of the Monte Carlo simulation procedure is the derivation of a
realization or synthetic outcome of the relevant activity durations. Once
these realizations are generated, standard scheduling techniques can be
applied. We shall present the formulas associated with the generation of
normally distributed activity durations, and then comment on the requirements
for other distributions in an example.
To generate normally distributed realizations of activity durations, we can
use a two step procedure. First, we generate uniformly distributed random
variables, u@-(i) in the interval from zero to one. Numerous techniques can be
used for this purpose. For example, a general formula for random number
generation can be of the form: With a method of generating uniformly distributed random numbers, we can
generate normally distributed random numbers using two uniformly distributed
realizations with the equations:[See T. Au, R.M. Shane, and L.A. Hoel,
Fundamentals of Systems Engineering - Probabilistic Models, Addison-Wesley
Publishing Company, 1972.] Correlated random number realizations may be generated making use of
conditional distributions. For example, suppose that the duration of an
activity d is normally distributed and correlated with a second normally
distributed random variable x which may be another activity duration or a
separate factor such as a weather effect. Given a realization x@-(k) of x, the
conditional distribution of d is still normal, but it is a function of the
value x@-(k). In particular, the conditional mean ( @g(m)'@-(d) | x = x@-(k) )
and standard deviation ( @g(s)'@-(d) | x = x@-(k) ) of a normally distributed
variable given a realization of the second variable is: Correlation coefficients indicate the extent to which two random variables
will tend to vary together. Positive correlation coefficients indicate one
random variable will tend to exceed its mean when the other random variable
does the same. From a set of n historical observations of two random
variables, x and y, the correlation coefficient can be estimated as: It is also possible to develop formulas for the conditional distribution of
a random variable correlated with numerous other variables; this is termed a
multi-variate distribution.[See N.L. Johnson and S. Kotz, Distributions in
Statistics: Continuous Multivariate Distributions, John Wiley & Sons, New
York, 1973.] Random number generations from other types of distributions are
also possible.[See, for example, P. Bratley, B. L. Fox and L.E. Schrage, A
Guide to Simulation, Springer-Verlag, New York, 1983.] Once a set of random
variable distributions is obtained, then the process of applying a scheduling
algorithm is required as described in previous sections.
Example 11-4: A Three Activity Project Example
Suppose that we wish to apply a Monte Carlo simulation procedure to a simple
project involving three activities in series. As a result, the critical path
for the project includes all three activities. We assume that the durations of
the activities are normally distributed with the following parameters: For the twelve sets of realizations shown in the table, the mean and
standard deviation of the project duration can be estimated to be 10.49 days
and 4.06 days respectively. In this simple case, we can also obtain an
analytic solution for this duration, since it is only the sum of three
independent normally distributed variables. The actual project duration has a
mean of 10.5 days, and a standard deviation of
----
V @+(2)##+##(2.4)@+(2)##+##(2.0)@+(2)) = 3.5 days. With only a limited(1.5
number of simulations, the mean obtained from simulations is close to the
actual mean, while the estimated standard deviation from the simulation differs
significantly from the actual value. This latter difference can be attributed
to the nature of the set of realizations used in the simulations; using a
larger number of simulated durations would result in a more accurate estimate
of the standard deviation.
Simulation!!
Number!! Activity A!!
Activity B!! Activity C!!
Project Duration
1!! 1.53!! 6.94!! 1.04!! 9.51
2!! 2.67!! 4.83!! 2.17!! 9.66
3!! 3.36!! 6.86!! 5.56!! 15.78
4!! 0.39!! 7.65!! 2.17!! 10.22
5!! 2.50!! 5.82!! 1.74!! 10.06
6!! 2.77!! 8.71!! 4.03!! 15.51
7!! 3.83!! 2.05!! 1.10!! 6.96
8!! 3.73!! 10.57!! 3.24!! 17.53
9!! 1.06!! 3.68!! 2.47!! 7.22
10!! 1.17!! 0.86!! 1.37!! 3.40
11!! 1.68!! 9.47!! 0.13!! 11.27
12!! 0.37!! 6.66!! 1.70!! 8.72
Estimated Mean Project
Duration!!!!!! 10.49
Estimated Standard Deviation
of Project Duration!!!! 4.06
Note: All durations in days.
Example 11-5: Generation of Realizations from Triangular Distributions
To simplify calculations for Monte Carlo simulation of schedules, the use of
a triangular distribution is advantageous compared to the normal or the beta
distributions. Triangular distributions also have the advantage relative to
the normal distribution that negative durations cannot be estimated. As
illustrated in Figure 11-0, the triangular distribution can be skewed to the
right or left and has finite limits like the beta distribution. If a is the
lower limit, b the upper limit and m the most likely value, then the mean and
standard deviation of a triangular distribution are:
Generating a random variable from this distribution can be accomplished with
a single uniform random variable realization using the inversion method. In
this method, a realization of the cumulative probability function, F(x) is
generated and the corresponding value of x is calculated. Since the cumulative
probability function varies from zero to one, the density function realization
can be obtained from the uniform value random number generator, Equation
(11.11.4). The calculation of the corresponding value of x is obtained from
inverting Equation (11.11-5): The previous sections discussed the duration of activities as either fixed
or random numbers with known characteristics. However, activity durations can
often vary depending upon the type and amount of resources that are applied.
Assigning more workers to a particular activity will normally result in a
shorter duration.[There are exceptions to this rule, though. More workers may
also mean additional training burdens and more problems of communication and
management. Some activities cannot be easily broken into tasks for numerous
individuals; some aspects of computer programming provide notable examples.
Indeed, software programming can be so perverse that examples exist of
additional workers resulting in slower project completion. See F.P. Brooks,
jr. , The Mythical Man-Month, Addison Wesley, Reading, MA 1975.] Greater
speed may result in higher costs and lower quality, however. In this section,
we shall consider the impacts of time, cost and quality tradeoffs in activity
durations. In this process, we shall discuss the procedure of project
crashing as described below.
A simple representation of the possible relationship between the duration of
an activity and its direct costs appears in Figure 11-0. Considering only this
activity in isolation and without reference to the project completion deadline,
a manager would undoubtedly choose a duration which implies minimum direct
cost, represented by D@-(ij) and C@-(ij) in the figure. Unfortunately, if each
activity was scheduled for the duration that resulted in the minimum direct
cost in this way, the time to complete the entire project might be too long and
substantial penalties associated with the late project start-up might be
incurred. This is a small example of sub-optimization, in which a small
component of a project is optimized or improved to the detriment of the entire
project performance. Avoiding this problem of sub-optimization is a
fundamental concern of project managers.
At the other extreme, a manager might choose to complete the activity in the
minimum possible time, D@+(c)@-(ij), but at a higher cost C@+(c)@-(ij). This
minimum completion time is commonly called the activity crash time. The
linear relationship shown in the figure between these two points implies that
any intermediate duration could also be chosen. It is possible that some
intermediate point may represent the ideal or optimal trade-off between time
and cost for this activity.
What is the reason for an increase in direct cost as the activity duration
is reduced? A simple case arises in the use of overtime work. By scheduling
weekend or evening work, the completion time for an activity as measured in
calendar days will be reduced. However, premium wages must be paid for such
overtime work, so the cost will increase. Also, overtime work is more prone to
accidents and quality problems that must be corrected, so indirect costs may
also increase. More generally, we might not expect a linear relationship
between duration and direct cost, but some convex function such as the
nonlinear curve or the step function shown in Figure 11-0. A linear function
may be a good approximation to the actual curve, however, and results in
considerable analytical simplicity.[For a discussion of solution procedures and
analogies of the general function time/cost tradeoff problem, see
C. Hendrickson and B.N. Janson, "A Common Network Flow Formulation for Several
Civil Engineering Problems," Civil Engineering Systems, Vol. 1, No. 4, 1984,
pp. 195-203.]
With a linear relationship between cost and duration, the critical path
time/cost tradeoff problem can be defined as a linear programming optimization
problem. In particular, let R@-(ij) represent the rate of change of cost as
duration is decreased, illustrated by the absolute value of the slope of the
line in Figure 11-0. Then, the direct cost of completing an activity is: One solution to the time-cost tradeoff problem is of particular interest and
deserves mention here. The minimum time to complete a project is called the
project-crash time. This minimum completion time can be found by applying
critical path scheduling with all activity durations set to their minimum
values (D@+(c)@-(ij)). This minimum completion time for the project can then be
used in the time-cost scheduling problem described above to determine the
minimum project-crash cost. Note that the project crash cost is not found by
setting each activity to its crash duration and summing up the resulting costs;
this solution is called the all-crash cost. Since there are some activities
not on the critical path that can be assigned longer duration without delaying
the project, it is advantageous to change the all-crash schedule and thereby
reduce costs.
Heuristic approaches are also possible to the time/cost tradeoff problem.
In particular, a simple approach is to first apply critical path scheduling
with all activity durations assumed to be at minimum cost (D@-(ij)). Next, the
planner can examine activities on the critical path and reduce the scheduled
duration of activities which have the lowest resulting increase in costs. In
essence, the planner develops a list of activities on the critical path ranked
in accordance with the unit change in cost for a reduction in the activity
duration. The heuristic solution proceeds by shortening activities in the
order of their lowest impact on costs. As the duration of activities on the
shortest path are shortened, the project duration is also reduced. Eventually,
another path becomes critical, and a new list of activities on the critical
path must be prepared. By manual or automatic adjustments of this kind, good
but not necessarily optimal schedules can be identified. Optimal or best
schedules can only be assured by examining changes in combinations of
activities as well as changes to single activities. However, by alternating
between adjustments in particular activity durations (and their costs) and a
critical path scheduling procedure, a planner can fairly rapidly devise a
shorter schedule to meet a particular project deadline or, in the worst case,
find that the deadline is impossible of accomplishment.
This type of heuristic approach to time-cost tradeoffs is essential when the
time-cost tradeoffs for each activity are not known in advance or in the case
of resource constraints on the project. In these cases, heuristic explorations
may be useful to determine if greater effort should be spent on estimating
time-cost tradeoffs or if additional resources should be retained for the
project. In many cases, the basic time/cost tradeoff might not be a smooth
curve as shown in Figure 11-0, but only a series of particular resource and
schedule combinations which produce particular durations. For example, a
planner might have the option of assigning either one or two crews to a
particular activity; in this case, there are only two possible durations of
interest.
Example 11-6: Time/Cost Trade-offs
The construction of a permanent transitway on an expressway median
illustrates the possibilities for time/cost trade-offs in construction
work.(This example was abstracted from work performed in Houston and reported
in U. Officer, "Using Accelerated Contracts with Incentive Provisions for
Transitway Construction in Houston," Paper Presented at the January 1986
Transportation Research Board Annual Conference, Washington, D.C.) One section
of 10 miles of transitway was built in 1985 and 1986 to replace an existing
contra-flow lane system (in which one lane in the expressway was reversed each
day to provide additional capacity in the peak flow direction). Three
engineers' estimates for work time were prepared:
In accepting bids for this construction work, the owner required both a
dollar amount and a completion date. The bidder's completion date was required
to fall between 360 and 540 days. In evaluating contract bids, a $ 5,000
credit was allowed for each day less than 540 days that a bidder specified for
completion. In the end, the successful bidder completed the project in 270
days, receiving a bonus of 5,000 (540-270) = $ 450,000 in the $8,200,000
contract. However, the contractor experienced fifteen to thirty percent higher
costs to maintain the continuous work schedule.
Example 11-7: Time cost trade-offs and project crashing
As an example of time/cost trade-offs and project crashing, suppose that we
needed to reduce the project completion time for a seven activity product
delivery project first analyzed in Section 10.3 as shown in Table 10-0 and
Figure 10-0. Table 11-0 gives information pertaining to possible reductions in
time which might be accomplished for the various activities. Using the minimum
cost durations (as shown in column 3 of Table 11-0), the critical path includes
activities C,E,F,G plus a dummy activity X. The project duration is 32 days in
this case, and the project cost is $ 70,000.
______________________________________________________________________________
Activity!! Minimum!! Normal!!
Crash!! Crash!! Change in
!! Cost!! Duration!! Cost!!
Duration!! Cost per Day
A!! 8!! 6!! 14!! 4!! 3
B!! 4!! 1!! 4!! 1!! -
C!! 8!! 8!! 24!! 4!! 4
D!! 10!! 5!! 24!! 3!! 7
E!! 10!! 9!! 18!! 5!! 2
F!! 20!! 12!! 36!! 6!! 2.7
G!! 10!! 3!! 18!! 2!! 8
Note: Dollar amounts in thousands; time durations in days.
______________________________________________________________________________
Examining the unit change in cost, R@-(ij) shown in column 6 of Table 11-0,
the lowest rate of change occurs for activity E. Accordingly, a good heuristic
strategy might be to begin by crashing this activity. The result is that the
duration of activity E goes from 9 days to 5 days and the total project cost
increases by $ 8,000. After making this change, the project duration drops to
28 days and two critical paths exist: (1) activities C,X,E,F and G, and (2)
activities C, D, F, and G.
Examining the unit changes in cost again, activity F has the lowest value of
R@-(i,j). Crashing this activity results in an additional time savings of 6
days in the project duration, an increase in project cost of $ 16,000, but no
change in the critical paths. The activity on the critical path with the next
lowest unit change in cost is activity C. Crashing this activity to its minimum
completion time would reduce its duration by 4 days at a cost increase of $
16,000. However, this reduction does not result in a reduction in the duration
of the project by 4 days. After activity C is reduced to 7 days, then the
alternate sequence of activities A and B lie on the critical path and further
reductions in the duration of activity C alone do not result in project time
savings. Accordingly, our heuristic corrections might be limited to reducing
activity C by only 1 day, thereby increasing costs by $ 4,000 and reducing the
project duration by 1 day.
At this point, our choices for reducing the project duration are fairly
limited. We can either reduce the duration of activity G or, alternatively,
reduce activity C and either activity A or activity B by an identical amount.
Inspection of Table 11-0 and Figure 10-0 suggest that reducing activity A and
activity C is the best alternative. Accordingly, we can shorten activity A to
its crash duration (from 6 days to 4 days) and shorten the duration of activity
C (from 7 days to 5 days) at an additional cost of $ 6,000 + $ 8,000 = $
14,000. The result is a reduction in the project duration of 2 days.
Our last option for reducing the project duration is to crash activity G
from 3 days to 2 days at an increase in cost of $ 8,000. No further reductions
are possible in this time since each activity along a critical path (comprised
of activities A, B, E, F and G) are at minimum durations. At this point, the
project duration is 18 days and the project cost is $ 120,000., representing a
fifty percent reduction in project duration and a seventy percent increase in
cost. Note that not all the activities have been crashed. Activity C has been
reduced in duration to 5 days (rather than its 4 day crash duration), while
activity D has not been changed at all. If all activities had been crashed,
the total project cost would have been $ 138,000, representing a useless
expenditure of $ 18,000. The change in project cost with different project
durations is shown graphically in Figure 11-0.
Example 11-8: Mathematical Formulation of Time-Cost Trade-offs
The same results obtained in the previous example could be obtained using a
formal optimization program and the data appearing in Tables 10-0 and 11-0. In
this case, the heuristic approach used above has obtained the optimal solution
at each stage. Using Eq. (11.11.5), the linear programming problem formulation
would be: The previous discussion of activity scheduling suggested that the general
structure of the construction plan was known in advance. With previously
defined activities, relationships among activities, and required resources, the
scheduling problem could be represented as a mathematical optimization problem.
Even in the case in which durations are uncertain, we assumed that the
underlying probability distribution of durations is known and applied
analytical techniques to investigate schedules.
While these various scheduling techniques have been exceedingly useful, they
do not cover the range of scheduling problems encountered in practice. In
particular, there are many cases in which costs and durations depend upon other
activities due to congestion on the site. In contrast, the scheduling
techniques discussed previously assume that durations of activities are
generally independent of each other. A second problem stems from the
complexity of construction technologies. In the course of resource
allocations, numerous additional constraints or objectives may exist that are
difficult to represent analytically. For example, different workers may have
specialized in one type of activity or another. With greater experience, the
work efficiency for particular crews may substantially increase.
Unfortunately, representing such effects in the scheduling process can be very
difficult. Another case of complexity occurs when activity durations and
schedules are negotiated among the different parties in a project so there is
no single overall planner.
A practical approach to these types of concerns is to insure that all
schedules are reviewed and modified by experienced project managers before
implementation. This manual review permits the incorporation of global
constraints or consideration of peculiarities of workers and equipment.
Indeed, interactive schedule revision to accomadate resource constraints is
often superior to any computer based heuristic. With improved graphic
representations and information availability, man-machine interaction is likely
to improve as a scheduling procedure.
More generally, the solution procedures for scheduling in these more
complicated situations cannot be reduced to mathematical algorithms. The best
solution approach is likely to be a "generate-and-test" cycle for alternative
plans and schedules. In this process, a possible schedule is hypothesized or
generated. This schedule is tested for feasibility with respect to relevant
constraints (such as available resources or time horizons) and desireability
with respect to different objectives. Ideally, the process of evaluating an
alternative will suggest directions for improvements or identify particular
trouble spots. These results are then used in the generation of a new test
alternative. This process continues until a satisfactory plan is obtained.
Two important problems must be borne in mind in applying a
"generate-and-test" strategy. First, the number of possible plans and
schedules is enormous, so considerable insight to the problem must be used in
generating reasonable alternatives. Secondly, evaluating alternatives also may
involve considerable effort and judgment. As a result, the number of actual
cycles of alternative testing that can be accomadated is limited. One hope for
computer technology in this regard is that the burdensome calculations
associated with this type of planning may be assumed by the computer, thereby
reducing the cost and required time for the planning effort. Some mechanisms
along these lines are described in Chapter 15.
Example 11-9: Man-machine Interactive Scheduling
An interactive system for scheduling with resource constraints might have
the following characteristics:(This description is based on an interactive
scheduling system developed at Carnegie Mellon University and described in
C. Hendrickson, C. Zozaya-Gorostiza, D. Rehak, E. Baracco-Miller and P. Lim,
"An Expert System for Construction Planning," ASCE Journal of Computing, Vol.
1, No. 4, 1987, pp. 253-269.)
Despite considerable attention by researchers and practitioners, the process
of construction planning and scheduling still presents problems and
opportunities for improvement. The importance of scheduling in insuring the
effective coordination of work and the attainment of project deadlines is
indisputable. For large projects with many parties involved, the use of formal
schedules is indispensable.
The network model for representing project activities has been provided as
an important conceptual and computational framework for planning and
scheduling. Networks not only communicate the basic precedence relationships
between activities, they also form the basis for most scheduling computations.
As a practical matter, most project scheduling is performed with the
critical path scheduling method, supplemented by heuristic procedures used in
project crash analysis or resource constrained scheduling. Many commercial
software programs are available to perform these tasks. Probabilistic
scheduling or the use of optimization software to perform time/cost trade-offs
is rather more infrequently applied, but there are software programs available
to perform these tasks if desired.
Rather than concentrating upon more elaborate solution algorithms, the most
important innovations in construction scheduling are likely to appear in the
areas of data storage, ease of use, data representation, communication and
diagnostic or interpretation aids. Integration of scheduling information with
accounting and design information through the means of database systems is one
beneficial innovation; many scheduling systems do not provide such integration
of information. The techniques discussed in Chapter 14 are particularly useful
in this regard.
With regard to ease of use, the introduction of interactive scheduling
systems, graphical output devices and automated data acquisition should produce
a very different environment than has existed. In the past, scheduling was
performed as a batch operation with output contained in lengthy tables of
numbers. Updating of work progress and revising activity duration was a time
consuming manual task. It is no surprise that managers viewed scheduling as
extremely burdensome in this environment. The lower costs associated with
computer systems as well as improved software make "user friendly" environments
a real possibility for field operations on large projects.
Finally, information representation is an area which can result in
substantial improvements. While the network model of project activities is an
extremely useful device to represent a project, many aspects of project plans
and activity inter-relationships cannot or have not been represented in network
models. For example, the similarity of processes among different activities is
usually unrecorded in the formal project representation. As a result, updating
a project network in response to new information about a process such as
concrete pours can be tedious. What is needed is a much more flexible and
complete representation of project information. Some avenues for change along
these lines are discussed in Chapter 15.
P11-1. For the project defined in Problem P10-1 (in Chapter 10), suppose
that the early, most likely and late time schedules are desired. Assume that
the activity durations are approximately normally distributed with means as
given in Table 10-0 and the following standard deviations: A: 4; B: 10; C: 1;
D: 15; E: 6; F: 12; G: 9; H: 2; I: 4; J: 5; K: 1; L: 12; M: 2; N: 1; O: 5. (a)
Find the early, most likely and late time schedules, and (b) estimate the
probability that the project requires 25% more time than the expected duration.
P11-2. For the project defined in Problem P10-2 (in Chapter 10), suppose
that the early, most likely and late time schedules are desired. Assume that
the activity durations are approximately normally distributed with measn as
given in Table 10-15 and the following standard deviations: A: 2, B: 2, C: 1,
D: 0, E: 0, F: 2; G: 0, H: 0, I: 0, J: 3; K: 0, L: 3; M: 2; N: 1. (a) Find the
early, most likely and late time schedules, and (b) estimate the probability
that the project requires 25% more time than the expected duration.
P11-3 to P11-6. The time-cost tradeoff data corresponding to each of the
Problems P10-1 to P10-4 (in Chapter 10), respectively are given in the table
for the problem (Tables P11-3 to P11-6). Determine the all-crash and the
project crash durations and cost based on the early time schedule for the
project. Also, suggest a combination of activity durations which will lead to
a project completion time equal to three days longer than the project crash
time but would result in the (approximately) maximum savings.
______________________________________________________________________________
Activity!! Shortest Possible!! Normal Completion!! Chg in Cost Per Day
!! Completion Time!! Time Cost!! Earlier Completion
A!! 3!! 150!! 20
B!! 5!! 250!! 30
C!! 1!! 80!! Infinity
D!! 10!! 400!! 15
E!! 4!! 220!! 20
F!! 6!! 300!! 25
G!! 6!! 260!! 10
H!! 2!! 120!! 35
I!! 4!! 200!! 20
J!! 3!! 180!! Infinity
K!! 3!! 220!! 25
L!! 9!! 500!! 15
M!! 2!! 100!! 30
N!! 2!! 120!! Infinity
O!! 5!! 240!! 10
______________________________________________________________________________
______________________________________________________________________________
Activity!! Shortest Possible!! Normal Completion!! Crash Completion
!! Completion Time!! Time Cost!! Time Cost
A!! 2!! 400!! 460
B!! 4!! 450!! 510
C!! 1!! 200!! 250
D!! 30!! 300!! 350
E!! 3!! 350!! 430
F!! 5!! 550!! 640
G!! 2!! 250!! 300
H!! 1!! 180!! 250
I!! 2!! 150!! 150
J!! 6!! 480!! 520
K!! 1!! 120!! 150
L!! 4!! 500!! 560
M!! 3!! 280!! 320
N!! 2!! 220!! 260
______________________________________________________________________________
______________________________________________________________________________
Activity!! Shortest Possible!! Normal Completion!! Crash Completion
!! Completion Time!! Time Cost!! Time Cost
A!! 4!! 70!! 90
B!! 8!! 150!! 210
C!! 11!! 200!! 250
D!! 4!! 60!! 80
E!! 1!! 40!! 60
F!! 9!! 120!! 140
G!! 6!! 100!! 130
H!! 2!! 50!! 70
I!! 3!! 70!! 90
J!! 2!! 60!! 80
K!! 7!! 120!! 150
L!! 3!! 70!! 100
______________________________________________________________________________
______________________________________________________________________________
Activity!! Shortest Possible!!
Normal!! Change in Cost
!! Completion Time!!
Completion Time!! Per Day Less Duration
A!! 3!! 50!! Infinity
B!! 5!! 150!! 50
C!! 2!! 90!! Infinity
D!! 20!! 125!! 40
E!! 5!! 300!! 30
F!! 3!! 240!! 20
G!! 5!! 80!! 15
H!! 6!! 270!! 30
I!! 6!! 120!! Infinity
J!! 4!! 600!! 40
K!! 5!! 300!! 50
L!! 2!! 80!! 40
M!! 2!! 140!! 40
______________________________________________________________________________
P11-7 to P11-10. Develop a project completion time versus cost tradeoff
curve for the projects in Problems P11-3 to P11-6. (Note: a linear programming
computer program or more specialized programs can reduce the calculating work
involved in these problems!)
P11-11. Suppose that the project described in Problem P10-5 proceeds
normally on an earliest time schedule with all activities scheduled for their
normal completion time. However, suppose that activity G requires 20 days
rather than the expected 5. What might a project manager do to insure
completion of the project by the originally planned completion time?
P11-12. For the project defined in Problem P10-1 (in Chapter 10), suppose
that a Monte Carlo simulation with ten repetitions is desired. Suppose further
that the activity durations have a triangular distribution with the following
lower and upper bounds: A:4,8; B:4,9, C: 0.5,2; D: 10,20; E: 4,7; F: 7,10; G:
8, 12; H: 2,4; I: 4,7; J: 2,4; K: 2,6; L: 10, 15; M: 2,9; N: 1,4; O: 4,11.
P11-13. Suppose that two variables both have triangular distributions and
are correlated. The resulting multi-variable probability density function has
a triangular shape. Develop the formula for the conditional distribution of
one variable given the corresponding realization of the other variable.
During the execution of a project, procedures for project control and record
keeping become indispensable tools to managers and other participants in the
construction process. These tools serve the dual purpose of recording the
financial transactions that occur as well as giving managers an indication of
the progress and problems associated with a project. The problems of project
control are aptly summed up in an old definition of a project as "any
collection of vaguely related activities that are ninety percent complete, over
budget and late."[Cited in Zoll, Peter F., "Database Structures for Project
Management," Proceedings of the Seventh Conference on Electronic Computation,
ASCE, 1979.] The task of project control systems is to give a fair indication
of the existence and the extent of such problems.
In this chapter, we consider the problems associated with resource
utilization, accounting, monitoring and control during a project. In this
discussion, we emphasize the project management uses of accounting information.
Interpretation of project accounts is generally not straightforward until a
project is completed, and then it is too late to influence project management.
Even after completion of a project, the accounting results may be confusing.
Hence, managers need to know how to interpret accounting information for the
purpose of project management. In the process of considering management
problems, however, we shall discuss some of the common accounting systems and
conventions, although our purpose is not to provide a comprehensive survey of
accounting procedures.
The limited objective of project control deserves emphasis. Project control
procedures are primarily intended to identify deviations from the project plan
rather than to suggest possible areas for cost savings. This characteristic
reflects the advanced stage at which project control becomes important. The
time at which major cost savings can be achieved is during planning and design
for the project. During the actual construction, changes are likely to delay
the project and lead to inordinate cost increases. As a result, the focus of
project control is on fulfilling the original design plans or indicating
deviations from these plans, rather than on searching for significant
improvements and cost savings. It is only when a rescue operation is required
that major changes will normally occur in the construction plan.
Finally, the issues associated with integration of information will require
some discussion. Project management activities and functional concerns are
intimately linked, yet the techniques used in many instances do not facilitate
comprehensive or integrated consideration of project activities. For example,
schedule information and cost accounts are usually kept separately. As a
result, project managers themselves must synthesize a comprehensive view from
the different reports on the project plus their own field observations. In
particular, managers are often forced to infer the cost impacts of schedule
changes, rather than being provided with aids for this process. Communication
or integration of various types of information can serve a number of useful
purposes, although it does require special attention in the establishment of
project control procedures.
For cost control on a project, the construction plan and the associated cash
flow estimates can provide the baseline reference for subsequent project
monitoring and control. For schedules, progress on individual activities and
the achievement of milestone completions can be compared with the project
schedule to monitor the progress of activities. Contract and job
specifications provide the criteria by which to assess and assure the required
quality of construction. The final or detailed cost estimate provides a
baseline for the assessment of financial performance during the project. To
the extent that costs are within the detailed cost estimate, then the project
is thought to be under financial control. Overruns in particular cost
categories signal the possibility of problems and give an indication of exactly
what problems are being encountered. Expense oriented construction planning
and control focuses upon the categories included in the final cost estimation.
This focus is particular relevant for projects with few activities and
considerable repetition such as grading and paving roadways.
For control and monitoring purposes, the original detailed cost estimate is
typically converted to a project budget, and the project budget is used
subsequently as a guide for management. Specific items in the detailed cost
estimate become job cost elements. Expenses incurred during the course of a
project are recorded in specific job cost accounts to be compared with the
original cost estimates in each category. Thus, individual job cost accounts
generally represent the basic unit for cost control. Alternatively, job cost
accounts may be disaggregated or divided into work elements which are related
both to particular scheduled activities and to particular cost accounts. Work
element divisions will be described in Section 12.8.
In addition to cost amounts, information on material quantities and labor
inputs within each job account is also typically retained in the project
budget. With this information, actual materials usage and labor employed can
be compared to the expected requirements. As a result, cost overruns or
savings on particular items can be identified as due to changes in unit prices,
labor productivity or in the amount of material consumed.
The number of cost accounts associated with a particular project can vary
considerably. For constructors, on the order of four hundred separate cost
accounts might be used on a small project.[Thomas Gibb reports a median number
of 400 cost accounts for a two-million dollar projects in a sample of 30
contractors in 1975. See T.W. Gibb, Jr., "Building Construction in
Southeastern United States," School of Civil Engineering, Georgia Institute of
Technology, 1975, reported in D.W. Halpin, Financial and Cost Concepts for
Construction Management, John Wiley and Sons, 1985.] These accounts record
all the transactions associated with a project. Thus, separate accounts might
exist for different types of materials, equipment use, payroll, project office,
etc. Both physical and non-physical resources are represented, including
overhead items such as computer use or interest charges. Table 12-0 summarizes
a typical set of cost accounts that might be used in building
construction.[This illustrative set of accounts was adapted from an ASCE Manual
of Practice: Construction Cost Control, Task Committee on Revision of
Construction Cost Control Manual, ASCE, New York, 1985.] Note that this set of
accounts is organized hierarchically, with seven major divisions (accounts 201
to 207) and numerous sub-divisions under each division. This hierarchical
structure facilitates aggregation of costs into pre-defined categories; for
example, costs associated with the superstructure (account 204) would be the
sum of the underlying subdivisions (ie. 204.1, 204.2, etc.) or finer levels of
detail (204.61, 204.62, etc.). The sub-division accounts in Table 12-0 could
be further divided into personnel, material and other resource costs for the
purpose of financial accounting, as described in Section 12.4.
In developing or implementing a system of cost accounts, an appropriate
numbering or coding system is essential to facilitate communication of
information and proper aggregation of cost information. Particular cost
accounts are used to indicate the expenditures associated with specific
projects and to indicate the expenditures on particular items throughout an
organization. These are examples of different perspectives on the same
information, in which the same information may be summarized in different ways
for specific purposes. Thus, more than one aggregation of the cost information
and more than one application program can use a particular cost account.
Separate identifiers of the type of cost account and the specific project must
be provided for project cost accounts or for financial transactions. As a
result, a standard set of cost codes such as the MASTERFORMAT codes described
in Chapter 9 may be adopted to identify cost accounts along with project
identifiers and extensions to indicate organization or job specific needs.
Similarly the use of databases or, at a minimum, inter-communicating
applications programs facilitate access to cost information, as described in
Chapter 14.
Converting a final cost estimate into a project budget compatible with an
organization's cost accounts is not always a straightforward task. As
described in Chapter 5, cost estimates are generally disaggregated into
appropriate functional or resource based project categories. For example,
labor and material quantities might be included for each of several physical
components of a project. For cost accounting purposes, labor and material
quantities are aggregated by type no matter for which physical component they
are employed. For example, particular types of workers or materials might be
used on numerous different physical components of a facility. Moreover, the
categories of cost accounts established within an organization may bear little
resemblance to the quantities included in a final cost estimate. This is
particularly true when final cost estimates are prepared in accordance with an
external reporting requirement rather than in view of the existing cost
accounts within an organization.
One particular problem in forming a project budget in terms of cost accounts
is the treatment of contingency amounts. These allowances are included in
project cost estimates to accommodate unforeseen events and the resulting
costs. However, in advance of project completion, the source of contingency
expenses is not known. Realistically, a budget accounting item for contingency
allowance should be established whenever a contingency amount was included in
the final cost estimate.
A second problem in forming a project budget is the treatment of inflation.
Typically, final cost estimates are formed in terms of real dollars and an item
reflecting inflation costs is added on as a percentage or lump sum. This
inflation allowance would then be allocated to individual cost items in
relation to the actual expected inflation over the period for which costs will
be incurred.
Example 12-1: Project Budget for a Design Office
An example of a small project budget is shown in Table 12-0. This budget
might be used by a design firm for a specific design project. While this
budget might represent all the work for this firm on the project, numerous
other organizations would be involved with their own budgets. In Table 12-0, a
summary budget is shown as well as a detailed listing of costs for individuals
in the Engineering Division. For the purpose of consistency with cost accounts
and managerial control, labor costs are aggregated into three groups: the
engineering, architectural and environmental divisions. The detailed budget
shown in Table 12-0 applies only to the engineering division labor; other
detailed budgets amounts for categories such as supplies and the other work
divisions would also be prepared. Note that the salary costs associated with
individuals are aggregated to obtain the total labor costs in the engineering
group for the project. To perform this aggregation, some means of identifying
individuals within organizational groups is required. Accompanying a budget of
this nature, some estimate of the actual man-hours of labor required by project
task would also be prepared. Finally, this budget might be used for internal
purposes alone. In submitting financial bills and reports to the client,
overhead and contingency amounts might be combined with the direct labor costs
to establish an aggregate billing rate per hour. In this case, the overhead,
contingency and profit would represent allocated costs based on the direct
labor costs.
Example 12-2: Project Budget for a Constructor
Table 12-0 illustrates a summary budget for a constructor. This budget is
developed from a project to construct a wharf. As with the example design
office budget above, costs are divided into direct and indirect expenses.
Within direct costs, expenses are divided into material, subcontract, temporary
work and machinery costs. This budget indicates aggregate amounts for the
various categories. Cost details associated with particular cost accounts
would supplement and support the aggregate budget shown in Table 12-0. A
profit and a contingency amount might be added to the basic budget of $
1,715,147 shown in Table 12-0 for completeness.
For the purpose of project management and control, it is not sufficient to
consider only the past record of costs and revenues incurred in a project.
Good managers should focus upon future revenues, future costs and technical
problems. For this purpose, traditional financial accounting schemes are not
adequate to reflect the dynamic nature of a project. Accounts typically focus
on recording routine costs and past expenditures associated with
activities.[For a fuller exposition of this point, see W.H. Lucas and T.L.
Morrison, "Management Accounting for Construction Contracts," Management
Accounting, 1981, pp. 59-65.] Generally, past expenditures represent sunk
costs that cannot be altered in the future and may or may not be relevant in
the future. For example, after the completion of some activity, it may be
discovered that some quality flaw renders the work useless. Unfortunately, the
resources expended on the flawed construction will generally be sunk and
cannot be recovered for re-construction (although it may be possible to change
the burden of who pays for these resources by financial withholding or charges;
owners will typically attempt to have constructors or designers pay for changes
due to quality flaws). Since financial accounts are historical in nature, some
means of forecasting or projecting the future course of a project is essential
for management control. In this section, some methods for cost control and
simple forecasts are described.
An example of forecasting used to assess the project status is shown in
Table 12-0. In this example, costs are reported in five categories,
representing the sum of all the various cost accounts associated with each
category:
For project control, managers would focus particular attention on items
indicating substantial deviation from budgeted amounts. In particular, the
cost overruns in the labor and in the "other expense category would be worthy
of attention by a project manager in Table 12-0. A next step would be to look
in greater detail at the various components of these categories. Overruns in
cost might be due to lower than expected productivity, higher than expected
wage rates, higher than expected material costs, or other factors. Even
further, low productivity might be caused by inadequate training, lack of
required resources such as equipment or tools, or inordinate amounts of re-work
to correct quality problems. Review of a job status report is only the first
step in project control.
The job status report illustrated in Table 12-0 employs explicit estimates
of ultimate cost in each category of expense. These estimates are used to
identify the actual progress and status of a expense category. Estimates might
be made from simple linear extrapolations of the productivity or cost of the
work to date on each project item. Algebraically, a linear estimation formula
is generally one of two forms. Using a linear extrapolation of costs, the
forecast total cost, C@-(f) , is: Alternatively, the use of measured unit cost amounts can be used for
forecasting total cost. The basic formula for forecasting cost from unit costs
is: The unit cost in Equation (12.12.3) may be replaced with the hourly
productivity and the unit cost per hour (or other appropriate time period),
resulting in the equation: More elaborate forecasting systems might recognize peculiar problems
associated with work on particular items and modify these simple proportional
cost estimates. For example, if productivity is improving as workers and
managers become more familiar with the project activities, the estimate of
total costs for an item might be revised downward. In this case, the
estimating equation would become: As a numerical example, suppose that the average unit cost has been $ 50 per
unit of work, but the most recent figure during a project is $ 45 per unit of
work. If the project manager was assured that the improved productivity could
be maintained for the remainder of the project (consisting of 800 units of work
out of a total of 1600 units of work), the cost estimate would be (50)(800) +
(45)(800) = $ 76,000 for completion of the activity. Note that this forecast
uses the actual average productivity achieved on the first 800 units and uses a
forecast of productivity for the remaining work. Historical changes in
productivity might also be used to represent this type of non-linear changes in
work productivity on particular activities over time.
In addition to changes in productivities, other components of the estimating
formula can be adjusted or more detailed estimates substituted. For example,
the change in unit prices due to new labor contracts or material supplier's
prices might be reflected in estimating future expenditures. In essence, the
same problems encountered in preparing the detailed cost estimate are faced in
the process of preparing exposure estimates, although the number and extent of
uncertainties in the project environment decline as work progresses. The only
exception to this rule is the danger of quality problems in completed work
which would require re-construction.
Each of the estimating methods described above require current information
on the state of work accomplishment for particular activities. There are
several possible methods to develop such estimates, including[For a description
of these methods and examples as used by a sample of construction companies,
see L.S. Riggs, Cost and Schedule Control in Industrial Construction, Report
to The Construction Industry Institute, Dec. 1986.]:
In some cases, automated data acquisition for work accomplishments might be
instituted. For example, transponders might be moved to the new work limits
after each day's activity and the new locations automatically computed and
compared with project plans. These measurements of actual progress should be
stored in a central database and then processed for updating the project
schedule. The use of database management systems in this fashion is described
in Chapter 14.
Example 12-3: Estimated Total Cost to Complete an Activity
Suppose that we wish to estimate the total cost to complete piping
construction activities on a project. The piping construction involves 1,000
linear feet of piping which has been divided into 50 sections for management
convenience. At this time, 400 linear feet of piping has been installed at a
cost of $ 40,000 and 500 man-hours of labor. The original budget estimate was
$ 90,000 with a productivity of one foot per man-hour, a unit cost of $ 60 per
man hour and a total material cost of $ 30,000. Firm commitments of material
delivery for the $ 30,000 estimated cost have been received.
The first task is to estimate the proportion of work completed. Two
estimates are readily available. First, 400 linear feet of pipe is in place
out of a total of 1000 linear feet, so the proportion of work completed is
400/1000 = 0.4 or 40%. This is the "units of work completed" estimation
method. Second, the cost ratio method would estimate the work complete as the
cost-to-date divided by the cost estimate or $ 40,000/$ 90,000 = 0.44 or 44%.
Third, the "incremental milestones" method would be applied by examining each
pipe section and estimating a percentage complete and then aggregating to
determine the total percentage complete. For example, suppose the following
quantities of piping fell into four categories of completeness: Once an estimate of work completed is available, then the estimated cost to
complete the activity can be calculated. First, a simple linear extrapolation
of cost results in an estimate of $ 40,000/0.4 = $ 100,000. for the piping
construction using the 40% estimate of work completed. This estimate projects
a cost overrun of 100,000 - 90,000 = $ 10,000.
Second, a linear extrapolation of productivity results in an estimate of
(1000 ft.)(500 hrs/400 ft.)($ 60/hr) + 30,000 = $ 105,000. for completion of
the piping construction. This estimate suggests a variance of 105,000 - 90,000
= $ 15,000 above the activity estimate. In making this estimate, labor and
material costs entered separately, whereas the two were implicitly combined in
the simple linear cost forecast above. The source of the variance can also be
identified in this calculation: compared to the original estimate, the labor
productivity is 1.25 hours per foot or 25% higher than the original estimate.
Example 12-4: Estimated Total Cost for Completion
The forecasting procedures described above assumed linear extrapolations of
future costs, based either on the complete experience on the activity or the
recent experience. For activities with good historical records, it can be the
case that a typically non-linear profile of cost expenditures and completion
proportions can be estimated. Figure 12-0 illustrates one possible non-linear
relationships derived from experience in some particular activity. The
progress on a new job can be compared to this historical record. For example,
point A in Figure 12-0 suggests a higher expenditure than is normal for the
completion proportion. This point represents 40% of work completed with an
expenditure of 60% of the budget. Since the historical record suggests only
50% of the budget should be expended at time of 40% completion, a 60 - 50 = 10%
overrun in cost is expected even if work efficiency can be increased to
historical averages. If comparable cost overruns continue to accumulate, then
the cost-to-complete will be even higher.
The cost accounts described in the previous sections provide only one of the
various components in a financial accounting system. Before further discussing
the use of cost accounts in project control, the relationship of project and
financial accounting deserves mention. Accounting information is generally
used for three distinct purposes:
Project costs are always included in the system of financial accounts
associated with an organization. At the heart of this system, all expense
transactions are recorded in a general ledger. The general ledger of accounts
forms the basis for management reports on particular projects as well as the
financial accounts for an entire organization. Other components of a financial
accounting system include:
In traditional bookkeeping systems, day to day transactions are first
recorded in journals. With double-entry bookkeeping, each transaction is
recorded as both a debit and a credit to particular accounts in the ledger.
For example, payment of a supplier's bill represents a debit or increase to a
project cost account and a credit or reduction to the company's cash account.
Periodically, the transaction information is summarized and transferred to
ledger accounts. This process is called posting, and may be done
instantaneously or daily in computerized systems.
In reviewing accounting information, the concepts of flows and stocks
should be kept in mind. Daily transactions typically reflect flows of dollar
amounts entering or leaving the organization. Similarly, use or receipt of
particular materials represent flows from or to inventory. An account balance
represents the stock or cumulative amount of funds resulting from these daily
flows. Information on both flows and stocks are needed to give an accurate
view of an organization's state. In addition, forecasts of future changes are
needed for effective management.
Information from the general ledger is assembled for the organization's
financial reports, including balance sheets and income statements for each
period. These reports are the basic products of the financial accounting
process and are often used to assess the performance of an organization.
Table12-0 shows a typical income statement for a small construction firm,
indicating a net profit of $ 330,000 after taxes. This statement summarizes
the flows of transactions within a year. Table 12-0 shows the comparable
balance sheet, indicated a net increase in retained earnings equal to the net
profit. The balance sheet reflects the effects of income flows during the year
on the overall worth of the organization.
In the context of private construction firms, particular problems arise in
the treatment of uncompleted contracts in financial reports. Under the
"completed-contract" method, income is only reported for completed projects.
Work on projects underway is only reported on the balance sheet, representing
an asset if contract billings exceed costs or a liability if costs exceed
billings. When a project is completed, the total net profit (or loss) is
reported in the final period as income. Under the "percentage-of-completion"
method, actual costs are reported on the income statement plus a proportion of
all project revenues (or billings) equal to the proportion of work completed
during the period. The proportion of work completed is computed as the ratio
of costs incurred to date and the total estimated cost of the project. Thus,
if twenty percent of a project was completed in a particular period at a direct
cost of $180,000 and on a project with expected revenues of $ 1,000,000, then
the contract revenues earned would be calculated as $ 1,000,000(0.2) = $
200,000. This figure represents a profit and contribution to overhead of $
200,000 - $ 180,000 = $ 20,000 for the period. Note that billings and actual
receipts might be in excess or less than the calculated revenues of $ 200,000.
On the balance sheet of an organization using the percentage-of-completion
method, an asset is usually reported to reflect billings and the estimated or
calculated earnings in excess of actual billings.
As another example of the difference in the "percentage-of-completion" and
the "completed-contract" methods, consider a three year project to construct a
plant with the following cash flow for a contractor: The "percentage-of-completion" method of reporting period earnings has the
advantage of representing the actual estimated earnings in each period. As a
result, the income stream and resulting profits are less susceptible to
precipitate swings on the completion of a project as can occur with the
"completed contract method" of calculating income. However, the
"percentage-of-completion" has the disadvantage of relying upon estimates which
can be manipulated to obscure the actual position of a company or which are
difficult to reproduce by outside observers. There are also subtleties such as
the deferral of all calculated income from a project until a minimum threshold
of the project is completed. As a result, interpretation of the income
statement and balance sheet of a private organization is not always
straightforward. Finally, there are tax disadvantages from using the
"percentage-of-completion" method since corporate taxes on expected profits may
become due during the project rather than being deferred until the project
completion. As an example of tax implications of the two reporting methods, a
study of forty-seven construction firms conducted by the General Accounting
Office found that $ 280 million in taxes were deferred from 1980 to 1984
through use of the "completed-contract" method.[As reported in the Wall Street
Journal, Feb. 19, 1986, pg. A1, c. 4.]
It should be apparent that the "percentage-of-completion" accounting
provides only a rough estimate of the actual profit or status of a project.
Also, the "completed contract" method of accounting is entirely retrospective
and provides no guidance for management. This is only one example of the types
of allocations that are introduced to correspond to generally accepted
accounting practices, yet may not further the cause of good project management.
Another common example is the use of equipment depreciation schedules to
allocate equipment purchase costs. Allocations of costs or revenues to
particular periods within a project may cause severe changes in particular
indicators, but have no real meaning for good management or profit over the
entire course of a project. As Johnson and Kaplan argue:[H.T. Johnson and R.S.
Kaplan, Relevance Lost, The Rise and Fall of Management Accounting, Harvard
Business School Press, pg. 1, 1987.]
Example 12-5: Calculating net profit
As an example of the calculation of net profit, suppose that a company began
six jobs in a year, completing three jobs and having three jobs still underway
at the end of the year. Details of the six jobs are shown in Table 12-0. What
would be the company's net profit under, first, the "percentage-of-completion"
and, second, the "completed contract method" accounting conventions?
As shown in Table 12-0, a net profit of $ 1,054,000 was earned on the three
completed jobs. Under the "completed contract" method, this total would be
total profit. Under the percentage-of completion method, the year's expected
profit on the projects underway would be added to this amount. For job 4, the
expected profits are calculated as follows:
Section 12.3 described the development of information for the control of
project costs with respect to the various functional activities appearing in
the project budget. Project managers also are involved with assessment of the
overall status of the project, including the status of activities, financing,
payments and receipts. These various items comprise the project and financing
cash flows described in earlier chapters. These components include costs
incurred (as described above), billings and receipts for billings to owners
(for contractors), payable amounts to suppliers and contractors, financing plan
cash flows (for bonds or other financial instruments), etc.
As an example of cash flow control, consider the report shown in Table 12-0.
In this case, costs are not divided into functional categories as in Table
12-0, such as labor, material, or equipment. Table 12-0 represents a summary
of the project status as viewed from different components of the accounting
system. Thus, the aggregation of different kinds of cost exposure or cost
commitment shown in Table 12-0 has not been performed. The elements in Table
12-0 include:
The overall status of the project requires synthesizing the different pieces
of information summarized in Table 12-0. Each of the different accounting
systems contributing to this table provides a different view of the status of
the project. In this example, the budget information indicates that costs are
higher than expected, which could be troubling. However, a profit is still
expected for the project. A substantial amount of money is due from the owner,
and this could turn out to be a problem if the owner continues to lag in
payment. Finally, the positive cash position for the project is highly
desirable since financing charges can be avoided.
The job status reports illustrated in this and the previous sections provide
a primary tool for project cost control. Different reports with varying
amounts of detail and item reports would be prepared for different individuals
involved in a project. Reports to upper management would be summaries, reports
to particular staff individuals would emphasize their responsibilities (eg.
purchasing, payroll, etc.), and detailed reports would be provided to the
individual project managers. Coupled with scheduling reports described in
Chapter 10, these reports provide a snapshot view of how a project is doing.
Of course, these schedule and cost reports would have to be tempered by the
actual accomplishments and problems occurring in the field. For example, if
work already completed is of sub-standard quality, these reports would not
reveal such a problem. Even though the reports indicated a project on time and
on budget, the possibility of re-work or inadequate facility performance due to
quality problems would quickly reverse that rosy situation.
In addition to cost control, project managers must also give considerable
attention to monitoring schedules. Construction typically involves a deadline
for work completion, so contractual agreements will force attention to
schedules. More generally, delays in construction represent additional costs
due to late facility occupancy or other factors. Just as costs incurred are
compared to budgeted costs, actual activity durations may be compared to
expected durations. In this process, forecasting the time to complete
particular activities may be required.
The methods used for forecasting completion times of activities are directly
analogous to those used for cost forecasting. For example, a typical
estimating formula might be: For example, Figure 12-0 shows the originally scheduled project progress
versus the actual progress on a project. This figure is constructed by summing
up the percentage of each activity which is complete at different points in
time; this summation can be weighted by the magnitude of effort associated with
each activity. In Figure 12-0, the project was ahead of the original schedule
for a period including point A, but is now late at point B by an amount equal
to the horizontal distance between the planned progress and the actual progress
observed to date.
Schedule adherence and the current status of a project can also be
represented on geometric models of a facility. For example, an animation of
the construction sequence can be shown on a computer screen, with different
colors or other coding scheme indicating the type of activity underway on each
component of the facility. Deviations from the planned schedule can also be
portrayed by color coding. The result is a mechanism to both indicate work in
progress and schedule adherence specific to individual components in the
facility.
In evaluating schedule progress, it is important to bear in mind that some
activities possess float or scheduling leeway, whereas delays in activities on
the critical path will cause project delays. In particular, the delay in
planned progress at time t may be soaked up in activities' float (thereby
causing no overall delay in the project completion) or may cause a project
delay. As a result of this ambiguity, it is preferable to update the project
schedule to devise an accurate protrayal of the schedule adherence. After
applying a scheduling algorithm, a new project schedule can be obtained. For
cash flow planning purposes, a graph or report similar to that shown in Figure
12-0 can be constructed to compare actual expenditures to planned expenditures
at any time. This process of re-scheduling to indicate the schedule adherence
is only one of many instances in which schedule and budget updating may be
appropriate, as discussed in the next section.
Scheduling and project planning is an activity that continues throughout the
lifetime of a project. As changes or discrepancies between the plan and the
realization occur, the project schedule and cost estimates should be modified
and new schedules devised. Too often, the schedule is devised once by a
planner in the central office, and then revisions or modifications are done
incompletely or only sporadically. The result is the lack of effective project
monitoring and the possibility of eventual chaos on the project site.
On "fast track" projects, initial construction activities are begun even
before the facility design is finalized. In this case, special attention must
be placed on the coordinated scheduling of design and construction activities.
Even in projects for which the design is finalized before construction begins,
change orders representing changes in the "final" design are often issued to
incorporate changes desired by the owner.
Periodic updating of future activity durations and budgets is especially
important to avoid excessive optimism in projects experiencing problems. If
one type of activity experiences delays on a project, then related activities
are also likely to be delayed unless managerial changes are made. Construction
projects normally involve numerous activities which are closely related due to
the use of similar materials, equipment, workers or site characteristics.
Expected cost changes should also be propagated thoughout a project plan. In
essence, duration and cost estimates for future activities should be revised in
light of the actual experience on the job. Without this updating, project
schedules slip more and more as time progresses. To perform this type of
updating, project managers need access to original estimates and estimating
assumptions.
Unfortunately, most project cost control and scheduling systems do not
provide many aids for such updating. What is required is a means of
identifying discrepancies, diagnosing the cause, forecasting the effect, and
propagating this effect to all related activities. While these steps can be
undertaken manually, computers aids to support interactive updating or even
automatic updating would be helpful.[One experimental program directed at this
problem is a knowledge based expert system described in R.E. Levitt and J.C.
Kunz, "Using Knowledge of Construction and Project Management for Automated
Schedule Updating," Project Management Journal, Vol. 16, 1985, pp. 57-76.
Expert systems and related developments are described in Chapter 15.]
Beyond the direct updating of activity durations and cost estimates, project
managers should have mechanisms available for evaluating any type of schedule
change. Updating activity duration estimations, changing scheduled start
times, modifying the estimates of resources required for each activity, and
even changing the project network logic (by inserting new activities or other
changes) should all be easily accomplished. In effect, scheduling aids should
be directly available to project managers.(For an example of a prototype
interactive project management environment that includes graphical displays and
scheduling algorithms, see R. Kromer, "Interactive Activity Network Analysis
Using a Personal Computer," Unpublished MS Thesis, Department of Civil
Engineering, Carnegie-Mellon University, Pittsburgh, PA, 1984.) Fortunately,
local computers are commonly available on site for this purpose.
Example 12-6: Schedule Updates in a Small Project
As an example of the type of changes that might be required, consider the
nine activity project described in Section 10.3 and appearing in Figure 12-0.
Also, suppose that the project is four days underway, with the current activity
schedule and progress as shown in Figure 12-0. A few problems or changes that
might be encountered include the following:
______________________________________________________________________________
201!!Clearing and Preparing Site
202!!Substructure
202.1!!Excavation and Shoring
202.2!!Piling
202.3!!Concrete Masonry
202.31!!Mixing and Placing
202.32!!Formwork
202.33!!Reinforcing
203!!Outside Utilities (water, gas, sewer, etc.)
204!!Superstructure
204.1!!Masonry Construction
204.2!!Structural Steel
204.3!!Wood Framing, Partitions, etc.
204.4!!Exterior Finishes (brickwork, terra cotta, cut stone, etc.)
204.5!!Roofing, Drains, Gutters, Flashing, etc.
204.6!!Interior Finish and Trim
204.61!!Finish Flooring, Stairs, Doors, Trim
204.62!!Glass, Windows, Glazing
204.63!!Marble, Tile, Terrazzo
204.64!!Lathing and Plastering
204.65!!Soundproofing and Insulation
204.66!!Finish Hardware
204.67!!Painting and Decorating
204.68!!Waterproofing
204.69!!Sprinklers and Fire Protection
204.7!!Service Work
204.71!!Electrical Work
204.72!!Heating and Ventilating
204.73!!Plumbing and Sewage
204.74!!Air Conditioning
204.75!!Fire Alarm, Telephone, Security, Miscellaneous
205!!Paving, Curbs, Walks
206!!Installed Equipment (elevators, revolving doors, mailchutes, etc.)
207!!Fencing
______________________________________________________________________________
______________________________________________________________________________
Budget Summary
!!Personnel
!!!!Architectural Division $ 67,251.00!!
!!!!Engineering 45,372.00!!
!!!!Environmental Division 28,235.00!!
!!Total $140,858.00!!
!!Other Direct Expenses
!!!!Travel $ 2,400.00!!
!!!!Supplies $ 1,500.00!!
!!!!Communication $ 600.00!!
!!!!Computer Services $ 1,200.00!!
!!Total $ 5,700.00!!
!!Overhead $ 175,869.60!!
!!Contingency and Profit $ 95,700.00!!
!!Total $ 418,127.60!!
Engineering Personnel Detail !!Senior Engineer $ 11,562.00!!
!!Associate Engineer 21,365.00!!
!!Engineer Technician 12,654.00!!
!!Total $ 45,372.00!!
______________________________________________________________________________
_____________________________________________________________________________
(Amounts in Thousands of Dollars)
!! Material!! Subcontract!!
Temporary!! Machinery!! Total
!! Cost!!
Work!! Work!! Cost!! Cost
Steel Piling!! 292,172.!!
129,178.!! 16,389.!!
0.!! 437,739.!!
Tie-rod!! 88,233.!! 29,254.!!
0.!! 0.!! 117,487.!!
Anchor-Wall!! 130,281.!!
60,873.!! 0.!! 0.!!
191,154.!!
Backfill!! 242,230.!!
27,919.!! 0.!! 0.!! 300,149.!!
Coping!! 42,880.!!
22,307.!! 13,171.!!
0.!! 78,358.!!
Dredging!! 0.!! 111,650.!!
0.!! 0.!! 111,650.!!
Fender!! 48,996.!! 10,344.!!
0.!! 1,750.!! 61,090.!!
Other!! 5,000.!! 32,250.!!
0.!! 0.!! 37,250.!!
Sub-total!! 849,800.!! 423,775.!!
29,560.!! 1,750.!! 1,304,885.!!
!!Summary
!!Total of direct cost 1,304,885.!!
!!Indirect Cost
!!!!Common Temporary Work 19,320.!!
!!!!Common Machinery 80,934.!!
!!!!Transportation 15,550.!!
!!!!Office Operating Costs 294,458.!!
!!Total of Indirect Cost 410,262.!!
!!Total Project Cost 1,715,147.!!
______________________________________________________________________________
______________________________________________________________________________
!! Budgeted!! Estimated!! Cost!! Cost!!
Cost!! Over or
Factor!! Cost!! Total Cost!! Committed!!
Exposure!! To Date!! (Under)
Labor!! $ 99,406.!! $ 102,342.!!
$ 49,596.!! - !! $ 52,746.!! $ 2,936
Material!! 88,499.!! 88,499.!!
42,506.!! 45,993.!! -!! 0.
Subcontracts!! 198,458.!! 196,323.!!
83,352.!! 97,832.!! 15,139.!! (2,135).
Equipment!! 37,543.!! 37,543!!
23,623.!! - !! 13,920.!! 0.
Other!! 72,693.!! 81,432.!!
49,356.!! - !! 32,076.!! 8,739.
Total!! 496,509.!! 506,139.!!
248,433.!! 143,825.!! 113,881.!! 5,950.
______________________________________________________________________________
______________________________________________________________________________
Income Statement
for the year ended December 31, 19xx
!!Gross project revenues $ 7,200,000.!!
!!Direct project costs on contracts 5,500,000.!!
!!Depreciation of equipment 200,000.!!
!!Estimating 150,000.!!
!!Administrative and other expenses 650,000.!!
!!Subtotal of cost and expenses 6,500,000.!!
!!Operating Income 700,000.!!
!!Interest Expense, net 150,000.!!
!!Income before taxes 550,000.!!
!!Income tax 220,000.!!
!!Net income after tax 330,000.!!
!!Cash dividends 100,000.!!
!!Retained earnings, current year 230,000.!!
!!Retention at beginning of year 650,000.!!
!!Retained earnings at end of year $ 880,000.!!
______________________________________________________________________________
______________________________________________________________________________
Balance Sheet
December 31, 19xx
Amount!!
Assets
Cash $ 150,000.!!
Payments Receivable 750,000.!!
Work in progress, not claimed 700,000.!!
Work in progress, retention 200,000.!!
Equipment at cost less accumulated depreciation 1,400,000!!
Total assets $ 3,200,000.!!
Liabilities and Equity
Accounts payable $ 950,000.!!
Other items payable (taxes, wages, etc.) 50,000.!!
Long term debts 500,000.!!
Shareholders' funds
40,000 shares of common stock
(Including paid-in capital) 900,000.!!
Retained Earnings 800,000.!!
Total Liabilities and Equity $ 3,200,000.!!
______________________________________________________________________________
______________________________________________________________________________
Net Profit on Completed Contracts (Amounts in thousands of dollars)
!!Job 1 $ 1,436.!!
!!Job 2 356.!!
!!Job 3 -738.!!
!!Total Net Profit on Completed Jobs 1,054.!!
Status of Jobs Underway
!! Job 4!! Job 5!! Job 6!!
Original Contract Price!! 4,200!! 3,800!! 5,630!!
Contract Changes (Change Orders, etc.)!!
400!! 600!! -300!!
Total Cost to Date!! 3,600!!
1,710!! 620!!
Payments Received or Due to Date!!
3,520!! 1,830!! 340.!!
Estimated Cost to Complete!! 500!!
2,300!! 5,000!!
______________________________________________________________________________
______________________________________________________________________________
Costs!! Charges!! Estimated!!
% Complete!! Projected!! Change!!
7/02!! 8,754,516!! 65,863,092!!
13.292!! 66,545,263!! 682,171!!
Billings!! Contract!!
Gross Bill!! % Billed!! Profit!!
7/01!! 67,511,602!!
9,276,621!! 13.741!! 966,339!!
Payables!!Paid!! Open!!
Retention!! Labor!! Total!!
7/01!! 6,719,103!! 1,300,089!!
391,671!! 343,653!! 8,754,516!!
Receivable!! Net Bill!!
Received!! Retention!! Open!!
7/02!! 8,761,673!!
7,209,344!! 514,948!! 2,067,277!!
Cash Position!! Paid!!
Received!! Position!!!!
!! 7,062,756!! 7,209,344!! 146,588!!
______________________________________________________________________________
The previous sections focused upon the identification of the budgetary and
schedule status of projects. Actual projects involve a complex
inter-relationship between time and cost. As projects proceed, delays
influence costs and budgetary problems may in turn require adjustments to
activity schedules. Trade-offs between time and costs were discussed in
Section 10.9 in the context of project planning in which additional resources
applied to a project activity might result in a shorter duration but higher
costs. Unanticipated events might result in increases in both time and cost to
complete an activity. For example, excavation problems may easily lead to much
lower than anticipated productivity on activities requiring digging.
While project managers implicitly recognize the inter-play between time and
cost on projects, it is rare to find effective project control systems which
include both elements. Usually, project costs and schedules are recorded and
reported by separate application programs. Project managers must then perform
the tedious task of relating the two sets of information.
The difficulty of integrating schedule and cost information stems primarily
from the level of detail required for effective integration. Usually, a single
project activity will involve numerous cost account categories. For example,
an activity for the preparation of a foundation would involve laborers, cement
workers, concrete forms, concrete, reinforcement, transportation of materials
and other resources. Even a more disaggregated activity definition such as
erection of foundation forms would involve numerous resources such as forms,
nails, carpenters, laborers, and material transportation. Again, different
cost accounts would normally be used to record these various resources.
Similarly, numerous activities might involve expenses associated with
particular cost accounts. For example, a particular material such as standard
piping might be used in numerous different schedule activities. To integrate
cost and schedule information, the disaggregated charges for specific
activities and specific cost accounts must be the basis of analysis.
A straightforward means of relating time and cost information is to define
individual work elements representing the resources in a particular cost
category associated with a particular project activity. Work elements would
represent an element in a two-dimensional matrix of activities and cost
accounts as illustrated in Figure 12-0. A numbering or identifying system for
work elements would include both the relevant cost account and the associated
activity. In some cases, it might also be desirable to identify work elements
by the responsible organization or individual. In this case, a three
dimensional representation of work elements is required, with the third
dimension corresponding to responsible individuals.[A three dimensional work
element definition was proposed by J.M. Neil, "A System for Integrated Project
Management," Proceedings of the Conference on Current Practice in Cost
Estimating and Cost Control, ASCE, Austin, Texas, 138-146, April 1983.] More
generally, modern computerized databases can accomadate a flexible structure of
data representation to support aggregation with respect to numerous different
perspectives; this type of system will be discussed in Chapter 14.
With this organization of information, a number of management reports or
views could be generated. In particular, the costs associated with specific
activities could be obtained as the sum of the work elements appearing in any
row in Figure 12-0. These costs could be used to evaluate alternate
technologies to accomplish particular activities or to derive the expected
project cash flow over time as the schedule changes. From a management
perspective, problems developing from particular activities could be rapidly
identified since costs would be accumulated at such a disaggregated level. As
a result, project control becomes at once more precise and detailed.
Unfortunately, the development and maintenance of a work element database
can represent a large data collection and organization effort. As noted
earlier, four hundred separate cost accounts and four hundred activities would
not be unusual for a construction project. The result would be up to 400x400 =
160,000 separate work elements. Of course, not all activities involve each
cost account. However, even a density of two percent (so that each activity
would have eight cost accounts and each account would have eight associated
activities on the average) would involve nearly thirteen thousand work
elements. Initially preparing this database represents a considerable burden,
but it is also the case that project bookkeepers must record project events
within each of these various work elements. Implementations of the "work
element" project control systems have typically fondered on the burden of data
collection, storage and book-keeping.
Until data collection is better automated, the use of work elements to
control activities in large projects is likely to be difficult to implement.
However, certain segments of project activities can profit tremendously from
this type of organization. In particular, material requirements can be tracked
in this fashion. Materials involve only a subset of all cost accounts and
project activities, so the burden of data collection and control is much
smaller than for an entire system. Moreover, the benefits from integration of
schedule and cost information are particularly noticeable in materials control
since delivery schedules are directly affected and bulk order discounts might
be identified. Consequently, materials control systems can reasonably
encompass a "work element" accounting system.
In the absence of a work element accounting system, costs associated with
particular activities are usually estimated by summing expenses in all cost
accounts directly related to an activity plus a proportion of expenses in cost
accounts used jointly by two or more activities. The basis of cost allocation
would typically be the level of effort or resource required by the different
activities. For example, costs associated with supervision might be allocated
to different concreting activities on the basis of the amount of work (measured
in cubic yards of concrete) in the different activities. With these
allocations, cost estimates for particular work activities can be obtained.
Quality control and safety represent increasingly important concerns for
project managers. Defects or failures in constructed facilities can result in
very large costs. Even with minor defects, re-construction may be required and
facility operations impaired. Increased costs and delays are the result. In
the worst case, failures may cause personal injuries or fatalities. Accidents
during the construction process can similarly result in personal injuries and
large costs. Indirect costs of insurance, inspection and regulation are
increasing rapidly due to these increased direct costs. Good project managers
try to ensure that the job is done right the first time and that no major
accidents occur on the project.
As with cost control, the most important decisions regarding the quality of
a completed facility are made during the design and planning stages rather than
during construction. It is during these preliminary stages that component
configurations, material specifications and functional performance are decided.
Quality control during construction consists largely of insuring conformance
to these original design and planning decisions.
While conformance to existing design decisions is the primary focus of
quality control, there are exceptions to this rule. First, unforeseen
circumstances, incorrect design decisions or changes desired by an owner in the
facility function may require re-evaluation of design decisions during the
course of construction. While these changes may be motivated by the concern
for quality, they represent occasions for re-design with all the attendant
objectives and constraints. As a second case, some designs rely upon informed
and appropriate decision making during the construction process itself. For
example, some tunneling methods make decisions about the amount of shoring
required at different locations based upon observation of soil conditions
during the tunneling process. Since such decisions are based on better
information concerning actual site conditions, the facility design may be more
cost effective as a result. Any special case of re-design during construction
requires the various considerations discussed in Chapter 3.
With the attention to conformance as the measure of quality during the
construction process, the specification of quality requirements in the design
and contract documentation becomes extremely important. Quality requirements
should be clear and verifiable, so that all parties in the project can
understand the requirements for conformance. Much of the discussion in this
chapter relates to the development and the implications of different quality
requirements for construction as well as the issues associated with insuring
conformance.
Safety during the construction project is also influenced in large part by
decisions made during the planning and design process. Some designs or
construction plans are inherently difficult and dangerous to implement, whereas
other, comparable plans may considerably reduce the possibility of accidents.
For example, clear separation of traffic from construction zones during roadway
rehabilitation can greatly reduce the possibility of accidental collisions.
Beyond these design decisions, safety largely depends upon education, vigilance
and cooperation during the construction process. Workers should be constantly
alert to the possibilities of accidents and avoid taken unnecessary risks.
A variety of different organizations are possible for quality and safety
control during construction. One common model is to have a group responsible
for quality assurance and another group primarily responsible for safety within
an organization. In large organizations, departments dedicated to quality
assurance and to safety might assign specific individuals to assume
responsibility for these functions on particular projects. For smaller
projects, the project manager or an assistant might assume these and other
responsibilities. In either case, insuring safe and quality construction is a
concern of the project manager in overall charge of the project in addition to
the concerns of personnel, cost, time and other management issues.
Inspectors and quality assurance personnel will be involved in a project to
represent a variety of different organizations. Each of the parties directly
concerned with the project may have their own quality and safety inspectors,
including the owner, the engineer/architect, and the various constructor firms.
These inspectors may be contractors from specialized quality assurance
organizations. In addition to on-site inspections, samples of materials will
commonly be tested by specialized laboratories to insure compliance.
Inspectors to insure compliance with regulatory requirements will also be
involved. Common examples are inspectors for the local government's building
department, for environmental agencies, and for occupational health and safety
agencies.
The US Occupational Safety and Health Administration (OSHA) routinely
conducts site visits of work places in conjunction with approved state
inspection agencies. OSHA inspectors are required by law to issue citations
for all standard violations observed. Safety standards prescribe a variety of
mechanical safeguards and procedures; for example, ladder safety is covered by
over 140 regulations. In cases of extreme non-compliance with standards, OSHA
inspectors can stop work on a project. However, only a small fraction of
construction sites are visited by OSHA inspectors and most construction site
accidents are not caused by violations of existing standards. As a result,
safety is largely the responsibility of the managers on site rather than that
of public inspectors.
While the multitude of participants involved in the construction process
require the services of inspectors, it cannot be emphasized too strongly that
inspectors are only a formal check on quality control. Quality control should
be a primary objective for all the members of a project team. Managers should
take responsibility for maintaining and improving quality control. Employee
participation in quality control should be sought and rewarded, including the
introduction of new ideas. Most important of all, quality improvement can
serve as a catalyst for improved productivity. By suggesting new work methods,
by avoiding rework, and by avoiding long term problems, good quality control
can pay for itself. Owners should promote good quality control and seek out
contractors who maintain such standards.
In addition to the various organizational bodies involved in quality
control, issues of quality control arise in virtually all the functional areas
of construction activities. For example, insuring accurate and useful
information is an important part of maintaining quality performance. Other
aspects of quality control include document control (including changes during
the construction process), procurement, field inspection and testing, and final
checkout of the facility.
Specifications of work quality are an important feature of facility designs.
Specifications of required quality and components represent part of the
necessary documentation to describe a facility. Typically, this documentation
includes any special provisions of the facility design as well as references to
generally accepted specifications to be used during construction.
General specifications of work quality are available in numerous fields and
are issued in publications of organizations such as the American Society for
Testing and Materials (ASTM), the American National Standards Institute (ANSI),
or the Construction Specifications Institute (CSI). Distinct specifications
are formalized for particular types of construction activities, such as welding
standards issued by the American Welding Society, or for particular facility
types, such as the Standard Specifications for Highway Bridges issued by the
American Association of State Highway and Transportation Officials. These
general specifications must be modified to reflect local conditions, policies,
available materials, local regulations and other special circumstances.
Construction specifications normally consist of a series of instructions or
prohibitions for specific operations. For example, the following passage
illustrates a typical specification, in this case for excavation for
structures:
In recent years, performance specifications have been developed for many
construction operations. Rather than specifying the required construction
process, these specifications refer to the required performance or quality of
the finished facility. The exact method by which this performance is obtained
is left to the construction contractor. For example, traditional
specifications for asphalt pavement specified the composition of the asphalt
material, the asphalt temperature during paving, and compacting procedures. In
contrast, a performance specification for asphalt would detail the desired
performance of the pavement with respect to impermeability, strength, etc. How
the desired performance level was attained would be up to the paving
contractor. In some cases, the payment for asphalt paving might increase with
better quality of asphalt beyond some minimum level of performance.
Example 13-1: Concrete Pavement Strength
Concrete pavements of superior strength result in cost savings by delaying
the time at which repairs or re-construction is required. In contrast,
concrete of lower quality will necessitate more frequent overlays or other
repair procedures. Contract provisions with adjustments to the amount of a
contractor's compensation based on pavement quality have become increasingly
common in recognition of the cost savings associated with higher quality
construction. Even if a pavement does not meet the "ultimate" design standard,
it is still worth using the lower quality pavement and re-surfacing later
rather than completely rejecting the pavement. Based on these life cycle cost
considerations, a typical pay schedule might be:[This illustrative pay factor
schedule is adapted from R.M. Weed, "Development of Multicharacteristic
Acceptance Procedures for Rigid Pavement," Transportation Research Record 885,
1982, pp. 25-36.] Quality control in construction typically involves insuring compliance with
minimum standards of material and workmanship in order to insure the
performance of the facility according to the design. These minimum standards
are contained in the specifications described in the previous section. For the
purpose of insuring compliance, random samples and statistical methods are
commonly used as the basis for accepting or rejecting work completed and
batches of materials. Rejection of a batch is based on non-conformance or
violation of the relevant design specifications. Procedures for this quality
control practice are described in the following sections.
An implicit assumption in these traditional quality control practices is the
notion of an acceptable quality level which is a allowable fraction of
defective items. Materials obtained from suppliers or work performed by an
organization is inspected and passed as acceptable if the estimated defective
percentage is within the acceptable quality level. Problems with materials or
goods are corrected after delivery of the product.
In contrast to this traditional approach of quality control is the goal of
total quality control. In this system, no defective items are allowed
anywhere in the construction process. While the zero defects goal can never be
permanently obtained, it provides a goal so that an organization is never
satisfied with its quality control program even if defects are reduced by
substantial amounts year after year. This concept and approach to quality
control was first developed in manufacturing firms in Japan and Europe, but has
since spread to many construction companies.
Total quality control is a commitment to quality expressed in all parts of
an organization and typically involves many elements. Design reviews to insure
safe and effective construction procedures are a major element. Other elements
include extensive training for personnel, shifting the responsibility for
detecting defects from quality control inspectors to workers, and continually
maintaining equipment. Worker involvement in improved quality control is often
formalized in quality circles in which groups of workers meet regularly to
make suggestions for quality improvement. Material suppliers are also required
to insure zero defects in delivered goods. Initally, all materials from a
supplier are inspected and batches of goods with any defective items are
returned. Suppliers with good records can be certified and not subject to
complete inspection subsequently.
The traditional microeconomic view of quality control is that there is an
"optimum" proportion of defective items. Trying to achieve greater quality
than this optimum would substantially increase costs of inspection and reduce
worker productivity. However, many companies have found that commitment to
total quality control has substantial economic benefits that had been
unappreciated in traditional approaches. Expenses associated with inventory,
rework, scrap and warranties were reduced. Worker enthusiasm and commitment
improved. Customers often appreciated higher quality work and would pay a
premium for good quality. As a result, improved quality control became a
competitive advantage.
Of course, total quality control is difficult to apply, particular in
construction. The unique nature of each facility, the variability in the
workforce, the multitude of subcontractors and the cost of making necessary
investments in education and procedures make programs of total quality control
in construction difficult. Nevertheless, a commitment to improved quality even
without endorsing the goal of zero defects can pay real dividends to
organizations.
Example 13-2: Experience with Quality Circles
Quality circles represent a group of five to fifteen workers who meet on a
frequent basis to identify, discuss and solve productivity and quality
problems. A circle leader acts as liason between the workers in the group and
upper levels of management. Appearing below are some examples of reported
quality circle accomplishments in construction:[B.A. Gilly, A. Touran, and
T. Asai, "Quality Control Circles in Construction," ASCE Journal of
Construction Engineering and Management, Vol. 113, No. 3, 1987, pg 432.]
An ideal quality control program might test all materials and work on a
particular facility. For example, non-destructive techniques such as x-ray
inspection of welds can be used throughout a facility. An on-site inspector
can witness the appropriateness and adequacy of construction methods at all
times. Even better, individual craftsmen can perform continuing inspection of
materials and their own work. Exhaustive or 100% testing of all materials and
work by inspectors can be exceedingly expensive, however. In many instances,
testing requires the destruction of a material sample, so exhaustive testing is
not even possible. As a result, small samples are used to establish the basis
of accepting or rejecting a particular work item or shipment of materials.
Statistical methods are used to interpret the results of test on a small sample
to reach a conclusion concerning the acceptability of an entire lot or batch
of materials or work products.
The use of statistics is essential in interpreting the results of testing on
a small sample. Without adequate interpretation, small sample testing results
can be quite misleading. As an example, suppose that there are ten defective
pieces of material in a lot of one hundred. In taking a sample of five pieces,
the inspector might not find any defective pieces or might have all sample
pieces defective. Drawing a direct inference that none or all pieces in the
population are defective on the basis of these samples would be incorrect. Due
to this random nature of the sample selection process, testing results can vary
substantially. It is only with statistical methods that issues such as the
chance of different levels of defective items in the full lot can be fully
analyzed from a small sample test.
There are two types of statistical sampling which are commonly used for the
purpose of quality control in batches of work or materials:
Whatever sampling plan is used in testing, it is always assumed that the
samples are representative of the entire population under consideration.
Samples are expected to be chosen randomly so that each member of the
population is equally likely to be chosen. Convenient sampling plans such as
sampling every twentieth piece, choosing a sample every two hours, or picking
the top piece on a delivery truck may be adequate to insure a random sample if
pieces are randomly mixed in a stack or in use. However, some convenient
sampling plans can be inappropriate. For example, checking only easily
accessible joints in a building component is inappropriate since joints that
are hard to reach may be more likely to have erection or fabrication problems.
Another assumption implicit in statistical quality control procedures is
that the quality of materials or work is expected to vary from one piece to
another. This is certainly true in the field of construction. While a
designer may assume that all concrete is exactly the same in a building, the
variations in material properties, manufacturing, handling, pouring, and
temperature during setting insure that concrete is actually heterogeneous in
quality. Reducing such variations to a minimum is one aspect of quality
construction. Insuring that the materials actually placed achieve some minimum
quality level with respect to average properties or fraction of defectives is
the task of quality control.
Sampling by attributes is a widely applied quality control method. The
procedure is intended to determine whether or not a particular group of
materials or work products is acceptable. In the literature of statistical
quality control, a group of materials or work items to be tested is called a
lot or batch. An assumption in the procedure is that each item in a batch
can be tested and classified as either acceptable or deficient based upon
mutually acceptable testing procedures and acceptance criteria. Each lot is
tested to determine if it satisfies a minimum acceptable quality level (AQL)
expressed as the maximum percentage of defective items in a lot or process.
In its basic form, sampling by attributes is applied by testing a
pre-defined number of sample items from a lot. If the number of defective
items is greater than a trigger level, then the lot is rejected as being likely
to be of unacceptable quality. Otherwise, the lot is accepted. Developing
this type of sampling plan requires consideration of probability, statistics
and acceptable risk levels on the part of the supplier and consumer of the lot.
Refinements to this basic application procedure are also possible. For
example, if the number of defectives is greater than some pre-defined number,
then additional sampling may be started rather than immediate rejection of the
lot. In many cases, the trigger level is a single defective item in the
sample. In the remainder of this section, the mathematical basis for
interpreting this type of sampling plan is developed.
More formally, a lot is defined as acceptable if it contains a fraction
p@-(1) or less defective items. Similarly, a lot is defined as unacceptable if
it contains a fraction p@-(2) or more defective units. Generally, the
acceptance fraction is less than or equal to the rejection fraction,
p@-(1)Lp@-(2), and the two fractions are often equal so that there is no
ambiguous range of lot acceptability between p@-(1) and p@-(2). Given a sample
size and a trigger level for lot rejection or acceptance, we would like to
determine the probabilities that acceptable lots might be incorrectly rejected
(termed producer's risk) or that deficient lots might be incorrectly accepted
(termed consumer's risk).
Consider a lot of finite number N, in which m items are defective (bad) and
the remaining (N-m) items are non-defective (good). If a random sample of n
items is taken from this lot, then we can determine the probability of having
different numbers of defective items in the sample. With a pre-defined
acceptable number of defective items, we can then develop the probability of
accepting a lot as a function of the sample size, the allowable number of
defective items, and the actual fraction of defective items. This derivation
appears below.
The number of different samples of size n that can be selected from a finite
population N is termed a mathematical combination and is computed as:
Suppose that the actual fraction of defectives in the lot is p and the
actual fraction of nondefectives is q, then p plus q is one, resulting in m =
Np, and N - m = Nq. Then, a function g(p) representing the probability of
having r or less defective items in a sample of size n is obtained by
substituting m and N into Eq. (13.13.6) and summing over the acceptable
defective number of items:
The function g(p) indicates the probability of accepting a lot, given the
sample size n and the number of allowable defective items in the sample r. The
function g(p) can be represented graphical for each combination of sample size
n and number of allowable defective items r, as shown in Figure 13-0. Each
curve is referred to as the operating characteristic curve (OC curve) in this
graph. For the special case of a single sample (n=1), the function g(p) can
be simplified:
For any combination of n and r, we can read off the value of g(p) for a
given p from the corresponding OC curve. For example, n = 15 is specified in
Figure 13-0. Then, for various values of r, we find:
In specifying the sampling plan implicit in the operating characteristic
curve, the supplier and consumer of materials or work must agree on the levels
of risk acceptable to themselves. If the lot is of acceptable quality, the
supplier would like to minimize the chance or risk that a lot is rejected
solely on the basis of a lower than average quality sample. Similarly, the
consumer would like to minimize the risk of accepting under the sampling plan a
deficient lot. In addition, both parties presumably would like to minimize the
costs and delays associated with testing. Devising an acceptable sampling plan
requires trade off the objectives of risk minimization among the parties
involved and the cost of testing.
Example 13-3: Acceptance probability calculation
Suppose that the sample size is five (n=5) from a lot of one hundred items
(N=100). The lot of materials is to be rejected if any of the five samples is
defective (r = 0). In this case, the probability of acceptance as a function
of the actual number of defective items can be computed by noting that for r =
0, only one term (x = 0) need be considered in Eq. (13.6.6). Thus, for N = 100
and n = 5: If the acceptable defective proportion was two percent (so p@-(1) = p@-(2) =
0.02), then the chance of an incorrect rejection (or producer's risk) is 1 -
g(0.02) = 1 - 0.9 = 0.1 or ten percent. Note that a prudent producer should
insure better than minimum quality products to reduce the probability or chance
of rejection under this sampling plan. If the actual proportion of defectives
was one percent, then the producer's risk would be only five percent with this
sampling plan.
Example 13-4: Designing a Sampling Plan
Suppose that an owner (or product "consumer" in the terminology of quality
control) wishes to have zero defective items in a facility with 5,000 items of
a particular kind. What would be the different amounts of consumer's risk for
different sampling plans?
With an acceptable quality level of no defective items (so p@-(1) = 0), the
allowable defective items in the sample is zero (so r = 0) in the sampling
plan. Using the binomial approximation, the probability of accepting the 5,000
items as a function of the fraction of actual defective items and the sample
size is: Example 13-5: Military Standard 105
Beginning in 1945, the US Department of Defense has issued standard
procedures for acceptance sampling by attribute. The procedures appeared as
MIL-STD-105 or, equivalently, ABC-STD-105 and have been widely adopted and
applied in industry.(Documentation for MIL-STD-105 can be obtained from the
National Technical Information Service, Washington D.C. 20402.) The procedures
appearing in MIL-STD-105 are also similar to the procedures adopted by the
International Organization for Standardization as ISO 2859. In its simplest
form, MIL-STD-105 requires specification of a desired inspection level and an
acceptable quality level (AQL). The desired inspection level permits greater
or lesser precision in making acceptance decisions by varying the sample size.
Implicit in the application of MIL-STD-105 is the assumption that samples are
random and that each item can be classified as having zero, one or multiple
defects. The procedures can be applied to the percentage of defective items or
to the percentage of defects in the lot, with the latter defined as the number
of defects divided by the number of items in the lot. The difference between
defects and defective items is readily seen by noting that a deficient item may
have one or more defects.
Table 13-0 shows the sample size code levels for different lot sizes and for
different inspection levels. Inspection level II is generally prescribed in
applications, while inspection levels I and and III represent tighter and more
lenient inspection levels. Special inspection levels are used when testing is
very expensive or destructive, and prescribe lower sample sizes.
______________________________________________________________________________
______________________________________________________________________________
Table 13-0 shows the trigger level for different sample sizes and acceptable
quality levels. As an illustration, suppose that the normal inspection level
II is desired for a lot of size 700. Using Table 13-0, the appropriate sample
size code letter is J in this case. Referring to Table 13-0, this code letter
implies a sample size of 80 out of the lot. For an acceptable quality level of
1.5 percent, the appropriate trigger level is four defective items. If four or
more items in the 80 item sample are defective, then the lot should be
rejected.
Selection of the appropriate inspection level and acceptable quality level
in the application of MIL-STD-105 requires the same sort of tradeoffs discussed
above between the cost of testing, the importance of item quality, the
producer's risk and the consumer's risk. The full documentation of MIL-STD-105
includes graphs of operating characteristic curves for the different sampling
plans, so these risk levels can be examined. For example, Figure 13-0 contains
operating characteristic curves for single, double and multiple sampling with
sampling plan K and average quality level AQL = 1.0 under normal inspection.
In this figure, it can be seen that the single, double and multiple sampling
plans result in approximately the same levels of risk. Using this figure, the
producer's risk at a 0.5 defective rate is approximately one percent, whereas
the consumer's risk for a three percent defective rate is about forty percent.
MIL-STD-105 also provides procedures for more complicated sampling plans.
First, provisions for normal, tightened and reduced inspection can be
accommodated. These are relevant in situations in which a continuing series of
material or work lots are received to be tested. If some lots are found to
have a large number of deficient items, then a tightened sampling plan
involving larger sample sizes or smaller trigger levels may be used to insure
adequate quality. Conversely, reduced inspection provides lower trigger levels
and increased consumer risk. Second, double and multiple sampling plans are
possible. These may be useful when testing can be performed rapidly so that
additional samples can be taken before the lot items are approved or used.
From the initial sample, three outcomes may occur in these plans: (1) the
number of defectives may be sufficiently low that the lot is accepted, (2) the
number of defectives may be sufficiently high that the lot is rejected, or (3)
the number of defectives may be in an ambiguous range in which further sampling
and testing is prescribed.
As described in the previous section, sampling by attributes is based on a
classification of items as good or defective. Many work and material
attributes possess continuous properties, such as strength, density or length.
With the sampling by attributes procedure, a particular level of a variable
quantity must be defined as acceptable quality. More generally, two items
classified as good might have quite different strengths or other attributes.
Intuitively, it seems reasonable that some "credit" should be provided for
exceptionally good items in a sample. Sampling by variables was developed for
application to continuously measurable quantities of this type. The procedure
uses measured values of an attribute in a sample to determine the overall
acceptability of a batch or lot. Sampling by variables has the advantage of
using more information from tests since it is based on actual measured values
rather than a simple classification. As a result, acceptance sampling by
variables can be more efficient than sampling by attributes in the sense that
fewer samples are required to obtain a desired level of quality control.
In applying sampling by variables, an acceptable lot quality can be defined
with respect to an upper limit U, a lower limit L, or both. With these
boundary conditions, an acceptable quality level can be defined as a maximum
allowable fraction of defective items, M. In Figure 13-0, the probability
distribution of item attribute x is illustrated. With an upper limit U, the
fraction of defective items is equal to the area under the distribution
function to the right of U (so that xGU). This fraction of defective items
would be compared to the allowable fraction M to determine the acceptability of
a lot. With both a lower and an upper limit on acceptable quality, the
fraction defective would be the fraction of items greater than the upper limit
or less than the lower limit. Alternatively, the limits could be imposed upon
the acceptable average level of the variable
In sampling by variables, the fraction of defective items is estimated by
using measured values from a sample of items. As with sampling by attributes,
the procedure assumes a random sample of a give size is obtained from a lot or
batch. In the application of sampling by variables plans, the measured
characteristic is virtually always assumed to be normally distributed as
illustrated in Figure 13-0. The probabilities of a normal distribution are
given by Table B.1 in Appendix B. The normal distribution is likely to be a
reasonably good assumption for many measured characteristics such as material
density or degree of soil compaction. The Central Limit Theorem provides a
general support for the assumption: if the source of variations is a large
number of small and independent random effects, then the resulting distribution
of values will approximate the normal distribution. If the distribution of
measured values is not likely to be approximately normal, then sampling by
attributes should be adopted. Deviations from normal distributions may appear
as skewed or non-symmetric distributions, or as distributions with fixed upper
and lower limits.
The fraction of defective items in a sample or the chance that the
population average has different values is estimated from two statistics
obtained from the sample: the sample mean and standard deviation.
Mathematically, let n be the number of items in the sample and
x@-[i],#i#=#1,2,3,...,n, be the measured values of the variable characteristic
x. Then an estimate of the overall population mean @g(m) is the sample mean
-
: The probability that the average value of a population is greater than a
particular lower limit is calculated from the test statistic: With an upper limit, the calculations are similar, and the probability that
the average value of a population is less than a particular upper limit can be
calculated from the test statistic: The calculations to estimate the fraction of items above an upper limit or
below a lower limit are very similar to those for the population average. The
only difference is that the square root of the number of samples does not
appear in the test statistic formulas: Instead of using sampling plans that specify an allowable fraction of
defective items, it saves computations to simply write specifications in terms
of the allowable test statistic values themselves. This procedure is
equivalent to requiring that the sample average be at least a pre-specified
number of standard deviations away from an upper or lower limit. For example,
-
with = 4.0, U = 8.5, s = 3.0 and n = 41, the sample mean is only about (8.5 -x
4.0)/3.0 = 1.5 standard deviations away from the upper limit.
To summarize, the application of sampling by variables requires the
specification of a sample size, the relevant upper or limits, and either (1)
the allowable fraction of items falling outside the designated limits or (2)
the allowable probability that the population average falls outside the
designated limit. Random samples are drawn from a pre-defined population and
tested to obtained measured values of a variable attribute. From these
measurements, the sample mean, standard deviation, and quality control test
statistic are calculated. Finally, the test statistic is compared to the
allowable trigger level and the lot is either accepted or rejected. It is also
possible to apply sequential sampling in this procedure, so that a batch may be
subjected to additional sampling and testing to further refine the test
statistic values.
With sampling by variables, it is notable that a producer of material or
work can adopt two general strategies for meeting the required specifications.
First, a producer may insure that the average quality level is quite high, even
if the variability among items is high. This strategy is illustrated in Figure
13-0 as a "high quality average" strategy. Second, a producer may meet a
desired quality target by reducing the variability within each batch. In
Figure 13-0, this is labeled the "low variability" strategy. In either case, a
producer should maintain high standards to avoid rejection of a batch.
Example 13-6: Testing for defective component strengths
Suppose that an inspector takes eight strength measurements with the
following results:
Example 13-7: Military Standard 414
As with sampling by attributes, a number of testing standards exist for
sampling-by-variables. Examples include Military Standard 414 (MIL-STD-414)
developed by the US Department of Defense or ISO-3951 provided by the
International Standards Organization. In MIL-STD-414, sampling plans are
chosen based on the pre-specified acceptable quality level, defined as the
maximum percent defective that is acceptable in a process. Inherent in the
sampling plans in MIL-STD-414 are the assumptions that the measured attribute
of interest is normally distributed, designated samples are chosen randomly,
and measurements are made without appreciable error.
Figure 13-0 illustrates the operating characteristic (OC) curves used in
MIL-STD-414. Different curves are shown for seven separate AQL values ranging
from one percent to fifteen percent. The OC curves indicate the percentage of
lots expected to be accepted as a function of the quality of submitted lots
(represented by the percentage of defective items in an average lot).
Table 13-0 illustrates the type of sampling plan prescribed by MIL-STD-414.
For example, suppose that sample size K (corresponding to 35 sample items) and
a AQL value of one percent were desired. Appropriate sample sizes are based on
desired inspection levels and lot sizes as in MIL-STD-105 (for sampling by
attributes) shown in Table 13-0. In this case, the designated k value is 1.89
as shown in Table 13-0. This value is compared to the sample quality index.
For example, with an upper level quality specification (U), the quality index
is computed as:
As with other sampling-by-variable standards, MIL-STD-414 has a number of
user options in the development of a sampling plan, including:
Construction is a relatively hazardous undertaking. As Table 13-0
illustrates, there are significantly more injuries and lost workdays due to
injuries or illnesses in construction than in virtually any other industry.
These work related injuries and illnesses are exceedingly costly. The
Construction Industry Cost Effectiveness Project estimated that accidents cost
$ 8.9 billion or nearly seven percent of the $ 137 billion (in 1979 dollars)
spent annually for industrial, utility and commercial construction in the
United States.[See Improving Construction Safety Performance, Report A-3, The
Business Roundtable, New York, NY, January 1982.] Included in this total are
direct costs (medical costs, premiums for workers' compensation benefits,
liability and property losses) as well as indirect costs (reduced worker
productivity, delays in projects, administrative time, and damage to equipment
and the facility). In contrast to most industrial accidents, innocent
bystanders may also be injuried by construction accidents. Several crane
collapses from high rise buildings under construction have resulted in
fatalities to passerbys. Prudent project managers and owners would like to
reduce accidents, injuries and illnesses as much as possible.
As with all the other costs of construction, it is a mistake for owners to
ignore a significant category of costs such as injury and illnesses. While
contractors may pay insurance premiums directly, these costs are reflected in
bid prices or contract amounts. Delays caused by injuries and illnesses can
present significant opportunity costs to owners. In the long run, the owners
of constructed facilities must pay all the costs of construction. For the case
of injuries and illnesses, this general principle might be slightly qualified
since significant costs are borne by workers themselves or society at large.
However, court judgements and insurance payments compensate for individual
losses and are ultimately borne by the owners.
The causes of injuries in construction are numerous. Table 13-0 lists the
reported causes of accidents in Britain in 1976. A similar catalogue of causes
would exist for the United States or other countries. The largest single
category for both injuries and fatalities are individual falls. Handling goods
is also a significant cause of injuries. From a management perspective,
however, these reported causes do not really provide a useful prescription for
safety policies. An individual fall may be caused by a series of coincidences:
a railing might not be secure, a worker might be inattentive, the footing may
be slippery, etc. Removing any one of these compound causes might serve to
prevent any particular accident. However, it is clear that conditions such as
unsecured railings will normally increase the risk of accidents.
Various measures are available to improve jobsite safety in construction.
Several of the most important occur before construction is undertaken. These
include design, choice of technology and education. By altering facility
designs, particular structures can be safer or more hazardous to construct.
Choice of technology can also be critical in determining the safety of a
jobsite. Safeguards built into machinery can notify operators of problems or
prevent injuries. For example, simple switches can prevent equipment from
being operating when protective shields are not in place. With the
availability of on-board electronics (including computer chips) and sensors,
the possibilities for sophisticated machine controllers and monitors has
greatly expanded for construction equipment and tools. Materials and work
process choices also influence the safety of construction. For example,
substitution of alternative materials for asbestos can reduce or eliminate the
prospects of long term illnesses such as asbestiosis.
Educating workers and managers in proper procedures and hazards can have a
direct impact on jobsite safety. The realization of the large costs involved
in construction injuries and illnesses provides a considerable motivation for
awareness and education.
Pre-qualification of contractors and sub-contractors with regard to safety
is another important avenue for safety improvement. If contractors are only
invitied to bid or enter negotiations if they have an acceptable record of
safety (as well as quality performance), then a direct incentive is provided to
insure adequate safety on the part of contractors.
During the construction process itself, the most important safety related
measures are to insure vigilance and cooperation on the part of managers,
inspectors and workers. Vigilance involves considering the risks of different
working practices. In also involves maintaining temporary physical safeguards
such as barricades, braces, guylines, railings, toeboards and the like.
While eliminating accidents and work related illnesses is a worthwhile goal,
it will never be attained. Construction has a number of characteristics making
it inherently hazardous. Large forces are involved in many operations. The
jobsite is continually changing as construction proceeds. Workers do not have
fixed worksites and must move around a structure under construction. The
tenure of a worker on a site is short, so the worker's familiarity and the
employer-employee relationship are less settled than in manufacturing settings.
Despite these peculiarities and as a result of exactly these special problems,
improving worksite safety is a very important project management concern.
Example 13-8: Trench collapse[This example was adapted from E. Elinski,
External Impacts of Reconstruction and Rehabilitation Projects with
Implications for Project Management, Unpublished MS Thesis, Department of
Civil Engineering, Carnegie Mellon University, 1985.]
To replace 1,200 feet of a sewer line, a trench of between 12.5 and 18 feet
deep was required down the center of a four lane street. The contractor chose
to begin excavation of the trench from the shallower end, requiring a 12.5 deep
trench. Initially, the contractor used a nine foot high, four foot wide steel
trench box for soil support. A trench box is a rigid steel frame consisting of
two walls supported by welded struts with open sides and ends. This method had
the advantage that traffic could be maintained in at least two lanes during the
reconstruction work.
In the shallow parts of the trench, the trench box seemed to adequately
support the excavation. However, as the trench got deeper, more soil was
unsupported below the trench box. Intermittent soil collapses in the trench
began to occur. Eventually, an old parallel six inch water main collapsed,
thereby saturating the soil and leading to massive soil collapse at the bottom
of the trench. Replacement of the water main was added to the initial
contract. At this point, the contractor began sloping the sides of the trench,
thereby requiring the closure of the entire street.
The initial use of the trench box was convenient, but it was clearly
inadequate and unsafe. Workers in the trench were in continuing danger of
accidents stemming from soil collapse. Disruption to surrounding facilities
such as the parallel water main was highly likely. Adoption of a tongue and
groove vertical sheeting system over the full height of the trench or,
alternatively, the sloping excavation eventually adopted are clearly
preferable.
Construction projects inevitably generate enormous and complex sets of
information. Effectively managing this bulk of information to insure its
availability and accuracy is an important managerial task. Poor or missing
information can readily lead to project delays, uneconomical decisions, or even
the complete failure of the desired facility. Pity the owner and project
manager who suddenly discover on the expected delivery date that important
facility components have not yet been fabricated and cannot be delivered for
six months! With better information, the problem could have been identified
earlier, so that alternative suppliers might have been located or schedules
arranged. Both project design and control are crucially dependent upon
accurate and timely information, as well as the ability to use this information
effectively. At the same time, too much unorganized information presented to
managers can result in confusion and paralysis of decision making.
As a project proceeds, the types and extent of the information used by the
various organizations involved will change. A listing of the most important
information sets would include:
While there may be substantial costs due to inaccurate or missing
information, there are also significant costs associated with the generation,
storage, transfer, retrieval and other manipulation of information. In
addition to the costs of clerical work and providing aids such as computers,
the organization and review of information command an inordinate amount of the
attention of project managers, which may be the scarcest resource on any
construction project. It is useful, therefore, to understand the scope and
alternatives for organizing project information.
Numerous sources of error are expected for project information. While
numerical values are often reported to the nearest cent or values of equivalent
precision, it is rare that the actual values are so accurately known. Living
with some uncertainty is an inescapable situation, and a prudent manager should
have an understanding of the uncertainty in different types of information and
the possibility of drawing misleading conclusions.
We have already discussed the uncertainty inherent in making forecasts of
project costs and durations sometime in the future. Forecast uncertainty also
exists in the short term. For example, consider estimates of work completed.
Every project manager is familiar with situations in which the final few bits
of work for a task take an inordinate amount of time. Unforeseen problems,
inadequate quality on already completed work, lack of attention, accidents, or
postponing the most difficult work problems to the end can all contribute to
making the final portion of an activity actually require far more time and
effort than expected. The net result is that estimates of the actual
proportion of work completed are often inaccurate.
Some inaccuracy in reports and estimates can arise from conscious choices
made by workers, foremen or managers. If the value of insuring accuracy is
thought to be low or nonexistent, then a rational worker will not expend effort
or time to gather or to report information accurately. Many project scheduling
systems flounder on exactly this type of non-reporting or mis-reporting. The
original schedule can quickly become extremely misleading without accurate
updating! Only if all parties concerned have specific mandates or incentives
to report accurately will the data be reliable.
Another source of inaccuracy comes from transcription errors of various
sorts. Typographical errors, incorrect measurements from reading equipment, or
other recording and calculation errors may creep into the sets of information
which are used in project management. Despite intensive efforts to check and
eliminate such errors, their complete eradication is virtually impossible.
One method of indicating the relative accuracy of numerical data is to
report ranges or expected deviations of an estimate or measurement. For
example, a measurement might be reported as 198 ft. + 2 ft. There are two
common interpretations of these deviations. First, a range (such as + 2)
might be chosen so that the actual value is certain to be within the indicated
range. In the case above, the actual length would be somewhere between 196 and
200 feet with this convention. Alternatively, this deviation might indicate
the typical range of the estimate or measurement. In this case, the example
above might imply that there is, say, a two-thirds chance that the actual
length is between 196 and 200.
When the absolute range of a quantity is very large or unknown, the use of a
statistical standard deviation as a measure of uncertainty may be useful. If a
quantity is measured n times resulting is a set of values x@-(i) (i =
1,2,...,n), then the average or mean value is given by: More generally, even information which is gathered and reported correctly
may be interpreted incorrectly. While the actual information might be correct
within the terms of the data gathering and recording system, it may be quite
misleading for managerial purposes. A few examples can illustrate the problems
which may arise in naively interpreting recorded information without involving
any conceptual understanding of how the information is actually gathered,
stored and recorded or how work on the project actually proceeds.
Example 14-1: Sources of Delay and Cost Accounts
It is common in construction activity information to make detailed records
of costs incurred and work progress. It is less common to keep detailed
records of delays and their causes, even though these delays may be the actual
cause of increased costs and lower productivity.(See D.F. Rogge, "Delay
Reporting Within Cost Accounting System," ASCE Journal of Construction
Engineering and Management, Vol. 110, No. 2, 1984, pp. 289-292.) Paying
exclusive attention to cost accounts in such situations may be misleading.
For example, suppose that the accounts for equipment and material inventories
show cost savings relative to original estimates, whereas the costs associated
with particular construction activities show higher than estimated
expenditures. In this situation, it is not necessarily the case that the
inventory function is performing well, whereas the field workers are the cause
of cost overrun problems. It may be that construction activities are delayed
by lack of equipment or materials, thus causing cost increases. Keeping a
larger inventory of materials and equipment might increase the inventory
account totals, but lead to lower overall costs on the project. Better yet,
more closely matching demands and supplies might reduce delay costs without
concurrent inventory cost increases. Thus, simply examining cost account
information may not lead to a correct diagnosis of a problem or to the correct
managerial responses.
Example 14-2: Interest Charges
Financial or interest charges are usually accumulated in a separate account
for projects, while the accounts associated with particular activities
represent actual expenditures. For example, planning activities might cost
$10,000 for a small project during the first year of a two year project. Since
dollar expenditures have a time value, this $10,000 cost in year 1 is not
equivalent in value to a $10,000 cost in year 2. In particular, financing the
early $10,000 involves payment of interest or, similarly, the loss of
investment opportunities. If the borrowing rate was 10%, then financing the
first year $10,000 expenditure would require $10,000 x 0.10 = $1,000 and the
value of the expenditure by the end of the second year of the project would be
$11,000. Thus, some portion of the overall interest charges represents a cost
associated with planning activities. Recognizing the true value of
expenditures made at different periods of time is an important element in
devising rational planning and management strategies.
Numerous formal methods and possible organizations exist for the information
required for project management. Before discussing the details of computations
and information representation, it will be useful to describe a record keeping
implementation, including some of the practical concerns in design and
implementation. In this section, we shall describe a computer based system to
provide construction yard and warehouse management information from the point
of view of the system users.(The system is based loosely upon a successful
construction yard management system originally for Mellon-Stuart Company,
Pittsburgh, PA. in 1983. The authors are indebted to A. Pasquale for providing
the information and operating experience of the system.) In the process, the
usefulness of computerized databases can be illustrated.
A yard or warehouse is used by most construction firms to store equipment
and to provide an inventory of materials and parts needed for projects. Large
firms may have several warehouses at different locations so as to reduce
transit time between project sites and materials supplies. In addition, local
"yards" or "equipment sheds" are commonly provided on the job site. Examples
of equipment in a yard would be drills, saws, office trailers, graders, back
hoes, concrete pumps and cranes. Material items might include nails, plywood,
wire mesh, forming lumber, etc.
In typical construction warehouses, written records are kept by warehouse
clerks to record transfer or return of equipment to job sites, dispatch of
material to jobs, and maintenance histories of particular pieces of equipment.
In turn, these records are used as the basis for billing projects for the use
of equipment and materials. For example, a daily charge would be made to a
project for using a concrete pump. During the course of a month, the concrete
pump might spend several days at different job sites, so each project would be
charged for its use. The record keeping system is also used to monitor
materials and equipment movements between sites so that equipment can be
located.
One common mechanism to organize record keeping is to fill out cards
recording the transfer of items to or from a job site. Table 14-0 illustrates
one possible transfer record. In this case, seven items were requested for the
Carnegie-Mellon job site (project number 83-1557). These seven items would be
loaded on a delivery truck, along with a copy of the transfer record. Shown in
Table 14-0 is a code number identifying each item (0609.02, 0609.03, etc.), the
quantity of each item requested, an item description and a unit price. For
equipment items, an equipment number identifying the individual piece of
equipment used is also recorded, such as grinder No. 4517 in Table 14-0; a unit
price is not specified for equipment but a daily rental charge might be
imposed.
Transfer sheets are numbered (such as No. 100311 in Table 14-0), dated and
the preparer identified to facilitate control of the record keeping process.
During the course of a month, numerous transfer records of this type are
accumulated. At the end of a month, each of the transfer records is examined
to compile the various items or equipment used at a project and the appropriate
charges. Constructing these bills would be a tedious manual task. Equipment
movements would have to be tracked individually, days at each site counted, and
the daily charge accumulated for each project. For example, Table 14-0 records
the transfer of grinder No. 4517 to a job site. This project would be charged
a daily rental rate until the grinder was returned. Hundreds or thousands of
individual item transfers would have to be examined, and the process of
preparing bills could easily require a week or two of effort.
In addition to generating billing information, a variety of reports would be
useful in the process of managing a company's equipment and individual
projects. Records of the history of use of particular pieces of equipment are
useful for planning maintenance and deciding on the sale or scrapping of
equipment. Reports on the cumulative amount of materials and equipment
delivered to a job site would be of obvious benefit to project managers.
Composite reports on the amount, location, and use of pieces of equipment of
particular types are also useful in making decisions about the purchase of new
equipment, inventory control, or for project planning. Unfortunately,
producing each of these reports requires manually sifting through a large
number of transfer cards. Alternatively, record keeping for these specific
projects could have to proceed by keeping multiple records of the same
information. For example, equipment transfers might be recorded on (1) a file
for a particular piece of equipment and (2) a file for a particular project, in
addition to the basic transfer form illustrated in Table 14-0. Even with these
redundant records, producing the various desired reports would be time
consuming.
Organizing this inventory information in a computer program is a practical
and desirable innovation. In addition to speeding up billing (and thereby
reducing borrowing costs), application programs can readily provide various
reports or views of the basic inventory information described above.
Information can be entered directly to the computer program as needed. For
example, the transfer record shown in Table 14-0 is based upon an input screen
to a computer program which, in turn, had been designed to duplicate the manual
form used prior to computerization. Use of the computer also allows some
interactive aids in preparing the transfer form. This type of aid follows a
simple rule: "Don't make the user provide information that the system already
knows."[Attributed to R. Lemons in J. Bentley "Programming Pearls,"
Communications of the ACM, Vol. 28, No. 9, 1985, pp. 896-899.] In using the
form shown in Table 14-0, a clerk need only enter the code and quantity for an
item; the verbal description and unit cost of the item then appear
automatically. A copy of the transfer form can be printed locally, while the
data is stored in the computer for subsequent processing. As a result,
preparing transfer forms and record keeping are rapidly and effectively
performed.
More dramatically, the computerized information allows warehouse personnel
both to ask questions about equipment management and to readily generate the
requisite data for answering such questions. The records of transfers can be
readily processed by computer programs to develop bills and other reports. For
example, proposals to purchase new pieces of equipment can be rapidly and
critically reviewed after summarizing the actual usage of existing equipment.
Ultimately, good organization of information will typically lead to the desire
to store new types of data and to provide new views of this information as
standard managerial tools.
Of course, implementing an information system such as the warehouse
inventory database requires considerable care to insure that the resulting
program is capable of accomplishing the desired task. In the warehouse
inventory system, a variety of details are required to make the computerized
system an acceptable alternative to a long standing manual record keeping
procedure. Coping with these details makes a big difference in the system's
usefulness. For example, changes to the status of equipment are generally made
by recording transfers as illustrated in Table 14-0. However, a few status
changes are not accomplished by physical movement. One example is a charge for
air conditioning in field trailers: even though the air conditioners may be
left in the field, the construction project should not be charged for the air
conditioner after it has been turned off during the cold weather months. A
special status change report may be required for such details. Other details
of record keeping require similar special controls.
Even with a capable program, simplicity of design for users is a critical
factor affecting the successful implementation of a system. In the warehouse
inventory system described above, input forms and initial reports were designed
to duplicate the existing manual, paper-based records. As a result, warehouse
clerks could readily understand what information was required and its ultimate
use. A good rule to follow is the Principle of Least Astonishment: make
communications with users as consistent and predictable as possible in
designing programs.
Finally, flexibility of systems for changes is an important design and
implementation concern. New reports or views of the data is a common
requirement as the system is used. For example, the introduction of a new
accounting system would require changes in the communications procedure from
the warehouse inventory system to record changes and other cost items.
In sum, computerizing the warehouse inventory system could save considerable
labor, speed up billing, and facilitate better management control. Against
these advantages must be placed the cost of introducing computer hardware and
software in the warehouse.
Given the bulk of information associated with construction projects, formal
organization of the information is essential so as to avoid chaos. Virtually
all major firms in the arena of project management have computer based
organization of cost accounts and other data. With the advent of
micro-computer database managers, it is possible to develop formal,
computerized databases for even small organizations and projects. In this
section, we will discuss the characteristics of such formal databases.
Equivalent organization of information for manual manipulation is possible but
tedious. Computer based information systems also have the significant
advantage of rapid retrieval for immediate use and, in most instances, lower
overall costs. For example, computerized specifications writing systems have
resulted in well documented savings. These systems have records of common
specification phrases or paragraphs which can be tailored to specific project
applications. [See Wilkinson, R.W. "Computerized Specifications on a Small
Project," ASCE Journal of Construction Engineering and Management, Vol. 110,
No. CO3, 1984, pp. 337-345.]
Formally, a database is a collection of stored operational information used
by the management and application systems of some particular enterprise.[See
C.J. Date, An Introduction to Database Systems, 3rd ed., Addison-Wesley
Publishing Company, Reading, MA, 1981.] This stored information has explicit
associations or relationships depending upon the content and definition of the
stored data, and these associations may themselves be considered to be part of
the database. Figure 14-0 illustrates some of the typical elements of a
database. The internal model is the actual location and representation of the
stored data. At some level of detail, it consists of the strings of "bits"
which are stored in a computer's memory, on the tracks of a recording disk, on
a tape, or on some other storage device.
A manager need not be concerned with the details of data storage since this
internal representation and manipulation is regulated by the Database Manager
Program (DBM). The DBM is the software program that directs the storage,
maintenance, manipulation and retrieval of data. Users retrieve or store data
by issuing specific requests to the DBM. The objective of introducing a DBM is
to free the user from the detail of exactly how data are stored and
manipulated. At the same time, many different users with a wide variety of
needs can use the same database by calling on the DBM. Usually the DBM will be
available to a user by means of a special query language. For example, a
manager might ask a DBM to report on all project tasks which are scheduled to
be underway on a particular date. The desirable properties of a DBM include
the ability to provide the user with ready access to the stored data and to
maintain the integrity and security of the data. Numerous commercial DBM exist
which provide these capabilities and can be readily adopted to project
management applications.
While the actual storage of the information in a database will depend upon
the particular machine and storage media employed, a Conceptual Data Model
exists which provides the user with an idea or abstract representation of the
data organization. (More formally, the overall configuration of the
information in the database is called the conceptual schema.) For example, a
piece of data might be viewed as a particular value within a record of a
datafile. In this conceptual model, a datafile for an application system
consists of a series of records with pre-defined variables within each record.
A record is simply a sequence of variable values, which may be text characters
or numerals. This datafile model is one of the earliest and most important
data organization structures. But other views of data organization exist and
can be exceedingly useful. The next section describes one such general model,
called the relational model.
Continuing with the elements in Figure 14-0, the data dictionary contains
the definitions of the information in the database. In some systems, data
dictionaries are limited to descriptions of the items in the database. More
general systems employ the data dictionary as the information source for
anything dealing with the database systems. It documents the design of the
database: what data are stored, how the data is related, what are the allowable
values for data items, etc. The data dictionary may also contain user
authorizations specifying who may have access to particular pieces of
information. Another important element of the data dictionary is a
specification of allowable ranges for pieces of data; by prohibiting the input
of erroneous data, the accuracy of the database improves.
External models are the means by which the users view the database. Of all
the information in the database, one particular user's view may be just a
subset of the total. A particular view may also require specific translation
or manipulation of the information in the database. For example, the external
model for a paycheck writing program might consist solely of a list of
employee names and salary totals, even if the underlying database would include
employee hours and hourly pay rates. As far as that program is concerned, no
other data exists in the database. The DBM provides a means of translating
particular external models or views into the overall data model. Different
users can view the data in quite distinct fashions, yet the data itself can be
centrally stored and need not be copied separately for each user. External
models provide the format by which any specific information needed is
retrieved. Database "users" can be human operators or other application
programs such as the paycheck writing program mentioned above.
Finally, the Database Administrator is an individual or group charged with
the maintenance and design of the database, including approving access to the
stored information. The assignment of the database administrator should not be
taken lightly. Especially in large organizations with many users, the database
administrator is vital to the success of the database system. For small
projects, the database administrator might be an assistant project manager or
even the project manager.
As an example of how data can be organized conceptually, we shall describe
the relational data model. In this conceptual model, the data in the database
is viewed as being organized into a series of relations or tables of data
which are associated in ways defined in the data dictionary. A relation
consists of rows of data with columns containing particular attributes. The
term "relational" derives from the mathematical theory of relations which
provides a theoretical framework for this type of data model. Here, the terms
"relation" and data "table" will be used interchangeably. Table 14-0 defines
one possible relation to record unit cost data associated with particular
activities. Included in the database would be one row (or tuple) for each of
the various items involved in construction or other project activities. The
unit cost information associated with each item is then stored in the form of
the relation defined in Table 14-0.
Using Table 14-0, a typical unit cost entry for an activity in construction
might be:
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
Industry!!! Total!!! Lost!!!
!!! Cases!!! Workdays!!!
Agriculture, forestry, fishing!!!7.7!!!86.0!!!
Mining!!!10.5!!!137.3!!!
Construction!!!14.6!!!115.7!!!
Manufacturing!!!10.2!!!75.0!!!
Transportation, utilities!!!8.5!!!96.7!!!
Wholesale and retail trade!!!7.2!!!45.5!!!
Finance, insurance, real estate!!!2.0!!!13.2!!!
Services!!!4.9!!!35.8!!!
Note: Data represent total number of cases and\*
lost workdays per 100 workers in US industries in 1982.
Source: U.S. Dept. of Commerce, Statistical Abstract of the United States,
Washington, D.C.: Government Printing Office, Table No. 713, Pg. 426, 1985.
______________________________________________________________________________
______________________________________________________________________________
All Accidents!!! Fatal Accidents!!!
Cause!!! Percentage!!! Cause!!! Percentage!!!
Falls of Persons!!! 30.0!!!Falls of Persons!!! 48.1!!!
Handling Goods!!!24.8!!!Falls of Materials!!! 11.7!!!
Falls of Materials!!! 8.0!!!Transport!!! 11.7!!!
Transport!!! 5.4!!!Lifting Equipment!!! 8.4!!!
Lifting Equipment!!! 1.6!!!Electricity!!! 5.2!!!
Excavation and Tunneling!!! 0.6!!!*\
Excavation and Tunneling!!! 4.5!!!
Miscellaneous!!! 29.5!!!Miscellaneous!!! 10.4!!!
Source: Department of Employment, "Reported Accidents in Construction,"
Health and Safety Executive, London: Her Majesty's Stationary Office, April
1978.
______________________________________________________________________________
______________________________________________________________________________
TRANSFER SHEET NUMBER 100311 !!!Deliver To: Carnegie-Mellon !!!Job. No. 83-1557
!!!Received From: Pittsburgh Warehouse !!!Job No. 99-PITT
ITEM NO.!!!EQ. NO.!!!QTY!!! DESCRIPTION!!!UNIT PRICE
0609.02!!!!!!200!!!Hilti Pins NK27!!! 0.36
0609.03!!!!!!200!!!Hilti Pins NK27!!! 0.36
0188.21!!!!!!1!!!Kiel, Box of 12!!! 6.53
0996.01!!!!!!3!!!Paint, Spray!!! 5.57
0607.03!!!!!!4!!!Plywood, 4 x 8 x 1/4"!!! 11.62
0172.00!!!4517!!!1!!!Grinder
0181.53!!!!!!1!!!Grinding Wheel, 6" Cup!!! 14.97
Preparer: Vicki!!!!!!Date: x/xx/xx
______________________________________________________________________________
______________________________________________________________________________
____________________________________________________________________________
This entry summarizes the unit costs associated with construction of 12" thick
brick masonry walls, as indicated by the item DESCRIPTION. The ITEM_CODE is a
numerical code identifying a particular activity. This code might identify
general categories as well; in this case, 04.2 refers to general masonry work.
ITEM_CODE might be based on the MASTERFORMAT or other coding scheme. The
CREW_CODE entry identifies the standard crew which would be involved in the
activity. The actual composition of the standard crew would be found in a CREW
RELATION under the entry 04.2-3, which is the third standard crew involved in
masonry work (04.2). This ability to point to other relations reduces the
redundancy or duplication of information in the database. In this case,
standard crew number 04.2-3 might be used for numerous masonry construction
tasks, but the definition of this crew need only appear once.
WORK_UNIT, OUTPUT and TIME_UNIT summarize the expected output for this task
with a standard crew and define the standard unit of measurement for the item.
In this case, costs are given per thousand bricks per shift. Finally, material
(MATL_UNIT_COST) and installation (INSTCOSTS) costs are recorded along with the
date (DATEMCOS and DATEICOS) at which the prices were available and entered in
the database. The date of entry is useful to insure that any inflation in
costs can be considered during use of the data.
The data recorded in each row could be obtained by survey during bid
preparations, from past project experience or from commercial services. For
example, the data recorded in the Table 14-0 relation could be obtained as
nationwide averages from commercial sources.
An advantage of the relational database model is that the number of
attributes and rows in each relation can be expanded as desired. For example,
a manager might wish to divide material costs (MATL_UNIT_COST) into attributes
for specific materials such as cement, aggregate and other ingredients of
concrete in the unit cost relation defined in Table 14-0. As additional items
are defined or needed, their associated data can be entered in the database as
another row (or tuple) in the unit cost relation. Also, new relations can be
defined as the need arises. Hence, the relational model of database
organization can be quite flexible in application. In practice, this is a
crucial advantage. Application systems can be expected to change radically
over time, and a flexible system is highly desirable.
With a relational database, it is straightforward to issue queries for
particular data items or to combine data from different relations. For
example, a manager might wish to produce a report of the crew composition
needed on a site to accomplish a given list of tasks. Assembling this report
would require accessing the unit price information to find the standard crew
and then combining information about the construction activity or item (eg.
quantity desired) with crew information. However, to effectively accomplish
this type of manipulation requires the definition of a "key" in each relation.
In Table 14-0, the ITEMCODE provides a unique identifier or key for each
row. No other row should have the same ITEMCODE in any one relation. Having a
unique key reduces the redundancy of data, since only one row is included in
the database for each activity. It also avoids error. For example, suppose
one queried the database to find the material cost entered on a particular
date. This response might be misleading since more than one material cost
could have been entered on the same date. Similarly, if there are multiple
rows with the same ITEMCODE value, then a query might give erroneous responses
if one of the rows was out of date. Finally, each row has only a single entry
for each attribute.[This is one example of a normalization in relational
databases. For more formal discussions of the normalizations of relational
databases and the explicit algebra which can be used on such relations, see
Date op cit.]
The ability to combine or separate relations into new arrangements permits
the definition of alternative views or external models of the information.
Since there are usually a number of different users of databases, this can be
very useful. For example, the payroll division of an organization would
normally desire a quite different organization of information about employees
than would a project manager. By explicitly defining the type and organization
of information a particular user group or application requires, a specific view
or subset of the entire database can be constructed. This organization is
illustrated in Fig. 14-0 with the DATA DICTIONARY serving as a translator
between the external data models and the database management system.
Behind the operations associated with querying and manipulating relations is
an explicit algebraic theory. This algebra defines the various operations that
can be performed on relations, such as union (consisting of all rows belonging
to one or the other of two relations), intersection (consisting of all rows
belonging to both of two relations), minus (consisting of all rows belonging to
one relation and not another), or projection (consisting of a subset of the
attributes from a relation). The algebraic underpinnings of relational
databases permits rigorous definitions and confidence that operations will be
accomplished in the desired fashion. [For a discussion of relational algebra,
see E.F. Codd, "Relational Completeness of Data Base Sublanguages," Courant
Computer Science Symposia Series, Vol. 6, Prentice-Hall, l972.]
Example 14-3: A Subcontractor Relation
As an illustration of the preceding discussion, consider the problem of
developing a database of possible subcontractors for construction projects.
This database might be desired by the cost estimation department of a general
contractor to identify subcontractors to ask to bid on parts of a project.
Appropriate subcontractors appearing in the database could be contacted to
prepare bids for specific projects. Table 14-0 lists the various attributes
which might be required for such a list and an example entry, including the
subcontractor's name, contact person, address, size (large, medium or small),
and capabilities.
______________________________________________________________________________
!!!Attribute!!! Example
!!!NAME!!!XYZ Electrical Co.
!!!CONTACT!!!Betty XYZ
!!!PHONE!!!(412) xxx-xxxx
!!!STREET!!!xxx Mulberry St.
!!!CITY!!!Pittsburgh
!!!STATE!!!PA
!!!ZIPCODE!!!152xx
!!!SIZE!!!large
!!!CONCRETE!!!no
!!!ELECTRICAL!!!yes
!!!MASONRY!!!no
!!! etc.
______________________________________________________________________________
To use this relation, a cost estimator might be interested in identifying
large, electrical subcontractors in the database. A query typed into the DBM
such as:
Other portions of the general contracting firm might also wish to use this
list. For example, the accounting department might use this relation to record
the addresses of subcontractors for payment of invoices, thereby avoiding the
necessity to maintain duplicate files. In this case, the accounting code
number associated with each subcontractor might be entered as an additional
attribute in the relation, and the accounting department could find addresses
directly.
Example 14-4: Historical Bridge Work Relation
As another simple example of a data table, consider the relation shown in
Table 14-0 which might record historical experience with different types of
bridges accumulated by a particular agency. The actual instances or rows of
data in Table 14-0 are hypothetical. The attributes of this relation are:
______________________________________________________________________________
Project Number!!!Type of Bridge!!!Location!!!Crossing ....!!!
170145!!!Steel Plate Girder!!!Altoona!!!Railroad ....!!!
169137!!!Concrete Arch!!!Pittsburgh!!!Highway ....!!!
197108!!!Steel Truss!!!Allentown!!!River ....!!!
...Site Conditions!!!Erection Time!!! Span (ft.)!!!Estimated less!!!
!!! (Months) !!!!!!Actual Cost!!!
...200' Valley!!!5!!!240!!!-50,000!!!
...Limestone!!!
...250' High!!!6!!!278!!!-27,500!!!
...Sandy Loam
...Urban Area!!!7!!!256!!!35,000!!!
...135' Deep!!!8!!!282!!!-84,800!!!
...Pile Foundation!!!
______________________________________________________________________________
As an example, suppose that a bridge is to be built with a span of 250 feet,
located in Pittsburgh PA, and crossing a river with limestone sub-strata. In
initial or preliminary planning, a designer might query the database four
separate times as follows:
The four queries may represent subsequent thoughts of a designer faced with
these problem conditions. He or she may first ask, "What experience have we
had with bridges of this span over rivers?" "What experience have we had with
bridges of this span with these site conditions? What is our experience with
steel girder bridges in Pennsylvania? For bridges of this span, how many and
which were erected without a sizable cost overrun? We could pose many more
questions of this general type using only the small data table shown in Table
14-0.
While the relational model offers a considerable amount of flexibility and
preserves considerable efficiency, there are several alternative models for
organizing databases, including network and hierarchical models. The
hierarchical model is a tree structure in which information is organized as
branches and nodes from a particular base.[See D.C. Trichritzis and F.H.
Lochovsky, "Hierarchical Data-Base Management," ACM Computing Surveys Vol. 8,
No. 1, 1976, pp. 105-123.] As an example, Figure 14-0 illustrates a
hierarchical structure for rented equipment costs. In this case, each piece of
equipment belongs to a particular supplier and has a cost which might vary by
the duration of use. To find the cost of a particular piece of equipment from
a particular supplier, a query would first find the supplier, then the piece of
equipment and then the relevant price.
The hierarchical model has the characteristic that each item has a single
predecessor and a variable number of subordinate data items. This structure is
natural for many applications, such as the equipment cost information described
above. However, it might be necessary to construct similar hierarchies for
each project to record the equipment used or for each piece of equipment to
record possible suppliers. Otherwise, generating these lists of assignments
from the database illustrated in Figure 14-0 would be difficult. For example,
finding the least expensive supplier of a crane might involve searching every
supplier and every equipment node in the database to find all crane prices.
The network model or database organization retains the organization of
information on branches and nodes, but does not require a tree of structure
such as the one in Figure 14-0.[For a more extensive comparison, see A.S.
Michaels, B. Mittman, and C.R. Carlson, "A Comparison of Relational and CODASYL
Approaches to Data-Base Management," ACM Computing Surveys, Vol. 8, No. 1,
1976, pp. 125-157.] This gives greater flexibility but does not necessarily
provide ease of access to all data items. For example, Figure 14-0 shows a
portion of a network model database for a building. The structural member
shown in the figure is related to four adjoining members, data on the joints
designed for each end, an assembly related to a room, and an aggregation for
similar members to record member specifications.
While the early, large databases were based on the hierarchical or network
organizations, the relational model is now preferred in many applications due
to its flexibility and conceptual simplicity.
More recently, some new forms of organized databases have appeared, spurred
in part by work in artificial intelligence. For example, Figure 14-0
illustrates a frame data structure used to represent a building design
element. This frame describes the location, type, cost, material, scheduled
work time, etc. for a particular concrete footing. A frame is a general
purpose data representation scheme in which information is arranged in slots
within a named frame. Slots may contain lists, values, text, procedural
statements (such as calculation rules), pointers or other entities. Frames can
be inter-connected so that information may be inherited between slots. Figure
14-0 illustrates a set of inter-connected frames used to describe a building
design and construction plan.[This organization is used for the central data
store in an integrated building design environment. See Fenves, S.,
U. Flemming, C. Hendrickson, M. Maher, and G. Schmitt, "An Integrated Software
Environment for Building Design and Construction," Proc. of the Fifth ASCE
Conference on Computing in Civil Engineering, 1987] Object oriented data
representation is similar in that very flexible local arrangements of data are
permitted. While these types of data storage organizations are active areas of
research, commercial database systems based on these organizations are not yet
available.
Whichever conceptual model or database management system is adopted, the use
of a central database management system has a number of advantages and some
costs compared to the commonly employed special purpose datafiles. A datafile
consists of a set of records arranged and defined for a single application
system. Relational information between items in a record or between records is
not explicitly described or available to other application systems. For
example, a file of project activity durations and scheduled times might be
assembled and manipulated by a project scheduling system. This datafile would
not necessarily be available to the accounting system or to corporate planners.
A centralized DBM has several advantages over such stand-alone systems:[For
a discussion, see D.R. Rehak and L.A. Lopez, Computer Aided Engineering
Problems and Prospects, Civil Engr. Systems Lab., Univ. of Illinois, Urbana,
IL, 1981.]
As an example, suppose that the Purchasing Department keeps records of
equipment rental costs on each project underway. This data is arranged so that
payment of invoices can be handled expeditiously and project accounts are
properly debited. The records are arranged by individual suppliers for this
purpose. These records might not be particularly useful for the purpose of
preparing cost estimates since:
A manager need not conclude from this discussion that initiating a formal
database will be a panacea. Life is never so simple. Installing and
maintaining databases is a costly and time consuming endeavor. A single
database is particularly vulnerable to equipment failure. Moreover, a central
database system may be so expensive and cumbersome that it becomes ineffective;
we will discuss some possibilities for transferring information between
databases in a later section. But lack of good information and manual
information management can also be expensive.
One might also contrast the operation of a formal, computerized database
with that of a manual filing system. For the equipment supplier example cited
above, an experienced purchasing clerk might be able to immediately find the
lowest cost supplier of a particular piece of equipment. Making this
identification might well occur in spite of the formal organization of the
records by supplier organization. The experienced clerk will have his (or her)
own subjective, conceptual model of the available information. This subjective
model can be remarkably powerful. Unfortunately, the mass of information
required, the continuing introduction of new employees, and the need for
consistency on large projects make such manual systems less effective and
reliable.
The usefulness of a database organization is particularly evident in
integrated design or management environments. In these systems, numerous
applications programs share a common store of information. Data is drawn from
the central database as needed by individual programs. Information requests
are typically performed by including pre-defined function calls to the database
management system within an application program. Results from one program are
stored in the database and can be used by subsequent programs without
specialized translation routines. Additionally, a user interface usually
exists by which a project manager can directly make queries to the database.
Figure 14-6 illustrates the role of an integrated database in this regard as
the central data store.
An architectural system for design can provide an example of an integrated
system.[See W.J. Mitchell, Computer-Aided Architectural Design, Van Nostrand
Reinhold Co., New York, 1977.] First, a database can serve the role of storing
a library of information on standard architectural features and component
properties. These standard components can be called from the database library
and introduced into a new design. The database can also store the description
of a new design, such as the number, type and location of individual building
components. The design itself can be composed using an interactive graphics
program. This program would have the capability to store a new or modified
design in the database. A graphics program typically has the capability to
compose numerous, two or three dimensional views of a design, to introduce
shading (to represent shadows and provide greater realism to a perspective),
and to allow editing (including moving, replicating, or sizing individual
components). Once a design is completed and its description stored in a
database, numerous analysis programs can be applied, such as:
The advantage of an integrated system of this sort is that each program need
only be designed to communicate with a single database. Accomplishing
appropriate transformations of data between each pair of programs would be much
more difficult. Moreover, as new applications are required, they can be added
into an integrated system without extensive modifications to existing programs.
For example, a library of specifications language or a program for joint design
might be included in the design system described above. Similarly, a
construction planning and cost estimating system might also be added; an
example is described in Chapter 15.
The use of integrated systems with open access to a database is not common
for construction activities at the current time. Typically, commercial systems
have a closed architecture with simple datafiles or a "captive," inaccessible
database management system. However, the benefits of an open architecture with
an accessible database are considerable as new programs and requirements become
available over time.
Example 14-5: An Integrated System Design
As an example, Figure 14-0 illustrates the computer aided engineering (CAE)
system envisioned for the knowledge and information-intensive construction
industry of the future.[This figure was adapted from Y. Ohsaki and M. Mikumo,
"Computer-aided Engineering in the Construction Industry," Engineering with
Computers, vol. 1, no. 2, 1985, pp. 87-102.] In this system, comprehensive
engineering and "business" databases support different functions throughout the
life time of a project. The construction phase itself includes overlapping
design and construction functions. During this construction phase, computer
aided design (CAD) and computer aided manufacturing (CAM) aids are available to
the project manager. Databases recording the "as-built" geometry and
specifications of a facility as well as the subsequent history can be
particularly useful during the use and maintenance life cycle phase of the
facility. As changes or repairs are needed, plans for the facility can be
accessed from the database.
The previous sections outlined the characteristics of a computerized
database. In an overabundance of optimism or enthusiasm, it might be tempting
to conclude that all information pertaining to a project might be stored in a
single database. This has never been achieved and is both unlikely to occur
and undesirable in itself. Among the difficulties of such excessive
centralization are:
While a single database may be undesirable, it is also apparent that it is
desirable to structure independent application systems or databases so that
measurement information need only be manually recorded once and communication
between the database might exist. Consider the following examples illustrating
the desirability of communication between independent application systems or
databases. While some progress has occurred, the level of integration and
existing mechanisms for information flow in project management is fairly
primitive. By and large, information flow relies primarily on talking, written
texts of reports and specifications and drawings.
Example 14-6: Time Cards
Time card information of labor is used to determine the amount which
employees are to be paid and to provide records of work performed by activity.
In many firms, the system of payroll accounts and the database of project
management accounts (i.e., expenditure by activity) are maintained
independently. As a result, the information available from time cards is often
recorded twice in mutually incompatible formats. This repetition increases
costs and the possibility of transcription errors. The use of a preprocessor
system to check for errors and inconsistencies and to format the information
from each card for the various systems involved is likely to be a significant
improvement (Figure 14-0). Alternatively, a communications facility between
two databases of payroll and project management accounts might be developed.
Example 14-7: Final Cost Estimation, Scheduling and Monitoring
Many firms maintain essentially independent systems for final cost
estimation and project activity scheduling and monitoring. As a result, the
detailed breakdown of the project into specific job related activities must be
completely re-done for scheduling and monitoring. By providing a means of
rolling-over or transferring the final cost estimate, some of this expensive
and time-consuming planning effort could be avoided.
Example 14-8: Design Representation
In many areas of engineering design, the use of computer analysis tools
applied to facility models has become prevalent and remarkably effective.
However, these computer-based facility models are often separately developed or
encoded by each firm involved in the design process. Thus, the architect,
structural engineer, mechanical engineer, steel fabricator, construction
manager and others might all have separate computer-based representations of a
facility. Communication by means of reproduced facility plans and prose
specifications is traditional among these groups. While transfer of this
information in a form suitable for direct computer processing is difficult, it
offers obvious advantages in avoiding repetition of work, delays and
transcription errors.
As described in earlier chapters, computer aids available for project
management include project scheduling, accounting and computer aided design.
Chapter 14 described the implementation of computerized databases and
information systems intended to support a broad range of such applications for
project management. Our attention on computer aids reflects the increasing
usefulness of these systems to a project manager. With the introduction of
less expensive computers and more capable, easier-to-use application programs,
the use of computers to aid project management has taken off. Now, it is
common to find microcomputers to aid managers even on construction sites. The
computer revolution has reached the practice of project management, and
project managers should be prepared to take full advantage of these automated
tools. It is this potential which has motivated the attention on computer
based aids in this text.
Even with the expansion of computer uses in project management, most
applications are restricted to formal numerical analysis of well defined
problems. In this chapter, some new types of computer based aids for project
management will be described. These are knowledge based expert systems, which
were originally developed as an outgrowth of research in artificial
intelligence. Knowledge based expert systems are often called knowledge based
systems or, more simply, expert systems. These systems are computer programs
which were originally intended to mimic the performance of a human expert in a
limited problem domain. By avoiding some of the restrictions associated with
conventional programs, these systems have the potential for greatly expanding
the range of available computer aids for a project manager. More generally,
artificial intelligence is the study of models of complex information
processing and simulation of human cognitive processes. Expert systems apply
"artificial" problem solving strategies to practical problems in limited
problem domains.
Expert systems use specific knowledge of an application area (or domain)
and heuristic problem solving methods to perform functions normally reserved
for a human expert. Heuristic methods are techniques which may not be complete
for all possible conditions or yield good results in all cases. For example, a
heuristic rule in scheduling the sequence of repairs on a number of vehicles
would be: "schedule the vehicles which are easiest to repair first." The
result is to minimize the number of vehicles waiting for repair, but to
increase the amount of time that vehicles needing major repairs must wait.
This is a simple scheduling heuristic that could be used in a variety of
applications. "Domain specific knowledge" in this vehicle repair example would
consist of rules indicating the ease with which particular repairs could be
undertaken. Other expert system applications would have quite different domain
specific information, even if the same scheduling heuristic was used. For
example, a warehouse scheduling system might give priority to "easy" orders
which require less handling time.
The success of any expert system depends mainly on the system developer's
ability to formalize and to represent the knowledge and problem solving
procedures employed by a particular expert. In some cases, this expertise may
consist of the ability to recognize a particular situation or pattern in the
environment out of the many thousands of possible situations. This pattern
recognition expertise is difficult to formalize in a computer program. In
other cases, a limited number of rules or organizational patterns may be
sufficient for good problem-solving. Practical expert systems exist with a few
dozen to many thousand rules. In either case, experts typically have
difficulty formalizing the methods they employ to reach conclusions, so the
development of an expert system is largely a matter of slowly experimenting and
expanding known bits of information relevant to the domain.
An important side benefit of this process of expert system development is
the formal organization of information that was previously unexpressed. As
knowledge and problem solving strategies are formalized in the expert system,
this information which had been available only to the domain expert can be
recorded for use elsewhere, validated, or generalized for new situations. It
is also possible that the process of developing an heuristic expert system may
reveal the potential for an optimization or analytic algorithmic solution,
thereby making the problem better understood, easier to solve and amenable to a
conventional computer aid.
Early research in artificial intelligence concentrated upon the general
representation and manipulation of symbols, especially in an effort to
duplicate human learning and problem solving techniques. Early systems began
with only general purpose problem solving strategies such as a structured
search process and no specific knowledge about the domain. The performance of
these "general purpose" systems was disappointing. The first generation of
expert systems emerged when these general problem-solving strategies were
intimately combined with specific domain knowledge. The results were systems
that could solve practical problems in limited domains such as geological
prospecting or molecular genetics experimentation. The next major development
occurred when problem-solving techniques and domain-specific knowledge were
separated, permitting the combination of new domain knowledge with existing
problem-solving frameworks. These problem-solving frameworks became expert
system shells or environments in which system developers only needed to add
domain specific knowledge to create a new expert system.
Reflecting this history, a usual characteristic of expert systems is the
separation of the knowledge base, the problem solving control strategy, and the
description of a particular problem. Consequently, a simple production expert
system consists of three central components: (1) a knowledge base expressed in
a series of rules specific to a particular domain, (2) the context which
describes the known or deduced information about a particular problem; and (3)
an inference engine or inference machine which is an operator to apply the
knowledge base rules to modify the contents of the context. As illustrated in
Figure 15-0, the knowledge base is extracted from an expert, and the problem
presented by a user is represented in the context. The problem description,
the steps used in the solution process and conclusions are communicated to the
user. In solving a problem, the inference engine decides what to do next to
alter the problem description in the context. A typical simple production
consists of an "if-then" rule stating the preconditions and corresponding
actions. Applying or firing a rule occurs only if the preconditions are true
and the result is an implementation of the actions specified by the rule.
As a simple example, suppose that the context included scheduling
information and the knowledge base included a rule of the following form: Of course, the three components shown in Figure 15-0 do not make a full
system: some additional facilities are required. First, an expert system
should have the capability of explaining conclusions or the reasoning employed
on a particular problem interactively (Figure 15-0). This dialogue is intended
to aid users and to provide a check on the performance of the system. Since
explanations are made of the specific problem at hand and of the problem
solving actions actually undertaken, an expert system's explanation facility
is quite different from the on-line "help" facilities provided in many programs
or the complete absence of explanations in some conventional, "black box"
application programs. The dialogue between a user and an expert system is
conducted by means of a user interface which can have a multitude of forms
including keyboards, drawings, or selection menus.
Another component in a full expert system is the knowledge acquisition
facility shown in Figure 15-0. Initially, this component permits the entry
and editing of domain knowledge from the expert for the creation of a new
system. As expert system frameworks have developed, this initial knowledge
entry has become easier. Originally, knowledge was entered in special computer
languages such as PROLOG or LISP. Improved expert system frameworks permit
different kinds of input, including some systems in which natural languages or
examples can be used to input rules. More importantly, this facility permits
incremental expansion of the system as new rules are added. As a result, new
knowledge can be represented or the system can be tailored to an individual
user's objectives and tastes. This incremental growth is quite different from
conventional systems in which patchwork corrections and modifications can be
extremely difficult. By separating the knowledge base from the control
mechanism and by using "if-then" rule productions or similar atomic information
representations, expert systems readily lend themselves to modification over
time.
It is also useful to reflect on the characteristics of a human expert that
typical expert systems lack. An expert system has very limited senses and
virtually no "common sense." An expert system knows only what it is told; it
has no independent means of obtaining information. In contrast, humans can
observe widely on a site and notice peculiarities that might never be reported
to a computer system. Expert systems are designed to operate in a limited
problem domain, and they usually will know nothing about common sense
requirements. For example, unless an expert system is explicitly "told" that
worker rest breaks are required, it would not plan for such breaks. In
addition to cognitive problem solving skills, more advanced expert systems
might also include other human qualities such as the ability to adapt and to
learn in the face of new circumstances or as experience accumulates. While
most existing expert systems do not possess automatic abilities of this type,
it is possible to envision mechanisms by which learning can be introduced.
Modeling of human cognition provided much of the early impetus for expert
system development. Early researchers in the area were interested in capturing
the actual processes used by human experts. While this artificial intelligence
research is still a fruitful analogy and source of new concepts, it is not
essential to maintain that all expert systems must incorporate or mimic human
thinking and problem solving. In particular, expert systems represent a useful
computer system development environment for many applications, whether or not
they represent a realistic model of human cognition. In many cases, "expert
system" environments represent the most convenient programming and problem
solving environment, regardless of their similarity or dissimilarity to human
thinking.
The principal distinction between expert systems and algorithmic programs
lies in the use of knowledge. A conventional algorithmic application program
is organized into data and program. Data manipulation is repetitive and fully
specified in advance. An expert system is organized to best represent and use
knowledge. It is not guaranteed to reach a correct solution nor is the course
of problem solving predictable in advance. As a result, the organization and
content of expert systems can be quite different from conventional programs.
Reflecting the different style of an expert system, a common difference
between expert systems and conventional programs is the separation of the
knowledge-base from the control mechanism. In Figure 15-0, this separation is
represented by the separate box around the inference engine component. By
maintaining this separation, expert systems can use complex rules and handle
difficult problem domains without become bogged down in the problem of program
control.
A second distinguishing characteristic of an expert system is the
self-knowledge inherent in the program. A true expert system can examine its
own reasoning and explain its operation during execution. Conventional "help"
facilities do not provide this level of dialog transparency since these
facilities are separate from the actual program execution.
A third characteristic of expert system is the identifiable expertise in the
program. Ideally, this expertise should be sufficient to permit expert
performance in a limited domain. The expertise should also be readable,
understandable, and capable of manipulation (i.e., displaying, searching,
modifying) apart from application of the system.
A final characteristic of an expert system is the ability for incremental
expansion without major changes to the control strategy. By permitting
modification over time, expert systems can be customized to particular users or
updated to reflect new situations.
Of course, none of these characteristics provide an acid test for
classifying an expert system. Generally, the boundaries between conventional
and expert system programs are fuzzy, with expert systems recognized as much by
intent as by style. The line between conventional programs and expert systems
is likely to become even more difficult to draw as better expert system
enviornments in conventional programmaing languages (e.g. FORTRAN, PASCAL, or
C) are developed and as richer integration of expert systems and conventional
programs appear.
Expert systems are appearing in many application areas. Of course, not all
tasks are amenable to this type of system. The range of possible applications
is growing, however, as users become more familiar with the capabilities of
expert systems, the software environments for expert systems improve, and new
problem solving and date representation strategies are devised. A partial list
of criteria to evaluate promising potential applications would include:
______________________________________________________________________________
______________________________________________________________________________
The process of building an expert system is similar in nature to producing a
plan of work or a facility design. Typical steps include problem
identification, system design, knowledge acquisition, implementation, testing,
and revision. Problem identification requires the development of a well
defined problem and domain for application, as well as the overall goals for
the system. System design involves the selection of the overall structure or
architecture of the expert system, including data representation and
appropriate problem solving strategies. After the design is formalized,
knowledge is acquired through interviews and interaction with a domain expert
as part of the knowledge acquisition process. Ideally, the domain expert
himself or herself might serve as the system developer, so the communication
required in this step is minimized. A useful strategy in the process of
knowledge acquisition is to produce simple systems that are refined through the
use of example problem solving. Encoding the system design and knowledge is
accomplished in the implementation phase. By taking advantage of the various
tools that are available for building expert systems, implementation of the
system can be greatly simplified. Testing and revision of the resulting
program are essential steps in the process. Indeed, the typical development of
an expert system requires the testing and modification of numerous prototype
systems in an iterative fashion.
The goals of developing expert systems are generally threefold: usefulness,
performance and transparency. In essence, the expert system must be capable of
performing a useful, problem solving function. It should have an acceptably
high level of performance over the desired range of applications. Ideally, it
should utilize the specialized knowledge that separates human experts from
novices to accomplish the desired performance level. Finally, the expert
system should be capable of explaining its actions and reasoning to a user. In
practice, expert systems are often used as assistants to human users, so
adequate explanations are essential.
The interaction of conventional programs and expert systems is likely to
lead to rapid development in the future. Originally, expert systems were
developed as stand-alone programs to assist a human user (Figure 15-0(a)).
More recently, the capabilities of expert systems for formulating problems,
checking the reasonableness of data, or providing explanations and
interpretations sparked considerable interest in expert system as
pre-processors or post-processors for conventional programs (Figure 15-0(b)).
The feature extraction and strategic planning capabilities of expert systems
provide incentives for the introduction of expert systems into sensor systems
and robots (Figure 15-0(c)). Finally, there is the possibility that expert
systems can interact with external databases or other application programs
(Figure 15-0). For project management applications, this interaction is
extremely important since extensive data exists about projects and a number of
existing application programs provide extremely useful results, such as
critical path scheduling. As a result, expert systems need not be used or
developed as independent programs, but can operate in concert with other
programs.
As an outgrowth of research in artificial intelligence, full blown expert
systems might be expected to duplicate the existing problem solving performance
of an expert but also to have the capability to adapt, learn, and invent in a
fashion similar to humans. This capability does not yet exist in practical
expert systems, and there are some observers who believe that artificial
intelligence programs will never exhibit these human characteristics. Even
without these dimensions, expert systems offer a means to deal with a variety
of the ill-structured aspects of project management. They represent an
important new tool in the repertoire of good project managers.
In rule based expert systems, the most common solution strategies are
forward chaining, backward chaining or a mixture of the two. Rule based expert
systems represent knowledge as a series of productions with a premise (an if
clause) and a conclusion (a then clause).
In the forward chaining approach, the system works from an initial state of
known facts and draws inferences until a final goal state is reached. With a
forward chaining strategy, the user inputs known information, and rules are
then applied to draw conclusions. Intermediate conclusions can be used to
decide which rules to apply next, so the problem solving strategy may be event
driven during applications. This problem solving strategy is particularly
useful if there are a large number of possible conclusions and few input data.
A forward chaining strategy is illustrated in Figure 15-0 for a simple
expert system containing four rules in the knowledge base.[This example has
been adapted from D.A. Waterman, A Guide to Expert Systems, Addison Wesley
Publishing Company, 1986.] For this example, a rule such as:
In Step 1 of the forward chaining solution (Figure 15-0), the inference
engine identifies Rule 3 as available for execution. This identification is
based on a comparison of the premise conditions for each rule with the
available facts in the context; in this case, only the premises for Rule 3 are
satisfied. Executing or firing Rule 3 requires the inference engine to modify
the context to include the result D.
In Step 2 of the forward chaining solution, the inference engine identifies
two applicable or active Rules, 2 and 4. Rule 3 is excluded from
consideration since it has already been applied. Some mechanism for choosing
which rule to fire is required at this stage; in this example, we will choose
to fire the rule with the smaller number of required premises. Applying this
rule leads to the execution of Rule 4 and the addition of fact W to the
context. Obviously, numerous other schemes for selection of the next rule to
fire could be adopted.
At the next stage, only Rule 2 is active, and execution results in the
addition of fact F to the context. Finally, the inference engine identifies
Rule 1 as executable. Firing Rule 1 results in the addition of fact Z to the
context. No further new matches are possible and the system has achieved a
desired goal, so execution of the program stops.
A simple mechanism for explanation exists by tracing back these rule
executions. For example, suppose a user wishes to know why the fact Z was
asserted or concluded. The direct answer is because facts F and W are true and
Rule 1 was applied. Tracing back further would identify the rules and data
used in asserting the facts F and W or other variables used in the inference
process. This process of re-tracing rule executions provides considerable
scope for user review of the program execution and the knowledge applied.
Backward chaining is an alternative problem solving technique in rule based
systems. In this strategy, calculation or inference of particular attributes
are expressed as a system goal to be satisfied. A backward chaining system
works by identifying the final goal and working backwards to identify the
necessary steps to reach the final goal. This backward chaining problem
solving strategy is widely employed in diagnostic or interpretive expert
systems in which a limited number of conclusions can be obtained.
Figure 15-0 illustrates a backward chaining strategy for the same problem
and knowledge base shown in Figure 15-0. In this case, a set of active goals
to be satisfied is recorded in the context in addition to known variable
values. Initially, the goal to "find Z" is active. This goal can be fulfilled
by applying Rule 1, which requires values for F and W. The first step in the
problem solving strategy is to define sub-goals to find F and W. (See Figure
15-0). No rule can be fired to directly obtain the values of Z, F or W, so the
next step is to generate additional sub-goals. In this case, Rule 2 is
evaluated and a new sub-goal D is derived. Note that C is already known to be
true, so no sub-goal is required for this case. At this point, the set of
desired goals include values for Z, F, W and D. The value of D can be obtained
from Rule 3 at this point, and the next step in the program execution would be
to fire or execute Rule 3. After updating the context, D is added as a known
fact and removed as a goal to be fulfilled. In step 4, another match is
available with Rule 2 and goal F. At this point, Rule 4 can be executed to
obtain a value for W. Finally, Rule 1 can be fired to fulfill the final goal Z.
Backward chaining requires the development of the set of goals and sub-goals
to be pursued in problem solving, and it results in a more complicated and
lengthy solution process in this case. However, by focusing on the particular
goals that are required for a specific problem, backward chaining can often
reduce the number of rule firings and thereby improve problem solving
efficiency in an expert system. Either forward chaining or backward chaining
problem solving strategy can report the series of rule activations and
intermediate results used in deriving a final conclusion. Thus, either
strategy can support an interactive explanation facility.
With different types of knowledge representation or with more complicated
expert systems, some additional problem strategies become useful. These
strategies include:
Another dimension for problem solving strategies is the type of knowledge
representation employed. The examples above pertained to rule based systems in
which the context information is generally available to any rule. In different
types of expert systems, the explicit relationships among items in the context
are of interest. For example, frame representations provide facilities for
storing information about a particular entity as well as links among the
different entities. This stored information may include procedural
instructions for calculations, default values, allowable ranges for values,
explanations, pointers to related objects, or other information.
MASON is a rule based expert system used in the estimation of masonry
construction activities.[MASON is further described in C. Hendrickson,
D. Martinelli and D. Rehak, "Hierarchical Rule-Based Activity Duration
Estimation," ASCE J. of Construction Engineering and Management, Vol. 113, No.
2, 1987, pp. 288-301.] The MASON knowledge base was developed from interviews
with several experienced masons. The system provides facilities for estimating
the duration of masonry construction, explaining the various calculations made,
and making recommendations for alternative crew compositions and technologies.
The estimation strategy employed by MASON is illustrated in Figure 15-0 as a
hierarchy of estimation tasks. Based on general job characteristics, the
maximum productivity that might be obtained is calculated. This maximum
productivity is modified to reflect special characteristics of the job such as
height or weather. An overall duration is calculated based on the estimated
productivity and the amount of work. Finally, general modifications may be
introduced to capture effects such as differing productivities due to learning
on the job. These estimation steps are organized in a hierarchical fashion.
Once an estimation is formed, the type and allocation of resources can be
critiqued using the same rules used for estimation.
As originally implemented, MASON employs a backward-chaining problem
solving approach in which calculation of particular attributes or quantities is
expressed as a system goal to be satisfied. For example, an important system
goal is to estimate an activity duration. Before this can be accomplished,
sub-goals associated with the estimation of crew productivity and idle time
must be fulfilled. MASON could also have been implemented as a forward
chaining system. In this case, a description of the masonry site would be
input and the MASON would apply all applicable rules to obtain a duration
estimate.
Examples of the knowledge rules included in MASON appear in Chapter 9.
These rules pertain to the estimation of maximum productivities achievable as
well as modifications in this optimistic projection for peculiar sites,
ancillary requirements (such as installing tie-backs), and external impacts
such as weather. An example of a full rule is:
In addition to the estimation procedures, MASON also includes a series of
rules intended to make recommendations concerning appropriate crew compositions
and technologies. These recommendations are based on a strategy of overcoming
the reductions imposed on the maximum productivity due to site conditions or
the crew composition. In essence, if a particular rule was used to modify
(reduce) the productivity, then a recommendation that would reverse this
modification might be possible. For example, if there are too few laborers
assigned to the crew, then a rule reduces the productivity accordingly.
However a recommendation to add more laborers to the crew can be made, yielding
an improvement in productivity.
Upon each recommendation, the user may respond yes to accept, thus
implementing the recommendation, no to reject it, or why to be given an
explanation of why the suggested recommendation will lead to the estimated
improvement. The appropriate explanation of a recommendation depends on the
specific job and activity conditions and may vary from session to session. If
the user has asked why, he will again be given the option of accepting or
rejecting the recommendation following the explanation. If the user wishes to
accept the recommendation, the productivity and the resulting activity duration
is adjusted for the improvement. If it is rejected, the productivity remains
the same.
Example 15-1: Example Expert System Dialogue: MASON
To illustrate the operation of MASON and the hierarchical approach to
duration estimation, a sample estimation session with MASON appears below.
Note that MASON provides duration estimates through an assessment of the
productivity and downtime inefficiencies at both the project and activity
levels. The system queries the user and determines if there exist possible
productivity impacts or downtime events that could have a bearing on the
duration. In such cases, the user is usually asked follow-up questions in
order to make assessments of these impacts and events. Thus, a session with
MASON includes input, recommendation, and explanation phases as well as the
estimation of durations and productivities. In what follows, user responses
are italicized, and menu based queries from MASON are omitted; notes are
included in regular font.
This example illustrates the interactive, explanatory characteristics of
MASON that would be quite useful in application. Graphic displays to improve
interaction and more sophisticated input control to avoid unnecessary questions
would enhance the usefulness of the system.
Supporting laborers are needed to mix mortar, keep the bricklayer stocked,
as well as assist him in laying out corners, etc. If there are more than 2
bricklayers for every laborer, then it is said that the laborers cannot keep up
and that the bricklayers will have to slow down.
Also, because FIRST is on the 4 floor, the added labor is necessary to
efficiently transport the materials and tools to the high elevation activity
site. Because you plan to use 6 bricklayers, I recommend that you add 1
laborers to each crew. By doing this, the bricklayers will not have to be
delayed.
You can increase the productivity on FIRST by 32.0 BLOCK per bricklayer per
day if at least 1 laborers are added to each crew.
Your increase in the number of laborers in each crew is confirmed.
You can increase the productivity on FIRST by 41.0 units per day per mason
if high strength mortar is used.
When working with regular strength mortar in the cool and damp conditions
expected for activity FIRST, the block does not set as fast. This situation
has significant impact on productivity when using 4 inch block. This is
because the thinner 4 inch block is, in general, more difficult to balance than
blocks of other thicknesses.
You can increase the productivity on FIRST by 41.0 units per day per mason
if high strength mortar is used.
The low temperatures expected for this activity has given rise to a 12% (of
the maximum) reduction in the productivity.
The design of emergency repairs and the growing inventory of failing
retaining walls present a considerable practical problem. Time and budget
constraints are pressing, especially for repair work. The available expertise
is limited and often dispersed among numerous individuals, so extensive
consultation may be required. RETAIN was developed to provide an expert system
assistant in such situations. RETAIN can diagnose causes of failure and make
recommendations concerning suitable repair or reconstruction strategies.[For
further detail on the RETAIN system, see T.M. Adams, C. Hendrickson, and
P. Christiano, An Expert System Architecture for Retaining Wall Design,
Technical Report, Department of Civil Engineering, Carnegie-Mellon University,
1987.] A database management program stores information on unit costs and will
also store a description of particular sites and designs. Thus, RETAIN
contains modules to accomplish failure diagnosis, generation of alternatives,
and evaluation as illustrated in Figure 15-0. Each module has a separate set
of inference rules and a separate problem solving strategy. RETAIN can be used
by an engineer called upon to evaluate a retaining wall failure, to conduct a
survey of existing walls, or to design a rehabilitation or new construction
strategy for a wall.
Diagnosing a failing retaining wall involves evaluating the wall's
structural stability and failure characteristics to determine the influencing
mechanisms. The first step is problem identification. A complete description
of the retaining wall, the surrounding site and the loading conditions is
collected. Examples of problem attributes are the wall type, construction
material and geometry, bearing and backfill soil properties, and surcharge load
types and magnitude. The identification phase contains knowledge for assigning
soil properties based on soil characteristics and for assigning appropriate
models for various surcharge load types. Engineering knowledge, including
equations and algorithms for computing earth pressures and surcharge load
pressures is applied in the analysis step. The pressure loads are combined to
determine resultant wall loads, bearing pressure, and factors of safety against
problems such as overturning or sliding. While analysis computations are for
the most part straightforward substitutions into equations and algorithms, they
are not independent of wall type. For instance, computing the bending
capacities of various cantilever wall types such as soldier piles and lagging
or cast-in-place reinforced concrete follow different algorithms. The final
step in the diagnosis phase is the application of a diagnostic network model to
the failing retaining wall. Diagnostic models contain heuristic knowledge on
failure possibilities.
Synthesis of alternative rehabilitation strategies follows the generate and
test problem solving strategy in RETAIN. In this strategy, possible solution
alternatives are formulated and then tested for feasibility. In its pure form,
generate and test would generates all possible solutions for consideration. A
common variation on the generate and test strategy is to plan, generate and
test, where the planning phase seeks out reasonable combinations before
synthesis of individual alternatives. Given the set of conditions that
establish the state of a specific wall, the retained backfill and the
constraints on the access of construction equipment, RETAIN will generate and
test all remedial actions. The scope of retaining wall rehabilitation
strategies includes reducing loads, underpinning, installing tiebacks,
buttressing, removing (then regrading), and rebuilding or resurfacing. Some
example rehabilitation alternatives are illustrated in Figure 15-0. For
example, rock or soil anchors are possible tieback strategies for repairing an
existing wall.
A prerequisite for testing rehabilitation strategies is the preliminary
design of each strategy. Preliminary designs include wall and footing
dimensions, drainage characteristics, approximate spacing of tiebacks and
anchors, amount of excavation, etc. Each strategy has associated knowledge
regarding conditions under which they are technically feasible or infeasible.
In the course of the testing phase these conditions are checked. For example,
the following list includes a selection of conditions under which replacement
by soldier piles and lagging may be technically feasible:
In the recommendation phase, all feasible rehabilitation strategies are
ranked according to how well they fulfill project objectives such as cost,
availability of materials, minimizing construction time and minimizing
disruptions to traffic and other structures. Cost estimation is handled by a
rule-based expert system, with algorithmic computational functions, which
queries a database for specific unit cost factors. Output from the
recommendation phase include the conditions leading to failure, what
circumstances caused rehabilitation alternatives to be considered infeasible,
and the overall evaluation and ranking of feasible rehabilitation alternatives.
Example 15-2: A Probabilistic Inference Network for Failure Diagnosis
In assessing possible failures, RETAIN applies a series of inference
networks recognizing the uncertainty of input information and causal
relationships. An example of an inference network used in RETAIN appears in
Figure 15-0. This network illustrates the information used to reach a
conclusion regarding the cause of forward tilting failures in a cast-in-place
concrete wall. Three possible causes are included in the figure: toe
settlement, overturning or bearing capacity failure, as illustrated in Figure
15-0.
The inference network in Figure 15-0 is traversed from the bottom to the
top. Three types of nodes are included in the figure: (1) inputs from
computations or filed observations that may be uncertain to some degree, (2)
inference rules, and (3) AND or OR combinations of results. For example, if
field observation reveals a soil bulge and a computation on other inputs
suggests that the bearing capacity is exceeded, then the conclusion may be
reached that a bearing capacity failure is likely. The inference networks in
RETAIN assign a certainty factor to such a conclusion. In Figure 15-0, each
relationship has two associated likelihood values. The sufficiency measure LS
is the degree of support of a hypothesis given positive evidence, while the
necessity measure LN is the degree of refutation when evidence is lacking.
With these values, an inference rule actually has two forms:
CONSTRUCTION PLANEX is a knowledge intensive expert system for construction
project planning. The system generates project activity networks, cost
estimates and schedules, including the definition of activities, specification
of precedences, selection of appropriate technologies and estimation of
durations and costs.[See C. Hendrickson, C. Zozaya-Gorostiza, D. Rehak,
E. Baracco-Miller and P. Lim, "Expert System for Construction Planning," ASCE
Journal of Computing in Civil Engineering, Vol. 1, No. 4, 1987, pp. 253-269.]
PLANEX involves interpretation of a final design plan, prediction of durations,
and the formation of the construction plan itself. As a result, PLANEX is a
fairly large system involving both expert system operators and algorithmic
processes for functions such as scheduling or animation of the construction
process.
In the initial creation of a construction plan, PLANEX would perform the
following operations:
Similar to other knowledge-based expert systems, CONSTRUCTION PLANEX has
three essential parts as illustrated in Figure 15-0. The Context contains
information on the particular project being considered, including the design,
site characteristics, the planning decisions made, and the current project
plan. The Operator Module contains operators that create, delete or modify
the information stored in the context. Operators are used for different tasks
such as technology choice, activity synthesis, duration estimation and others.
The Knowledge-Base contains distinct knowledge sources of tables and rules
specific to particular technology choices, activity durations, or other
considerations. In addition to these three components, CONSTRUCTION PLANEX
contains a menu driven interface used to control the execution of the operators
and a Knowledge Source Acquisition Module used to modify the contents of the
Knowledge Base.
In the Context, information is stored in a series of hierarchically
organized frames. Each frame is linked to parent or children frames from
which information can be inherited. Frames are named and contain various slots
to record information. For example, element activity frames record
information on classification, location, geometry and specifications of the
activity. These different frames are organized to represent the current
project plan, decisions made during the planning process, and different
aggregation schemes. Figure 15-0 shows the general structure of the context.
On top of the hierarchy there are frames used to store information at the
project, sector, block and floor levels. Below them, there are trees for
design elements, element activities and project activities. Element
activities are linked to design elements, to element activity groups and to
project activities. Decisions and computations undertaken during the planning
process can be stored in any of the frames of this hierarchy and inherited by
element activities. Furthermore, inherited values can be overridden by local
decisions for particular cases. Thus, the set of project activities can form a
conventional project network while the system context contains a more extensive
network which also records the planning process and other information.
The operator modules alter the system context by creating frames or
modifying attributes. The exact modifications made are found by evaluating
relevant knowledge sources in the knowledge base.
The knowledge base is organized into a set of knowledge sources (KS) that
represent rules, heuristics, and calculation functions. These knowledge
sources can best be pictured as decision tables, although they are actually
written as frames and production rules. A KS functions as a small expert
system, in a fashion similar to the MASON activity duration estimating system
described above.
Example 15-3: A PLANEX Knowledge Source
An example of a knowledge source appears in Figure 15-0. This KS contains
two conditions, three rules and three possible actions. The first rule
indicates that if the soil-type is hard and the result of evaluating
KS-water-level is not wet, then the appropriate technology is power-shovel.
The second rule indicates that if the soil-type is not hard and the result of
evaluating KS-water-level is wet, then the appropriate technology is
clamshell. Finally, the third rule indicates that if none of the previous two
rules were fired, the appropriate technology is special-machine. Knowledge
sources can involve recursion, binding of attributes, functional calculations,
and other operations.
Architectural design, structural engineering and construction planning for
buildings are typically performed by separate organizations with communication
relying upon drawings and specifications. In Chapter 14, we described the
possibility of integrating disparate processes through means of a central
database of information used by numerous application programs. The Integrated
Building Design Environment is an experimental prototype to provide just this
type of integration.[This environment is described in Fenves, S.J.,
U. Flemming, C. Hendrickson, M.L. Maher and G. Schmitt, An Integrated Software
Environment for Building Design and Construction, Technical Report,
Engineering Design Research Center, Carnegie Mellon University, 1987.] In
addition, a specialized blackboard architecture and centralized agenda
control provided a means of overall control on the design process.
The integrated building design environment includes the following processes
(Figure 15-0):
In addition to the central data store, the blackboard architecture and
agenda control for message passing were critical components of the integrated
system. A blackboard provides a mechanism for a computer program to place a
message that can be read by other programs. Once a process finishes a
particular task, an appropriate message is posted on the blackboard. The
central controller in the design environment monitors the system blackboard for
such messages. If a particular process completes a task successfully, then the
central controller posts a message for a subsequent process to commence. The
sequence of processes to be invoked, including alternative courses of action in
case of process failure, is also determined by the central controller.
While this integrated building design is an experimental system, it
illustrates a number of features required for a new generation of computer aids
in project management. The central data base is extended to provide a richer
representation of the building design and construction plan. This extended
information can support knowledge based expert system applications. A flexible
controller permits automation of the entire process and modifications over time
in the number and type of processes in the system. At the same time, existing
processes such as graphic displays of construction progress can be maintained.
While many construction tasks have been mechanized, construction has seen
little automation. Construction remains a labor intensive industry which has
been resistant to the introduction of new technology. Regulatory restrictions
and the fragmentation of the construction industry present severe
organizational restraints on the implementation of new technology.
Technically, the unstructured environment of construction sites and the
difficulty of transporting large, pre-fabricated components have also hindered
the large scale introduction of automated processes. Recent advances in
robotic technology and the related experience in manufacturing industries
suggests that greater automation may be extremely beneficial for constructed
facilities. In addition, construction in hazardous environments may be greatly
expanded by the use of construction robots. In this chapter, we shall examine
the possibilities for greater automation in the construction industry. The
overall purpose of this review is to suggest the scope of technological
possibilities that will be influencing construction in the next decades.
There are several means by which construction automation and robotics might
repay the additional equipment and development costs associated with high
technology investments. First, robotics offers opportunities for extending the
scope of practical construction activities into hazardous environments,
including outer space, nuclear reactors, or undersea construction. Even
standard construction sites represent hazardous environments as suggested by
the large number of industrial accidents associated with construction. Second,
robotics may permit the practical introduction and broader use of non-human
senses and capabilities on construction sites. For example, robotic technology
permits construction activities within highly constrained spaces such as
pipelines. As another example, robots can use extraordinary senses of radar or
sonar to perceive operational opportunities during a construction process.
Third, automation and robotics may permit the expansion of construction
operations over time. Continuous operation of construction processes and
shorter construction times might be more easily achieved by tireless robot
workers. Fourth, it may be possible to achieve improved quality in the
finished product by means of automation and robots. With automated control,
the work tasks in a construction project might be achieved with greater
consistency and precision. This greater precision may in itself lead to
greater productivity. For example, one advantage cited for automated tunnel
boring equipment is the greater precision of drilling and consequent faster
progress in tunneling. Finally, the introduction of automation and robots may
result in cost savings due to the direct elimination of labor.
Achieving these potential benefits is an extremely challenging task.
Construction involves a wide variety of tasks in a constantly changing, hostile
environment. Construction robots must be hardened for extreme conditions of
vibration and environmental distress. After all, many existing manufacturing
robots would be ruined if they sat out in the rain! In addition to the
technical problems, institutional and organizational impediments to the
introduction of automation might be expected from existing workers and
managers. Nevertheless, the benefits of automation can be so large that some
form of automation and robotization is inevitable in many activities.
In considering construction automation and robotics, it is difficult to draw
firm lines between advanced mechanized equipment and true robotics. Clearly,
machines that look like humans and can undertake many manual tasks would be
classified as robots. However, anthropomorphic machines of this type are
unlikely to be used in construction in the foreseeable future. More likely is
the adoption of specialized equipment that can perform a number of tasks of
particular kinds. For example, surveying robots may look like small tractors
rather than human surveying parties. Moreover, mobility might not even be a
crucial characteristic of important construction robots. Adoption of flexible
manufacturing with immovable robots in factories or in assembly plants on a
construction site may make pre-fabrication of components increasingly
attractive and significantly reduce construction costs.
A common definition of a robot is a reprogrammable, multi-functional
manipulator designed to move material, parts, tools or specialized devices
through various programmed motions for the performance of a variety of
tasks.(See V.D. Hunt, Industrial Robotics Handbook, Industrial Press Inc., New
York, 1983.) This definition reflects the present predominance of
manufacturing robots in that the necessity of coping with unstructured
environments, mobility and large scale forces as required in construction
robotics are omitted. Also, the entire class of remote or teleoperated
machines is omitted from this definition since they are not necessarily
programmable; many organizations define and treat teleoperated machines as
robots even though these devices are limited in capability and scope. For
construction applications, each of the three major categories of robots can
fulfill a role: (1) teleoperated robots in hazardous or inaccessible
environments, (2) programmed robots as commonly seen in industrial
applications, and (3) cognitive or intelligent robots that can sense, model
the world, plan and act to achieve working goals.
Robots form an important ingredient in modern automation since the
multi-functional capability and flexibility of a robot permits a wider scope
than stationary automated equipment. These capabilities will be especially
important in attacking the many ill-structured tasks in a construction
environment. However, the economic impact of automated plants without robots
should not be ignored. Process plants for producing construction materials
such as concrete have already been automated in many instances.
In manufacturing industries, robots have found permanent employment in a
variety of tasks, including machine tool processing, welding, palletizing,
paint spraying, inspection, assembly, casting, loading and unloading. While
mobile robots exist in manufacturing plants, they are usually restricted to
tasks associated with the movement of materials. Robots used for manipulation
or assembly are usually stationary, with raw materials and product components
brought to them. As a result, complicated problems of motion and stability are
avoided by most industrial robots. In addition, locational problems are
reduced since industrial robots can always reference their position with
respect to their fixed base. A second characteristic of most industrial robots
is the reliance on programmed, repetitive task performance. Since
manufacturing often requires the repetition of the same task on different
components (such as paint spraying the side of numerous automobiles being
assembled), the use of programmed robot control is often effective. In
contrast, construction tasks usually involve at least displacement from place
to place if not modification to account for changes in the environment. For
example, brick laying operations change when openings for doors and windows are
required. Finally, many industrial robots need not apply large scale forces in
work tasks. For example, an extremely successful application of industrial
robotics is assembly of small electronic components. In contrast, construction
materials are usually bulky and heavy, requiring greater force in assembly and
manipulation.
This description of manufacturing sector robots suggests pre-fabrication as
an immediate use for construction robotics. If facility components can be
fabricated in a controlled, factory environment, then existing industrial robot
technology can be employed. Possible pre-fabricated components might include
wall sections, small rooms, HVAC machinery, transportation equipment (such as
elevators), and others. For example, large pre-stressed concrete blocks are
now made in several automated production facilities. Automated fabrication
might be accomplished in a central factory or in a temporary facility close to
a construction site. One difficulty with this application stems from the
limited number of repetitions for many facility components: there are far fewer
identical units used in construction than in manufacturing. However, as system
programming becomes easier and industrial robots more flexible, the economic
feasibility of small production lots increases correspondingly.
Even on the construction site, there exist numerous tasks that are
relatively well-structured and sufficiently repetitive to warrant robotization.
A prime example would be surface finishing works involving spraying, scraping,
blasting or similar activities. These activities are often required for large
areas and involve repetition of simple tasks. In most cases, only small forces
are required to effect the desired changes: in sand blasting, for example, a
robot would only have to properly position and move existing sand blasting
equipment. By locating the geometric limits of work manually or through some
sensing mechanism, the basic work tasks of this type can be accomplished by
conventional programmed control. Existing prototypes of this type of robot
include insulation sprayers and painting robots. One existing spray robot
applies insulation faster and as accurately as a human worker. The robot also
avoids exposing a human to a dirty, uncomfortable environment.
At the highest level, there is also the potential for introducing robots
with the ability to plan, act and respond to changing conditions on their own.
This type of robot is the most difficult to develop, yet offers the greatest
potential for impact on the construction site. An example would be a robot
excavator that would be given only the location and dimensions of a desired
excavation. From that point on, the robot excavator would plan the excavation
activity, sense the environment, react to changes as excavation proceeds, and
accomplish the desired excavation without human intervention.
Experimental or production robots have been developed for a variety of
construction tasks. In this section, we shall give some examples of existing
robots.[Unless otherwise noted, the examples in this section have been adapted
from I.J. Oppenheim and M.J. Skibniewski, "Robots in Construction,"
Encyclopedia of Robotics, John Wiley & Sons, Inc., 1988.] This discussion
will be organized by functional applications, including material handling,
tunneling and excavation, finishing, and inspection. Our discussion is only
intended to introduce the range of possible construction robots; we will not
survey all existing robots or all possible robot applications.
Material handling is a pervasive activity on construction sites and in
factories. It includes moving material between locations, placing materials in
specific arrangements, and positioning large objects at a specific location and
orientation. Materials handling applications often require mobility and the
ability to apply large lifting forces.
Example 16-1: Shotcrete Robot
Spraying concrete can be a laborious, expensive and hazardous task. It also
requires considerable expertise to properly regulate the amount of concrete to
be sprayed and the quality of the hardening agent to be applied. In
applications such as the New Austrian Tunneling Method that employs extensive
shotcrete, concrete spraying can take as much as thirty percent of the total.
To improve and speed up the shotcreting process, Kajima Company developed a
computer controlled applicator. This machine can be remote controlled (as a
teleoperated robot), semi-automatically controlled (involving both computer and
operator inputs) or used to play back specific sets of movements. The machine
resembles a conventional track-propelled excavator but with a flexible
manpulator holding a nozzle.
Example 16-2: Reinforcement placing robot
Kajima Company's reinforcing bar placing robot can carry up to twenty bars
and automatically place these bars in preselected patterns in both floors and
walls. The equipment has achieved forty to fifty percent savings in labor and
ten percents savings in time on several Japanese projects. Rebars in these
applications can be long and heavy, so the rebar placing robot can exert
considerable force as required.
Tunneling and excavation are common tasks in construction. It is an
interesting robot application since the nature and disposition of the material
being excavated is usually only partially known during the tunneling or
excavation process. Robots must respond to changes in the material being
excavated. In the extreme, robots should be able to sense and recognize
unforeseen obstacles such as pipes or large boulders.
Example 16-3: REX
A prototype robotic excavator (REX) developed at Carnegie Mellon University
to uncover buried utility pipes as shown in Figure 16-0. This application is
of particular interest in the hazardous process of excavating leaking gas
pipes. REX mapped the excavation site using magnetic vision, planned the
digging operations and controlled the excavation equipment. Thus, REX is an
example of an autonomous construction robot. The excavation tool used by REX
was an air jet.
Example 16-4: Five-Boom Drilling Robot
Kajima Company has developed and used a drilling robot with up to five
active booms. This machine can be used for drilling, blasting, mucking and
shotcreting operations in tunnel bores. The company reports increased
efficiency with the machine and increased accuracy in drilling and tunneling.
Surface finishing is a widespread construction task that is particularly
amenable to automation. Typical finishing activities involve surface treatment
(such as grinding, brushing, or smoothing) and surface coating (with
fireproofing, paint, plaster, mortar, etc.). Numerous robots and mechanized
aids have been developed for this application, such as the two robots described
below.
Example 16-5: Slab Finishing Robot
Smoothing the rough surface of a cast-in-place concrete slab is a laborious
yet common procedure. Since the process is confined to a flat, two dimensional
surface, simple robotic machines may be applied. Kajima Company has used a
computer controlled applicator involving a mobile platform equipped with
mechanical trowels. By means of a gyro-compass and a linear distance sensor,
the machine navigates throughout a pre-specified slab area. The machine was
designed to replace at least six skilled workers.
Example 16-6: Fireproofing Spray Robot
Typical materials for fireproofing are rock wool and cement slurry. Rock
wool can be sprayed in wool-permeated air. Performing this operation is
laborious and can be hazardous, although it is a necessary operation in many
high rise buildings. Shimizu Company has developed several robots for this
purpose. As illustrated in Figure 16-0, one robot model has a mobile base,
hydraulic stabilizers, an articulated robot arm, and a rock wool nozzle. This
robot can spray faster than a human worker, but requires time for
transportation and set up.
Inspection is a required construction task in many applications to insure
adequate quality of materials and work. Robot inspectors can have the
advantage of using super-human senses such as magnetic vision as well as
reaching inaccessible spots. However, robots do not have the flexibility and
intelligence of human inspectors, so their autonomous role in inspection may be
limited.
Example 16-7: Wall Climbing Inspection Robot
Nordmed Shipyards of Dunkerque, France, developed a wall climbing robot
called RM3 for tasks such as video inspections of ship hulls, gamma-ray
inspection of structural welds, and high pressure washing, deburring, painting,
shotblasting, and barnacle removal. The RM3 weighs 206 lbs and has three legs,
one arm, and two bodies. Magnetic cups on its hydraulic actuated legs allow
the RM3 to ascend a vertical steel plate, such as a ship's hull, at a speed of
8.2 ft/min. (150 m/hr). RM3 has a cleaning rate of 53,800 sq.ft./day (5,000
m@+[2] per day) and a 320 foot range.
Example 16-8: Robotic Core Boring and Reconnaissance
Carnegie Mellon University developed a roving, teleoperated vehicle used in
the radioactively contaminated areas at the Three Mile Island (TMI) nuclear
power plant in Pennsylvania. One special purpose tool mounted on the roving
reconnaissance vehicle was a remotely controlled concrete core boring tool to
provide samples of contamination (Figure 16-0).
By their very nature, robotics and automation borrow heavily from
developments in related areas such as computer hardware, tooling, navigation
algorithms, robotic vision, and software control procedures. Knowledge based
expert systems are examples of a new technology developed in an independent
area (in this case, artificial intelligence research) which has filled an
important requirement in the control of advanced robot systems. Since
construction robotic applications are in their infancy, existing technologies
used in industrial settings are also a fertile source of relevant construction
automation technology. In this section, we briefly review some of the more
important pieces of technology required for successful implementation of
construction robots.
Manipulators comprising robot arms are a useful starting point in the
discussion of robot technology. Stationary robots with flexible, articulated
arms represent the most common form of industrial robot. These industrial
robots are in a sense extremely limited: a comparable human would be someone
who is blind, deaf, dumb, one-armed, and with feet set in concrete.
Nevertheless, the tireless nature and flexibility of robot arms make them
effective workers in industrial environments.
The essential role of a robot arm is to move a tool or effector into the
proper orientation relative to a workpiece. To achieve necessary flexibility,
arms typically require six axis of movement (or degrees of freedom): three
translational movements (right/left, forward/back, up/down) and three
rotational movements (pitch, roll and yaw). Various movements can be
accomadated with quite different robot architectures. For example, Figure
16-0(a) shows a robot arm that works in rectangular coordinate axes similar to
a gantry crane. Three directions of movement are shown in the figure,
corresponding to movements along the three rectangular coordinates. In
contrast, the manipulator in Figure 16-0(b) works in a cylindrical space with
two extension joints and one rotational joint. In Figure 16-0(c), a
manipulator configured to work in spherical coordinate is shown. Finally, the
manipulators shown in Figure 16-0(d) and (e) more closely duplicate human arm
or wrist movements.
Movement of robot arms require drive mechanisms able to influence the
various degrees of movements. Typical mechanisms used in practice include
hydraulic cylinders and electric drives. Special consideration must be given
to precise control over the speed and extent of all the possible movements.
Accuracy and repeatability of movements are greatly influenced by the accuracy
and reliability of the drive mechanism. Transmissions to convert drive
movements into appropriate speeds and directions may also be required.
Perched on a robot arm manipulator, a variety of tools or effectors may be
employed. Sprayers, scrappers, grippers, sensors and other tools would be
typically used for construction tasks. These tools could be identical to those
used by human workers or specially designed for easier control and manipulation
by machine. In Figure 16-0, for example, a teleoperated robot is shown
operating a gripping tool. Integrated effectors may be sophisticated robotic
machines in themselves, involving sensors and control algorithms. An example
of a sophisticated effector would be a wrench capable of sensing torque and
elongation of bolts and automatically shutting off the turning force at the
proper degree of tightness. Another example is the development of robot
effectors capable of either spot or arc welding.
On construction sites themselves, mobility and locomotion are extremely
desirable characteristics for robots. In many case, work must be performed in
situ, so a stationary robot has a quite limited usefulness. Fortunately, a
variety of mobile platforms can be used to support particular manipulators.
Indeed, mobile platforms may be identical to those used for existing mechanized
equipment except for the control system and the payload. Thus, numerous
wheeled or tracked platforms are commercially available.
Unfortunately, construction sites are not always accessible for wheeled or
tracked vehicles, however. A research topic of considerable interest is the
development of climbing or walking robots capable of general movement about a
construction site. Cable supported robots are also of interest. In these
systems, a robot would be supported and moved by a remote crane. More
specialized robots to crawl along beams or flat surfaces are also possible.
Robot control is the most important distinction between a robot and a piece
of mechanized equipment, although there is no general agreement on exactly
where to draw the line between robots and other machines. All robot
controllers possess mechanisms for controlling the position and movement of
robot arms and effectors. These control programs will typically have memory
available so that a sequence of movements can be "taught" and played back as
required. At a higher level of abstraction, a robot controller may be able to
plan movements and sequences of actions given a desired goal.
Computer based controllers can work at each level of abstraction. Actuator
level languages were the first to be developed and include commands for
movements of particular joints in a robot manipulator. For each desired
movement, a programmer must specify individual movements and positions for each
joint in the manipulator arm. At a higher level of abstraction, manipulator
level or end effector languages exist. These languages include commands
specifying desired movements or positions of the end effector of a robot
manipulator. When such a command is issued, the software must determine what
actuator level commands are required to achieved the desired final position.
Finally, at the highest level are languages and control systems that can plan
manipulator movements in response to goal statements or sensor information.
These languages are often called object level since they include commands
related to objects in the robot's world. Knowledge based expert systems are
one possibility for an object level command systems.
Sensors are also components of all but primitive robots. A sensor is any
device or transducer that converts an environmental condition into an
electrical signal. An environmental condition might be mechanical, optical,
electrical, acoustic, magnetic, or other physical effect. A simple example is
a microswitch installed on an end effector that will go on when an object is
touched. In this case, the microswitch sensor sends an on (ie. "contact") or
off (ie. "no contact") signal to the robot controller. More complicated
sensors make measurements of desired parameters, such as flow rates in an air
supply or the current position of the robot manipulator. These measurements
are used to control robot movements and, in advanced robots, to plan
operations.
While measuring different physical effects can be achieved in a variety of
fashions, interpreting sensor information for the purpose of robot control is a
very difficult and computer intensive process. Consequently, most existing
robots have only limited capabilities to sense the environment. As with
control languages, different levels of interpretation exist. At the lowest
level, mechanisms for receiving each sensor signal must be implemented, so
sensor level programs are required. Direct sensor measurements are converted
into parameters describing the physical effect being considered. Finally,
parameter values are integrated into a world model of the robot environment at
the object level. Since performing all these different interpretation
operations is computationally burdensome, there has been considerable attention
devoted to smart sensors in which the calculation of parameters is handled
internally. As a result, the robot controller computer does not have to devote
time to polling and interpreting direct sensor signals. Since robots require
real time interpretation to guide robot movements, this form of parallel or
distributed processing can be very helpful.
Artificial vision represents an extreme example of sensor and interpretation
complexity. In essence, vision is an information processing task in which two
dimensional arrays of brightness values received by a camera or other type of
sensor are manipulated to form a two or three dimensional model of a scene.
This process may involve inferring the types of objects or material
characteristics presents in a scene. Figure 16-0 illustrates the image
processing used in a magnetic vision system. In this case, the scene consists
of two reinforcing bars crossing at right angles. The initial brightness
pattern shown in Figure 16-0 represents intensity readings from a magnetic
sensor moving over the scene. These intensity readings are digitized and
manipulated to accomplish the extraction of features, mapping the likely
location of reinforcing bars, and classifying the size and depth of the bars in
the scene. Figure 16-0 shows the progressive interpretation of the original
scene. As might be imagined, vision is extremely computationally intensive,
with each bit in the scene requiring considerable interpretation. In this
example, magnetic sensing permits mapping of reinforcing bars embedded in a
material such as concrete.
Integrating sensor information and robot control can be accomplished at
various levels of abstraction. At the lowest level, tactile or proximity
sensors may be added to a robot to react to imminent collisions. At higher
levels, sensors provide the information required to construct a world model of
a robot's surroundings. This world model is then used to plan robot movements
to accomplish some prescribed goal. It is this overall integration that
distinguishes cognitive robots that are able to sense, interpret and plan
activities.
The various types of sandblasting work on structures are usually performed
by highly specialized and small or medium-sized contracting firms. For
example, a firm specialized in masonry restoration sandblasting would not be
prepared to perform rust removal from the bearing elements of a highway steel
bridge, and a steel container sandblasting contractor would usually not perform
blasting of concrete or brick walls. The work styles, due to somewhat
different occurrences and intensities of health and safety hazards, are also
different, since the surfaces and environment in which laborers work differ
considerably.
The sandblasting process involves only a few relatively very simple work
tasks, lending themselves to partial or full performance by an automated
machine. These tasks include:
The productivity and work quality of sandblasting is largely affected by
human factors. Eliminating some of the human limitations and drawbacks could
decrease the labor cost and possibly increase the quality of work considerably.
For example, existing work rules require one worker to watch the sand hopper
while to other are operating the blast nozzles. Every three hours a rotation
is mandatory. Each sandblaster is also entitled to 4 hrs of rest after
performing four hours of work at the nozzle. Experience indicates that on a
typical job site, due to workers' partial exhaustion, up to 70% of day's
production is normally completed between 8 and 12 a.m. Also, the overall day's
productivity is down by about 20% if the air temperature is over 75 degree
F. Operating conditions are often arduous, and in addition with the operator
working on scaffolding or in tanks, his tiredness will grow rapidly if he works
too long without rest. Apart from wearing cumbersome clothing and wearing a
compressed air fed helmet his vision will gradually be impaired as the visor
becomes dimmed with abrasive action and dust. This often precludes
satisfactory control of the blast outcome on the surface during the work
itself, and later corrections of previous work are often costly and cumbersome.
Expected cost savings on labor are partially a direct result of eliminating
the same factors that affect productivity. Reorganization of the sandblasting
crew to meet the needs of the robotic sandblaster wwould require the
elimination of the operator and assistant work tasks. Instead, technical
supervision of robotized equipment would be necessary.
The following robot features are necessary for successful performance of the
sandblasting task. A diagram of a possible design appears in Figure 16-0.
The robotic components necessary for the construction of the autonomous
sandblasting machine are available on the commercial market in the United
States and/or other industrialized countries. Most of them already constitute
elements or segments of existing industrial robotics. With respect to the
components specified above, there are in most cases several options from which
to select the desired hardware and controls. Manufacturers' catalogs contain
an overview of selected commercially available components applicable to the
subsystems of the considered sandblasting robot.
The sandblasting robot would consist of the following components:
The sandblasting robot would perform a continuous task of applying a stream
of pressurized sand onto the cleaned surface. To accomplish this objective,
the following steps are required:
The robot system mechanical setup must be particularly rugged to withstand
typical and unforeseen work site conditions. However, no large external forces
exerted on the machine are anticipated. The manipulator arm frame could even
be be made of lightweight metal material.
Robots certainly have considerable limitations relative to human workers.
The limited capabilities of existing industrial robots would not be
particularly useful on existing, uncontrolled construction sites. However,
robots are rapidly becoming more capable. Moreover, it is often possible to
structure environments or particular tasks so that robots are technically
feasible. And the various super-human senses and tireless work of robots can
be quite useful in many applications. Consequently, robots for construction
are likely to be inevitable developments in the future.
The development of capable software and computation power is particularly
important for construction robotics. Currently, high level controllers and
sensing programs require considerable programming and engineering expertise.
The development of more capable and user friendly programming environments
should be of great benefit. Cheaper computation hardware would also play a
role in enhancing robot capabilities.
Initially, one can expect robots to be used in hazardous environments such
as nuclear reactor maintenance and demolition. Robots designed to assist human
operators are also likely to be the rule in the next decades. These robots
would be teleoperated or have only limited autonomous intelligence. An example
general purpose, teleoperated robot called the Workhorse is shown in Figure
16-0.[See W. Whittaker, J. Bares and L. Champeny, "Three Remote Systems for
TMI-2 Basement Recovery," International Conference on CAD and Robotics in
Architecture and Construction, Marseilles, France, 1986.] This machine can
collapse to fit through doorways, extend to reach high workplaces, can exert
large forces (including sufficient force to lift itself up) and can operate
numerous effector tools. The Workhorse was designed to operate in radioactive
environments. Stationary robots will also be a trend in that numerous
construction operations can be performed in a factory either off-site or near a
construction site. Improvements in work quality or reduction in worker hazard
are likely to be the most important incentives for automation.
Project Management for Construction
Fundamental Concepts for Owners,
Engineers, Architects and Builders
In essence, adopting the viewpoint of the owner focuses attention on the cost
effectiveness of facility construction rather than competitive provision of
services by the various participants.
1. The Owners' Perspective
1.1 Introduction
By common consensus and every available measure, the United States no longer
gets it's money's worth in construction, the nation's largest industry ... The
creeping erosion of construction efficiency and productivity is bad news for
the entire U.S. economy. Construction is a particularly seminal industry. The
price of every factory, office building, hotel or power plant that is built
affects the price that must be charged for the goods or services produced in it
or by it. And that effect generally persists for decades ... Too much of the
industry remains tethered to the past, partly by inertia and partly by historic
divisions...
Improvement of project management not only can aid the construction industry,
but may also be the engine for the national and world economy. However, if we
are to make meaningful improvements, we must first understand the construction
industry, its operating environment and the institutional constraints affecting
its activities as well as the nature of project management.
1.2 The Project Life Cycle
The Project Life Cycle of a Constructed Facility
1.3 Major Types of Construction
Residential Housing Construction
Illustration of Residential Housing Construction
Institutional and Commercial Building Construction
Institutional and commercial building construction encompasses a great variety
of project types and sizes, such as schools and universities, medical clinics
and hospitals, recreational facilities and sports stadiums, retail chain stores
and large shopping centers, warehouses and light manufacturing plants, and
skyscrapers for offices and hotels. The owners of such buildings may or may
not be familiar with construction industry practices, but they usually are able
to select competent professional consultants and arrange the financing of the
constructed facilities themselves. Specialty architects and engineers are
often engaged for designing a specific type of building, while the builders or
general contractors undertaking such projects may also be specialized in only
that type of building.
Illustration of Construction of the PPG Building in Pittsburgh, PA
Specialized Industrial Construction
Illustration of Construction of a Benzene Plant in Lima, Ohio
Infrastructure and Heavy Construction
Infrastructure and heavy construction includes projects such as highways, mass
transit systems, tunnels, bridges, pipelines, drainage systems and sewage
treatment plants. Most of these projects are publicly owned and therefore
financed either through bonds or taxes. This category of construction is
characterized by a high degree of mechanization, which has gradually replaced
some labor intensive operations.
Illustration of Construction of the Dame Point Bridge in Jacksonville, Florida
1.4 Selection of Professional Services
Financial Planning Consultants
At the early stage of strategic planning for a capital project, an owner often
seeks the services of financial planning consultants such as certified public
accounting (CPA) firms to evaluate the economic and financial feasibility of
the constructed facility, particularly with respect to various provisions of
federal, state and local tax laws which may affect the investment decision.
Investment banks may also be consulted on various options for financing the
facility in order to analyze their long-term effects on the financial health of
the owner organization.
Architectural and Engineering Firms
Traditionally, the owner engages an architectural and engineering (A/E) firm or
consoritum as technical consultant in developing a preliminary design. After
the engineering design and financing arrangements for the project are
completed, the owner will enter into a construction contract with a general
contractor either through competitive bidding or negotiation. The general
contractor will act as a constructor and/or a coordinator of a large number of
subcontractors who perform various specialties for the completion of the
project. The A/E firm completes the design and may also provide on site
quality inspection during construction. Thus, the A/E firm acts as the prime
professional on behalf of the owner and supervises the construction to insure
satisfactory results. This practice is most common in building construction.
Design/Construct Firms
A common trend in industrial construction, particularly for large projects, is
to engage the services of a design/construct firm. By integrating design and
construction management in a single organization, many of the conflicts between
designers and constructors might be avoided. In particular, designs will be
closely scrutinized for their constructibility. However, an owner engaging a
design/construct firm must insure that the quality of the constructed facility
is not sacrificed by the desire to reduce the time or the cost for completing
the project. Also, it is difficult to make use of competitive bidding in this
type of design/construct process. As a result, owners must be relatively
sophisticated in negotiating realistic and cost-effective construction
contracts.
Professional Construction Managers
In recent years, a new breed of construction managers (CM) offers professional
services from the inception to the completion of a construction project. These
construction managers mostly come from the ranks of A/E firms or general
contractors who may or may not retain dual roles in the service of the owners.
In any case, the owner can rely on the service of a single prime professional
to manage the entire process of a construction project. However, like the A/E
firms of several decades ago, the construction managers are appreciated by some
owners but not by others. Before long, some owners find that the construction
managers too may try to protect their own interest instead of that of the
owners when the stakes are high.
Operation and Maintenance Managers
Although many owners keep a permanent staff for the operation and maintenance
of constructed facilities, others may prefer to contract such tasks to
professional managers. Understandably, it is common to find in-house staff for
operation and maintenance in specialized industrial plants and infrastructure
facilities, and the use of outside managers under contracts for the operation
and maintenance of rental properties such as apartments and office buildings.
However, there are exceptions to these common practices. For example,
maintenance of public roadways can be contracted to private firms. In any
case, managers can provide a spectrum of operation and maintenance services for
a specified time period in accordance to the terms of contractual agreements.
Thus, the owners can be spared the provision of in-house expertise to operate
and maintain the facilities.
Facilities Management
As a logical extension for obtaining the best services throughout the project
life cycle of a constructed facility, some owners and developers are receptive
to adding strategic planning at the beginning and facility maintenance as a
follow-up to reduce space-related costs in their real estate holdings.
Consequently, some architectural/engineering firms and construction management
firms with computer-based expertise, together with interior design firms, are
offering such front-end and follow-up services in addition to the more
traditional services in design and construction. This spectrum of services is
described in Engineering News-Record (now ENR) as follows:["Hot New Market
Lures A-E Players to Cutting Edges," Engineering News-Record, April 4, 1985,
pp. 30-37.]
Facilities management is the discipline of planning, designing, constructing
and managing space -- in every type of structure from office buildings to
process plants. It involves developing corporate facilities policy, long-range
forecasts, real estate, space inventories, projects (through design,
construction and renovation), building operation and maintenance plans and
furniture and equipment inventories.
1.5 Construction Contractors
General Contractors
The function of a general contractor is to coordinate all tasks in a
construction project. Unless the owner performs this function or engages a
professional construction manager to do so, a good general contractor who has
worked with a team of superintendents, specialty contractors or subcontractors
together for a number of projects in the past can be most effective in
inspiring loyalty and cooperation. The general contractor is also
knowledgeable about the labor force employed in construction. The labor force
may or may not be unionized depending on the size and location of the projects.
In some projects, no member of the work force belongs to a labor union; in
other cases, both union and non-union craftsmen work together in what is called
an open shop, or all craftsmen must be affiliated with labor unions in a closed
shop. Since labor unions provide hiring halls staffed with skilled journeyman
who have gone through apprentice programs for the projects as well as serving
as collective bargain units, an experienced general contractor will make good
use of the benefits and avoid the pitfalls in dealing with organized labor.
Specialty Contractors
Specialty contractors include mechanical, electrical, foundation, excavation,
and demolition contractors among others. They usually serve as subcontractors
to the general contractor of a project. In some cases, legal statutes may
require an owner to deal with various specialty contractors directly. In the
State of New York, for example, specialty contractors, such as mechanical and
electrical contractors, are not subjected to the supervision of the general
contractor of a construction project and must be given separate prime contracts
on public works. With the exception of such special cases, an owner will hold
the general contractor responsible for negotiating and fulfilling the
contractual agreements with the subcontractors.
Material and Equipment Suppliers
Major material suppliers include specialty contractors in structural steel
fabrication and erection, sheet metal, ready mixed concrete delivery,
reinforcing steel bar detailers, roofing, glazing etc. Major equipment
suppliers for industrial construction include manufacturers of generators,
boilers and piping and other equipment. Many suppliers handle on-site
installation to insure that the requirements and contractual specifications are
met. As more and larger structural units are prefabricated off-site, the
distribution between specialty contractors and material suppliers becomes even
less obvious.
1.6 Financing of Constructed Facilities
Construction Financing
Construction loans to contractors are usually provided by banks or savings and
loan associations for construction financing. Upon the completion of the
facility, construction loans will be terminated and the post-construction
facility financing will be arranged by the owner.
Facility Financing
Many private corporations maintain a pool of general funds resulting from
retained earnings and long-term borrowing on the strength of corporate assets,
which can be used for facility financing. Similarly, for public agencies, the
long-term funding may be obtained from the commitment of general tax revenues
from the federal, state and/or local governments. Both private corporations
and public agencies may issue special bonds for the constructed facilities
which may obtain lower interest rates than other forms of borrowing.
Short-term borrowing may also be used for bridging the gaps in long-term
financing. Some corporate bonds are convertible to stocks under circumstances
specified in the bond agreement. For public facilities, the assessment of user
fees to repay the bond funds merits consideration for certain types of
facilities such as toll roads and sewage treatment plants.(See Hendrickson, C.,
"Financing Civil Works with User Fees," Civil Engineering, Vol. 53, No. 2,
February 1983, pp. 71-72.) The use of mortgages is primarily confined to
rental properties such as apartments and office buildings.
1.7 Legal and Regulatory Requirements
Legal Responsibilities
Activities in construction often involve risks, both physical and financial.
An owner generally tries to shift the risks to other parties to the degree
possible when entering into contractual agreements with them. However, such
action is not without cost or risk. For example, a contractor who is assigned
the risks may either ask for a higher contract price to compensate for the
higher risks, or end up in non-performance or bankruptcy as an act of
desperation. Such consequences can be avoided if the owner is reasonable in
risk allocation. When risks are allocated to different parties, the owner must
understand the implications and spell them out clearly. Sometimes there are
statutory limitations on the allocation of liabilities among various groups,
such as prohibition against the allocation of negligence in design to the
contractor. An owner must realize its superior power in bargaining and hence
the responsibilities associated with this power in making contractual
agreements.
Mitigation of Conflicts
It is important for the owner to use legal counselors as advisors to mitigate
conflicts before they happen rather than to wield conflicts as weapons against
other parties. There are enough problems in design and construction due to
uncertainty rather than bad intentions. The owner should recognize the more
enlightened approaches for mitigating conflicts, such as using owner-controlled
wrap-up insurance which will provide protection for all parties involved in
the construction process for unforeseen risks, or using arbitration, mediation
and other extra-judicial solutions for disputes among various parties.
However, these compromise solutions are not without pitfalls and should be
adopted only on the merit of individual cases.
Government Regulation
To protect public safety and welfare, legislatures and various government
agencies periodically issue regulations which influence the construction
process, the operation of constructed facilities, and their ultimate disposal.
For example, building codes promulgated by local authorities have provided
guidelines for design and construction practices for a very long time. Since
the 1970's, many federal regulations that are related directly or indirectly to
construction have been established in the United States. Among them are safety
standards for workers issued by the Occupational Health and Safety
Administration, environmental standards on pollutants and toxic wastes issued
by the Environmental Protection Agency, and design and operation procedures for
nuclear power plants issued by the Nuclear Regulatory Commission. The
proliferation of environmental protection laws in recent decades can be noted
from Figure 1-0.
U.S. Laws on Environmental Protection, 1895 - 1985
1.8 The Changing Environment of the Construction Industry
Value of New Construction in U.S., 1950-1985
New Technologies
In recent years, technological innovation in design, materials and construction
methods have resulted in significant changes in construction costs.
Computer-aids have improved capabilities for generating quality designs as well
as reducing the time required to produce alternative designs. New materials
not only have enhanced the quality of construction but also have shortened the
time for shop fabrication and field erection. Construction methods have gone
through various stages of mechanization and automation, including the latest
development of construction robotics.
Labor Productivity
The term productivity is generally defined as a ratio of the production output
volume to the input volume of resources. Since both output and input can be
quantified in a number of ways, there is no single measure of productivity that
is universally applicable, particularly in the construction industry where the
products are often unique and there is no standard for specifying the levels
for aggregation of data. However, since labor constitutes a large part of the
cost of construction, labor productivity in terms of output volume (constant
dollar value or functional units) per person-hour is a useful measure. Labor
productivity measured in this way does not necessarily indicate the efficiency
of labor alone but rather measures the combined effects of labor, equipment and
other factors contributing to the output.
Public Scrutiny
Under the present litigious climate in the United States, the public is
increasingly vocal in the scrutiny of construction project activities.
Sometimes it may result in considerable difficulty in siting new facilities as
well as additional expenses during the construction process itself. Owners
must be prepared to manage such crises before they get out of control.
Public Acceptance toward New Facilities
International Competition
A final trend which deserves note is the increasing level of international
competition in the construction industry. Owners are likely to find
non-traditional firms bidding for construction work, particularly on large
projects. Separate bids from numerous European, North American, and Asian
construction firms are not unusual. In the United States, overseas firms are
becoming increasingly visible and important. In this environment of heightened
competition, good project management and improved productivity are more and
more important.
Through most of the postwar years, the nation's biggest builders of offshore
oil platforms enjoyed an unusually cozy relationship with the Big Oil Companies
they served. Their top officials developed personal friendships with oil
executives, entertained them at opulent hunting camps- and won contracts to
build nearly every major offshore oil platform in the world....But this summer,
the good-old boy network fell apart. Shell [Oil Co.] awarded the main contract
for [a new] platform - taller than Chicago's Sears Tower, four times heavier
than the Brooklyn Bridge - to a tiny upstart.
The winning bidder arranged overseas fabrication of the rig, kept overhead
costs low, and proposed a novel assembly procedure by which construction
equipment was mounted on completed sections of the platform in order to speed
the completion of the entire structure. The result was lower costs than those
estimated and bid by traditional firms.
Contractor Financed Projects
Increasingly, some owners look to contractors or joint ventures as a resource
to design, to build and to finance a constructed facility. For example, a
utility company may seek a consortium consisting of a design/construct firm and
a financial investment firm to assume total liability during construction and
thereby eliminate the risks of cost escalation to ratepayers, stockholders and
the management. On the other hand, a local sanitation district may seek such a
consortium to provide private ownership for a proposed new sewage treatment
plant. In the former case, the owner may take over the completed facility and
service the debt on construction through long-term financing arrangements; in
the latter case, the private owner may operate the completed facility and
recover its investment through user fees. The activities of joint ventures
among design, construction and investment firms are sometimes referred to as
financial engineering.
1.9 The Role of Project Managers
It is customary to think of engineering as a part of a trilogy, pure science,
applied science and engineering. It needs emphasis that this trilogy is only
one of a triad of trilogies into which engineering fits. This first is pure
science, applied science and engineering; the second is economic theory,
finance and engineering; and the third is social relations, industrial
relations and engineering. Many engineering problems are as closely allied to
social problems as they are to pure science.
As engineers advance professionally, they often spend as much or more time on
planning, management and other economic or social problems as on the
traditional engineering design and analysis problems which form the core of
most educational programs. It is upon the ability of engineers to tackle all
such problems that their performance will ultimately be judged.
1.10 References
2. Organizing for Project Management
2.1 What is Project Management?
Project management is the art of directing and coordinating human and
material resources throughout the life of a project by using modern management
techniques to achieve predetermined objectives of scope, cost, time, quality
and participation satisfaction.
By contrast, the general management of business and industrial corporations
assumes a broader outlook with greater continuity of operations. Nevertheless,
there are sufficient similarities as well as differences between the two so
that modern management techniques developed for general management may be
adapted for project management.
Basic Ingredients in Project Management
2.2 Trends in Modern Management
Illustrative Hierarchical Structure of Management Functions
2.3 Strategic Planning and Project Programming
Ability to Influence Construction Cost Over Time
To compound the problem, mega projects are often constructed in remote
environments away from major population centers and subject to severe climate
conditions. Consequently, special features of each mega project must be
evaluated carefully.
2.4 Effects of Project Risks on Organization
2.5 Organization of Project Participants
It should be pointed out that some decompositions may work out better than
others, depending on the circumstances. In any case, the prevalence of
decomposition makes the subsequent integration particularly important. The
critical issues involved in organization for project management are:
Example of a Matrix Organization
Example of a Project-Oriented Organization
The Matrix Organization in an Engineering Division
Coordination between Owner and Consultant
2.6 Traditional Designer-Constructor Sequence
2.7 Professional Construction Management
Consequently, it is important to recognize the changing nature of the
organizational structure as a project is carried out in various stages.
2.8 Owner-Builder Operation
Organization of a District of Corps of Engineers
2.9 Turnkey Operation
2.10 Leadership and Motivation for the Project Team
2.11 Interpersonal Behavior in Project Organizations
2.12 Perceptions of Owners and Contractors
Conversely, the key factors cited for unsuccessful projects are:
2.13 References
3. The Design and Construction Process
3.1 Design and Construction as an Integrated System
Recommended Responsibility for Shop Drawings
3.2 Innovation and Technological Feasibility
The great pioneering steel bridges of the United States were built by an open
or covert alliance between designers and constructors. The turnkey approach of
designer-constructor has developed and built our chemical plants, refineries,
steel plants, and nuclear power plants. It is time to ask, seriously, whether
we may not have adopted a restrictive approach by divorcing engineering and
construction in the field of bridge construction.
If a contractor-engineer, by some stroke of genius, were to present to design
engineers today a wonderful new scheme for long span prestressed concrete
bridges that made them far cheaper, he would have to make these ideas available
to all other constructors, even limiting or watering them down so as to "get a
group of truly competitive bidders." The engineer would have to make sure that
he found other contractors to bid against the ingenious innovator.
If an engineer should, by a similar stroke of genius, hit on such a unique
and brilliant scheme, he would have to worry, wondering if the low bidder would
be one who had any concept of what he was trying to accomplish or was in any
way qualified for high class technical work.
Proposed Structural Systems for Steel Buildings
3.3 Innovation and Economic Feasibility
Market Demand and Total Cost Relationship
Illustrative Relationships between Building Size and Input Labor
by Types of Building
3.4 Design Methodology
Conceptual Design Process
An Analogy between the Structural Design and Computer Program Development
Processes
The design of a new facility often begins with the search of the files for a
design that comes as close as possible to the one needed. The design process
is guided by accumulated experience and intuition in the form of heuristic
rules to find acceptable solutions. As more experience is gained for this
particular type of facility, it often becomes evident that parts of the design
problem are amenable to rigorous definition and algorithmic solution. Even
formal optimization methods may be applied to some parts of the problem.
3.5 Functional Design
Hence, the procedure for seeking the goals can be recycled iteratively in
order to make tradeoffs and thus improve the solution of spatial layouts.
A Model for Top-Down Design of a Hospital
A Model for Bottom-up Design of an Examination Suite
3.6 Physical Structures
Steel Frame Supporting a Turbo-Blower
3.7 Geotechnical Engineering Investigation
Typical Cross Section of Hillside Adjoining Site
Schematic Section of Anchored Steel Sheet Pile Retaining Wall
3.8 Construction Site Environment
Cross Section Illustration of a Landfill
The excavation and reburial of even a small landfill site can be very
expensive. For example, the estimated reburial cost for a landfill like that
shown in Figure 3-0 was in excess of $ 4 million in 1978.
3.9 Value Engineering
3.10 Construction Planning
3.11 Industrialized Construction and Pre-fabrication
3.12 Computer-Aided Engineering
3.13 References
4. Labor, Material and Equipment Utilization
4.1 Historical Perspective
[T]he work could not have done any faster or more efficiently in our day,
despite all technological and mechanical advances in the time since, the reason
being that no present system could possibly carry the spoil away any faster or
more efficiently than the system employed. No motor trucks were used in the
digging of the canal; everything ran on rails. And because of the mud and
rain, no other method would have worked half so well.[McCullough, David, The
Path Between the Seas, Simon and Schuster, 1977, pg. 531.]
In contrast to this view of one large project, one may also point to the
continual change and improvements occurring in traditional materials and
techniques. Bricklaying provides a good example of such changes:
Bricklaying...is said not to have changed in thousands of years; perhaps in
the literal placing of brick on brick it has not. But masonry technology has
changed a great deal. Motorized wheelbarrows and mortar mixers, sophisticated
scaffolding systems, and forklift trucks now assist the bricklayer. New epoxy
mortars give stronger adhesion between bricks. Mortar additives and
cold-weather protection eliminate winter shutdowns.[Rosefielde, Steven and
Daniel Quinn Mills, "Is Construction Technologically Stagnant?", in Lange,
Julian E. and Daniel Quinn Mills, The Construction Industry, Lexington Books,
1979, pg. 83.]
Add to this list of existing innovations the possibility of robotic
bricklaying; automated prototypes for masonry construction already exist.
Technical change is certainly occurring in construction, although it may occur
at a slower rate than in other sectors of the economy.
4.2 Labor Productivity
Productivity at the Job Site
Productivity in the Construction Industry
4.3 Factors Affecting Job-Site Productivity
Project Work Conditions
Non-Productive Activities
Illustrative Relationship between
Productivity Index and Job Size
500,000 - 650,000
I = 1.0 + (1.1-1.0) ## ## = 0.85-----------------
500,000 - 400,000
This implies that labor is 15% less productive on the large job than on the
standard project.
Determine the productive labor yield after the above factors are taken into
consideration.
A 417
##=## ##=##6#%- -----
L 7,500
B 1,415
##=## ##=##19#%- -----
L 7,500
C 1,141
##=## ##=##15#%- -----
L 7,500
D 1,431
##=## ##=##19#%- -----
L 7,500
The total percentage of time X for all non-productive activities is:
A#+#B#+#C#+#D
X##=## ##=###6#%##+##19#%##+##15#%##+##19#%##=##59#%-------------
L
The productive labor yield, Y, when the given factors for A, B, C and D are
considered, is as follows:
L##-##A##-##B##-##C##-##D
Y = = 100#%#-#6#%#-#19#%#-#15#%#-#19#%#=#41#%-------------------------
L
As a result, only 41% of the budgeted labor time was devoted directly to work
on the facility.
!!!Productive time!!!40%
!!!Unproductive time
!!!!!!Administrative delays !!!20%
!!!!!!Inefficient work methods!!!20%
!!!!!!Labor jurisdictions and other work restrictions!!!15%
!!!Personal time!!!5%
In this estimate, as much time is spent on productive work as on delays due to
management and inefficiencies due to antiquated work methods.
4.4 Labor Relations in Construction
Unionized Construction
Non-Unionized Construction
4.5 Problems in Collective Bargaining
Regional Bargaining
Multicraft Bargaining
Improvement of Bargaining Performance
4.6 Materials Management
Against these various benefits, the costs of acquiring and maintaining a
materials management system has to be compared. However, management studies
suggest that investment in such systems can be quite beneficial.
4.7 Material Procurement and Delivery
Freight Delivery for the Alaska Pipeline Project
Activities!!!Duration!!!Cumulative
!!! (days)!!!Duration
Requisition ready by designer!!!0!!!0
Owner approval!!!5!!!5
Inquiry issued to vendors!!!3!!!8
Vendor quotations received!!!15!!!23
Complete bid evaluation by designer!!!7!!!30
Owner approval!!!5!!!35
Place purchase order!!!5!!!40
Receive preliminary shop drawings!!!10!!!50
Receive final design drawings!!!10!!!60
Fabrication and delivery!!!60-200!!!120-260
As a result, this type of equipment procurement will typically require four to
nine months. Slippage or contraction in this standard schedule is also
possible, based on such factors as the extent to which a fabricator is busy.
4.8 Inventory Control
Purchase Costs
Order Cost
Holding Costs
Unavailability Cost
4.9 Tradeoffs of Costs in Materials Management.
t
P (T L t) = p(u)S
u=0
b
E[T] = t[p(t)]S
t=a
L = E[T] + D
Delivery Date on Orders and Probability of Delivery for an Example
16
E[T]#=## t[p(t)]S
t=10
#####=##(10)(0.1)#+#(11)(0.1)#+#(12)(0.15)#+
\*
#(13)0(.20)#+#(14)(0.30)#+#(15)(0.10)#=#13.0
4.10 Construction Equipment
Excavation and Loading
Typical Machines in the Crane-Shovel Family
Compaction and Grading
Some Major Types of Compaction Equipment
Drilling and Blasting
Lifting and Erecting
Mixing and Paving
Construction Tools and Other Equipment
Automation of Equipment
4.11 Choice of Equipment and Standard Production Rates
By comparing various types of machines for excavation, for example, power
shovels are generally found to be the most suitable for excavating from a level
surface and for attacking an existing digging surface or one created by the
power shovel; furthermore, they have the capability of placing the excavated
material directly onto the haulers. Another alternative is to use bulldozers
for excavation.
Dump trucks are usually used as haulers for excavated materials as they can
move freely with relatively high speeds on city streets as well as on highways.
C
R##=##-
T
or
C
T##=##-
R
where C@-(e) and T@-(e) are cycle capacity (in units of volume) and cycle time
(in hours) of the excavator respectively.
C@-(e)H@-(e)
P@-(e)##=##R@-(e)H@-(e)##=##------------
T@-(e)
The loading time is related to the cycle time of the excavator T@-(e) and the
relative capacities C@-(h) and C@-(e) of the hauler and the excavator
respectively. In the optimum or standard case:
2#D
T@-(t)##=##---
S
For a given dumping time T@-(d), the cycle time T@-(h) of the hauler is given
by:
C@-(h)
T@-(o)##=##T@-(e)------
C@-(e)
The daily standard production rate P@-(h) of a hauler can be obtained by
multiplying its standard production rate R@-(h) by the number of operating
hours H@-(h) per day. Hence:
2#D C@-(h)
T@-(h)##=## ##+##T@-(e)# ##+##T@-(d)--- ------
S C@-(e)
This expression assumes that haulers begin loading as soon as they return from
the dump site.
C@-(h)#H@-(h)
P@-(h)##=##R@-(h)#H@-(h)##=##-------------
T@-(h)
w#P@-(e)
N@-(h)##=##--------
P@-(h)
On the other hand, the cycle time T' at the job site will be increased by
these factors, reflecting actual work conditions. If only these factors are
involved, T@+(1) is related to the standard cycle time T as:
R'##A##R#F@-(1)#F@-(2)# : : : #F@-(n)
Each of these various adjustment factors must be determined from experience or
observation of job sites. For example, a bulk composition factor is derived
for bulk excavation in building construction because the standard production
rate for general bulk excavation is reduced when an excavator is used to create
a ramp to reach the bottom of the bulk and to open up a space in the bulk to
accommodate the hauler.
T
T'##A##----------------------------
F@-(1)#F@-(2)# : : : #F@-(n)
(1#cu.#yd.)(8#hr.)(3,600#sec./hr.)
P@-(e)##=## ##=##960#cu.#yd.----------------------------------
30#sec.
In practice, of course, this standard rate would be modified to reflect
various production inefficiencies, as described in Example 4-11.
(2)(4#mi.)(3,600#sec./hr.)
T@-(t)##=## ##=##960sec.--------------------------
(30#mi./hr.)
6#cu.#yd.
T@-(o)##=##(30#sec.)## ## ## ##=##180#sec.---------
1#cu.#yd.
T@-(h)##=##960##+##180##+##30##=##1,170#sec.
Hence, the daily hauler productivity is:
(6#cu.#yd.)(8#hr.)(3,600#sec./hr.)
P@-(h)##=## ##=##147.7#cu.#yd.----------------------------------
(1,170#sec.)
Finally, from Equation (4.4.11), the number of trucks required is:
(1.1)(960#cu.#yd.)
N@-(h)##=## ##=##7.1------------------
147.7#cu.#yd.
implying that 8 trucks should be used.
Work Conditions at the Site!!!Factors
Bulk composition!!! 0.954
Soil properties and water content!!! 0.983
Equipment idle time for worker breaks!!! 0.8
Management efficiency!!! 0.7
Using Equation (4.4.11), the job site productivity of the power shovel per day
is given by:
P'@-(e)##=##(960#cu.#yd.)(0.954)(0.983)(0.8)(0.7)##=##504#cu.#yd.
The actual cycle time can be determined as follows:
(30#sec.)
T'@-(e)##=## ##=##57#sec.------------------------
(0.954)(0.983)(0.8)(0.7)
Noting Equation (4.4.11), the actual cycle time can also be obtained from the
relation T'@-(e) = C@-(e)H@-(e)/P'@-(e). Thus:
(1#cu.#yd.)(8#hr.)(3,600#sec./hr.)
T'@-(e)##=## ##=##57#sec.----------------------------------
504#cu.#yd.
T'@-(t)##=##
Hence, the actual cycle time is:
Num "T@-(t)", Denom "F@-[1]F@-[2]"
##=##
Num
"(2)(4#mi.)(3,600#sec./hr.)", Denom "(30#mi./hr.)(0.8)(0.7)"
##=##1,714#sec.
T'@-(o)##=##
Num "T'@-(e)", denom "F@-{1} F@-{2}"
#
Num "C@-(h)",
Denom "C@-(e)"
##=## ##
Num "57#sec.", denom "(0.8) (0.7)"
## ## ##
Num
"6#cu.#yd.",
Denom "1#cu.#yd."
## ##=##342#sec.
T'@-(d)##=##
Num "T@-(d)", Denom "F@-[1]F@-[2]"
##=##
Num
"30#sec.", Denom "(0.8)(0.7)"
##=##54#sec.
T'@-(h)##=##T'@-(t)##+##T'@-(o)##+##T'@-(d)##=##1714##+##611
*\
##+##54##=##2,379#sec.
The jobsite productivity P'@-(h) of the dump truck per day is:
P'@-(h)##=##
The number of trucks needed daily is:
Num "C@-(h)H@-(h)", Denom "T'@-(h)"
##=##
Num
"(6#cu.#yd.)(8#hr.)(3,600#sec./hr.)", Denom "2,379#sec."
##=##72.6#cu.#yd.
N'@-(h)##=##
so 8 trucks are required.
Num "wP'@-(e)", Denom "P'@-(h)"
##=##
Num
"(1.1)(504#cu.#yd.)", Denom "72.6#cu.#yd."
##=##7.6
4.12 Construction Processes
Illustration of a Concrete-Placing Simulation Model
4.13 Queues and Resource Bottlenecks
Single-Server with Deterministic Arrivals and Services
@g[D]A@-(t) = A(t) - A(t-1)
A(t) - A(t-1)
A@+(')(t)##=## = A(t) - A(t-1)-------------
@g[D]t
The slope of the cumulative departure function is:
@g{D}D@-[t] = D(t) - D(t-1)
D(t) - D(t-1)
D't = = D(t) - D(t-1)-------------
@g{D}t
Cumulative Arrivals and Departures in a Deterministic Queue
For example, suppose a queue begins to form at time t@-(i) and is dispersed by
time t@-(k). The maximum number of customers waiting or queue length is
represented by the maximum difference between the cumulative arrival and
cumulative departure functions between t@-(i) and t@-(k), i.e. the maximum
value of Q(t). The total waiting time for service is indicated by the total
area between the cumulative arrival and cumulative departure functions.
Q(t) = A(t) - D(t)
@g[D]D@-(1) = minimum {x;@g[D]A@-[1]}
A(t) =A(t-1) + @g{D}A@-(t)
Q(t) = Q(t-1) + @g{D}A@-(t) - @g{D}D@-(t)
@g{D}D@-(t) = minimum {x; Q(t-1) + @g{D}A@-(t)}
D(t) = D(t-1) + @g{D}D@-(t)
@g[D]w = Q(t) (@g{D}t)
t@-(k)
W = @g{D}wS
t=t@-{i}
W
w = ---------------------
A(t@-{k}) - A(t@-{i})
Cases of No Queue and Permanent Bottleneck
Single-Server with Random Arrivals and Constant Service Rate
w##=##
num"a", denom<2#x@+[2]# ##1 -##
num"a", denom "x"
## >
Then, Eq. (4.4.13) becomes:
a
u = -
x
In this equation, the ratio u of arrival rate to service rate is very
important: if the average arrival rate approaches the service rate, the waiting
time can be very long. If a G x, then the queue expands indefinitely.
Resource bottlenecks will occur with random arrivals unless a measure of extra
service capacity is available to accommodate sudden bunches in the arrival
stream. Figure 4-0 illustrates the waiting time resulting from different
combinations of arrival rates and service times.
u
w = -------
2x(1-u)
Illustrative Waitfing Times for Different Average
Arrival Rates and Service Times
Multiple Servers
A(t) =
A queue is formed at t = 0 because of the breakdown, but it dissipates at
A(t) = D@-(2)(t). Let
num "t", denom "10"
##for## t G 0
D@-(1)(t) = 0 ### for ### 0 L t L 90 min
D@-(2)(t) =
num "t-90", denom "5"
### for ### t G 90 min
from which we obtain
num "t", denom "10"
=
num "t-90", denom "5"
t## =## 180 ##minutes####and ### A(180##=##D@-(2)(180)##=##18##loads.
The total waiting time W can be calculated as the area between the cumulative
arrival and service functions in Figure 4-0. Algebraically, this is
conveniently calculated as the difference in the areas of two triangles:
W## =## so the average delay per load is w = 810/18 = 45 minutes.
Num "(18)(180)", Denom "2"
##-##
Num
"(18)(90)", Denom "2"
##=##810#minutes
Arrivals and Services of Crane Loads with a Crane Breakdown
At a resource cost of $ 30.00 per hour, this waiting would represent a cost of
(30)(0.4)(5) = $ 60.00 per hour on the project.
num "5/6", denom "(2)(6)## -## (1# -# 5/6)"
## =## 0.4## hours.
which has only a cost of (30) (0.05) (5) = $ 7.50 per hour.
num "0.5", denom "(2)(10)(1#-#0.5)"
## =## 0.05## hours.
6:00-7:00 AM.!!! 4 per hour!!! 12:00-4:00 PM.!!!8 per hour
7:00-8:00 AM.!!!15 per hour!!! 4:00-6:00 PM.!!!4 per hour
8:00-11:00 AM.!!!25 per hour!!! 6:00 PM-6:00 AM.!!!0 per hour
11:00-12:00 AM.!!!5 per hour
Using the above information of arrival and service rates
Computation of Queue Length and Waiting Time
Period!!!Arrival!!!Cumulative!!!!!!Departure!!!Cumulative!!!Waiting
!!!Rate!!!Arrivals!!!Queue!!!Rate!!!Departures!!!Time
!!!!!!A(t)!!!!!!!!!D(t)
5-7:00!!!4!!!4!!!0!!!4!!!4!!!0
7-8:00!!!15!!!19!!!0!!!15!!!19!!!0
8-9:00!!!25!!!44!!!5!!!20!!!39!!!5
9-10:00!!!25!!!69!!!10!!!20!!!59!!!10
10-11:00!!!25!!!94!!!15!!!20!!!79!!!15
11-12:00!!!5!!!99!!!0!!!20!!!99!!!0
12-1:00!!!8!!!107!!!0!!!8!!!107!!!0
1-2:00!!!8!!!115!!!0!!!8!!!115!!!0
2-3:00!!!8!!!123!!!0!!!8!!!123!!!0
3-4:00!!!8!!!131!!!0!!!8!!!131!!!0
4-5:00!!!4!!!135!!!0!!!4!!!135!!!0
5-6:00!!!4!!!139!!!0!!!4!!!139!!!9
6-7:00!!!0!!!139!!!0!!!0!!!139!!!0
7-8:00!!!0!!!139!!!0!!!0!!!139!!!0
!!!!!!!!!!!!Total Waiting Time = 30
!!!!!!!!!!!!Maximum Queue = 15
Delay of Lift Loads on a Building Site
4.14 References
4.15 Problems
A. 360 for holidays and strikes
B. 1,152 for absentees
C. 785 for temporary stoppage
D. 1,084 for indirect labor
Determine the productive labor yield after the above factors are taken into
consideration.
-0.016#x@+{2}# +# 0.16x# + #0.6## for# 0 < # x #L #5
I## =## B
1.0 ##### for ## x ## G ## 5
Find the value of the index I for x = 0, 1, 2, 3, 4 and 5 and plot the
relationship in a graph.
Table P4-5
t!!!p(t)!!!P{T L t}
12!!!0.05!!!0.05
13!!!0.10!!!0.15
14!!!0.25!!!0.40
15!!!0.35!!!0.75
16!!!0.15!!!0.90
17!!!0.10!!!1.00
!!!Work conditions at site Factors
!!!Bulk composition 0.972
!!!Soil properties and water content 0.960
!!!Equipment idle time for breaks 0.750
!!!Management inefficiency 0.750
!!!(a)!!!(b)
6-7:00 am!!!0!!!0
7-8:00 am!!!25!!!10
8-9:00 am!!!25!!!10
9-10:00 am!!!25!!!15
10-11:00 am!!!25!!!15
11-12:00 am!!!10!!!10
12-1:00 am!!!8!!!15
1-2:00 pm!!!0!!!15
2-3:00 pm!!!0!!!15
3-4:00 pm!!!0!!!10
4-5:00 pm!!!0!!!10
After 5 pm!!!0!!!0
Total number of arrivals!!!110!!!110
5. Cost Estimation
5.1 Costs Associated with Constructed Facilities
The operation and maintenance cost in subsequent years over the project life
cycle includes the following expenses:
The magnitude of each of these cost components depends on the nature, size and
location of the project as well as the management organization, among many
considerations. The owner is interested in achieving the lowest possible
overall project cost that is consistent with its investment objectives.
Resource Requirements of Some Major Energy Projects
5.2 Approaches to Cost Estimation
5.3 Types of Construction Cost Estimates
For each of these different estimates, the amount of design information
available typically increases.
Design Estimates
Bid Estimates
Control Estimates
Illustration of Grout Bottom Seal Liner at a Landfill
8 acres = (8)
(43,560 sq.ft./acre) = 348,480 sq. ft.
(As an approximation, use 360,000 sq.
ft. to account for the bowl shape)
The number of bore holes in a 50 ft. by 50 ft. grid pattern covering 360,000
sq. ft. is given by:
The average depth of the bore holes is estimated to be 20 ft. Hence, the
total amount of drilling is (144)(20) = 2,880 ft.
Num "360,000#sq.#ft.",
Denom "(50#ft.)(50#ft.)"
##=##144
for a 4 ft. layer, volume = (4 ft.)
(360,000 sq. ft.) = 1,440,000 cu. ft.
for a 6 ft. layer, volume = (6 ft.)
(360,000 sq. ft.) = 2,160,000 cu. ft.
It is estimated from soil tests that the voids in the soil layer are between
20% and 30% of the total volume. Thus, for a 4 ft. soil layer:
grouting in 20 % voids =
(20 %)(1,440,000) = 288,000 cu. ft.
grouting in 30 % voids =
(30 %)(1,440,000) = 432,000 cu. ft.
and for a 6 ft soil layer:
grouting in 20 % voids =
(20 %)(2,160,000) = 432,000 cu. ft.
grouting in 30 % voids =
(30 %)(2,160,000) = 648,000 cu. ft.
for a 4 ft. layer with 20% voids, grouting cost = $ 1,152,000 to $ 2,880,000
for a 4 ft. layer with 30% voids, grouting cost = $ 1,728,000 to $ 4,320,000
for a 6 ft. layer with 20% voids, grouting cost = $ 1,728,000 to $ 4,320,000
for a 6 ft. layer with 30% voids, grouting cost = $ 2,592,000 to $ 6,480,000
(5 ft)(360,000 sq. ft.)(25 %)($ 7/cu.ft.) = $ 3,150,000
An important point to note is that this screening estimate is based to a large
degree on engineering judgment of the soil characteristics, and the range of
the actual cost may vary from $ 1,152,000 to $ 6,480,000 even though the
probabilities of having actual costs at the extremes are not very high.
!!!1. Ball, Ball & Brosame, Inc., Danville CA $ 14,129,798!!!
!!!2. National Projects, Inc., Phoenix, AR $ 15,381,789!!!
!!!3. Kiewit Western Co., Murray, Utah $ 18,146,714!!!
It was astounding that the winning bid was 32% below the engineer's estimate.
Even the third lowest bidder was 13% below the engineer's estimate for this
project. The disparity in pricing can be attributed either to the very
conservative estimate of the engineer in the Utah Department of Transportation
or to area contractors who are hungrier than usual to win jobs.
5.4 Effects of Scale on Construction Cost
y = a + bx
where a and b are positive constants to be determined on the basis of
historical data. Note that in Equation (5.5.4), a fixed cost of y = a at x = 0
is implied as shown in Figure 5-0. In general, this relationship is applicable
only in a certain range of the variable x, such as between x = c and x = d. If
the values of y corresponding to x = c and x = d are known, then the cost of a
facility corresponding to any x within the specified range may be obtained by
linear interpolation. For example, the construction cost of a school building
can be estimated on the basis of a linear relationship between cost and floor
area if the unit cost per square foot of floor area is known for school
buildings within certain limits of size.
y = a x@+(b)
where a and b are positive constants to be determined on the basis of
historical data. For 0 < b < 1, Equation (5.5.4) represents the case of
increasing returns to scale, and for b > 1, the relationship becomes the case
of decreasing returns to scale, as shown in Figure 5-0. Taking the logarithm
of both sides this equation, a linear relationship can be obtained as follows:
ln y = ln a + b ln x
Although no fixed cost is implied in Eq. (5.2), the equation is usually
applicable only for a certain range of x. The same limitation applies to Eq.
(5.3).
where m usually varies from 0.5 to 0.9, depending on a specific type of
facility. A value of m = 0.6 is often used for chemical processing plants.
The exponential rule can be reduced to a linear relationship if the logarithm
of Equation (5-4) is used:
y = y@-(n) ##
num "Q", denom "Q@-(n)"
@+[m]
The exponential rule can be applied to estimate the total cost of a complete
facility or the cost of some particular component of a facility.
ln#y### =### ln# y@-(n)# +# m# ln#
num "Q", denom "Q@-{n}"
#
or
ln## ##
Num "y", Denom "y@-{n}"
# ##=### m ###ln# #
Num "Q", Denom "Q@-{n}"
#
For ln(y/y@-(n)) = 0.1765, y/y@-(n) = 1.5, while the corresponding value of
Q/Q@-(n) is 2. In words, for m = 0.585, the cost of a plant increases only 1.5
times when the capacity is doubled.
m =
num"0.1765", denom"0.301"
= 0.585
y###=###K#Q@+(m)
where
K##=##
If m and K are known for a given type of facility, then the cost y for a
proposed new facility of specified capacity Q can be readily computed.
Num "y@-(n)", Denom "(Q@-(n))@+(m)"
y##=##($#399)(15,000)@+(0.60)##A##$#128,000.
5.5 Unit Cost Method of Estimation
Simple Unit Cost Formula
where n is the number of units. Based on characteristics of the construction
site, the technology employed, or the management of the construction process,
the estimated unit cost, u@-(i) for each element may be adjusted.
y =
from "i=1", to "n"
u@-(i)Q@-(i)
Factored Estimate Formula
where n is the number of major equipment components included in the project.
The factored method is essentially based on the principle of computing the cost
of ancillary items such as piping and valves as a fraction or a multiple of the
costs of the major equipment items. The value of C@-(i) may be obtained by
applying the exponential rule so the use of Equation (5.5.5) may involve a
combination of cost estimation methods.
y = ##
from"i=1", To "n"
C@-(i) +
from
"i=1", to "n"
f@-(i)C@-(i)####=##
from "i=1",
to "n"
##C@-(i)#(1#+#f@-(i))
Formula Based on Labor, Material and Equipment
y# =#
from "i=1", to "n"
#y@-(i)##=##
from "i=1",to "n"
# Q@-[i] (M@-[i]#+# E@-(i)#+# W@-[i] L@-[i])
5.6 Methods for Allocation of Joint Costs
Similarly, let z be the total direct field cost which includes the total basic
cost and the field supervision cost of the project, and z@-(i) be the direct
field cost for task i. If G is the general office overhead for proration to
all tasks, and G@-(i) is the share for task i, then
F@-(i)##=##F##
num"y@-[i]",
denom"y"
Finally, let w be the grand total cost of the project which includes the
direct field cost and the general office overhead cost charged to the project
and w@-(i) be that attributable task i. Then,
G@-(i)##=##G##
num"z@-(i)", denom"z"
z## =## F## +## y## =## F## +##
from"i=1",to"n"
y@-(i)
and
w## =## G## +## z## =## G## +##
from"i=1", to"n"
z@-(i)
z = 13,245 + 88,300 = $ 101,545
G = (0.04)(101,545) = $ 4,062
w = 101,545 + 4,062 = $ 105,607
The results of the proration of costs to various elements are shown in Table
5--1.
5.7 Historical Cost Data
5.8 Cost Indices
j@-[t+1] =
Num "I@-[t+1]-I@-[t]", Denom "I@-[t]"
## (##100%)
or
If the price index at the base year t=0 is set at a value of 100, then the
price indices l@-[1], l@-[2]...l@-[n] for the subsequent years t=1,2...n can be
computed successively from changes in the total price charged for the package
of goods measured in the index.
I@-[t+1] = I@-[t] (1 + j@-[t+1])
Conversely
A@+[']@-[t]## =## A@-[t](1+j@-[1])(1+j@-[2])...
(1+j@-[t-1])(1+j@-[t])##=##A@-(t)## ##
Num "I@-(t)", Denom "I@-(o)"
##
A@-[t]## = ##A@+[']@-[t](1+j@-[t])
@+[-1](1+j@-[t-1])@+[-1]...(1+j@-[2])
@+[-1](1+j@-[1])@+[-1]##=##A'
@-(t)## ##
Num "I
@-(o)",
Denom "I@-(t)"
##
A@-[t]@+['] = A@-[t](1+j)@+[t]
and
A@-[t] = A@-[t](1+j)@+[-1]
Estimation of the future rate increase j is not at all straightforward. A
simple expedient is to assume that future inflation will continue at the rate
of the previous period:
j = j@-(t-1)
A longer term perspective might use the average increase over a horizon of n
past periods:
More sophisticated forecasting models to predict future cost increases include
corrections for items such as economic cycles and technology changes.
j##=##
from "i=1", to "n"
##
Num "j@-(t-i)", Denom
"n"
5.9 Applications of Cost Indices to Estimating
Some of these adjustments may be done using compiled indices, whereas others
may require field investigation and considerable professional judgment to
reflect differences between a given project and standard projects performed in
the past.
Unit Prices in Two Contractors' Bids for Roadway Construction
Unit Prices in Bids Submitted by Two Contractors, (Continued)
Linear Cost Relationship with Economies of Scale
Nonlinear Cost Relationship with Increasing or
Decreasing Economies of Scale
Log-Log Scale Graph of Exponential Rule Example
Estimated Values of Cost Exponents for Water Treatment Plants
Cost Factors of Processing Units for Treatment Plants
Illustrative Decomposition of Building Foundation Costs
!!!!!!Contract Elements
Design!!!!!!!!!!!!Total
Elements!!!Formwork!!!Re-bars!!!Concrete!!!Cost
Footings!!!$5,000!!!$10,000!!!$13,000!!!$28,000
Foundation Walls!!!$15,000!!!$18,000!!!$28,000!!!$61,000
Elevator Pit!!!$9,000!!!$15,000!!!$16,000!!!$40,000
Total Cost!!!$29,000!!!$43,000!!!$57,000!!!$129,000
Illustrative Cost Estimate Using Labor, Material and Equipment Rates
Proration of Field Supervision and Office Overhead Costs
!!!!!!Allocated!!!!!!Allocated
!!!Direct!!!Field Sup.!!!
Total Field!!!Overhead!!!Total
!!!Cost!!!Cost!!!Cost!!!Cost!!!Cost
Description!!!y@-(i)!!!F
@-(i)!!!z@-(i)!!!G@-(i)!!!w@-(i)
Formwork!!!$50,400!!!$7,560!!!
$57,960!!!$ 2,319!!!$ 60,279
Re-bars!!!$4,400!!!$660!!!
$5,060!!!$202!!!$5,262
Concrete!!!$33,500!!!$5,025!!!
$38,525!!!$1,541!!!$40,066
Total!!!$88,300!!!$13,245!!!
$101,545!!!$4,062!!!$105,607
Standard Cost Report for a Type of Valve
Illustrative Cost Data for Earthwork - Bulk Excavating with Backhoe
Illustrative Cost Data for Crews Operating Construction Equipment
Changes in the GNP Price Deflator and the ENR Building Cost
Indices, 1955-1985
Changes in the Turner Construction Company Building Index, 1955-1985
Summary of Input and Output Price Indices
Comparison of Standard Highway Costs, 1940-1980
Comparison of Residential Building Costs, 1970-1980
100 - 5 = 95
(95)#
num "300,000",
denom "200,000"
@+[0.6] =
(95)(1.5)@+[0.6] = 121.2
(121.2) (1.08)@+(4) = 164.6
(164.6) ##
num "1.14",
denom "0.92"
## = 204.6
204.6 + 7 = 211.6
(211.6) (1 - 0.01) = 209.5
Cost Data for Equipment and Ancillary Items
The solution of this problem can be carried out according to the steps as
outlined in the problem statement:
Results of Linear Interpolation for an Estimation Example
(5,333)(1.37) + (3,333)(1.42) + (2,667)(1.47) + (2,000)(1.57)
= 2,307 + 4,733 + 3,920 + 3,140 = 19,100.
(19,100)(63/47) = 25,600
(0.95) (25,600,000) + 500,000 A $ 24,800,000
5.10 Estimate Based on Engineer's List of Quantities
5.11 Allocation of Construction Costs Over Time
5.12 Estimation of Operating Costs
C = 596 + 0.0019 V + 21.7 A
where C is the annual cost of routine maintenance per lane-mile (in 1967
dollars), V is the volume of traffic on the roadway (measured in equivalent
standard axle loads, ESAL, so that a heavy truck is represented as equivalent
to many automobiles), and A is the age of the pavement in years since the last
resurfacing. According to this model, routine maintenance costs will increase
each year as the pavement service deteriorates. In addition, maintenance costs
increase with additional pavement stress due to increased traffic or to heavier
axle loads, as reflected in the variable V.
C = 596 + (0.0019)(500,300) + (21.7)(5)
= 596 + 950.5 + 108.5 = 1,655 (in 1967 dollars)
5.13 References
5.14 Problems
!!!1. W.W. Clyde & Co., Springville, Utah $ 21,384,919
!!!2. Sletten Construction company, Great Falls, Montana $ 26,701,018
!!!3. Gilbert Western Corporation, Salt Lake city, Utah $ 30,896,203
Find the percentage of each of these bidders below the engineer's cost
estimate.
C = (16,000)(Q + 50,000)@+(1/2)
where Q is the daily production capacity of batteries and C is the cost of
the building in 1987 dollars. If a similar plant is planned for a daily
production capacity of 200,000 batteries, find the screening estimate of the
building in 1987 dollars.
!!!Excavation!!!$ 240,000
!!!Subgrade!!!$ 100,000
!!!Base course!!!$ 420,000
!!!Concrete pavement!!!$ 640,000
!!!Total!!!$ 1,400,000
Assuming that field supervision cost is 10% of the basic cost, and the
general office overhead is 5% of the direct costs (sum of the basic costs
and field supervision cost), find the prorated field supervision costs,
general office overhead costs and total costs for the various elements of
the project.
P = C@-[1] AL (10@+[5])
The annual operating cost of the power line is assumed to be measured by
the power loss. The power loss S (in kwh) is known to be
J@+[2]R L (10@+[5]) J@+[2]RL
S = [ ] [ ] = (10@+[2])--------- ----------- --------
(10@+[3]) A A
where J is the electric current in amperes, R is the resistivity in
ohm-centimeters. Let C@-[2] be the unit operating cost (in dollars per
kwh). Then, the annual operating cost U (in dollars) is given by
J@+[2]RL
U = C@-[2] (10@+[2])--------
A
Suppose that the power line is expected to last n years and the life cycle
cost T of the power line is equal to:
T = P + UK
where K is a discount factor depending on the useful life cycle n and the
discount rate i (to be explained in Chapter 6). In designing the power
line, all quantitites are assumed to be known except A which is to be
determined. If the owner wants to minimize the life cycle cost, find the
best cross-sectional area A in terms of the known quantities.
6. Economic Evaluation of Facility Investments
6.1 Project Life Cycle and Economic Feasibility
6.2 Basic Concepts of Economic Evaluation
It is important to emphasize that many assumptions and policies, some implicit
and some explicit, are introduced in economic evaluation by the decision maker.
The decision making process will be influenced by the subjective judgment of
the management as much as by the result of systematic analysis.
A@-(t,x) = B@-(t,x)- C@-(t,x)
where A@-(t,x) is positive, negative or zero depends on the values of B@-(t,x)
and C@-(t,x), both of which are defined as positive quantities.
6.3 Costs and Benefits of a Constructed Facility
6.4 Interest Rates and the Costs of Capital
6.5 Investment Profit Measures
6.6 Methods of Economic Evaluation
Net Present Value Method
where the symbol (P|F,i,t) is a discount factor equal to (1+i)@+[-t] and reads
as follows: "To find the present value P, given the future value F=1,
discounted at an annual discount rate i over a period of t years." When the
benefit or cost in year t is multiplied by this factor, the present value is
obtained. Then, the net present value of the project x is calculated as:
BPV@-(x) =
from "t=0",to "n"
B@-(t,x)(1+i)@+{-t} =
from"t=0",to"n"
B@-(t,x)(P | F,i,t)
CPV@-(x) =
from "t=0",to "n"
C@-(t,x)(1+i)@+[-t] =
from "t=0",to "n"
C@-(t,x)(P| F,i,t)
or
NPV@-(x) = BPV@-(x) - CPV@-(x)
NPV@-(x) =
from "t=0",to "n"
(B@-(t,x)-C@-(t,x))(P| F,i,t) =
from "t=0",to "n"
A@-(t,x)(P| F,i,t)
NPV@-(x) > 0
For mutually exclusive proposals (x = 1,2,...,m), a proposal j should be
selected if it has the maximum nonnegative net present value among all m
proposals, i.e.
NPV@-(j) = Max@-[x I m]{ NPV@-(x) }
provided that NPV@-(j) > 0.
Net Future Value Method
NFV@-(x) = NPV@-(x) (1 + i)@+(n) = NPV@-(x)(F|P,i,n)
Consequently, if NPV@-(x) > 0, it follows that NFV@-(x) > 0, and vice versa.
Bid Price of Contractor 1 in a Highway Project
Bid Price of Contractor 1 in a Highway Project (Continued)
Rate of Work Progress over Project Time
Value of Work Completed over Project Time
Calculation of Value of Work Completed
!!!Time!!!Case A!!!Case B!!!Case C
!!!0!!!0!!!0!!!0
!!!1!!!3.1%!!!6.2%!!!2.1%
!!!2!!!12.5%!!!18.7%!!!8.3%
!!!3!!!25.0%!!!31.2%!!!18.8%
!!!4!!!37.5%!!!43.7%!!!31.3%
!!!5!!!50.0%!!!56.2%!!!43.8%
!!!6!!!62.5%!!!68.7%!!!56.3%
!!!7!!!75.0%!!!81.2%!!!68.8%
!!!8!!!87.5%!!!91.7%!!!81.9%
!!!9!!!96.9%!!!97.9%!!!93.8%
!!!10!!!100.0%!!!100.0%!!!100.0%
Time Stream of Costs over the Life of a Highway Pavement
Table P5-7
Equipment!!!Equipment Cost ($1000)!!!Factor for Ancillary Items
Type!!!150,000 bbl!!!600,000 bbl!!!150,000 bbl!!!600,000 bbl
Furnace!!!3,000!!!10,000!!!0.32!!!0.24
Tower!!!2,000!!! 6,000!!!0.42!!!0.36
Drum!!!1,500!!! 5,000!!!0.42!!!0.32
Pumps, etc.!!!1,000!!! 4,000!!!0.54!!!0.42
Figure P5-12
Figure P5-13
Nominal and Real Interest Rates on U.S. Bonds, 1955-1985
Net Equivalent Uniform Annual Value Method
where the symbol (U | P,i,n) is referred to as the capital recovery factor
and reads as follows: "To find the equivalent annual uniform amount U, given
the present value P=1, discounted at an annual discount rate i over a period of
t years." Hence, if NPV@-(x) >0, it follows that NUV@-(x) >0, and vice
versa.
NUV@-(x)##=##NPV@-(x)##
Num "i(1+i)@+<n>", Denom "(1+i)@+<n>-1"
## =##NPV@-(x) (U | P,i,n)
Benefit-Cost Ratio Method
However, a project with the maximum benefit-cost ratio among a group of
mutually exclusive proposals generally does not necessarily lead to the
maximum net benefit. Consequently, it is necessary to perform incremental
analysis through pairwise comparisons of such proposals in selecting the best
in the group. In effect, pairwise comparisons are used to determine if
incremental increases in costs between projects yields larger incremental
increases in benefits. This approach is not recommended for use in selecting
the best among mutually exclusive proposals.
num "BPV@-(x)",denom "CPV@-(x)"
> 1
Internal Rate of Return Method
Cash Flow Profiles of Four Independent Projects (in $ million)
[NPV@-(1)]@-(20%) = -77 + (235)(P
| F, 20%, 5) = -77 + 94.4 = 17.4
[NPV@-(2)]@-(20%) = -75.3 + (28)(P
| U, 20%, 5) = -75.3 + 83.7 = 8.4
[NPV@-(3)]@-(20%) = -39.9 + (28)(P
| U, 20%, 4) - (80)(P | F, 20%, 5)
= -39.9 + 72.5 - 32.2 = 0.4
[NPV@-(4)]@-(20%) = 18 + (10)(P
| F, 20%, 1) - (40)(P
| F, 20%, 2) - (60)(P | F, 20%, 3) +
(30)(P
| F, 20%, 4) + (50)(P | F, 20%, 5)
= 18 + 8.3 - 27.8
- 34.7 + 14.5 + 20.1 = -1.6
Hence, the first three independent projects are acceptable, but the last
project should be rejected.
6.7 Depreciation and Tax Effects
T@-(t) = D@-(1) + D@-(2) + ... + D@-(t)
and
B@-(t) = P - T@-(t) = B@-(t-1) - D@-(t)
Y@-(t) = A@-(t) - X@-(t)(A@-(t)-D@-(t))
where A@-(t) is the net revenue before tax in year t, D@-(t) is the
depreciation allowable for year t and X@-(t) is the marginal corporate income
tax rate in year t.
[NPV]@-(8%) # = # -55,000## +##
from"t=1",to"5"
####(13,300 )(P
| F, 8%, t) ### + (5,000)
(P | F, 8%, 5) # = # $1,510
The positive result indicates that the project is worthwhile.
After-Tax Cash Flow Computation
6.8 Price Level Changes: Inflation and Deflation
If these approaches are applied correctly, they will lead to identical
results.
i' = i + j + ij
and
When the inflation rate j is small, these relations can be approximated by
i =
num "i ' - j", denom "1 + j"
i' = i + j or i = i' - j
Note that inflation over time has a compounding effect on the price levels in
various periods, as discussed in connection with the cost indices in Chapter 5.
NPV = A@-(0) +
from "t=1",to "n"
A@-(t) (1+i)@+(-t)
or
NPV = A@-(0) +
from "t=1",to "n"
A'@-(t) (1+i')@+(-t)
A@-(t)@+(') = A@-(t)(1 + j)@+(t) =
A@-(t)(1 + 0.05)@+(t)
Y@-(t)@+(') = A@-(t)@+(') -
X@-(t)(A@-(t)@+(') - D@-(t)) =
A@-(t)@+(') - (34%)(A@-(t)@+(') - 10,000)
Y@-(t) = Y@-(t)@+(')(1+ j)@+(-t) =
Y@-(t)@+(')(1 + 0.05)@+(-t)
The detailed computation of the after-tax cash flow is recorded in Table 6-0.
The net present value discounted at 8% excluding inflation is obtained by
substituting Y@-(t) for A@-(t) in Eq. (6.6.8). Hence,
[NPV]@-(8%) = -55,000 + (13,138)(P|F,
8%,1) + (12,985)(P|F,8%, 2) +
(12,837)(P|F, 8%, 3)
+ (12,697)(P|F, 8%, 4) +
(12,564 + 5,000)(P|F, 8%, 5)
= -$227
With 5% inflation, the investment is no longer worthwhile because the value of
the depreciation tax deduction is not increased to match the inflation rate.
After-Tax Cash Flow Including Inflation
6.9 Uncertainty and Risk
where q = 1,....,m represents possible events, (B@-<t|q> ) and (C@-<t|q> ) are
benefits and costs respectively in period t due to the occurrence of q, Pr{q}
is the probability that q occurs, and E[B@-(t)] and E[C@-(t)] are respectively
expected benefit and cost in period t. Hence, the expected net benefit in
period t is given by:
E[B@-(t)]## =
from"q=1",To"m"
(B@-<t | q >) .##Pr{q}
and
E[C@-(t)]## =
from"q=1",To"m"
(C@-(t| q )).##Pr{q}
E[A@-(t)] = E[B@-(t)] - E[C@-(t)]
r = r@-[f] + r@-[p]
In using the risk-adjusted rate of return r to compute the net present value
of an estimated net cash flow A@-[t] (t = 0, 1, 2, ..., n]) over n years, it is
tacitly assumed that the values of A@-[t] become more uncertain as time goes
on. That is:
[NPV]@-[r] =
from "t=0", to "n"
A@-[t](1 + r)@+[-t]
Note that if r@-[f]r@-[p] is negligible in comparison with r, then
[NPV]@-[r@-{f}] =
from"t=0",to"n"
(a@-[t]A@-[t]) (1 +##r@-[f])@+[-t]
(1 + r@-[f])(1 + r@-[p]) = 1 +r@-[f] + r@-[p] + r@-[f] r@-[p] = 1 + r
Hence, for Eq. (6.6.9)
A@-[t] (1 + r)@+[-t] = (a
@-[t]A@-[t]/a@-[t]) (1 + r@-[f])@+[-t]
(1 + r@-[p])@+[-t] =[(a@-[t]A@-[t]) (1
+ r@-[f])@+[-t]] [(1 + r@-[p])@+[-t]/a@-[t]]
If a@-[t] = (1 + r@-[p])@+[-t] for t = 1,2,...,n, then Eqs. (6.6.9) and
(6.6.9) will be identical. Hence, the use of the risk-adjusted rate r for
computing NPV has the same effect as accepting a@-[t] = (1 + r@-[p])@+[-t] as a
"certainty equivalent" factor in adjusting the estimated cash flow over time.
Determination of a Certainty Equivalent Value
6.10 Effects of Financing on Project Selection
6.11 Combined Effects of Operating and Financing Cash Flows
APV = [NPV]@-(i) + [FPV]@-(i)
where each function is evaluated at i=MARR if both the operating and the
financing cash flows have the same degree of risk or if the risks are taken
care of in other ways such as by the use of certainty equivalents. Then,
project selection involving both design and financing alternatives is
accomplished by selecting the combination which has the highest positive
adjusted present value. The use of this adjusted net present value method will
result in the same selection as an evaluation based on the net present value
obtained from the combined cash flow of each alternative combination directly.
-
-
AA@-[t] = A@-[t] + @-[t]A
-
Similarly, let @-[t] and YY@-[t] be the corresponding cash flows after taxY
such that:
-
YY@-[t] = Y@-[t] + @-[t]Y
- -
@-[t] =Y A
@-[t] + X@-[t]I@-[t]
where I@-[t] is the interest paid in year t and X@-[t] is the marginal
corporate income tax rate in year t. In view of Eqs. (6.13), (6.27) and
(6.28), we obtain
-
YY@-[t] = A@-[t] + @-[t]A
- X@-[t] (A@-[t] - D@-[t] - I@-[t])
APV = [NPV]@-[r] + [FPV]@-[r@-[f]]
where NPV is discounted at r and FPV is obtained from the r@-(f) rate. Note
that the net present value of the financial cash flow includes not only tax
shields for interest on loans and other forms of government subsidy, but also
on transactions costs such as those for legal and financial services associated
with issuing new bonds or stocks.
(a) a design is selected before financing plans are considered, or
(b) the decision is made simultaneously rather than sequentially.
Illustration of Different Design and Financing Alternatives
6.12 Public versus Private Ownership of Facilities
Differences in Required Rates of Return
Tax Implications of Public Versus Private Organizations
Effects of Financing Plans
Effects of Capital Grant Subsidies
Implications for Design and Construction
6.13 Economic Evaluation of Different Forms of Ownership
n
NPV = S
t=0 n
A@-(t)(1 + i)@+(-t) =S B@-(t)(1 + i)
n t=0
@+(-t) - S
C@-(t)(1 + i)@+(-t)t=0
Then, a project is acceptable if NPV G 0. When the annual gross receipt is
uniform, i.e., B@-(t) = B for t = 1, 2, ..., n and B@-(o) = 0, then, for NPV =
0:
n n
B S (1 + i)@+(-t) =S C@-(t)(1 + i)@+(-t)
t=1 t=0
Thus, the minimum uniform annual gross receipt B which makes the project
economically acceptable can be determined from Equation (6.32), once the
acquisition and operation costs C@-(t) of the facility are known and the MARR
is specified.
Required Uniform Annual Gross Receipts for Public and Private
Ownership of a Facility
Effects of Depreciation and Tax Deductions for Private Ownership
in a Facility
Effects of Borrowing on a Publicly Owned Facility
Effects of Financial Leverage and Tax Shields on Private Ownership
of a Facility
Summary Effects of Financial Leverage and Tax Shields on Private
Ownership
6.14 References
6.15 Problems
!!!!!!Before-tax uniform
!!!initial cost!!!annual net benefits
Alternatives!!!($million)!!!($ million)
1!!! 4.0!!! 1.5
2!!! 3.5!!! 1.1
3!!! 3.0!!! 1.0
4!!! 3.7!!! 1.3
-
Year Operating!!!!!! Financing @-(t)A
t A@-(t) !!! (a) !!! (b) !!! (c) !!!
0 -80,000!!! 40,000!!! 40,000!!! 40,000!!!
1 30,000!!! -10,200!!! -3,200!!! -13,200!!!
2 30,000!!! -10,020!!! -3,200!!! -12,400!!!
3 30,000!!! -10,020!!! -3,200!!! -11,600!!!
4 30,000!!! -10,020!!! -3,200!!! -10,800!!!
5 30,000!!! -10,020!!! -43,200!!! 0!!!
Year (t)!!!(a)!!!(b)!!!(c)
1!!!800!!!3,200!!!3,200
2!!!664!!!3,200!!!2,400
3!!!516!!!3,200!!!1,600
4!!!357!!!3,200!!! 800
5!!!185!!!3,200!!! 0
Year!!!Design No. 1!!!Design No. 2
t!!! ($1000s)!!! ($1000s)
0!!! 1,000!!! 900
1-16(each)!!! 150!!! 180
Both designs will last 16 years with no salvage value. The federal
government will subsidize 50% of the initial capital cost, and the state
government has a policy to subsidize 10% of the annual maintenance cost.
The local community intends to obtain a loan to finance 30% of the initial
capital cost at a borrowing rate of 10% with sixteen equal annual payments
including principal and interest. The MARR for this type of project is 12%
reflecting its operating risk. What is the uniform annual revenue that must
be collected in the next 16 years to make each of the two designs worthwhile
from the view of the local authority? Which design has lower cost from this
perspective?
7. Financing of Constructed Facilities
7.1 The Financing Problem
7.2 Institutional Arrangements for Facility Financing
Funds Raised in United States Credit Markets - 1985
Illustrative Process and Timing for Issuing Revenue Bonds
7.3 Evaluation of Alternative Financing Plans
APV = [NPV]@-(r) + [FPV]@-(r@-{f})
where r is the MARR reflecting the risk of the operating cash flow and r@-(f)
is the MARR representing the cost of borrowing for the financial cash flow.
Thus,
where A@-(t) and @-[t] are respectively the operating and financial cashA
flows in period t.
APV##=##
-
from"t=0", to"n"
##
num "A@-{t}",
denom "(1#+#r#)@+(t)"
##+##
from"t=0", to"n"
##
-
num " @-{t}",A
denom "(1#+#r@-{f}#)@+{t}"
If interest is accrued semi-annually, i.e., p = 2, the interest rate per
period is i@-(p)/2; similarly if the interest is accrued monthly, i.e., p = 12,
the interest rate per period is i@-(p)/12. On the other hand, the effective
annual interest rate i@-(e) is given by:
i###=###
num"i@-(p)", denom"p"
Note that the effective annual interest rate, i@-(e), takes into account
compounding within the year. As a result, i@-(e) is greater than i@-(p) for
the typical case of more than one compounding period per year.
i@-(e)###=###(1##+##i)@+(p)##-##1##=## ##1##+##
num"i@-(p)",
denom"p"
# @+(p)##-1
In purchasing a coupon bond, a discount from or a premium above the face value
may be paid.
I@-(p)###=###iQ###=###i@-(p)##
num "Q", denom "2"
where (U|P,i,n) is a uniform series compound interest factor which reads: "to
find U, given P=1, for an interest rate i over n periods." Compound interest
factors are as tabulated in Appendix A. The number of repayment periods n will
clearly influence the amounts of payments in this uniform payment case.
Uniform payment bonds or mortgages are based on this form of repayment.
#####U##=##Q##
Num "i(1+i)@+(n)",Denom "(1+i)@+(n)#-#1"
##=Q##(U | P,i,n)
Q@-(o) = P@-(o) + K
If the origination fee is expressed as k percent of the original loan, i.e., K
= kQ@-(o), then:
Since interest and sometimes parts of the principal must be repaid
periodically in most financing arrangements, an amount Q considerably larger
than Q@-(o) is usually borrowed in the beginning to provide adequate reserve
funds to cover interest payments, construction cost increases and other
unanticipated shortfalls. The net amount received from borrowing is deposited
in a separate interest bearing account from which funds will be withdrawn
periodically for necessary payments. Let the borrowing rate per period be
denoted by i and the interest for the running balance accrued to the project
reserve account be denoted by h. Let A@-(t) be the net operating cash flow for
-
period t (negative for construction cost in period t) and @-(t) be the netA
financial cash flow in period t (negative for payment of interest or principal
or a combination of both). Then, the running balance N@-(t) of the project
reserve account can be determined by noting that at t=0,
Q@-(o)##=##
num "P@-(o)", denom "1-k"
where the value of A@-(t) or @-(t) may be zero for some period(s). EquationsA
(7.7.3) and (7.7.3) are approximate in that interest might be earned on
intermediate balances based on the pattern of payments during a period instead
of at the end of a period.
N@-(o)##=##Q##-##K##+##A@-(o)
-
and at t = 1,2,...,n:
N@-(t)##=##(1##+##h)N@-(t-1)##+##A@-(t)##+##
-
@-(t)A
[FPV]@-(5%) = 10.5 - (0.525) (P| U, 5%, 40) - (10.5) (P| F, 5%, 40) = 0
This result is expected since the corporation will be indifferent between
borrowing and diverting capital from other uses when the MARR is identical to
the borrowing rate. Note that the effective annual rate of the bond may be
computed according to Eq. (7.4) as follows:
i@-(e) = (1 + 0.05)@+(2) - 1 = 0.1025 = 10.25%
If the interest payments were made only at the end of each year over twenty
years, the annual payment should be:
0.525 (1 + 0.05) + 0.525 = 1.076
where the first term indicates the deferred payment at the mid-year which
would accrue interest at 5% until the end of the year, then:
[FPV]@-(10.25%) = 10.5 - (1.076)
(P|U, 10.25%, 20) - (10.5)
(P|F, 10.25%, 20) = 0
In other words, if the interest is paid at 10.25% annually over twenty years
of the loan, the result is equivalent to the case of semi-annual interest
payments at 5% over the same lifetime.
If the minimum attractive rate of return of the corporation is greater than
15%, then this lease arrangement is advantageous as a financing scheme since
the net present value of the leasing cash flow would be less than the cash flow
associated with construction from retained earnings. For example, with MARR
equal to 20%:
From "t=1", To "30"
##
Num "10",Denom
"(1.15)@+(t)"
##=##(10)##(P |
U,##15%,##30)##=##$#65.66##million
[FPV]@-(20%)## =## 65.66## - ##(10)# (P
| U, 20%, 30)## =## $#15.871## million
On the other hand, with MARR equal to 10%:
[FPV]@-(10%)## =## 65.66## -## (10) (P
| U, 10%, 30)## =## -$#28.609# million
and the lease arrangement is not advantageous.
The current corporate MARR is 15%, and short term cash funds can be deposited
in an account having a 10% annual interest rate.
Discounting at ten percent in this calculation reflects the interest earned in
the intermediate periods. With a 10% annual interest rate, the accrued
interests for the first two years from the project account of $ 10.331 at t=0
will be:
#####P@-(o)##=##
Num "5", Denom "(1.1)"
##+##
Num"7", Denom
"(1.1)@+(2)"
##=##$#10.331#million
Year 1, I@-(1) = (10%) (10.331) = $1.033 million
Year 2, I@-(2) = (10%) (10.331 + 1.033 - 5.0) = 0.636 million
Since the issuance charge is 0.75% of the loan, the amount borrowed from the
bank at t=0 to cover both the construction cost and the issuance charge is
Q@-(o)##=##
The issuance charge is 10.409 - 10.331 = $ 0.078 million or $78,000.
num "10.331", denom "1-0.0075"
##=##$#10.409 ##million.
####U##=##(10.409)#
Num "(0.112)#(1.112)@+(20)", Denom
"(1.112)@+(20)#-#1"
##=##$#1.324#million
Q@-(o)## =## 10.331## +## 0.169## =## $#10.5 #million
With an annual interest charge of 10.25% over a twenty year life time, the
annual payment would be $1.076 million except in year 20 when the sum of
principal and interest would be 10.5 + 1.076 = $11.576 million. The
computation for this case of borrowing has been given in Example 7-2.
Cash Flow Illustration of Three Alternative Financing Plans
7.4 Secured Loans with Bonds, Notes and Mortgages
The required repayment R@-(c) at the end of the period c can also be obtained
by noting the net present value of the repayments in the remaining (n-c)
periods discounted at the borrowing rate i to t=c as follows:
R@-(c)##=##Q(1+c)@+(c)##-##
from "t=1", to "c"
-
## @-(t)##(1+i)@+(c-t)A
For coupon bonds, the required repayment R@-(c) after the redemption of the
coupon at the end of period c is simply the original borrowed amount Q. For
uniform payment bonds, the required repayment R@-(c) after the last payment at
the end of period c is:
R@-(c)##=##
from "t=1", to "n-c"
##
-
num " @-(t)",A
denom "(1+i)@+{t}"
##=##(P | U,i,n-c)
R@-(c)##=##
from "t=1", to "n-c"
##
num "U", denom "(1+i)@+(t)"
##=##U(P#|#U, i, n-c)
where V@-(c) is the current market value after c periods have lapsed since the
-
issuance of the bond, @-(t) is the bond cash flow in period t, and r is theA
market yield. Since all the bond cash flows are positive after the initial
issuance, only one value of the yield to maturity will result from Eq. (7.14).
#######V@-(c)##=##
From "t=1", To "n-c"
##
-
Num " @-(t)", DenomA
"(1#+#r)@+(t)"
Year 0, AA@-(0) = 10.356 - 0.025 = 10.331
Year 1, AA@-(1) = 1.033 - 5.0 - 1.118 = -5.085
Year 2, AA@-(2) = 0.636 - 7.0 - 1.118 = -7.482
Year 3, AA@-(3) = -1.118
Year 4, AA@-(4) = -1.118
Year 5, AA@-(5) = -1.118 - 10.356 = -11.474
At the current corporate MARR of 15%,
[APV]@-(15%)##=##
from "t=0",to "5"
##
num "AA@-(t)", denom
"(1.15)@+(t)"
##=##-6.828
which is inferior to the 20-year coupon bond analyzed in Table 7-3.
At t=0, N@-(o) = 10.356 - 0.025 = $ 10.331 million
At t=1, N@-(1) = (1 + 0.1) (10.331) - 5.0 = 6.364 million
At t=2, N@-(2) = (1 + 0.1) (6.364) - 7.0 = 0
Example of Two Borrowing Cash Flows
The total sources of funds (including interest from account balances) and uses
of funds are summarized in Table 7-0.
Illustrative Sources and Uses of Funds from Revenue Bonds During Construction
Provision of Variable Rate for Bonds
The Bonds will be issued as fully registered bonds in the denomination of
$5,000 or any multiple thereof. Principal or redemption price of the bonds
will be payable upon surrender thereof. Interest on the Bonds will be payable
on May 1, 1988, and semi-annually thereafter on November 1 and May 1 by check
mailed to the Bondowners registered on the State Authority's books on the
Record Date. The proceeds of the Bonds will be loaned to Atwood City under a
loan agreement, dated as of November 1, 1987 between the State Authority and
Gerald Bank as Trustee and Paying Agent. The Bonds will bear interest at a
semi-annual fixed rate of 4% for the initial interest periods from December 1,
1987 through April 1, 1990, after which the Bonds may be converted to
semi-annual variable mode at the option of Atwood City upon proper notice. If
the bonds are so converted, such Bonds must be tendered for mandatory purchase
at par, plus 1/8th of 1% of principal amount under certain circumstances and
accrued interest to the Purchase Date (unless the Bondowner files a Non-tender
Election). To be so purchased, Bonds must be delivered, accompanied by a
notice of election to tender the Bonds, to the Paying Agent between the opening
of business on the first day of the month preceding the effective rate date of
the Bonds and 4:00 pm New York City time on the fifteenth day preceding such
effective rate date for the Bonds.
7.5 Overdraft Accounts
N@-(t) = N@-(t-1) + I@-(t) + P@-(t) - E@-(t)
where I@-(t) = iN@-(t-1) for a negative N@-(t-1) and I@-(t) = hN@-(t-1) for a
positive N@-(t-1). The net cash flow A@-(t) = P@-(t) - E@-(t) is positive for
a net receipt and negative for a net payment. This equation is approximate in
that the interest might be earned on intermediate balances based on the pattern
of payments during the period instead of at the end of a period. The account
balance in each period is of interest because there will always be a maximum
limit on the amount of overdraft available.
N@-(t) = (1 + i) N@-(t-1) + A@-(t)
and as soon as N@-(t) reaches a positive value or zero, the account is closed.
Illustrative Payments, Receipts and Overdrafts for a Six Year Project
Year 0 1 2 3 4 5 6 7
Cash Flow -500 110 112 114 116 118 120 122
The MARR of the corporation before tax is 10%. The corporation will finance
the facility be using $200,000 from retained earnings and by borrowing the
remaining $300,000 through an overdraft credit account which charges 14%
interest for borrowing. Is this proposed project including financing costs
worthwhile?
N@-(0) = -500 + 200 = -300
N@-(1) = (1.14) (-300) + 110 = -232
N@-(2) = (1.14) (-232) + 112 = -152.48
N@-(3) = (1.14) (-152.48) + 114 = -59.827
N@-(4) = (1.14) (-59.827) +116 = +47.797
Since N@-(4) is positive, it is revised to exclude the net receipt of 116 for
this period. Then, the revised value for the last balance is
N@-(4)' = N@-(4) - 116 = -68.203
-
The financial cash flow @-(t) resulting from using overdrafts and makingA
repayments from project receipts will be:
-
@-[0] = -N@-(0) = 300A
-
@-[1] = -A@-(1) = -110A
-
@-[2] = -A@-(2) = -112A
-
@-[3] = -A@-(3) = -114A
-
@-[4] = N@-(4) - A@-(4) = -68.203A
The adjusted net present value of the combined cash flow discounted at 15% is $
27,679 as shown in Table 7-8. Hence, the project including the financing
charges is worthwhile.
Evaluation of Facility Financing Using Overdraft
End of!!!Operating!!!Overdraft!!!Financing!!!Combined
Year!!!Cash Flow!!!Balance!!!Cash Flow!!!Cash Flow
-
t!!! A@-(t)!!! N@-(t)!!! @-(t)!!! AA@-(t)A
0!!!-500!!!-300!!!300!!!-200
1!!!110!!!-232!!!-110!!!0
2!!!112!!!-152.480!!!-112!!!0
3!!!114!!!-59.827!!!-114!!!0
4!!!116!!!0!!!-68.203!!!47.797
5!!!118!!!0!!!0!!!118
6!!!120!!!0!!!0!!!120
7!!!122!!!0!!!0!!!120
[PV]@-(15%)!!!21.971!!!!!!5.708!!!27.679
Note: All monetary values are in thousands of dollars
7.6 Refinancing of Debts
###R@-(6)##=##
The new loan would be in the amount of $ 9.152 million plus the issuing cost
of $ 0.05 million for a total of $ 9.202 million. Based on the new loan
interest rate of 9%, the new uniform annual payment on this loan from years 7
to 20 would be:
From "t=1", To "14"
##
Num "1.324", Denom
"(1.112)@+(t)"
##=##$ 9.152##million
###U'##=##(9.202)(U# | P,#9%,#14)##=##$#1.182##million
The net present value of the financial cash flow for the new loan would be
obtained by discounting at the corporate MARR of 15% to the end of year six as
follows:
#####FPV##=##
Since the annual payment on the new loan is less than the existing loan ($
1.182 versus $ 1.324 million), the new loan is preferable.
From "t=1", To "t=14"
##
Num "1.182", Denom"(1.15)@+(t)"
##=##$#6.766##million
7.7 Project versus Corporate Finance
Illustration of a Twenty-five Year Maturity Schedule for Bonds
7.8 Shifting Financial Burdens
...there were days in New York City when city agencies had trouble attracting
bidders; yet contractors were beating on the door to get work from Consolidated
Edison, the local utility. Why? First, the city was a notoriously slow payer,
COs (change orders) years behind, decision process chaotic, and payments made
60 days after close of estimate.
Con Edison paid on the 20th of the month for work done to the first of the
month. Change orders negotiated and paid within 30 days-60 days. If a
decision was needed, it came in 10 days.
The number of bids you receive on your projects are one measure of your
administrative efficiency. Further, competition is bound to give you the
lowest possible construction price.
Even after bids are received and contracts signed, delays in payments may
form the basis for a successful claim against an agency on the part of the
contractor.
An Example of the Effects of Payment Timing
950,000 - 100,000 - 900,000 = -$ 50,000
Finally, the net cash flow for period 6 is:
1,300,000 - 900,000 = $ 400,000
Thus, the cumulative net cash flow from periods 1 through 5 as shown in Column
2 of Table 7-0 results in maximum shortfall of $ 300,000 in period 5 in Column
3. For the case of a two period payment delay to the subcontractors, the
general contractor even runs a positive balance during construction as shown in
Column 5. The positive balance results from the receipt of owner payments
prior to reimbursing the subcontractor's expenses. This positive balance can
be placed in an interest bearing account to earn additional revenues for the
general contractor. Needless to say, however, these payment delays mean extra
costs and financing problems to the subcontractors. With a two period delay in
payments from the general contractor, the subcontractors have an unpaid balance
of $ 1,800,000, which would represent a considerable financial cost.
An Example of the Cash Flow Effects of Delayed Payments
7.9 Construction Financing for Contractors
Contractor's Expenses and Owner's Payments
A@-(t) = P@-(t) - E@-(t)
where A@-(t) is positive for a surplus and negative for a shortfall.
F@-(t) = N@-(t-1) - E@-(t)
where N@-(t-1) is the cumulative net cash flows from year 0 to period (t-1).
Furthermore, the cumulative net operating cash flow after receiving payment
P@-(t) at the end of period t (for t G 1) is:
N@-(t) = F@-(t) + P@-(t) = N@-(t-1) + A@-(t)
The use of N@-(n) as a measure of the gross operating profit has the
disadvantage that it is not adjusted for the time value of money.
G##=##
From "t=0", To "n"
##(P@-(t)##-##E
@-(t))##=##
From "t=0", To "n"
##A
@-(t)##=##N@-(n)
########NPV##=##
From "t=0", To "n"
##A
@-(t)##(1+i)@+(-t)##=##0
-
-
@-(t)##=##i#I
-
N
@-(t-1)##-##
num
"i#E@-(t)", denom "2"
-
If @-(t) isN
positive and h is the investment rate for the surplus,
-
@-(t)##=##h#I
-
N
@-(t-1)##-##
num "i#E@-(t)",
denom "2"
- -
@-(t)##=##F N
-
@-(t-1)##+## I
@-(t)##-##E@-(t)
-
-
@-(t)##=##N
-
@-(t)##+##P@-(t)##=##F
- -
@-(t)##+##N I
@-(t)##-##E@-(t)##+##P@-(t)
-
- -
##=## @-(n)G N
Example of Contractor's Expenses and Owner's Payments ($ Million)
Effects of Overdraft Financing
Example Cumulative Cash Flows Including Interests for a Contractor
($ Million)
7.10 Effects of Other Factors on a Contractor's Profits
Example of Overdraft Financing Based on Inflated Dollars ($ Million)
Effects of Inflation and Work Stoppage
Example of the Effects of Work Stoppage
and Inflation on a Contractor ($ Million)
7.11 References
7.12 Problems
Year 0 1 2 3 4 5 6 7
Cash Flow -500 110 112 114 116 118 120 122
The MARR of the corporation before tax is 10%. The corporation will
finance the facility by using $200,000 from retained earning and by
borrowing the remaining amount through one of the following two plans:
Which financing plan is preferable?
Year 0 1 2 3 4 5
Cash Flow -400 -200 280 300 320 340
The MARR of the agency is 10% including inflation. If the agency can
financing this facility in one of the following two ways, which financing
scheme is preferable?
!!!Year!!!0!!!1!!!2!!!3!!!4!!!5!!!6
!!!Cash Flow!!!-600!!!-250!!!350!!!400!!!450!!!500!!!550
The agency has a MARR of 9% and is not subject to tax. If the project can
be financed in one of the two following ways, which financing scheme is
preferable?
Year!!! 0!!! 1!!! 2!!! 3!!! 4!!! 5
Receipts!!! 0!!!4.764!!!7.456!!!8.287!!!6.525!!!2.468
Expenditures!!!1.250!!!6.821!!!9.362!!!7.744!!!4.323!!! 0
Table P7-11
End of!!!Contractor's!!!Owner's
Month!!!Expenses!!!Payments
0!!!-200,000!!!0
1!!!-250,000!!!225,000
2!!!-400,000!!!360,000
3!!!-520,000!!!468,000
4!!!-630,000!!!567,000
5!!!-780,000!!!702,000
6!!!-750,000!!!675,000
7!!!-660,000!!!594,000
8!!!-430,000!!!387,000
9!!!-380,000!!!342,000
10!!!-332,000!!!298,800
11!!!-256,000!!!230,400
12!!!-412,000!!!370,800
13!!!0!!!1,080,000
14!!!0!!!600,000
Total!!!6,000,000!!!6,900,000
Table P7-12
End of!!!Contractor's!!!Owner's
Month!!!Expenses!!!Payment
0!!!-200,000!!!0
1!!!-251,250!!!225,000
2!!!-404,000!!!360,000
3!!!-527,852!!!468,000
4!!!-642,726!!!567,000
5!!!-799,734!!!702,000
6!!!-772,800!!!675,000
7!!!-683,430!!!594,000
8!!!-447,501!!!387,000
9!!!-397,442!!!342,000
10!!!-348,965!!!298,800
11!!!-270,438!!!230,400
12!!!-437,420!!!370,800
13!!!0!!!1,080,000
14!!!0!!!600,000
Total!!!-6,183,558!!!6,900,000
Table P7-13
End of!!!Contractor's!!!Owner's
Month!!!Expenses!!!Payments
0!!!$50,000!!!$0
1!!!$85,000!!!$47,500
2!!!$176,000!!!$80,700
3!!!$240,000!!!$167,200
4!!!$284,000!!!$228,000
5!!!$252,000!!!$270,000
6!!!$192,000!!!$237,500
7!!!$123,000!!!$182,400
8!!!$98,000!!!$116,800
9!!!$0!!!$319,900
Total!!!$1,500,000!!!$1,650,000
8. Construction Pricing and Contracting
8.1 Pricing for Constructed Facilities
Competitive Bidding
Negotiated Contracts
The fixed percentage or fixed fee is determined at the outset of the project,
while variable fee and target estimates are used as an incentive to reduce
costs by sharing any cost savings. A guaranteed maximum cost arrangement
imposes a penalty on a contractor for cost overruns and failure to complete the
project on time.
Speculative Residential Construction
Force-Account Construction
8.2 Contract Provisions for Risk Allocation
8.3 Risks and Incentives on Construction Quality
8.4 Types of Construction Contracts
Lump Sum Contract
Unit Price Contract
Cost Plus Fixed Percentage Contract
Cost Plus Fixed Fee Contract
Cost Plus Variable Percentage Contract
Target Estimate Contract
Guaranteed Maximum Cost Contract
8.5 Relative Costs of Construction Contracts
B = E + M
The underestimation of the cost of work in the original contract is defined
as:
U = A - E
Then, at the completion of the project, the contractor's actual cost for the
original scope of work is:
A = E + U
For various types of construction contracts, the contractor's markup and the
price for construction agreed to in the contract are shown in Table 8-0. Note
that at the time of contract award, it is assumed that A = E, even though the
effects of underestimation on the contractor's gross profits are different for
various types of construction contracts when the actual cost of the project is
assessed upon its completion.
Original Estimated Contract Prices
Owner's Actual Payment with Different Contract Provisions
Contractor's Gross Profit with Different Contract Provisions
!!!(a) U = 0, C = 0
!!!(b) U = 0, C = 6% E = $360,000
!!!(c) U = 4% E = $240,000, C = 0
!!!(d) U = 4% E = $240,000 C = 6% E = $360,000
!!!(e) U = -4% E = -$240,000, C = 0
!!!(f) U = -4% E = -$240,000, C = 6% E = $360,000
Contractor's Gross Profits under Different Conditions (in $1,000)
Owner's Actual Payments under Different Conditions (in $1,000)
8.6 Principles of Competitive Bidding
Exogenous Economic Factors
Characteristics of Bidding Competition
Objectives of General Contractors in Bidding
8.7 Bidding Simulation: An Example
Environment for the Game
Typical Demand Curve for Projects in the Bidding Game
Geographical Locations of Districts for the Bidding Game
General Contractor Bidding and Award
Measurement Performance
Illustration of a Company's Performance in a Construction Management Game
Income Statement!!! Amount
A. Income from construction contracts!!!412,510.00
Cost of contracts:
B. Subcontracts and supervision of subcontractors!!!347,891.00
C. Field Overhead!!! 2,063.00
D. Gross profit!!! 62,556.00
Administrative and general expenses:
E. Office operating cost!!! 10,921.00
F. Information costs!!! 650.00
G. Bidding costs!!! 1,733.00
H. Interest on existing loans!!! 900.00
I. Earnings before federal income taxes!!! 48,352.00
J. Federal income taxes!!! 17,411.00
K. Net earnings!!! 30,941.00
L. Retained earnings at beginning of period!!!208,422.00
M. Liquid assets!!!239,363.00
Loans
N. Existing loans!!! 60,000.00
O. New loans (one year notes)!!! 25,000.00
P. Loans due this time period!!! 10,000.00
Q. Total cash-on-hand!!!314,363.00
R. Retained earnings at end of period!!!239,363.00
S. Percentage gain or loss up to end of period!!! +19.7
8.8 Principles of Contract Negotiation
Illustration of a Pareto Optimal Agreement Set
8.9 Negotiation Simulation: An Example
CMG Gas has the opportunity to provide natural gas to an automobile factory
under construction. Service will require a new sixteen mile pipeline through
farms and light forest. The terrain is hilly with moderate slopes, and
equipment access is relatively good. The pipeline is to be buried three feet
deep.
Construction of the pipeline itself will be contracted to a qualified
design/construction firm, while required compression stations and ancillary
work will be done by CMG Gas. As project manager for CMG Gas, you are about to
enter negotiations with a local contractor, "Pipeline Constructors, Inc." This
firm is the only local contractor qualified to handle such a large project. If
a suitable contract agreement cannot be reached, then you will have to break
off negotiations soon and turn to another company.
The Pipeline Constructors, Inc. instructions offers a similar overview.
A final contract requires an agreement on each of these issues, represented on
a form signed by both negotiators.
Instructions to the Pipelines Constructors, Inc. Representative
Example of a Negotiated Contract between CMG Gas and Pipeline Constructors, Inc
}
Duration!!!38 weeks
Penalty for Late Completion!!!$ 6,800 per day
Bonus for Early Completion!!!$ 0 per day
Report Format!!!traditional CMG form
Frequency of Progress Reports!!!weekly
Conform to Pending Pipeline Marking Legislation!!!yes
Contract Type!!!flat fee
Amount of Flat Fee!!!$ 5,050,000.
Percentage of Profit!!!Not applicable
CMG Gas Clerk on Site!!!yes
Penalty for Late Starting Date!!!$ 3,000 per day
Signed:
CMG Gas Representative
Pipeline Constructors, Inc.
Instruction To The Pipeline Constructors, Inc. Representative
!!!!!!System A!!!System B
!!!Under 36 Weeks!!!NA!!!NA
!!!36 weeks!!!0!!!NA
!!!37 weeks !!!+5!!!-10
!!!38 weeks!!!+10!!!0
!!!39 weeks!!!+20!!!+10
!!!40 weeks!!!+40!!!+20
2. REPORTS
!!!Required Standard Report!!!-20!!!0
!!!Agreed Reports!!!-5!!!0
3. PENALTY FOR LATENESS ($ PER DAY)
!!!!!! DURATION(WEEKS)
!!!Scoring System A!!!36!!!37!!!38!!!39!!!40
!!!Scoring System B!!!37!!!38!!!39!!!40!!!41
!!!0-999!!!-1!!!-1!!!-1!!!0!!!0
!!!1000 - 1999!!!-2!!!-2!!!-2!!!-1!!!0
!!!2000 - 2999!!!-4!!!-3!!!-3!!!-2!!!-1
!!!3000 - 3999!!!-6!!!-5!!!-4!!!-3!!!-1
!!!4000 - 4999!!!-8!!!-7!!!-5!!!-4!!!-2
!!!5000 - 5999!!!-11!!!-9!!!-7!!!-5!!!-2
!!!6000 - 6999!!!-14!!!-12!!!-9!!!-6!!!-3
!!!7000 - 7999!!!-18!!!-14!!!-11!!!-7!!!-3
!!!Over 8000!!!NA!!!NA!!!NA!!!NA!!!NA
4. BONUS FOR BEING EARLY ($ PER DAY)
!!!Scoring System A!!!36!!!37!!!38!!!39!!!40
!!!Scoring System B!!!38!!!39!!!40!!!41!!!42
!!!0 - 999!!!0!!!0!!!0!!!0!!!2
!!!1000 - 1999!!!0!!!0!!!2!!!2!!!2
!!!2000 - 2999!!!0!!!2!!!4!!!4!!!4
!!!3000 - 3999!!!1!!!4!!!6!!!6!!!8
!!!4000 - 4999!!!2!!!6!!!8!!!10!!!12
!!!5000 - 5999!!!3!!!8!!!10!!!14!!!16
!!!6000 - 6999!!!4!!!10!!!14!!!18!!!22
!!!7000 - 7999!!!5!!!12!!!18!!!24!!!28
!!!8000 - 8999!!!6!!!14!!!22!!!28!!!36
!!!9000 - 9999!!!7!!!16!!!26!!!32!!!40
!!!Over 10,000!!!8!!!18!!!30!!!36!!!45
5. CONFORM TO PENDING LEGISLATION (MARKING PIPELINES)
!!!!!!A!!!B
!!!Yes!!!+5!!!+10
!!!No!!!+15!!!+10
6. HOW OFTEN FOR THE PROGRESS REPORTS
!!!!!!A!!!B
!!!Daily!!!NA!!!0
!!!Weekly!!!-20!!!0
!!!Bi-weekly!!!-10!!!0
!!!Monthly!!!-6!!!0
7. CONTRACT TYPE
!!!!!!A!!!B
!!!Flat Fee!!!0!!!0
!!!Cost + X%!!!+25!!!+25
!!!If Flat Fee do part 8 and skip parts 9 and 10
!!!If Cost + X% do parts 9 and 10 and skip part 8.
8. FLAT FEE ($)
!!!!!!A!!!B
!!!Below 4,500,000!!!NA!!!-15 for each 10,000
!!!Over 4,500,000!!!+1 for each!!!+2 for each
!!!!!! 10,000!!! 10,000
9. IF COST PLUS X%
!!!!!!A!!!B
!!!Below 6%!!!NA!!!NA
!!!6%!!!+250!!!NA
!!!7%!!!+375!!!+300
!!!8%!!!+450!!!+330
!!!9%!!!+475!!!+360
!!!10%!!!+500!!!+400
!!!11%!!!+525!!!+440
!!!12%!!!+550!!!+480
!!!13%!!!+600!!!+540
!!!14%!!!+725!!!+600
!!!Over 14%!!!+900!!!+800
10. GAS CO. FIELD CLERK ON SITE
!!!!!!A!!!B
!!!Yes!!!0!!!0
!!!No!!!0!!!+10
11. PENALTY FOR DELAYED STARTING DATE DUE TO GAS COMPANY
ERROR ($ PER DAY)
!!!!!!A!!!B
!!!0 - 499!!!NA!!!NA
!!!500 - 1499!!!-6!!!-10
!!!1500 - 2499!!!-4!!!-7
!!!1500 - 3499!!!-2!!!-5
!!!3500 - 4499!!!-1!!!-3
!!!4500 - 5499!!!0!!!-1
!!!5500 - 6499!!!+1!!!0
!!!6500 - 7499!!!+2!!!+3
!!!7500 or more!!!+4!!!+6
Instructions to the CMG Gas Company Representative
!!!!!!POINTS
1. DURATION
!!!!!!A!!!B
!!!Over 40 weeks!!!NA!!!-40
!!!40 weeks!!!0!!!-10
!!!39 weeks!!!+2!!!+2
!!!38 weeks!!!+4!!!+8
!!!37 weeks!!!+5!!!+14
!!!0 - 36 weeks!!!+6!!!+14
2. REPORTS
!!!!!!A!!!B
!!!Required Standard Report!!!+2!!!0
!!!"Traditional" CMG Gas Reports!!!+10!!!0
3. PENALTY FOR LATENESS ($ PER DAY)
!!!!!! DURATION (WEEKS)
!!!Scoring System A!!!36!!!37!!!38!!!39!!!40
!!!Scoring System B!!!38!!!39!!!40!!!41!!!42
!!!0-999!!!NA!!!NA!!!NA!!!NA!!!NA
!!!1000 - 1999!!!9!!!7!!!6!!!3!!!0
!!!2000 - 2999!!!10!!!9!!!8!!!5!!!2
!!!3000 - 3999!!!11!!!10!!!9!!!6!!!4
!!!4000 - 4999!!!12!!!11!!!10!!!7!!!5
!!!5000 - 5999!!!13!!!12!!!11!!!8!!!6
!!!6000 - 6999!!!14!!!13!!!12!!!9!!!7
!!!7000 - 7999!!!15!!!15!!!13!!!11!!!8
!!!8000 - 8999!!!16!!!15!!!14!!!12!!!9
!!!9000 - 9999!!!17!!!16!!!15!!!13!!!10
!!!10,000 or more!!!18!!!16!!!15!!!13!!!11
4. BONUS FOR BEING EARLY ($ PER DAY)
!!!!!!A!!!B
!!!8000 or more!!!NA!!!-5
!!!7000 - 7999!!!+3!!!-2
!!!6000 - 6999!!!+6!!!-1
!!!5000 - 5999!!!+8!!!0
!!!4000 - 4999!!!+10!!!+5
!!!3000 - 3999!!!+12!!!+7
!!!2000 - 2999!!!+13!!!+9
!!!1000 - 1999!!!+14!!!+13
!!!0 - 999!!!+15!!!+17
5. CONFORM TO PENDING LEGISLATION (MARKING PIPELINES)
!!!!!!A!!!B
!!!yes!!!+25!!!0
!!!no!!!-25!!!NA
6. HOW OFTEN FOR THE PROGRESS REPORTS
!!!!!!A!!!B
!!!Daily!!!+45!!!+50
!!!Weekly!!!+50!!!+30
!!!Bi-weekly!!!+30!!!+10
!!!Monthly!!!NA!!!+5
7. CONTRACT TYPE
!!!!!!A!!!B
!!!Flat Fee!!!+25!!!+25
!!!Cost + X%!!!0!!!0
!!!If Flat Fee do part 8 and skip parts 9 and 10
!!!If Cost + X% do parts 9 and 10 and skip part 8.
8. FLAT FEE ($)
!!!!!!A!!!B
!!!Over 5,500,000!!!NA!!!NA
!!!0 - 5,000,000!!!+1 for each!!!+1 for each
!!!!!! 10,000 below!!! 10,000 below
!!!!!! 10,000,000!!! 10,000,000
9. IF COST PLUS X%
!!!!!!A!!!B
!!!Below 5%!!!+950!!!+700
!!!5%!!!+800!!!+660
!!!6%!!!+700!!!+620
!!!7%!!!+600!!!+590
!!!8%!!!+550!!!+570
!!!9%!!!+525!!!+550
!!!10%!!!+500!!!+535
!!!11%!!!+475!!!+500
!!!12%!!!+450!!!+440
!!!13%!!!+400!!!+380
!!!14%!!!+300!!!+300
!!!15%!!!+200!!!+100
!!!Over 15%!!!NA!!!+10
10. GAS CO. FIELD CLERK ON SITE
!!!!!!A!!!B
!!!Yes!!!+20!!!+10
!!!No!!!+5!!!+0
11. PENALTY FOR DELAYED STARTING DATE DUE TO UNAVAILABLE
RIGHT-OF-WAYS ($ PER DAY)
!!!!!!A!!!B
!!!0 - 1999!!!+10!!!+3
!!!2000 - 3999!!!+8!!!+2
!!!4000 - 5999!!!+6!!!+1
!!!6000 - 7999!!!+4!!!0
!!!8000 - 9999!!!+2!!!-10
!!!10,000+!!!NA!!!-20
8.10 Resolution of Contract Disputes
Some of these procedures may be court sponsored or required for particular
types of disputes.
8.11 References
8.12 Problems
P = R(2E - A + C) + A + C + DT(1 + 0.4C/E)
The value of T is set at $ 5,000 per day, and the project is completed 30
days behind schedule. If all other conditions remain unchanged, find the
contractor's profit and the owner's actual payment under this contract for
the given conditions of U and C.
P = R(2E - A + C) + A + C + DT(1 + 0.2C/E)
The value of T is set at $ 10,000 per day, and the project is completed 20
days ahead schedule. If all other conditions remain unchanged, find the
contractor's profit and the owner's actual payment under this contract for
the given conditions of U and C.
!!!Pipeline Constructors Inc.!!!CMG Gas
a.!!! System A!!! System A
b.!!! System A!!! System B
c.!!! System B!!! System A
d.!!! System B!!! System B
Since the scoring systems are confidential information, your instructor will
not disclose the combination used for the assignment. Your instructor may
divide the class into groups of two students, each group acting as
negotiators representing the two companies in the game. To keep the game
interesting and fair, do not try to find our the scoring system of your
negotiating counterpart. To seek insider information is unethical and
illegal!
9. Construction Planning
9.1 Basic Concepts in the Development of Construction Plans
Most people, if you describe a train of events to them, will tell you what
the result would be. They can put those events together in their minds, and
argue from them that something will come to pass. There are few people,
however, who, if you told them a result, would be able to evolve from their own
inner consciousness what the steps were which led up to that result. This
power is what I mean when I talk of reasoning backward...[A.C. Doyle, "A Study
in Scarlet," The Complete Sherlock Holmes, Doubleday & Co., pg. 83, 1930.]
Like a detective, a planner begins with a result (i.e. a facility design) and
must synthesize the steps required to yield this result. Essential aspects of
construction planning include the generation of required activities, analysis
of the implications of these activities, and choice among the various
alternative means of performing activities. In contrast to a detective
discovering a single train of events, however, construction planners also face
the normative problem of choosing the best among numerous alternative plans.
Moreover, a detective is faced with an observable result, whereas a planner
must imagine the final facility as described in the plans and specifications.
Alternative Emphases in Construction Planning
9.2 Choice of Technology and Construction Method
9.3 Defining Work Tasks
This detailed task breakdown of the activity "clean concrete forms" would not
generally be done in standard construction planning, but it is essential in the
process of programming or designing a robot to undertake this activity since
the various specific tasks must be well defined for a robot implementation.[See
Skibniewski, M.J. and C.T. Hendrickson, "Evaluation Method for Robotics
Implementation: Application to Concrete Form Cleaning," Proc. Second Intl.
Conf. on Robotics in Construction, Carnegie-Mellon University, Pittsburgh,
PA., 1985, for more detail on the work process design of a concrete form
cleaning robot.]
For example, the activity "prepare and check shop drawings" should be divided
into a task for preparation and a task for checking since different individuals
are involved in the two tasks and there may be a time lag between preparation
and checking.
Illustrative Hierarchical Activity Divisions for a Roadway
Project
9.4 Defining Precedence Relationships Among Activities
Illustrative Set of Four Activities with Precedences
Example of an Impossible Work Plan
In revising schedules as work proceeds, it is important to realize that
different types of precedence relationships have quite different implications
for the flexibility and cost of changing the construction plan. Unfortunately,
many formal scheduling systems do not possess the capability of indicating this
type of flexibility. As a result, the burden is placed upon the manager of
making such decisions and insuring realistic and effective schedules. With all
the other responsibilities of a project manager, it is no surprise that
preparing or revising the formal, computer based construction plan is a low
priority to a manager in such cases. Nevertheless, formal construction plans
may be essential for good management of complicated projects.
A. Site clearing (of brush and minor debris),
B. Removal of trees,
C. General excavation,
D. Grading general area,
E. Excavation for utility trenches,
F. Placing formwork and reinforcement for concrete,
G. Installing sewer lines,
H. Installing other utilities,
I. Pouring concrete.
Precedence Relations and Durations for a Nine Activity
Project Example
Activity-on-Branch Representation of a Nine Activity Project
Activity-on-Node Representation of a Nine Activity Project
All Activity Precedence Relationships for a Nine
Activity Project
9.5 Estimating Activity Durations
Durations and Predecessors for a Four Activity Project Illustration
where A@-(ij) is the required formwork area to assemble (in square yards),
P@-(ij) is the average productivity of a standard crew in this task (measured
in square yards per hour), and N@-(ij) is the number of crews assigned to the
task. In some organizations, unit production time, T@-(ij), is defined as the
time required to complete a unit of work by a standard crew (measured in hours
per square yards) is used as a productivity measure such that T@-(ij) is a
reciprocal of P@-(ij).
D@-(ij)## =##
Num "A@-(ij)",
Denom "P@-(ij)##N@-(ij)"
Illustration of Productivity Changes Due to Learning
A Hierarchical Estimation Framework for Masonry Construction
-
@g(m)## A ## ## =##
x
From "k=1",
To "n"
##
Num "x@-(k)", Denom "n"
where we assume that n different observations x@-(k) of the random variable x
are available. This estimation process might be applied to activity durations
directly (so that x@-(k) would be a record of an activity duration D@-(ij) on a
past project) or to the estimation of the distribution of productivities (so
that x@-(k) would be a record of the productivity in an activity P@-(ij) on a
past project) which, in turn, is used to estimate durations using Equation
(9.9.5). If more accuracy is desired, the estimation equations for mean and
standard deviation, Equations (9.9.5) and (9.9.5) would be used to estimate the
mean and standard deviation of the reciprocal of productivity to avoid
non-linear effects. Using estimates of productivities, the standard deviation
of activity duration would be calculated as:
@g(s)@+(2)## A ##
From "k=1",
To "n"
##
-
Num "( x@-(k) - )@+(2)",x
Denom "n-1"
@g(s)@-(ij) A A@-(ij)*W@-(ij)*@g(s)@-(1/P)
where @g(s)@-(1/P) is the estimated standard deviation of the reciprocal of
productivity that is calculated from Equation (9.9.5) by substituting 1/P for
x.
9.6 Estimating Resource Requirements for Work Activities
R@+(k)@-(ij) = D@-(ij) N@-(ij) U@+(k)@-(ij)
where R@+(k)@-(ij) are the resources of type k required by activity ij,
D@-(ij) is the duration of activity ij, N@-(ij) is the number of standard crews
allocated to activity ij, and U@+(k)@-(ij) is the amount of resource type k
used per standard crew per unit of time. For example, if an activity required
eight hours with two crews assigned and each crew required three workers, the
effort would be R = 8 * 2 * 3 = 48 labor-hours.
9.7 Coding Systems
0534.02220.21.A.00.cf34
The first four digits indicate the project for this activity; this code refers
to an activity on project number 0534. The next five digits refer to the
MASTERFORMAT secondary division; referring to Table 9-0, this activity would be
02220 "Excavating, Backfilling and Compacting." The next two digits refer to
specific activities defined within this MASTERFORMAT code; the digits 21 in
this example might refer to excavation of column footings. The next character
refers to the block or general area on the site that the activity will take
place; in this case, block A is indicated. The digits 00 could be replaced by
a code to indicate the responsible organization for the activity. Finally, the
characters cf34 refer to the particular design element number for which this
excavation is intended; in this case, column footing number 34 is intended.
Thus, this activity is to perform the excavation for column footing number 34
in block A on the site. Note that a number of additional activities would be
associated with column footing 34, including formwork and concreting.
Additional fields in the coding systems might also be added to indicate the
responsible crew for this activity or to identify the specific location of the
activity on the site (defined, for example, as x, y and z coordinates with
respect to a base point).
9.8 References
9.9 Problems
For this robot, answer the following questions:
How do these capabilities change your answer to Problem P9-6 and P9-7?
10. Fundamental Scheduling Procedures
10.1 Relevance of Construction Schedules
10.2 The Critical Path Method
!!!Activity!!!Predecessors
!!! A !!! -
!!! B !!! -
!!! C !!! A,B
!!! D !!! C
!!! E !!! C
!!! F !!! D
!!! G !!! D,E
Forming an activity-on-branch network for this set of activities might begin be
drawing activities A, B and C as shown in Figure 10-0(a). At this point, we
note that two activities (A and B) lie between the same two event nodes; for
clarity, we insert a dummy activity X and continue to place other activities as
in Figure 10-0(b). Placing activity G in the figure presents a problem,
however, since we wish both activity D and activity E to be predecessors.
Inserting an additional dummy activity Y along with activity G completes the
activity network, as shown in Figure 10-0(c). A comparable activity-on-node
representation is shown in Figure 10-0, including project start and finish
nodes. Note that dummy activities are not required for expressing precedence
relationships in activity-on-node networks.
10.3 Calculations for Critical Path Scheduling
Minimize z = x@-(n)
subject to
x@-(0) = 0
x@-(j) - x@-(i) - D@-(ij) G 0 for each activity (i,j).
This is a linear programming problem since the objective value to be minimized
and each of the constraints is a linear equation.(See Au, T., Introduction to
Systems Engineering, Deterministic Models, Addison-Wesley Publishing Company,
Reading, MA, 1973, for a detailed description of linear programming as a form
of mathematical optimization.)
The earliest finish time of each activity (i,j) can be calculated by:
ES(i,j)## = ## E(i)
EF(i,j)## = ## E(i) ## + ## D@-(ij)
The latest start time of each activity (i,j) cvan be calculated by:
LF(i,j) ## = ## L(j)
LS(i,j) ## = ## L(j)## - ## D@-(ij)
E(i)## = ##L(i)
E(j)## = ##L(j)
E(i)## + ## D@-(ij)## = ##L(j)
Step 1 R E(0) = 0
Step 2
j = 1 R E(1) = Max{E(0) + D@-(01)}
= Max{ 0 + 4 } = 4
j = 2 R E(2) = Max{E(0) + D@-(02); E(1) + D@-(12)}
= Max{ 0 + 3; 4 + 8 } = 12
j = 3 R E(3) = Max{E(1) + D@-(13); E(2) + D@-(23)}
= Max{ 4 + 7; 12 + 9 } = 21
j = 4 R E(4) = Max{E(2) + D@-(24); E(3) + D@-(34) }
= Max{ 12 + 12; 21 + 2 } = 24
j = 5 R E(5) = Max{E(3) + D@-(35); E(4) + D@-(45) }
= Max{ 21 + 5; 24 + 6} = 30.
Thus, the minimum time required to complete the project is 30 since E(5) = 30.
In this case, each event had at most two predecessors.
Step 1 R L(5) = E(5) = 30
Step 2
j = 4 R L(4) = Min{L(5) -
D@-(45)}
= Min{ 30 - 6 } = 24
j = 3 R L(3) = Min{L(5) -
D@-(35); L(4) - D@-(34)}
= Min{ 30 -5; 24 - 2 } = 22
j = 2 R L(2) = Min{L(4) -
D@-(24); L(3) - D@-(23)}
= Min{ 24 - 12; 22 - 9} = 12
j = 1 R L(1) = Min{L(3) -
D@-(13); L(2) - D@-(12) }
= Min{ 22 - 7; 12 - 8 } = 4.
j = 0 R
L(0) = Min{L(2) - D@-(02); L(1) - D@-(01) }
= Min{ 12 - 3; 4 - 4 } = 0.
10.4 Activity Float and Schedules
Each of these "floats" indicates an amount of flexibility associated with an
activity. In all cases, total float equals or exceeds free float, while
independent float is always less than or equal to free float. Also, any
activity on a critical path has all three values of float equal to zero. The
converse of this statement is also true, so any activity which has zero total
float can be recognized as being on a critical path.
FF(i,j) ## = ## E(j) ## - ## E(i) ## - ## D@-(ij)
0
IF(i,j) ## = ## Max ## B
E(j)# - # L(i) # - # D@-(ij)
TF(i,j) ## = ## L(j) ## - ## E(i) ## - ## D@-(i,j)
10.5 Presenting Project Schedules
Examples of Maximum Productivity Estimates for Masonry Work
Examples of Possible Adjustments to Maximum Productivities
for Masonry Construction
Illustration of Beta and Normally Distributed Activity Durations
Major Divisions in the Uniform Construction Index
Secondary Divisions in MASTERFORMAT for Site Work
Figure P9-6: Illustrative Block Positions for Robot Motion Planning
Illustration of Dummy Activities in a Project Network
Example of an Activity-on-Branch Network for Critical Path Scheduling
Example of an Activity-on-Node Network for Critical Path Scheduling
Critical Path Scheduling Algorithms (Activity-on-Branch Representation)
Illustration of a Nine Activity Project Network
Precedence Relations and Durations for a Nine Activity
Project Example
Identification of Activities on the Critical Path for a Nine
Activity Project
Illustration of Activity Float
Illustration of a Seven Activity Project Network
Precedences and Durations for a Seven Activity Project
Event Times for a Seven Activity Project
Earliest Start, Latest Start and Activity Floats for a Seven
Activity Project
Illustration of a Time Scaled Network Diagram with Nine Activities
An Example Bar Chart for a Nine Activity Project
Example of Percentage Completion versus Time for
Alternative Schedules with a Nine Activity Project
Illustration of Actual Percentage Completion versus Time for a
Nine Activity Project Underway
Illustration of Resource Use over Time for a Nine Activity Project
activities. The hierarchy of diagrams can also be introduced to the production
of reports so that summary reports for groups of activities can be produced.
Thus, detailed representations of particular activities such as plumbing might
be prepared with all other activities either omitted or summarized in larger,
aggregate activity representations. The CSI/MASTERSPEC activity definition
codes described in Chapter 9 provide a widely adopted example of a hierarchical
organization of this type. Even if summary reports and diagrams are prepared,
the actual scheduling would use detailed activity characteristics, of course.
Illustration of a Sub-Network in a Summary Diagram
10.6 Critical Path Scheduling with Leads, Lags, and Windows
While the eight precedence relationships in Table 10-0 are all possible, the
most common precedence relationship is the straightforward direct precedence
between the finish of a preceding activity and the start of the successor
activity with no required gap (so FS = 0).
Eight Possible Activity Precedence Relationships
E(j) = Maximum { E(i) + D@-(ij); E(i) + SS@-(ij) }
where SS@-(ij) represents a start-to-start lead between activity (i,j) and any
of the activities starting at event j.
10.7 Calculations for Scheduling with Leads, Lags and Windows
ES(i) + SS(i,k) for non-split
preceding activities or when DA(i) > SS(i,k)
EF(i) - D(i) + SS(i,k) for split
preceding activities with DA(i) < SS(i,k)
where DA(i) is the duration of the first sub-activity of the preceding
activity.
EF(k) = Maximum { ES(k) + D(k),
EF(i) + FF(i,k) for
each preceding activity with a FF precedence,
ES(i) + SF(i,k) for
each preceding activity with a SF precedence
and which is not split or has DA(i) > SF(i,k), and
EF(i) - D(i) + SF(i,k)
for each preceding activity with a SF precedence
and which is split
and has DA(i) < SF(i,k). }
Finally, the necessity to split an activity is also considered. If the
earliest possible finish time is greater than the earliest start time plus the
activity duration, then the activity must be split.
ES(0) = 0
ES(1) = 0
EF(1) = ES(1) + D(1) = 0 + 5 = 5
ES(2) = EF(1) + FS(1,2) = 5 + 0 = 5
EF(2) = ES(2) + D(2) = 5 + 5 = 10
ES(3) = EF(2) + FS(2,3) = 10 + 0 = 10 = EF(3)
So the earliest project completion time is ten days.
ES(0) = 0
ES(1) = 0
EF(1) = ES(1) + D(1) = 0 + 5 = 5
ES(2) = ES(1) + SS(1,2) = 0 + 2 = 2
EF(2) = ES(2) + D(2) = 2 + 5 = 7
ES(3) = EF(2) + FS(2,3) = 7 + 0 = 7.
In this case, activity 2 can begin two days after the start of activity 1 and
proceed in parallel with activity 1. The result is that the project completion
date drops from ten days to seven days.
ES(0) = 0 = EF(0)
ES(1) = EF(0) + FS(0,1) = 0 + 0 = 0
EF(1) = ES(1) + D(1) = 0 + 5 = 5
ES(2) = EF(1) + FF(1,2) - D(2) = 5 + 2 - 5 = 2
EF(2) = ES(2) + D(2) = 2 + 5 = 7
ES(3) = EF(2) + FS(2,3) = 7 + 0 = 7 = EF(3)
In this case, the earliest finish for activity 2 is on day seven to allow the
necessary two day lag from the completion of activity 1. The minimum project
completion time is again seven days.
ES(0) = EF(0) = 0
ES(1) = Max{ 0; EF(0) + FS(0,1) } = Max { 0; 0 + 0 } = 0.
EF(1) = ES(1) + D(1) = 0 + 2 = 2
ES(2) = Max{ 0; EF(0) + FS(0,1) } = Max{ 0; 0 + 0 } = 0.
EF(2) = ES(2) + D(2) = 0 + 5 = 5
ES(3) = Max{ 0; WES(3); ES(1) + SS(1,3) } = Max{ 0; 2; 0 + 1 } = 2.
EF(3) = ES(3) + D(3) = 2 + 4 = 6
Note that in the calculation of the earliest start for activity 3, the start
was delayed to be consistent with the earliest start time window.
ES(4) = Max{ 0; ES(0) + FS(0,1) } = Max{ 0; 0 + 0 } = 0.
EF(4) = ES(4) + D(4) = 0 + 3 = 3
ES(5) = Max{ 0; ES(2) + SS(2,5); EF(2) +
FF(2,5) - D(5) } = Max{ 0; 0+2; 5+2-5 } = 2
EF(5) = ES(5) + D(5) = 2 + 5 = 7
ES(6) = Max{ 0; WES(6); EF(1) + FS(1,6);
EF(3) + FS(3,6) } = Max{ 0; 6; 2+2; 6+0 } = 6
EF(6) = ES(6) + D(6) = 6 + 6 = 12
ES(7) = Max{ 0; ES(4) + SS(4,7); EF(5) +
FS(5,7) } = Max{ 0; 0+2; 7+1 } = 8
EF(7) = ES(7) + D(7) = 8 + 2 = 10
ES(8) = Max{ 0; EF(4) + FS(4,8); ES(5) +
SS(5,8) } = Max{ 0; 3+0; 2+3} = 5
EF(8) = ES(8) + D(8) = 5 + 4 = 9
ES(9) = Max{ 0; EF(7) + FS(7,9); EF(6) +
FF(6,9) - D(9) } = Max{ 0; 10+0; 12+4-5 } = 11
EF(9) = ES(9) + D(9) = 11 + 5 = 16
ES(10) = Max{ 0; EF(8) + FS(8,10); EF(9) +
FS(9,10) } = Max{ 0; 9+0; 16+0 } = 16
EF(10) = ES(10) + D(10) = 16
As the result of these computations, the earliest project completion time is
found to be 16 days.
LF(10) = LS(10) = ES(10) = EF(10) = 16
LF(9) = Min{ LF(10); LS(16) - FS(9,10) }
= Min{ 16; 16-0 } = 16
LS(9) = LF(9) - D(9) = 16 - 5 = 11
LF(8) = Min{ LF(10); LS(16) - FS(8,10) }
= Min{ 16; 16-0 } = 16
LS(8) = LF(8) - D(8) = 16 - 4 = 12
LF(7) = Min{ LF(10); LS(9) - FS(7,9) }
= Min{ 16; 11-0 } = 11
LS(7) = LF(7) - D(7) = 11 - 2 = 9
LF(6) = Min{ LF(10); WLF(6); LF(9) - FF(6,9) }
= Min{ 16; 16; 16-4 } = 12
LS(6) = LF(6) - D(6) = 12 - 6 = 6
LF(5) = Min{ LF(10); WLF(10); LS(7) - FS(5,7);
LS(8) - SS(5,8) + D(8) }
= Min{ 16; 16; 9-1; 12-3+4 } = 8
LS(5) = LF(5) - D(5) = 8 - 5 = 3
LF(4) = Min{ LF(10); LS(8) - FS(4,8); LS(7)
- SS(4,7) + D(7) } = Min{ 16; 12-0; 9-2+2 } = 9
LS(4) = LF(4) - D(4) = 9 - 3 = 6
LF(3) = Min{ LF(10); LS(6) - FS(3,6) } =
Min{ 16; 6-0 } = 6
LS(3) = LF(3) - D(3) = 6 - 4 = 2
LF(2) = Min{ LF(10); LF(5) - FF(2,5); LS(5) -
SS(2,5) + D(5) } = Min{ 16; 8-2; 3-2+5 } = 6
LS(2) = LF(2) - D(2) = 6 - 5 = 1
LF(1) = Min{ LF(10); LS(6) - FS(1,6); LS(3) -
SS(1,3) + D(3); Lf(4) - SF(1,4) + D(4) }
LS(1) = LF(1) - D(1) = 2 -2 = 0
LF(0) = Min{ LF(10); LS(1) - FS(0,1); LS(2) -
FS(0,2); LS(4) - FS(0,4) }
= Min{ 16; 0-0; 1-0; 6-0 } = 0
LS(0) = LF(0) - D(0) = 0
10.8 Resource Oriented Scheduling
Minimize z = Maximum
11
S t@-(i) x@-(i1);
11 i=1
S t@-(i) x@-(i2);
i=111
S t@-(i) x@-(i3);
i=111
S t@-(i) x@-(i4);
11i=1
S t@-(i) x@-(i5)
i=1
subject to the constraints:
5
S
j=1
x@-(ij) = 1 for each section i
x@-(ij) is 0 or 1.
where the constraints simply insure that each section is assigned to one and
only one crew. A modification permits a more conventional mathematical
formulation, resulting in a generalized bottleneck assignment problem:
Minimize z
subject to the constraints:
9
z G S t@-(i)x@-(ij) for each crew j
i=1
5
S x@-(ij) = 1 for each section i
j=1
x@-(ij) is 0 or 1.
This problem can be solved as an integer programming problem, although at
considerable computational expense. A common extension to this problem would
occur with differential productivities for each crew, so that the time to
complete an activity, t@-(ij), would be defined for each crew. Another
modification to this problem would substitute a cost factor, c@-(i), for the
time factor, t@-(i), and attempt to minimize overall costs rather than
completion time.
10.9 Scheduling with Resource Constraints and Precedences
The resulting profile of resource use is shown in Figure 10-0. Note that
activities F and I were not considered in applying the heuristic since these
activities did not require the special equipment being considered. In the
figure, activity I is scheduled after the completion of activity H due to the
requirement of 4 workers for this activity. As a result, the project duration
has increased to 41 days. During much of this time, all four workers are not
assigned to an activity. At this point, a prudent planner would consider
whether or not it would be cost effective to obtain an additional piece of
equipment for the project.
10.10 References
10.11 Problems
Formulate an activity-on-node network representation and recompute the
critical path with these precedence relationships.
Formulate an activity-on-node network representation and recompute the
critical path with these precedence relationships.
11. Advanced Scheduling Techniques
11.1 Use of Advanced Scheduling Techniques
A final section in the chapter describes some possible improvements in the
project scheduling process. In Chapter 14, we consider issues of computer
based implementation of scheduling procedures, particularly in the context of
integrating scheduling with other project management procedures.
11.2 A Unified Activity Network Representation
These eight links represent four precedence relationships and four window
constraint types (numbers 1, 2, 7 and 8 above) of a minimum or greater than
type.
Again, eight different precedence and window constraint types exist for
greater than constraints. Unfortunately, positive cycles may be introduced in
the network by allowing the negative links, so the longest path solution
algorithms become more complicated than the algorithm presented in Section
10.2.
Critical Path Scheduling Algorithms with Leads, Lags and Windows
(Activity-on-Node Representations)
Activity Numbering Algorithm
Step 1: Give the starting activity number 0.
Step 2: Give the next number to any unnumbered activity whose
predecessor activities are each already numbered.
Repeat Step 2 until all activities are numbered, k = 0,1,2,...,m
Forward Pass
Step 0: Set the earliest start
and the earliest finish of the
initial activity to zero
(ES(0) = EF(0) = 0).
Repeat the following steps for each
activity k = 0,1,2,...,m:
Step 1: Compute the earliest
start time (ES(k)) of activity k:
ES(k) = Maximum { 0; WES(k)
for the earliest start window time,
WEF(k) - D(k) for the
earliest finish window time;
EF(i) + FS(i,k) for each
preceding activity with a F-S constraint;
ES(i) + SS(i,k) for each
preceding activity with a S-S constraint;
EF(i) + FF(i,k) - D(k) for
each preceding activity with a F-F constraint;
ES(i) + SF(i,k) - D(k) for
each preceding activity with a S-F constraint. }
Step 2: Compute the earliest finish time EF(k) of activity k:
EF(k) = ES(k) + D(k).
Backward Pass Computations
Step 0: Set the latest finish and
latest start of the terminal activity to the early start time:
LF(m) = LS(m) = ES(m) = EF(m)
Repeat the following steps for each
activity in reverse order, k = m-1,m-2,...,2,1,0:
Step 1: Compute the latest finish time for activity k:
LF(k) = Min{ LF(m), WLF(k) for the
latest finish window time;
WLS(k) + D(k) for the
latest start window time;
LS(j) - FS(k,j) for each
succeeding activity with a F-S constraint;
LF(j) - FF(k,j) for each
succeeding activity with a FF constraint,
LS(j) - SS(k,j) + D(k) for
each succeeding activity with a SS constraint;
LF(j) - SF(k,j) + D(k) for
each succeeding activity with a SF constraint. }
Step 2: Compute the
latest start time for activity k:
LS(k) = LF(k) - D(k)
Predecessors, Successors, Windows and Durations for an Example Project
Example Project Network with Lead and Lag Precedences
Precedences in a Eleven Activity Project Example
Summary of Activity Start and Finish Times for an Example Problem
Estimated Required Time for Each Work Task in a Resource Allocation
Problem
Example Allocation of Crews to Work Tasks
A Resource Oriented Scheduling Procedure
Step 1: Rank all resources from the most important to the least
important, and number the resources i = 1,2,3,...,m.
Step 2: Set the scheduled start time for
each activity to the earliest start time.
For each resource i = 1,2,3,...,m in turn:
Step 3: Start at the project beginning, so set t = 0.
Step 4: Compute the demand for resource
i at time t by summing up the requirements
for resource i for all activities scheduled
to be underway at time t.
If demand for resource i in time t is greater than
the resource availability, then
select the activity with the greatest late
start time requiring
resource i at time t, and shift its scheduled
start time to time t+1.
Repeat Step 4 until the resource constraint at time
t for resource i is satisfied.
Step 5: Repeat step 4 for each project period
in turn, setting t = t+1.
Resources Required over Time for Nine Activity Project:
Schedule I
Resources Required and Starting Times for a Nine Activity Project
Resources Required over Time for Nine Activity Project:
Schedule II
Table P10-1
Table P10-2
Table P10-3
Table P10-4
Table P10-11
Table P10-12
A Two Activity Network with Eight Precedence and Window Constraint Types
A Two Activity Network with Eight Maximum Duration Links
Calculations for the Unified Network Model with Negative Link Durations
A Small Unified Network Model
Floats for Constraints and Activities for Example 1
FLOATS
Link(i,j) E(i) L(i) E(j) L(j) D(i,j) Indep. Free Total
A 0 2 4 7 4 0 0 3
B 1 3 3 5 2 0 0 2
C 5 5 11 11 6 0 0 0
D 6 7 10 11 4 0 0 1
E 11 11 13 16 2 0 0 3
1 0 0 6 7 6 0 0 1
2 0 0 0 2 0 0 0 2
3 0 0 5 5 5 0 0 0
4 0 2 1 3 1 0 0 2
5 3 5 5 5 0 0 2 2
6 4 7 11 11 6 0 1 1
7 4 7 6 7 0 0 2 3
8 5 5 10 11 3 2 2 3
9 11 11 11 11 0 0 0 0
10 10 11 16 16 5 0 1 1
11 11 11 16 16 5 0 0 0
12 13 16 16 16 0 0 3 3
Solution to the Unified Model with Maximum Durations
11.3 Scheduling with Uncertain Durations
and
@g(m)(i,j) ## = ##
Num "1",
Denom "6"
##(a@-(i,j) # + # 4m@-(i,j)# + # b@-(i,j))
where @g(m)(i,j), @g(s)@+(2)(i,j) are the mean duration and its variance,
respectively, of an activity (i,j). Three activity durations estimates (i.e.,
optimistic, most likely, and pessimistic durations) are required in the
calculation. The use of these optimistic, most likely, and pessimistic
estimates stems from the fact that these are thought to be easier for managers
to estimate subjectively. The formulas for calculating the mean and variance
are derived by assuming that the activity durations follow a probabilistic beta
distribution under a restrictive condition.[See M.W. Sasieni, "A Note on PERT
Times," Management Science, Vol. 32, No. 12, p 1986, p. 1652-1653, and T.K.
Littlefield and P.H. Randolph, "An Answer to Sasieni's Question on Pert Times,"
Management Science, Vol. 33, No. 10, 1987, pp. 1357-1359. For a general
discussion of the Beta distribution, see N.L. Johnson and S. Kotz, Continuous
Univariate Distributions-2, John Wiley & Sons, 1970, Chapter 24.] The
probability density function of a beta distributions for a random varable x is
given by:
@g(s)@+(2)(i,j) ## =##
Num "1",
Denom "36"
## (b@-(i,j) # -# a@-(i,j))@+(2)
where k is a constant which can be expressed in terms of @g(a) and @g(b).
Several beta distributions for different sets of values of @g(a) and @g(b) are
shown in Figure 11-0. For a beta distribution in the interval a L x L b having
a modal value m, the mean is given by:
f(x) ## = ##k(x#-#a)@+[@g(a)](b#-#x)
@+[@g(b)]########a# L #x#
L #b;###@g[a,b]#
>#-1
If @g{a + b} = 4, then Eq. (11.11.3) will result in Eq. (11.11.3). Thus, the
use of Eqs. (11.11.3) and (11.11.3) impose an additional condition on the beta
distribution. In particular, the restriction that @g[s] = (b-a)/6 is imposed.
@g(m) ## = ##
Num "a #+# (@g<a+b>)m #+#b",
Denom "@g<a+b+2>"
Illustration of Several Beta Distributions
The difference between Eqs. (11.11.3) and (11.11.3) comes only in the value of
the divisor, with 36 used for absolute limits and 10 used for ninety-five
percentile limits. This difference might be expected since the difference
between b@-(i,j) and a@-(i,j) would be larger for absolute limits than for the
ninety-fifth percentile limits.
@g(s)@+(2)(i,j) ## = ##
num "1",
Denom "10"
##(b@+(95%)@-{i,j} #####
- ## a@+(95%)@-(i,j)
######)@+(2)
Activity Duration Estimates for a Nine Activity Project
Project Duration Results from Various Techniques and Assumptions
for an Example
11.4 Calculations for Monte Carlo Schedule Simulation
u@-(i) = Fractional part of [ ( @g(p) + u@-(i-1) )@+(5)]
where @g(p) = 3.14159265 and u@-(i-1) was the previously generated random
number or a pre-selected beginning or seed number. For example, a seed of
u@-(0) = 0.215 in Eq. (11.11.4) results in u@-(1) = 0.0820, and by applying
this value of u@-(1), the result is u@-(2) = 0.1029. This formula is a special
case of the mixed congruential method of random number generation. While
Equation (11.11.4) will result in a series of numbers that have the appearance
and the necessary statistical properties of true random numbers, we should note
that these are actually "pseudo" random numbers since the sequence of numbers
will repeat given a long enough time.
x@-(k) = @g(m)@-(x) + s sin t
with
--------------
s = @g(s)@-(x) V-2##ln##u@-(1)
t = 2 @g(p) u@-(2)
where x@-(k) is the normal realization, @g(m)@-(x) is the mean of x,
@g(s)@-(x) is the standard deviation of x, and u@-(1) and u@-(2) are the two
uniformly distributed random variable realizations. For the case in which the
mean of an activity is 2.5 days and the standard deviation of the duration is
1.5 days, a corresponding realization of the duration is s = 2.2365, t = 0.6465
and x@-(k) = 2.525 days, using the two uniform random numbers generated from a
seed of 0.215 above.
{ @g(m)'@-(d) | x = x@-(k) } =
@g(r)@-(dx)(@g(s)@-(d) / @g(s)@-(x) ) (x@-(k) -
@g(m)@-(x)) + @g(m)@-(d)
{ @g(s)'@-(d) | x = x@-(k) }
= @g(s)@-(d)
---------------
V1#-#@g(r)@-(dx)
where @g(r)@-(dx) is the correlation coefficient between d and x. Once x@-(k)
is known, the conditional mean and standard deviation can be calculated from
Eq. (11.8) and then a realization of d obtained by applying Equation (11.11.4).
The value of @g(r)@-(xy) can range from one to minus one, with values near one
indicating a positive, near linear relationship between the two random
variables.
@g(r)@-(xy)##=##
Num <n#
From "i=1", To"n"
#x@-(i)y@-(i)##-##
From "i=1", To "n"
#x@-(i)##
From "i=1", To"n"
#y@-(i)>, Denom< ##n#
From "i=1", To "n"
x@-(i)@+(2)##-## #
From"i=1",To"n"
#x@-(i) @+(2) #@+(1/2) ##n#
From "i=1", To "n"
x@-(i)@+(2)##-## #
From "i=1",To"n"
#x@-(i) @+(2) #@+(1/2)>
Activity Mean (Days) Standard Deviation (Days)
A 2.5 1.5
B 5.6 2.4
C 2.4 2.0
To simulate the schedule effects, we generate the duration realizations shown
in Table 11-0 and calculate the project duration for each set of three activity
duration realizations.
Duration Realizations for a Monte Carlo Schedule Simulation
The cumulative probability function for the triangular distribution is:
@g(m)##=##
Num "a#+#b#+#m", Denom "3"
--------------------
(a@+(2)#+#b@+(2)#+#m
@g(s)##=##V /18)@+(2)##+##a#b##+##a#m##+##m#b
where F(x) is the probability that the random variable is less than or equal
to the value of x.
Num "(x#-#a)@+(2)",
Denom"(b#-#a)(m#-#a)"
#####
for##a#L#x#L#m
F(x)##=## B
1##-##
Num "(b#-#x)@+(2)",
Denom"(b#-#a)(b#-#m)"
#####
for##m#L#x#L#b
Illustration of Two Triangular Activity Duration Distributions
For example, if a = 3.2, m = 4.5 and b = 6.0, then @g(m)@-(x) = 4.8 and
@g(s)@-(x) = 2.7. With a uniform realization of u = 0.215, then for
(m-a)/(b-a) G 0.215, x will lie between a and m and is found to have a value of
4.1 from Equation (11.11-5).
------------
##a#+#V u@-(k)(b#-#a
(m#-#a))####if##u
@-(k)#L#
Num "m#-#a", Denom "b#-#a"
x@-(k)##= B
-----------
b#-#V (1#-#u@-(k)
(b#-#a)(b#-#m))#####
if##u@-(k)#G#
Num "m#-#a", Denom
"b#-#a"
11.5 Crashing and Time/Cost Tradeoffs
Illustration of a Linear Time/Cost Tradeoff for an Activity
Illustration of Non-linear Time/Cost Tradeoffs for an Activity
c@-(ij) = C@-(ij) + R@-(ij) (D@-(ij) - d@-(ij))
where the lower case c@-(ij) and d@-(ij) represent the scheduled duration and
resulting cost of the activity ij. The actual duration of an activity must
fall between the minimum cost time (D@-(ij)) and the crash time (D@+(c)@-(ij)).
Also, precedence constraints must be imposed as described earlier for each
activity. Finally, the required completion time for the project or,
alternatively, the costs associated with different completion times must be
defined. Thus, the entire scheduling problem is to minimize total cost (equal
to the sum of the c@-(ij) values for all activities) subject to constraints
arising from (1) the desired project duration, PD, (2) the minimum and maximum
activity duration possibilities, and (3) constraints associated with the
precedence or completion times of activities. Algebraically, this is:
Minimize z = S c@-(i,j)
all#(i,j)
= S [C@-(i,j) + R@-(i,j)(D@-(i,j) - d@-(i,j))]
all#(i,j)
subject to the constraints:
x(n) L PD
x(i) + d@-(i,j) L x(j) for all activities (i,j)
D@+{c}@-(i,j) L d@-(i,j) L D@-(i,j) for all activities (i,j)
where the notation is defined above and the decision variables are the
activity durations d@-(i,j) and event times x(k). The appropriate schedules
for different project durations can be found by repeatedly solving this problem
for different project durations PD. The entire problem can be solved by linear
programming or more efficient algorithms which take advantage of the special
network form of the problem constraints.
The savings from early completion due to operating savings in the contra-flow
lane and contract administration costs were estimated to be $5,000 per day.
Activity Durations and Costs for a Seven Activity Project
Project Cost Versus Time for a Seven Activity Project
7
Minimize z = S c@-(k)
k=1
= [8+3(6-d@-(A))] + [4] +
[8+4(8-d@-(C))] + [10+7(5-d@-(D))] +
[10+2(9-d@-(E))] +
[20+2.7(9-d@-(F))] + [10+2(3-d@-(G))]
subject to the constraints
x(6) = PD
x(0) + d@-(A) L x(2)
x(0) + d@-(C) L x(1)
x(1) L x(3)
x(2) + d@-(E) L x(4)
x(1) + d@-(D) L x(4)
x(4) + d@-(F) L x(5)
x(5) + d@-(G) L x(6)
x(0) = 0
4 L d@-(A) L 6
1 L d@-(B) L 1
4 L d@-(C) L 8
3 L d@-(D) L 5
5 L d@-(E) L 9
6 L d@-(F) L 12
2 L d@-(G) L 3
which can be solved for different values of project duration PD using a linear
programming algorithm or a network flow algorithm. Note that even with only
seven activities, the resulting linear programming problem is fairly large.
11.6 Scheduling in Poorly Structured Problems
Figure 11-0 shows an example of a screen for this system. In Figure 11-0, a
bar chart appears in one window, a description of an activity in another
window, and a graph of the use of a particular resource over time appears in a
third window. These different "windows" appear as sections on a computer
screen displaying different types of information. With these capabilities, a
project manager can call up different pictures of the construction plan and
make changes to accomadate objectives or constraints that are not formally
represented. With rapid response to such changes, the effects can be
immediately evaluated.
Example of a Bar Chart and Other Windows for Interactive Scheduling
11.7 Improving the Scheduling Process
11.8 References
11.9 Problems
Table P11-3
Table P11-4
Table P11-5
Table P11-6
12. Cost Control, Monitoring and Accounting
12.1 The Cost Control Problem
12.2 The Project Budget
12.3 Forecasting for Activity Cost Control
The current status of the project is a forecast budget overrun of $ 5,950.
with 23 percent of the budgeted project costs incurred to date.
where C@-(t) is the cost incurred to time t and p@-(t) is the proportion of
the activity completed at time t. For example, an activity which is 50 percent
complete with a cost of $ 40,000 would be estimated to have a total cost of $
40,000/0.5 = $ 80,000. More elaborate methods of forecasting costs would
disaggregate costs into different categories, with the total cost the sum of
the forecast costs in each category.
C@-(t)
C@-(f)##=##------
p@-(t)
C@-(f) = W c@-(t)
where C@-(f) is the forecast total cost, W is the total units of work, and
c@-(t) is the average cost per unit of work experienced up to time t. If the
average unit cost is $ 50 per unit of work on a particular activity and 1,600
units of work exist, then the expected cost is 1,600 * 50 = $ 80,000 for
completion.
where the cost per work unit (c@-(t)) is replaced by the time per unit,
h@-(t), divided by the cost per unit of time, u@-(t).
h@-(t)
C@-(f)##=##W##------
u@-(t)
C@-(f) = C@-(t) + ( W - W@-(t) ) c@-(t)
where forecast total cost, C@-(f), is the sum of cost incurred to date,
C@-(t), and the cost resulting from the remaining work (W - W@-(t) ) multiplied
by the expected cost per unit time period for the remainder of the activity,
c@-(t).
Systematic application of these different estimating methods to the various
project activities enables calculation of the percentage complete or the
productivity estimates used in preparing job status reports.
Spool in place: 20% of work and 20% of cumulative work.
Ends welded: 40% of work and 60% of cumulative work.
Hangars and Trim Complete: 30% of work and 90% of cumulative work.
Hydrotested and Complete: 10% of work and 100% of cumulative work.
Thus, a pipe section for which the ends have been welded would be reported
as 60% complete.
complete (100%) 380 ft.
hangars and trim complete (90%) 20 ft.
ends welded (60%) 5 ft.
spool in place (20%) 0 ft.
Then using the incremental milestones shown above, the estimate of completed
work would be 380 + (20)(0.9) + (5)(0.6) + 0 = 401 ft. and the proportion
complete would be 401 ft./1,000. ft = 0.401 or 40% after rounding.
12.4 Financial Accounting Systems and Cost Accounts
External reports are constrained to particular forms and procedures by
contractual reporting requirements or by generally accepted accounting
practices. Preparation of such external reports is referred to as financial
accounting. In contrast, cost or managerial accounting is intended to aid
internal managers in their responsibilities of planning, monitoring and
control.
Contract Payments
Year Expenses Received
1 $ 700,000. $ 900,000.
2 180,000. 250,000.
3 320,000. 150,000.
Total $1,200,000. $1,300,000.
The supervising architect determines that 60% of the facility is complete in
year 1 and 75% in year 2. Under the "percentage-of-completion" method, the net
income in year 1 is $780,000 (60% of $1,300,000) less the $ 700,000 in expenses
or $ 80,000. Under the "completed-contract" method, the entire profit of $
100,000 would be reported in year 3.
Today's management accounting information, driven by the procedures and cycle
of the organization's financial reporting system, is too late, too aggregated
and too distorted to be relevant for managers' planning and control
decisions....
Management accounting reports are of little help to operating managers as
they attempt to reduce costs and improve productivity. Frequently, the reports
decrease productivity because they require operating managers to spend time
attempting to understand and explain reported variances that have little to do
with the economic and technological reality of their operations...
The managagement accounting system also fails to provide accurate product
costs. Cost are distributed to products by simplistic and arbitrary measures,
usually direct labor based, that do not represent the demands made by each
product on the firm's resources.
As a result, complementary procedures to those used in traditional financial
accounting are required to accomplish effective project control, as described
in the preceding and following sections. While financial statements provide
consistent and essential information on the condition of an entire
organization, they need considerable interpretation and supplementation to be
useful for project management.
Current contract price =
Original contract price +
Contract Changes
= 4,200 + 400 + 4,600.
Credit or debit to date =
Total costs to date -
Payments received or due to date
= 3,600 - 3,520 = - 80.
Contract value of uncompleted work =
Current contract price -
Payments received or due
= 4,600 - 3,520 = 1,080.
Credit or debit to come =
Contract value of uncompleted work -
Estimated Cost to Complete
= 1,080 - 500 = 580.
Estimated final gross profit =
Credit or debit to date +
Credit or debit to come
= -80. + 580. = 500.
Estimated total project costs =
Contract price - Gross profit
= 4,600 - 500 = 4,100.
Estimated Profit to date =
Estimated final gross profit x
Proportion of work complete
= 500. (3600/4100)) = 439.
Similar calculations for the other jobs underway indicate estimated profits to
date of $ 161,000 for Job 5 and $ -42,000 for Job 6. As a result, the net
profit using the "percentage-of-completion" method would be $ 1,612,000 for the
year. Note that this figure would be altered in the event of multi-year
projects in which net profits on projects completed or underway in this year
were claimed in earlier periods.
12.5 Control of Project Cash Flows
Each of the rows shown in Table 12-0 would be derived from different sets of
financial accounts. Additional reports could be prepared on the financing cash
flows for bonds or interest charges in an overdraft account.
12.6 Schedule Control
D@-(f) = W h@-(t)
where D@-(f) is the forecast duration, W is the amount of work, and h@-(t) is
the observed productivity to time t. As with cost control, it is important to
devise efficient and cost effective methods for gathering information on actual
project accomplishments. Generally, observations of work completed are made by
inspectors and project managers and then work completed is estimated as
described in Section 12.3. Once estimates of work complete and time expended
on particular activities is available, deviations from the original duration
estimate can be estimated. The calculations for making duration estimates are
quite similar to those used in making cost estimates in Section 12.3.
12.7 Schedule and Budget Updates
As can be imagined, it is not at all uncommon to encounter changes during the
course of a project that require modification of durations, changes in the
network logic of precedence relationships, or additions and deletions of
activities. Consequently, the scheduling process should be readily available
as the project is underway.
Illustrative Set of Project Cost Accounts
Example of a Small Project Budget for a Design Firm
An Example of a Project Budget for a Wharf Project
Illustration of a Job Status Report
Illustration of Proportion Completion versus Expenditure for an Activity
Illustration of an Accounting Statement of Income
Illustration of an Accounting Balance Sheet
Example of Financial Records of Projects
An Example of a Cash Flow Status Report
Illustration of Planned versus Actual Progress over Time on a Project
Illustration of Planned versus Actual Expenditures on a Project
A Nine Activity Example Project
Current Schedule for an Example Project Presented as a Bar Chart
required, using the procedures described in Section 10.9.
12.8 Relating Cost and Schedule Information
Illustration of a Cost Account and Project Activity Matrix
12.9 References
12.10 Problems
Percentage of Completion!! Expected Expenditure
0%!! 0%
20%!! 10%
40%!! 25%
60%!! 55%
80%!! 90%
100%!! 100%
!!Weekly Unit Costs ($/LF)
Quantity Placed (LF)
Total Cost
Week!!Labor!!Materials!!Total!!Week!!To Date!!Week!!To Date
1!! 12.00!! 4.00!! 16.00!! 250!! 250!! 4000!! 4000
2!! 8.57!! 4.00!! 12.57!! 350!! 600!! 4400!! 8400
3!! 6.67!! 4.00!! 10.67!! 450!! 1050!! 4800!! 13200
!!Resource!!Quantity!!Cost
!!Machines!!1200 hours!!$ 60,000.
!!Labor!!6000 hours!! 150,000.
!!Trucks!!2400 hours!!75,000.
!!Total!!!!$285,000.
After 95,000 cubic yards of excavation was completed, the following
expenditures had been recorded:
!!Resource!!Quantity!!Cost!!
!!Machines!!1063 hours!!$ 47,835.!!
!!Labor!!7138 hours!! 142,527.!!
!!Trucks!!1500 hours!!46,875.!!
!!Total!!!!$237,237.
Monthly Number of
Month Expenditure Work Units Completed
1 $ 1,200 30
2 $ 1,250 32
3 $ 1,260 38
4 $ 1,280 42
5 $ 1,290 42
6 $ 1,280 42
Answer the following questions:
Monthly Number of
Month Expenditure Work Units Completed
1 $ 1,200 30
2 $ 1,250 35
3 $ 1,260 45
4 $ 1,280 48
5 $ 1,290 52
6 $ 1,300 54
Original Work Plan Information
Activity Duration Predecessors Estimated Cost
(months) ($ thousands)
A 2 - 7
B 5 - 9
C 5 B 8
D 2 C 4
E 3 B 1
F 8 - 7
G 4 E,F 6
H 7 E,C 5
I 11 B 10
J 2 E,F 3
Original Contract Information
Total Direct Cost 64
Overhead 64
Total Direct and Ovd 128
Profit 12.8
Total Contract Amount 140.8
First Year Cash Flow
Expenditures $ 56,000.
Receipts $ 60,800.
The markup on the activities' costs included 100% overhead and a profit of
10% on all costs (including overhead). This job was suspended for one year
after completion of the first four activities, and the owner paid a total of
$ 30,800 to the engineer. Now the owner wishes to re-commence the job.
However, general inflation has increased costs by ten percent in the
intervening year. The engineer's discount rate is 15 percent per year (in
current year dollars). For simplicity, you may assume that all cash
transactions occur at the end of the year in making discounting calculations
in answering the following questions:
13. Quality Control and Safety During Construction
13.1 Quality and Safety Concerns in Construction
13.2 Organizing for Quality and Safety
13.3 Work and Material Specifications
Conform to elevations and dimensions shown on plan within a tolerance of plus
or minus 0.10 foot, and extending a sufficient distance from footings and
foundations to permit placing and removal of concrete formwork, installation of
services, other construction, and for inspection. In excavating for footings
and foundations, take care not to disturb bottom of excavation. Excavate by
hand to final grade just before concrete reinforcement is placed. Trim bottoms
to required lines and grades to leave solid base to receive concrete.
This set of specifications requires judgment in application since some items
are not precisely specified. For example, excavation must extend a
"sufficient" distance to permit inspection and other activities. Obviously,
the term "sufficient" in this case may be subject to varying interpretations.
In contrast, a specification that tolerances are within plus or minus a tenth
of a foot is subject to direct measurement. However, specific requirements of
the facility or characteristics of the site may make the standard tolerance of
a tenth of a foot inappropriate. Writing specifications typically requires a
trade-off between assuming reasonable behavior on the part of all the parties
concerned in interpreting words such as "sufficient" versus the effort and
possible inaccuracy in pre-specifying all operations.
Load Ratio Pay Factor
<0.50 Reject
0.50-0.69 0.90
0.70-0.89 0.95
0.90-1.09 1.00
1.10-1.29 1.05
1.30-1.49 1.10
>1.50 1.12
In this table, the Load Ratio is the ratio of the actual pavement strength to
the desired design strength and the Pay Factor is a fraction by which the total
pavement contract amount is multiplied to obtain the appropriate compensation
to the contractor. For example, if a contractor achieves concrete strength
twenty percent greater than the design specification, then the load ratio is
1.20 and the appropriate pay factor is 1.05, so the contractor receives a five
percent bonus. Load factors are computed after tests on the concrete actually
used in a pavement. Note that a 90% pay factor exists in this case with even
pavement quality only 50% of that originally desired. This high pay factor
even with weak concrete strength might exist since much of the cost of
pavements are incurred in preparing the pavement foundation. Concrete
strengths of less then 50% are cause for complete rejection in this case,
however.
13.4 Total Quality Control
1. On a highway project under construction by Taisei Corporation, it was
found that the loss rate of ready-mixed concrete was too high. A quality
circle composed of cement masons found out that the most important reason for
this was due to an inaccurate checking method. By applying the circle's
recommendations, the loss rate was reduced by 11.4%.
2. In a building project by Shimizu Construction Company, may cases of faulty
reinforced concrete work were reported. The iron workers quality circle
examined their work thoroughly and soon the faulty workmanship disappeared. A
10% increase in productivity was also achieved.
13.5 Quality Control by Statistical Methods
13.6 Statistical Quality Control with Sampling by Attributes
where a factorial, n! is n:(n-1):(n-2) : : : (1) and zero factorial (0!) is
one by convention. The number of possible samples with exactly x defectives is
the combination associated with obtaining x defectives from m possible
defective items and n-x good items from N-m good items:
from"N",chosen"n"
#=#
num[N(N-1) : : : #(N-n#+#1)],denom<n!>
##=##
num"N!",denom<n!(N-n
!>)
Given these possible numbers of samples, the probability of having exactly x
defective items in the sample is given by the ratio as the hypergeometric
series:
from"m",chosen"x"
#
from"N-m",chosen"n-x"
#=#
num"m!",denom<x!(m-x
!>)##*##
num"(N-m)!",denom<(n-x)!(N-m-n#+#x)!>
With this function, we can calculate the probability of obtaining different
numbers of defectives in a sample of a given size.
P#(X=x)#=#
num[
x#=#1,#2, : : : ,#m
from"m",chosen"x"
#
from"N-m",chosen"n-x"
],denom<
from"N",chosen"n"
>
If the number of items in the lot, N, is large in comparison with the sample
size n, then the function g(p) can be approximated by the binomial
distribution:
g(p)##=##
from"x=o",to"r"
#P(X#=#x)#=#
from"x=o",to"r"
#
num[
from"Np",chosen"x"
from"Nq",chosen"n-x"
],denom<
from"N",chosen"x"
>
g(p)#=#
from"x=0",to"r"
#
from"n",chosen"x"
#p@+(x)q@+(n-x)
or
g(p)#=#1#-#
from"x=r+1",to"n"
#
from"n",chosen"x"
#p@+(x)q@+(n-x)
so that the probability of accepting a lot is equal to the fraction of
acceptable items in the lot. For example, there is a probability of 0.5 that
the lot may be accepted from a single sample test even if fifty percent of the
lot is defective.
g(p)#=#
from"1",chosen"0"
#p@+(0)q@+(1)#=#q
Example Operating Characteristic Curves Indicating Probability of
Lot Acceptance
!!!r=0!!!p=24%!!!g(p) A 2%!!!
!!!r=0!!!p=4%!!!g(p) A 54%!!!
!!!r=1!!!p=24%!!!g(p) A 10%!!!
!!!r=1!!!p=4%!!!g(p) A 88%
The producer's and consumer's risk can be related to various points on an
operating characteristic curve. Producer's risk is the chance that otherwise
acceptable lots fail the sampling plan (ie. have more than the allowable
number of defective items in the sample) solely due to random fluctuations in
the selection of the sample. In contrast, consumer's risk is the chance that
an unacceptable lot is acceptable (ie. has less than the allowable number of
defective items in the sample) due to a better than average quality in the
sample. For example, suppose that a sample size of 15 is chosen with a trigger
level for rejection of one item. With a four percent acceptable level and a
greater than four percent defective fraction, the consumer's risk is at most
eighty-eight percent. In contrast, with a four percent acceptable level and a
four percent defective fraction, the producer's risk is at most 1 - 0.88 = 0.12
or twelve percent.
For a two percent defective fraction (p = 0.02), the resulting acceptance
value is:
#######g(p)##=##
num[
from"100p",chosen"0"
from"100q",chosen"5"
],denom<
from"100",chosen"5"
>
#######g(p)###=###
Using the binomial approximation in Eq. (13.13.6), the comparable calculation
would be:
num[
###=###
from"2",chosen"0"
from"98",chosen"5"
],
denom<
from"100",chosen"5"
>
num[
###=###
num<98!>,denom<93!#:#5!>
],denom
[
num(100!),denom(95!:5!)
]
num<98!:95!>,denom<93!:100!>
###=###0.9020
g(p)###A###
which is a difference of 0.0019, or 0.21 percent from the actual value of
0.9020 found above.
from[5], chosen[0]
###p@+(0)
q@+(5)###=### q@+(5)###=###(0.98)@+(5)###=###0.9039
g(p)###=###(1-p)@+(n)
To insure a ninety percent chance of rejecting a lot with an actual percentage
defective of one percent (p = 0.01), the required sample size would be
calculated as:
g(p)###=###1-0.90###=###0.1###=###(1-0.01)@+(n)
As can be seen, large sample sizes are required to insure relatively large
probabilities of zero defective items.
Then,
n###=###
Num "ln(0.1)",
Denom "ln(0.99)"
###=###
Num "-2.30",
Denom "-0.01"
###A###229.
Illustrative Sample Size Codes for MIL-STD-105
!!!!!!General Inspection
!!!Special inspection levels!!!!!!levels
Lot or batch size!!!S-1!!!S-2!!!S-3!!!S-4!!!I!!!II!!!III
2-8!!!A!!!A!!!A!!!A!!!A!!!A!!!B
9-15!!!A!!!A!!!A!!!A!!!A!!!B!!!C
16-25!!!A!!!A!!!B!!!B!!!B!!!C!!!D
26-50!!!A!!!B!!!B!!!C!!!C!!!D!!!E
51-90!!!B!!!B!!!C!!!C!!!C!!!E!!!F
91-150!!!B!!!B!!!C!!!D!!!D!!!F!!!G
151-280!!!B!!!C!!!D!!!E!!!E!!!G!!!H
281-500!!!B!!!C!!!D!!!E!!!F!!!H!!!J
501-1,200!!!C!!!C!!!E!!!F!!!G!!!J!!!K
1,201-3,200!!!C!!!D!!!E!!!G!!!H!!!K!!!L
3,201-10,000!!!C!!!D!!!F!!!G!!!J!!!L!!!M
10,001-35,000!!!C!!!D!!!F!!!H!!!K!!!M!!!N
35,001-150,000!!!D!!!E!!!G!!!J!!!L!!!N!!!P
150,001-500,000!!!D!!!E!!!G!!!J!!!M!!!P!!!Q
500,001 and over!!!D!!!E!!!H!!!K!!!N!!!Q!!!R
13.7 Statistical Quality Control with Sampling by Variables
x
An estimate of the population standard deviation is s, the square root of the
sample variance statistic:
-
@g(m)###A### ###=###
x
num{1},denom{n}
###
from{i=1},to{n}
x@-(i)
Based on these two estimated parameters and the desired limits, the various
fractions of interest for the population can be calculated.
@g(s)@+(2)###A###s@+(2)###=###
num[1],
denom[n-1]
###
From[i=1],To[n]
###(x@-(i)#-\*
-
# )@+@*x
(2)###=###
num[1],denom[n-1]
#
From[i=1],
To[n]
-
x@-(i)@+(2)###-###n# @+@*x
(2)#
which is t-distributed with n-1 degrees of freedom. If the population
standard deviation is known in advance, then this known value is substituted
for the estimate s and the resulting test statistic would be normally
distributed. The t distribution is similar in appearance to a standard normal
distribution, although the spread or variability in the function decreases as
the degrees of freedom parameter increases. As the number of degrees of
freedom becomes very large, the t-distribution coincides with the normal
distribution. Tables of the t-distribution appear in Appendix B. Note that the
two t-distribution tables appearing in Appendix B represent the same
information, but one is a lookup by t value (Table B.2) and the other is a
-
lookup by probability value (Table B.3). For example, if = 4.5, L = 4.0, s =x
-
3.0 and n = 5, the test statistic value t is (4.5#-#4.0)(V )#/#3.0#=#0.37.5
Using the tables in Appendix B, this value corresponds to slightly less than a
forty percent chance that the actual lot average is less than the lower limit
value; with four degrees of freedom and a single tail probability of forty
percent, the corresponding t-distribution value is 0.271. If this probability
was unacceptable, the lot could be rejected or subjected to additional testing.
t@-(L)###=###
-
num[ ###-###L],\*x
denom[
\*
###=###
-
num(s), denom(V )n
]
- -
num[( ##-##L):V ],x n
denom[s]
With both upper and lower limits, the sum of the probabilities of being above
the upper limit or below the lower limit can be calculated.
t@-(U)###=###
num[U###-###
-
###],denom[
###=###
x
num(s),\*
-
denom(V )n
]
-
num[(U##-## ):x
-
V ],\*n
denom[s]
and
t@-(AL)###=###
-
num[ ###-###L],denom[s]x
where t@-(AL) is the test statistic for all items with a lower limit and
t@-(AU) is the test statistic for all items with a upper limit. For example,
-
the test statistic for items above an upper limit of 5.5 with = 4.0, s = 3.0,x
and n = 5 is t@-(AU) = (8.5 - 4.0)/3.0 = 1.5 with n - 1 = 4 degrees of freedom.
Referring to Tables B.2 and B.3 in Appendix B, the corresponding probability
value or fraction of items greater than 5.5 is approximately ten percent.
t@-(AU)###=###
-
num[U###-### #],denom[s]x
4.3, 4.8, 4.6, 4.7, 4.4, 4.6, 4.7, 4.6
In this case, the sample mean and standard deviation can be calculated using
Equations (13.13.7) and (13.13.7):
-
## = ## The percentage of items below a lower quality limit of L = 4.3 is estimated
from the test statistic t@-(AL) in Equation (13.13.7):x
Num "1",
Denom "8"
## ##4.3 # + #4.8 #
+ #4.6 # + #4.7# + #4.4 # +
#4.6 # +#4.7 # + #4.6
## ##=##4.59
s@+(2)##=##
Num "1",
Denom "8 - 1"
## ##(4.3-
4.59)@+(2)#+#(4.8-4.59)@+(2)#+\*
#(4.6-4.59)@+(2)#+#(4.7-4.59)@+(2)
######################+#(4.4-4.59)@+(2)#+#(4.6-4.59)@+(2)#+
\*
#(4.7-4.59)@+(2)#+#(4.6-4.59)@+(2)### ##=##0.16
t@-(AL) ## = ##
Referring to Table B.2 in Appendix B, the fraction of items with strength
below 4.3 is approximately 0.05 or 5% with t@-(AL) = 1.81 and degrees of
freedom 8 - 1 = 7.
Num "4.59 # - 4.3", Denom "0.16"
## = ## 1.81
where the sample mean and sample standard deviation, s, are computed fromx
Equations 13.7 and 13.7. If the quality index (Q@-(U)) exceeds the value k,
then the lot is acceptable.
Q@-(U)#=#
-
num<U#-#x>,denom<s>
As a result of all these options, the number of tables and OC curves
associated with MIL-STD-414 is large.
13.8 Safety
13.9 References
13.10 Problems
"Water used in mixing or curing shall be reasonably clean and free of oil,
salt, acid, alkali, sugar, vegetable, or other substance injurious to the
finished product...Water known to be potable quality may be used without
test. Where the source of water is relatively shallow, the intake shall be
so enclosed as to exclude silt, mud, grass, or other foreign
materials."[American Association of State Highway and Transportation
Officials, Guide Specifications for Highway Construction, Washington, D.C.,
Section 714.01, pg. 244.]
14. Organization and Use of Project Information
14.1 Types of Project Information
Some of these sets of information evolve as the project proceeds. The
financial accounts of payments over the entire course of the project is an
example of overall growth. The passage of time results in steady additions in
these accounts, whereas the addition of a new actor such as a contractor leads
to a sudden jump in the number of accounts. Some information sets are important
at one stage of the process but may then be ignored. Common examples include
planning or structural analysis databases which are not ordinarily used during
construction or operation. However, it may be necessary at later stages in the
project to re-do analyses to consider desired changes. In this case, archival
information storage and retrieval become important. Even after the completion
of construction, an historical record may be important for use during
operation, to assess responsibilities in case of facility failures or for
planning similar projects elsewhere.
14.2 Accuracy and Use of Information
The standard deviation @g(s) can be estimated as the square root s of the
sample variance s@+(2), i.e. @g(s) A s, where:
- n x@-(i)
##=## #x S ------
i=1 n
The standard deviation @g(s) is a direct indicator of the spread or
variability in a measurement, in the same units as the measurement itself.
Higher values of the standard deviation indicate greater and greater
uncertainty about the exact value of the measurement. For the commonly
encountered normal distribution of a random variable, the average value plus
-
or minus one standard deviation, + @g(s), will include about two-thirds ofx
the actual occurrences. A related measure of random variability is the
coefficient of variation, defined as the ratio of the standard deviation to the
mean:
n -
#(x@-(i)#-# )@+(2)S x
i=1
@g(s)##=##----------------------
n#-#1
Thus, a coefficient of variation indicates the variability as a proportion of
the expected value. A coefficient of variation equal to one (c = 1) represents
substantial uncertainty, whereas a value such as c = 0.1 or ten percent
indicates much smaller variability.
@g(s)
c##=##-----
-
x
14.3 Computerized Organization and Use of Information
14.4 Organizing Information in Databases
14.5 Relational Model of Databases
ITEM_CODE: 04.2-66-025
DESCRIPTION: common brick masonry,
!!!12" thick wall,, 19.0 bricks per S.F.
WORK_UNIT: 1000 bricks
CREW_CODE: 04.2-3
OUTPUT: 1.9
TIME_UNIT: Shift
MATL_UNIT_COST: 124
DATEMCOS: June-09-79
INSTCOST: 257
DATEICOS: August-23-79
Illustrative Master Sampling Plan Table for MIL-STD-105
Illustrative Operating Characteristic Curves for a MIL-STD-105
Sampling Plan
Illustration of Variable Probability Distributions and Acceptance
Regions
Alternative Production Strategies to Meet Quality Specifications
Illustrative Operating Characteristic Curves in MIL-STD-414
Illustrative Table of Master Sampling Plans for MIL-STD-414
Illustrative Occupational Injury and Illness Incidence Rates
Reported Accidents in Construction in Britain 1976
Illustration of a Construction Warehouse Transfer Record
Illustration of a Database Management System Architecture
Illustration of a Relation Description:
Unit Price Information Attributes
Attribute Name!!!Attribute Description!!!Attribute Type!!!Key
ITEM_CODE!!!Item Code Number!!!Pre-defined Code!!!Yes
DESCRIPTION!!!Item Description!!!Text!!!No
WORK_UNIT!!!Standard Unit of!!!Text !!!No
!!!Work for the Item!!! (restricted to allowable units)
CREW_CODE!!!Standard Crew Code for Activity!!!Pre-defined Code!!!No
OUTPUT!!!Average Productivity of Crew!!!Numerical!!!No
TIME_UNIT!!!Standard Unit of OUTPUT!!!Text!!!No
MATL_UNIT_COST!!!Material Unit Cost!!!Numerical ($)!!!No
DATEMCOS!!!Date of MATL_UNIT_COST!!!Date Text!!!No
INSTCOST!!!Installation Unit Cost!!!Numerical ($)!!!No
DATEICOS!!!Date of INSTCOST!!!Date Text!!!No
Subcontractor Relation Example
SELECT from SUBCONTRACTORS where SIZE = Large and ELECTRICAL = Yes
would result in the selection of all large subcontractors performing electrical
work in the subcontractor's relation. More specifically, the estimator might
want to find subcontractors in a particular state:
SELECT from SUBCONTRACTORS where SIZE = Large and ELECTRICAL = Yes
and STATE = VI.
In addition to providing a list of the desired subcontractors' names and
addresses, a utility application program could also be written which would
print mailing labels for the selected firms.
These attributes could be used to answer a variety of questions concerning
construction experience useful during preliminary planning.
Example of Bridge Work Relation
Each SELECT operation would yield the bridge examples in the database which
corresponds to the desired selection criteria. In practice, an input/output
interpreter program should be available to translate these inquiries to and
from the DBM and an appropriate problem oriented language.
14.6 Other Conceptual Models of Databases
Hierarchical Data Organization
Example of a Network Data Model
Illustration of Data Stored in a Frame
Illustration of a Frame Based Data Storage Hierarchy
14.7 Centralized Database Management Systems
For the purpose of project management, the issue of improved availability is
particularly important. Most application programs create and own particular
datafiles in the sense that information is difficult to obtain directly for
other applications. Common problems in attempting to transfer data between
such special purpose files are missing data items, unusable formats, and
unknown formats.
An alternative arrangement might be to separately record equipment rental costs
in (1) the Purchasing Department Records, (2) the Cost Estimating Division, and
(3) the Company warehouse. While these multiple databases might each be
designed for the individual use, they represent considerable redundancy and
could easily result in inconsistencies as prices change over time. With a
central DBM, desired views for each of these three users could be developed
from a single database of equipment costs.
14.8 Databases and Applications Programs
Illustration of an Integrated Applications System
Production information can also be obtained from the integrated system, such
as:
Computer Aided Engineering in the Construction Industry
14.9 Information Transfer and Flow
In addition to these problems, there will always be a set of untidy
information which cannot be easily defined or formalized to the extent
necessary for storage in a database.
Application of an Input Pre-processor
14.10 References
14.11 Problems
15. Knowledge Based Expert Systems in Project Management
15.1 Computer Aids for Project Management
15.2 What is an Expert System?
Central Components of a Rule-based Expert System
IF: activity has no total float time (TF = 0)
THEN: activity is on the critical path.
In this case, the inference engine could select this rule, apply it to a
particular activity for which the precondition is true (in this case, the
precondition is that the total float time of the activity is zero), and record
the conclusion that the activity is on the critical path. The context
description of the activity would be altered to indicate that this activity was
on the critical path. After this, additional rules might be used to suggest
adding resources to critical activities to reduce their duration, to
re-schedule non-critical activities, or other actions. These additional rules
would be selected by the inference engine as the rules' preconditions became
true (such as a precondition identifying at least one activity on the critical
path).
Complete Facilities of a Rule-based Expert System
15.3 Developing Expert Systems
A variety of problems encountered by project managers or by other participants
in the provision of constructed facilities meet these criteria. As a result,
the range of potential expert system applications is correspondingly large.
Table 15-0 summarizes some possible systems, progressing from derivative or
interpretive problems to more complicated formative or generative problems.
Some Possible Expert System Applications in Project
Management
Illustration of Expert System Uses
15.4 Problem Solving Strategies in Expert Systems
F and W R Z
is interpretated as "If F is true and W is true, then Z is true." "Truth"
might represent the literal correctness of the fact Z or the existence of a
calculated value for a previously unknown variable Z; application of a rule
might include calculation instructions for the variable value. The overall
system goal in this small example is to establish the truth of Z if possible.
Initially, the context contains the facts represented by the variables A, B, C,
E, G and H (Figure 15-0). Given these facts, the inference engine works to
apply the rules in the knowledge base.
Illustration of a Forward Chaining Problem Solving Strategy
Illustration of a Backward Chaining Problem Solving Strategy
15.5 An Example Expert System for Estimating Activity Durations: MASON
MASON's Hierarchical Estimation Framework
IF the maximum productivity assessment is desired
AND eight inch block is to be used on the activity
THEN the maximum productivity on the activity is 400 units
per day per mason
AND a maximum productivity assessment is no longer desired
This rule can be applied when the goal to "find maximum productivity" is active
(i.e., desired) and the site characteristics match the premises (i.e., eight
inch block). The conclusion reflects the maximum productivity that might be
obtained and a de-activation of the goal to "find maximum productivity." Over
one hundred rules appear in MASON for productivity estimation under various
conditions.
Welcome to MASON.
What is the name of the job ?
Martinelli's
What type of job is it ?
Steel-frame
Is this job large or small ?
large
Is this an addition for an existing building ?
no
What would you like to call this activity ?
first
What is the expected temperature level during this activity ?
Low (Note: "Low" implies a temperature under 50 degrees F.)
...and the precipitation level ?
High (Note: more sophisticated input control would omit this \*
question for interior jobs)
Where on the job is this activity located ?
Interior-Wall
How many crews are you putting on this activity ?
1
How many laborers are on each crew ?
2
...and how many masons?
6
Are you using union or nonunion labor ?
union
I need to know how many openings there are ?
9
Will this wall be insulated ?
no
What type of material is being laid ?
Block
... and how many orders of this material were placed ?
1
What thickness of block was ordered for this activity [inches] ?
4 inch
Will high strength mortar be used?
no
What type of finishing will be placed over the block?
Drywall
What is the average length of the wall-s [feet] ?
50
Will FIRST take place on more than one floor ? [yes,no]
no
On what floor will FIRST take place ? [0 for foundation]
4
What is the average width of the opening-s [feet] ?
2
...and the height ?
3
How much area is to be covered [sq-ft] ?
10000
How will strap anchors be attached to steel ?
Shoot with Hildy-Guns
Input is now complete.
THE DURATION OF ACTIVITY: FIRST IS 16.4 DAYS
THE PRODUCTIVITY IS 176.0 UNITS PER DAY PER BRICKLAYER
THE TOTAL DOWNTIME IS 5.7 DAYS
Would you like recommendations to improve productivity ?
yes
You can increase the productivity on FIRST by 32.0 BLOCK per bricklayer per day
if at least 1 laborers are added to each crew.
Would you like increase the number of laborers by 1 ?
why
Would you like increase the number of laborers by 1 ?
yes
Do you wish to switch to high strength mortar ?
why
Do you wish to switch to high strength mortar ?
yes
Revised duration estimation is complete.
THE DURATION OF ACTIVITY: FIRST IS 13.2 DAYS
THE PRODUCTIVITY IS 249.0 UNITS PER DAY PER BRICKLAYER
THE TOTAL DOWNTIME IS 5.7 DAYS
Would you like to know the factors considered in calculating the
productivity ?
yes
15.6 An Expert System for Retaining Wall Diagnosis and Design: RETAIN
Architecture of the RETAIN Expert System
A Hierarchical Network of Possible Retaining Wall Rehabilitation
Strategies
Illustration of a Small Failure Diagnosis Inference Network
Illustration of Forward Tilting Failures of Cast-in-place Concrete Walls
If Evidence E exists,
Then Hypothesis H is true to degree LS
If Evidence E does not exist,
Then Hypothesis H is not true to degree LN
Application of rules of this sort can also take into account the probability
that evidence E actually exists. In addition, each node has an associated
prior or base probability. Given particular inputs and their associated
certainties, the result of applying these likelihood values and evidence
probabilities is some probability of existence for each possible conclusion.
15.7 An Expert System for Construction Planning: CONSTRUCTION PLANEX
Overview of CONSTRUCTION PLANEX
Illustration of the CONSTRUCTION PLANEX Context
Illustration of a CONSTRUCTION PLANEX Knowledge Source
15.8 An Integrated Building Design Environment
These different processes can run on different computers, with communication
and data transfer taking place over a network. In automatic mode, requirements
for a building can be entered originally and the system will then develop a
building design and construction plan. Alternatively, each of the processes
can be monitored and decisions reviewed as they are made.
Architecture of an Integrated Building Design Environment
15.9 References
16. Construction Automation and Robotics
16.1 Introduction
16.2 Types of Robots and Automation
16.3 Some Illustrative Construction Robots
Material handling
Tunneling and Excavation
Illustration of REX, a Robot EXcavator
Surface Finishing
Illustration of a Fireproof Spraying Robot
Inspection
Illustration of a Remotely Controlled Reconnaissance and Core Boring Robot
16.4 Construction Robot Technology
Manipulators
Typical Configurations of Industrial Robots: (a) Rectangular; (b)
Cylindrical; (c) Spherical; (d) Jointed; (e) Wrist.
Robot Effectors
Illustration of a Gripping Robot Effector
Mobility Systems
Robot Control
Sensors
Robot Vision: Raw Intensity Data and Progressive Interpretation
of Crossing Reinforcing Bars
16.5 A Sandblasting Robot Example
Each of these tasks can be performed with currently available robotic
technology and have been attempted with success for other applications in the
manufacturing industries.
General Setup of the Sandblasting System.
16.6 Future Prospects for Automation and Robotics in Construction
An Illustration of the Workhorse Teleoperated Robot
16.7 References
I. Compound Interest Tables
II. Statistical Tables